230 WHT Public Defenders Relocation to CAB Study

Project Lead: GBBN

06/13/13 – Kick-off Meeting via conference call to the Facilities Department

06/13/13 – Call to Jack Herbert to ask programming questions per Diana Supe’s request.

06/14/13 – Design Team meeting to discuss scope and deliverables.

06/17/13 – Bert Watts escorts Design Team around CAB 9th Floor Computer Room and adjacent spaces.

06/19/13 – GBBN submits list of scope questions to Diana Supe to finalize scope for SOSS (F088) preparation..

06/21/13 -GBBN finalizes Kick-off meeting date with Design Team, County Facilities and Prosecuting Attorney.

06/27/13 – Kick-off meeting date with Design Team, County Facilities and Prosecuting Attorney held in B-90.