800 – Elevator Monitoring System Upgrade

PM: John Nester, Mike Barth

03/24/21 – HCFD requests SOSS for project. TEI submits SOSS and receives approval of the SOSS and the PO. kickoff meeting with facilities and building manager to be scheduled week of 03/29/21.
04/28/21 – TEI and HCFD meet with building manager and kick off design of the project. Project in design process.
05/26/21 – Project in process. TEI to confirm pathways from machine room to machine room, and then will submit review set to HCFD for comments.
06/23/21 – Project in process. TEI to confirm pathways from machine room to machine room, and then will submit review set to HCFD for comments.
07/28/21 – TEI submits drawings to HCFD for review comments. Receives comments from JN, awaiting comments from building manager. Package will be issued upon receipt of all comments.
08/26/21 – TEI and HCFD PM finalize bid set. Project out to bid date is 08/31/21, and bids due on 09/22/21. ITB # = 081-21
10/26/21 – Bids received. Fujitek is low bidder. TEI vets their bid, and the contract and PO was approved. Materials are on order, and upon receipt, installation will be scheduled.
12/13/21 – Installation pending arrival of parts.
01/25/22 – Installation pending contractor background checks.
02/23/22 – Preconstruction meeting scheduled for 02/22/22 – cancelled due to vendor having C-19.   Pre Construction meeting re-scheduled for 3/8/22 at 9:00 AM.
04/27/22 – Project construction has began.   Work occurring in the penthouses.
05/26/22 – Construction completion pending materials arrival.
06/28/22 – Construction completion pending materials arrival.
07/27/22 – Fujitec, HCFD and TEI meet to discuss the existing software and the proposed software, and the incompatibility issues.  TEI and HCFD to develop response and plan moving forward.
09/26/22 – Fujitec to install updated software.
10/26/22 – Waiting on install from Fujitec.
12/15/22 – Waiting on Install from Fujitec.
01/25/23 – John Nester receives notice from Fujitec that all project personnel are no longer working for Fujitec.   TEI and HCFD working to get new contact information to have Fujitec complete the project.
02/23/23 – Fujitec new personnel working to complete project.
03/29/23 – Fujitec experiencing a lot of personnel turn over.   This project still pending.  There are issues with one of the elevators on the monitoring system and until that is repaired, Fujitec not comfortable taking down the other cabs.
04/27/23 – No update from Fujitec.
05/23/23 – No updates from Fujitec.
06/28/23 – No updates from Fujitec.
07/26/23 – Fujitec!!!
08/31/23 – Fujitec and Kone working together to repair obsolete equipment in the building. Billing is not right.
10/26/23 – TEI works with Fujitec to correct billing (several attempts).  TEI certifies pay application and delivers to HCFD for payment.
12/06/23 – No updates from Fujitec.
06/27/24 – No updates. Fujitec needs Kone aftermarket group to furnish some missing parts so they can continue working.
07/24/24 – HCFD, TEI and newer Fujitec regional sales mgr meet in B-90. Speak of issues. Fujitec asks for 3-4 weeks to look into issues and solutions.
08/28/24 – No Updates from Fujitec.
07/30/25 – This will be picked up in the elevator modernization project.
08/28/25 – OK to Archive.