Hamilton County Facilities

230

230 East Ninth

230 – East Exterior Lighting

PM = Rycca Thacker, Mike Barth

07/29/26 – HCFD requests SOSS. DEG submits SOSS.
08/26/26 – DEG sends fixture model number to HCFD to get trades to check pricing and lead times. DEG finalizing the plans for permitting and trades to install.
09/23/26 – DEG submits drawings to IBI for approval and permit.
10/28/26 – Permit and plan review approved. HCFD trades has approved plans and permit. Trades to complete the install. DEG will call for inspections once work is installed.

230 – East Exterior Lighting Read More »

230 – Plumbing Upgrades

PM: Megan, Terry Cannon,
04/30/26 – Project opened on website. DEG started fieldwork and is working on bid CD documents. Need to check on SOSS approval.
05/27/26 – Need to request meeting with new building manager before proceeding. Meeting June 4 at 9am for design meeting with Jesse.
06/25/26 – First review set probably ready in July.
07/30/26 – Plumbing ready for review, electric will be ready soon then to County for Owner review.
08/26/26 – Review sets sent to County and limited comments received back. Floor plans updated. The project will be ready to bid soon.
09/15/26 – Prebid
09/18/26 – Addendum 1 issued.
09/22/26 – Addendum 2 issued.
09/24/26 – Bid due Friday.
09/25/26 – Bids received. Triton and QCM Mechanical submitted bids. DK and others did not bid the project.
10/22/26 – Facilities notified DEG that the bids are not awarded due to contract technicalities. TTC informed Triton in person.
10/27/26 – TTC & Rycca discussed how to rebid the job with a few small changes and make it suitable for award. DEG will update the bid documents adn send back out for a price refresh from the same vendors.

230 – Plumbing Upgrades Read More »

230 – 11th Flr Training Rm Acoustics

PM: Rycca, Eryn
04/30/26 – SOSS to be submitted shortly.
05/28/26 – SOSS submitted.
06/25/26 – Acoustic testing occurred 06/19. Consultant will provide design recommendations based on report.
07/30/26 – Report provided by testing consultant to HCFD. Elevar to research other panel providers and will provide report in layman’s terms.
08/27/26 – Report and design options provided. Consultant working on final design images based on actual photos of the space.
09/24/26 – Rendering photo and samples provided to COA.
10/29/26 -Costs provided to COA.

230 – 11th Flr Training Rm Acoustics Read More »

230 – Lobby Security Upgrades

PM: Rycca Thacker, Eryn Thamann
02/26/26: Added as new project. Need meeting with COA/Probate/HCFD to review scope.
03/26/26: SOSS provided for concepts/SD phase.
04/30/26 – No update.
05/28/26 – Will wrap into elevator project. Elevar to provide new SOSS and will work on design options.
06/25/26 – SOSSs in process for approval with HCFD now.
07/30/26 – Concepts reviewed at initial meeting and working thru final concept now. Will review with HCFD prior to scheduling full group meeting. 230 Court Admins wanted this work to be completed faster than if combined into 230 Lobby Security project.
08/27/26 – A third option for the rear secure elevator area was discussed with Rycca and will be provided this week. Another meeting with the main group will then be scheduled. Exterior Lighting portion broken back out to separate project.
09/24/26 – A third option was provided to the entire group and another meeting was held. Another revision was sent to entire group for input and potential third meeting.
10/29/26 – Another mtg was just held and option 7 is under design.

230 – Lobby Security Upgrades Read More »

230 – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and initial site walk scheduled for 03/27 with JN.
04/24/25 – Walk-thru occurred and drawings have progressed. Elevar to coordinate with Champlin on design in near future.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. Need to know if paint removal was successful on stickers.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

230 – Fire Door Repairs Read More »

230 – Elevator Modernization

PM: Rycca Thacker, Mike Barth
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (4) elevators in 230 East 9th Street Building. TEI and Elevar meet to discuss roles on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar SOSS provided to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
01/29/25 – TEI/Elevar/HC met and TEI has design schedule. Field work is ongoing now.
02/25/25 – Elevar performed field work for all.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting scheduled with HCFD. SD meeting scheduled for 04/02.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team meets with the Courts committee to review security and finishes. DD documents are progressing.
06/25/25 – Team meets with Court Admins. TEI to submit updated schedule.
07/30/25 – Team sends proposed schedule and RFIs to HCFD for direction.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Low bid being vetted by design team.
04/30/26 – Contract in process with HC Purchasing.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027). The contract phase and procurement deposit caused the delay.

230 – Elevator Modernization Read More »

230 – 10th Floor Marriage License Reno 2024

PK = Matt Butz, Mike Barth, Eryn Thamann
05/29/24 – TEI submits SOSS for approval.  Project pending PO and signed SOSS.
06/05/24 – Elevar submits SOSS for approval. Project pending PO and signed SOSS.
06/26/24 – Project pending PO and signed SOSS.
07/24/24 – TEI, Elevar and HCFD meet on site with end user. Scope changed and SOSS’s to be resubmitted for new revised scope.
08/27/24 – Elevar submitted new SOSS on 07/26 and awaiting approval.
08/28/24 – TEI receives signed SOSS and PO.
09/24/24 – Elevar scheduled a design kick off meeting for 10/01.
10/30/24 – Concepts provided to Probate for review.
12/09/24 – Finalizing concepts this week.
01/27/25 – ThermalTech awaiting schedule from HC/Elevar, HVAC SD level completed. In CD phase with 75% review in next few weeks. Electrical to finalize field confirmation after the partner meeting on 01/30/25.
02/25/25 – 75% review set sent to Probate for review and schedule of onsite meeting. Elevar still owes additional SOSS for lift removal/office add.
03/26/25 – Team met with Probate and has a few revisions. Still need finishes from HCFD. Elevar still owes additional SOSS for lift removal/office.
04/23/25 – Team is awaiting approval of lift/office SOSS to complete CDs.
05/28/25 – Progressing with CD drawings while waiting on final finishes approval.
06/26/25 – CD set was reviewed Probate and approved. Final finishes and systems furniture selected. Waiting for Probate to approved final SOSS for lift removal and additional office at which time they will be added to the drawings.
07/31/25 – Probate set to issue PO for additional work last wee/this week. Elevar to coordinate additional work and provide backgrounds. Need final approval for bidding from HCFD.
08/05/25 – THP received project authorization and signed agreement.
08/22/25 – THP – Elevar, County and THP reviewed field conditions for infill project.
08/28/25 – Additional SOSS approved and THP made site visit to field verify existing lift. Project will be ready to start HC review/bidding prep after this final scope is completed.
09/08/25 – THP issued infill repair detail for review.
09/25/25 – Drawings 95% complete and likely ready for a final review. ROM cost estimate sent to Probate for review.
10/21/25 – THP issued structural bid documents for project package.
10/30/25 – Project out to bid as of 10/22. Pre-bid mtg scheduled with team for 11/05.
12/11/25 – Post-bid vetting meeting scheduled for Alpha on 12/10 with Triton as next lowest.
01/29/26 – Permit/revisions applied for at City. Waiting on final contracts thru Purchasing.
02/26/26 – Contract awarded to Alpha on 02/19. Elevar to schedule construction kick-off mtg.
03/26/26 – Elevar to schedule construction kick-off mtg after Alpha provides construction schedule; expect this soon. HCFD to award special inspections SOSS.
04/30/26 – Construction kick-off meeting scheduled for end of May.
05/28/26 – Construction kickoff mtg occurred 05/27. Eryn to issue mtg mins and setup recurring progress mtgs. Construction to start June 1.
06/25/26 – Construction ongoing.
07/30/26 – Construction ongoing. Approx. carpet delivery is Aug 4. Phase 1 is waiting on carpet install prior to shifting to Phase 2.
08/27/26 – Construction ongoing in phase 2. Working on HVAC duct issue.
09/24/26 – Punch list for Ph. 2 occurred and contractor moved to Ph. 3.
10/29/26 – Approx. 2 weeks from Phase 3 completion. Furniture move is scheduled for 10/28. Closeouts will also remain.

230 – 10th Floor Marriage License Reno 2024 Read More »