230 WHT Public Defenders Renovation Study

Project Lead: GBBN

04/02/13 – Kick-off Meeting with Public Defenders and Facilities Department

04/05/13 – Design Team Kick-off Meeting with IPM.

04/08/13 – SOSS submitted to Bert Watts

04/09/13 – Bert Watts calls to request modified SOSS for Schematic Design and Construction Opinion of Probable Costs only.

04/10/13 – GBBN resubmits SOSS (F086) to Bert Watts.

04/22/13 – GBBN receives approved SOSS with Purchase Order.

04/24/13 – GBBN coordinates with PDO for site visit the following day to field verify existing systems furniture.

05/29/13- Revision made to Archibus estimate as a result of additional programming data from Public Defenders Office.

06/06/13- Revised drawings sent to Public Defenders Office based on changes requested by the PDO.

06/13/13- Revision made to Archibus estimate as a result of the drawing change approvals from PDO on the additional programming data from Public Defenders Office.