250 WHT – Public Health Lobby Renovation (2nd Flr)

03/31/21 – SOSS approved. Kickoff meeting scheduled for 5/6.
04/29/21 – Kickoff meeting schedule for 5/6/21.

05/06/21 – Kickoff meeting held

05/17/21 – Field visit to verify existing conditions

06/04/21 – Progress set sent to Greg Varner for review

06/08/21 – Updates from Greg received

06/10/21 – Updated plan sent to Greg

06/22/21 – HC, PH, and ES decided to combine project scopes of 2nd floor lobby and 1st floor lobby into one bid.

06/23/21 – Updated plan sent to Greg.

07/09/21 – 95% review meeting to review scope and budget. Raised questions related to code requirements. required additional research.

07/29/21 – Meeting scheduled for Final Review Set.

08/10/21 – Project Issued

08/23/21 – Pre-bid Meeting Held

09/09/21 – Bid opening – Triton was apparent low bidder.

09/15/21 – Zoom meeting with Champlin, Thermaltech and Triton to vet the bid. Sent Letter of Recommendation to County.

10/28/21 – Ready to archive.

 

 

 