PM: Matt Butz, Paul Bellman
09/15/22 – Hamilton County requested SOSS.
09/29/22 – THP to publish SOSS on 9/30/22.
09/30/22 – THP published SOSS. (8 years ahead of schedule).
03/27/23 – THP Revit Model in progress.
04/25/23 – Revit Model 95% complete.
05/23/23 – No updates from THP.
07/20/23 – Hamilton County on site meeting with THP to review scoping.
08/23/23 – County placed project on hold.
09/27/23 – THP to provide Hamilton County with status drawings the first week of October.
10/23/23 – THP provided review documents (drawings and project manual), plus economic inclusion opinion of probable costs.
01/31/24 – No updates from THP.
02/29/24 – No updates. On hold.
03/27/24 – On hold.
04/25/24 – On hold.
05/30/24 – No updates. On hold.
06/26/24 – No updates. On hold.
07/24/24 – No updates. On hold.
08/29/24 – No updates. On hold.
09/26/24 – No updates. On hold.
10/31/24 – No updates. On hold.
12/11/24 – No updates. On hold.
12/12/24 – Champlin to check on const 2B vs 5B and maybe we submit an engineering change to modify it to 5B.