CH – Chiller & Boiler Room Control Updates

PM: Terry Cannon, Tony Matre
04/23/21 – Tony requested an SOSS for a chiller study on controls and operations.
05/26/21 – Discussed scope with Tony Matre today and he wants better control of the system and better maintenance.
06/25/21 – Based on recent conversations with everyone about upcoming projects, I have not submitted a separate SOSS for this work yet.
07/28/21 – SOSS approved. The study will begin next week.
08/18/21- TTC discussed similar scope with Ameresco and their findings on the Courthouse Chillers
08/24/21 – TTC met with Honeywell and discussed chiller, cooling tower, free cooling controls and programming and learned a lot about what has been changed in the last few years. Honeywell can meet with ThermalTech and the County late September given Randy current scheduled. TTC will advise Matt and Tony on this schedule.
09/27/21 – Reached out to Ameresco and discussed previous jobs with Garyne and Brad and get download on what they’ve done.
10/27/21 – Contacted Randy for pricing on recommissioning project and scope.
10/28/21 – Emailed and called Randy today for pricing for recommissioning today. Randy called back today and promised to give us his recommissioning cost by Nov 4, TTC to turn over to Matt and Tony immediately afterward.
12/13/21 – TTC scheduled the Chiller Recommissioning work with Randy and County for 12/27 at 9:00am on site.
12/30/21 – TTE collected and sent sequences to Honeywell for use on this project. Cc’ed the County.
01/22/22 – Honeywell working on new sequences and project schedule. TTC to check on VFD repairs.
02/24/22 – Honeywell started the fieldwork and deficiency report work last week and was down at the Courthouse collecting data.
03/31/22 – met Randy and corporate on-site. Getting deficiency report for next steps.
04/28/22 – Honeywell turned over all the existing points list and we have gone through it. We have not seen the due diligence report yet but Randy is working on it. I have stayed in touch with Randy weekly on this job. CH-3 will not be here unit August for installation. Comm is Bacent MSTP on the existing chillers.
05/25/22 – Randy is working up a new controller that will handle the sequences we need for this job and getting pricing, all hopefully, within his budget. And help promises to send an deficiency report to me via email.
06/30/22 – As soon as Randy is done with the Server Room, he will start the Chiller Room work.
07/27/22 – Randy is onsite now working on controls, he may get to some of the Chiller Room controls this week.
08/03/22 – Trane Chiller #3 ships 9/18/22, Tony wants chiller controls completed before then.
08/18/22 – Met with Dave Johnson on CH Boiler Room Controls today. We discussed his scope and schedule for integrating the boiler plant into two control scenarios. 1) Courthosue controls which will be minimal boiler operation and 2) CH & JC and what does that look like? Dave will update his controller for two scendarios and we will work in the HTX-5 operation with the Summer Reheat operation.
08/24/22 – Reached out to Randy for Chiller update and reminded him this work to be done before 9/18.
09/22/22 – Randy back on 9/21 but he spent that time on CH Server Room job. He is coming back next week.
08/24/22 – Randy will be back on 8/31 with a new controller board and continue to work on CH updates. He owes us a quote for a new controller to get the chiller RECX done before 9/19.
10/26/22 – Randy has made some progress. Honeywell will be back Monday. NO updates form TPC on CH boiler controls.
12/15/22 – Vendors have been contacted multiple times to complete this work but I have not gotten them on site to do this work yet. I will have to try harder this month.
01/24/23 – Randy promised he will be down to do the CH Controls work on Friday. Dave Johnson does not call me back.
02/21/23 – Honeywell on-site twice last month but the new controller is not installed yet. Met with DJ and he is working on new controls programming.
03/29/23 – Honeywell Randy to install new controller this week. Dave Johnson working with TTC.
03/30/23 – Randy confirmed this morning is installed and controls completed.
04/26/23 – Honeywell coming back May 5 to finish programming on the chiller plant.
05/21/23 – Checked in wtih Honeywell last week, no updates yet.
06/28/23 – Chiller and Cooling Tower controls are in place. Next step Boiler Controls.
07/26/23 – ThermalTech will check programming on Thursday when on the building BAS system. DJ having open heart surgery, his work may have to wait.
08/29/23 – Chiller controls in place. Boiler controls awaiting DJ recovery.
09/27/23 – No updates on this yet, will check in with DJ in October.
10/25/23 – TTC contacted DJ on health condition to see if he is ready to return to work yet, no answer yet.
12/06/23 – Chiller Controls are in. Dave Johnson said that he will call me back with a day to come down and do the boiler reprogramming so he is feeling better and back in business. We will get this on the schedule and get it done very soon. TTE reviewed the plan for having a Courthouse Mode and a Justice Center mode. DJ has to program some of this ahead of time.
01/31/24 – Randy Waddell to be onsite by this date for CH Chiller Controls. Trane sent all data he need for Chiller integration. Dave Johnson not answering phone calls about boiler controls.
02/23/24 – Randy Waddell was onsite this month installed controller for chillers. New wires ran to VFD, but no power is on new VFD’s yet. MCC update coming soon.
03/22/24 – Honeywell was onsite two days last week and pulled their controls back to the front end. four VFD’s powered up with controls. The Carrier chilled is not hooked up yet.
04/24/24 – Honeywell says they are done but the Carrier chiller is not hooked up to DDC nor can we see the KW on it. TTE to reach out to Don Webber. Randy Waddell has to come back to the building to work on Bacnet points, add the generator to the systems and the deficiency report items. Dave Johnson has suggested May 18 and 19th for his weekend work at the CH.
05/28/24 – Chiller work is complete, all chillers are on graphics.
06/26/24 – Honeywell has completed their work and the systems appear to be working. Dave Johnson is being scheduled for July.
07/24/24 – Chillers are complete and working well. Boilers are scheduled August 24,25th with Dave Johnson.
08/10/24 – Met Dave Johnson and Tyler Laws on site and reprogrammed the boilers. We got most of the reprogramming done on Saturday but we will have to come back on Sunday.
08/11/24 – Met Dave Johnson on site Sunday to wrap up the boiler programming updates. The boiler room was flooded due to the boilers being off and some of the recirculation pumps being off. Later we discovered a room upstairs flooded too, note to self turn off all pumps when the boilers are off. Programming complete with two operator settable modes and three working modes. (1) Courthouse, (2) JC Low Load March-November, and (3) JC High Load Dec-Feb.
09/24/24 – Dave J contacted multiple times this month for Summer Boiler troubleshooting and Modbus map for boiler controls to ALC to no affect.
10/30/24 – Dave Johnson coming back in November to finish up but boilers are running okay so far.
12/12/24 – Dave Johnson has not returned yet and I have not gotten a new commitment date from him.
01/28/25 – Talked to Dave last weekend and he is going to send some availability for February to finished the Summer Boiler work.
02/27/25 – Original proposal cancelled by Auditor. TPC sent new proposal for recommissioning and troubleshooting services. New proposal rejected due to wording. Tony requested new proposal.
03/25/25 – New proposal sent last week with updated language and 2025 rates including additional troubleshooting for the summer boiler. TPC also included sole source letter.
04/23/25 – PO sent to Dave Johnson for troubleshooting work and summer boiler integration.
05/28/25 – TTC trying to get summer boiler date from Dave Johnson. No luck on confirmed date of work yet.
06/25/25 – No commitment from Dave Johnson on summer boiler startup.
07/30/25 – No updates from Dave Johnson, spoke to Tony about Emcor proposal to take over boiler controls.
08/26/25 – Helped Tony get BBC in the vendor database, now we can schedule David through BBC.
09/24/25 – Sole source letter on BBC letterhead received. TTC requested schedule dates to troubleshoot summer boiler.
10/29/25 – Repeated attempt to schedule Dave Johnson back down for summer boiler startup were unsuccessful.
12/12/25 – No updates from Dave on performing the summer boiler work. Just Archive and put this job out of its misery.