237 WHT – HCPHD TB Clinic Entrance Security Access Control.

PM – John Nester, Mike Barth

03/24/21 – HCFD requests SOSS from TEI for SD/Estimating. TEI and HCFD conduct phone call with Greg Varner of Public Health to clarify scope on 03/24/21 and then TEI will finalize and submit SOSS.
04/28/21 – TEI and HCFD meet with Greg Varner and walk the space. TEI authors and submits SOSS. Project pending SOSS approval and PO.
05/26/21 – Project pending SOSS approval and PO.
06/23/21 – TEI receives approved SOSS and PO. Project field work to be scheduled with JN of HCFD
07/28/21 – TEI develops SD drawings and estimates for HCFD review. TEI to send to JN for review and comments by 08/06/21 – then finalize for official submission upon receipt of JN comments.
08/26/21 – TEI sends SD package to HCFD to send to public health. TEI sends HCFD PM estimate of fees for taking project through CD’s and CA. Project pending approval funding.
10/26/21 – Project pending approval of SOSS and PO.
10/28/21 – SOSS approved and work can continue.
12/13/21 – Final review documents to be sent for owenr review on 12/17/21.  Review teams Meeting scheduled for 12/20/21 at 2:00 PM.
01/25/22 – Project has been issued for bids.  Prebid meeting is scheduled for February 2, 2022
02/23/22 – Project issued for bidding per HC small project bidding process.   Bids due to TEI on 02/25/22.
04/27/22 – Project re-bid per ITB process.   (1) bid received from Triton.   TEI vets bid and recommends Triton for project.  Contracts drafted and at prosecutors office for review.  Construction to commence upon approved contracts and PO issuance.
05/26/22 – Construction to commence upon approved contracts and PO issuance.
06/28/22 – Construction to commence upon approved contracts and PO issuance.

07/27/22 – Project to commence upon material procurement.

08/24/22 – Project to commence upon material procurement.  All submittals retturned.

09/26/22 – Project to commence upon material procurement.

10/26/22 – TEI, HCFD and HCPH have kick off meeting with Triton.  Materials on order and project schedule being developed by Triton.

12/15/22 – Walls and door frames installed.   DK to mobilize Monday 12/19/22 to begin the Electrical install.

01/25/23 – Construction progressing.  Upon approved inspection, walls can be closed up.   Final door hardware not arrived yet.  Powered door operator not on site yet.  Construction completion pending materials arrivals.

02/23/23 – Ready to Archive.

03/29/23 – HCFD and TEI provide preliminary punchlist.   Items being addressed and waiting on final inspections.

04/27/23 – HCFD and TEI to perform final punchlist.

05/23/23 – Once punchlist is complete, the project is complete, with the exception of the door outside of the scope of the project that the inspection agency wants panic hardware installed on.

06/28/23 – Triton working to resolve final panic hardware issues, and then will have final inspection.