Project Lead: GBBN
04/02/13 – Kick-off Meeting with Public Defenders and Facilities Department
04/05/13 – Design Team Kick-off Meeting with IPM.
04/08/13 – SOSS submitted to Bert Watts
04/09/13 – Bert Watts calls to request modified SOSS for Schematic Design and Construction Opinion of Probable Costs only.
04/10/13 – GBBN resubmits SOSS (F086) to Bert Watts.
04/22/13 – GBBN receives approved SOSS with Purchase Order.
04/24/13 – GBBN coordinates with PDO for site visit the following day to field verify existing systems furniture.
05/29/13- Revision made to Archibus estimate as a result of additional programming data from Public Defenders Office.
06/06/13- Revised drawings sent to Public Defenders Office based on changes requested by the PDO.
06/13/13- Revision made to Archibus estimate as a result of the drawing change approvals from PDO on the additional programming data from Public Defenders Office.