230 – Magistrate & Mediation Construction

PM: Matt Butz, Sam Hofmann
09/29/22 – Two projects combined into one Construction project. Some furniture will be reused.
10/21/22 – Contracts finalized and Pre-construction meeting held. Kick-off meeting to be scheduled when submittals are returned.
12/15/22 – Kick-off meeting to be scheduled
01/26/23 – Kick-off meeting held. Construction to start in near future. Waiting on all background checks to return.
02/01/23 – Notice to proceed issued.
02/22/23 – Construction on going. First progress meeting held.
03/30/23 – Construction ongoing.
04/26/23 – ThermalTech reviewed the HVAC and Fire RFI’s and discussed final design for these services.
04/27/23 – Construction on going. Will move onto 9th floor this month.
05/25/23 – Punch completed for 11th and 12th floor. Construction started on 9.
06/29/23 – 11 and 12th floor punched. Work is underway on 9th. Everything to be complete by end of month. HVAC and Electric change orders approved, TTE to cover these cost.
07/27/23 – 11 and 12th floor nearly complete. 9th floor to be complete mid august. Waiting on Alpha to provide pricing for potential flooring change order TTE provided a 10″ neck diffuser for Alpha to get installed. Trades will help clean up the 11th floor inefficiencies. Inspections are complete for MEP on 9, 11, 12 floors. 9th floor punchlist coming up soon. Barth talked to Delta and they may be able to provide two can lights for the Reception area from leftover stock.
08/31/23 – Added flooring on order. Install at end of September. Work on 9 is finishing up. a pre-punch list has been submitted to Alpha for less than satisfactory work.
09/28/23 – Alpha has not completed contract work yet. New flooring to begin on 10/3.
10/25/23 – Contract work is still not complete. Flooring has been pushed back until the space can be occupied. No firm install date scheduled.
12/07/23 – All work is complete. Minor punch list items outstanding.
01/31/24 – Closeout documents received. TEI noted there were not redline markups for as-built drawings received for this job.
02/29/24 – Punch list items complete. closeouts in review.
03/28/24 – Hardcopies from Alpha outstanding.
04/25/24 – Closeouts received.
05/30/24 – Waiting on release of liens.
06/27/24 – Closeouts still outstanding.
07/25/24 – No Update.
08/29/24 – No Update.
09/26/24 – Final pay app returned.
09/26/24 – Flooring still not great but ready to Archive.