Hamilton County Facilities

2020 – Security Camera System Upgrade

PM = Matt Butz, Mike Barth

09/26/22 – HCFD requests SOSS for the Project.  TEI Submits SOSS.
10/26/22 – TEI receives signed SOSS and PO for Project.   TEI meets with Matt Butz to discuss project.  Kick off meeting with building staff to discuss scope and project details.
12/15/22 – TEI progressing in design.  Will schedule a 75% design review with HCFD and 2020 staff after the holiday break.
01/25/23 – TEI, HCFD and HCJC meet to review project design.   TEI schedules working “Mock up” with Vicon rep on 02/01/23 so the staff at 2020 can see the views that will be provided with new system.   Design will be finalized after Mock up meeting.
02/23/23 – TEI, HCFD and HCJC meet with rep for mock up.  Camera types selected.  TEI has documents 90+% complete for issuance.  All new camera locations have the view area inserted on plans.  Upon final review with HCJC, Project will be issued for ITB.
03/29/23 – Project will be sent to purchasing on 03/31/23 for a 04/03/23 Out to bid issuance.  Prebid meeting is scheduled for 04/20/23 at 2:00 PM.  Bids will be due on 05/04/23.
04/27/23 – Project in bidding phase.  Prebid meeting was 04/20/23.   Well attended prebid.   Addendum 1 already issued.   Addendum 2 to be issued 04/28/23.
05/23/23 – Bids received for project.  (2) bids, DK and Glenwood.  Glenwood Electric Apparent low bidder.  TEI vets the bid, and recommends contract with Glenwood.  Project is in contract approval phase.  Upon contract approval and PO issuance, the project construction can commence.
06/28/23 – Project was approved at the BOCC meeting on June 15.  Glenwood recieves PO and is now working on submittals for approval.  Upon submittal approval, construction schedule will be developed and mobilization will be scheduled pending product procurement.
07/26/23 – Project construction kickoff meeting to be scheduled week of 8/7.  Construction schedule to be issued from Glenwood at kickoff meeting.
08/24/23 – Glenwood electric scheduled to mobilize to project site on 8/28/23.  Construction to commence.
09/26/23 – Construction commenced on project.   Multiple meetings with IT to discuss the network configuration.   Glenwood continuing installation of backbone of system.
10/26/23 – Construction under way.   4th Floor New Cameras are installed, as well as POD 203.  Juv Crt IT has not confirmed Network architecture.  Meeting schedule for 10/30/23 with all parties to finalize decision.
12/06/23 – Construction ongoing.  Network architecture finalized and programmed.  Glenwood has been working in non-housing areas first so that building staff can learn and get used to new VMS system.
01/31/24 – Working on floors. They have a computer in the room and are working on parallel system now, testing on two systems including the Valerus system for training.
02/28/24 – Construction continues on project.  Training occurred on 02/28/24 on site with building staff.  Ready to work on the PODs and move the residents.
03/27/24 – Work continues.  Most of exterior cameras switched over.  Close to working on 3rd floor (final housing units).   Anticipated completion in next 30-60 days.
04/24/24 – Project nearing completion of original scope.  CO cameras being installed.
05/29/24 – Glenwood has a hand full of interior cameras that remain to be installed, and then a few on the exterior.
06/26/24 – Glenwood ready for punchlist on all remaining areas. All main project cameras installed. CO cameras being installed. Demo complete and painted. Encoders being removed now.
07/24/24 – TEI and HCFD to finalize punch and issues on site in August.
08/28/24 – Glenwood has Cornerstone update the PLC system on site with new cameras to endure call ups are correct and working. TEI and HCFD will perform final walk thru once notified by Glenwood that everything complete.
09/25/24 – No Updates. Glenwood and Cornerstone working on scheduling modifications to the PLC.
12/11/24 – Glenwood notifies HCFD and TEI that PLC integration is complete. TEI and HCFD to perform final punchlist.
01/29/25 – Final punchlist completed and issued. Project complete pending closeouts.
02/26/25 – Project complete pending closeout.
04/23/25 – Project complete pending closeout.
05/28/25 – No updates.
05/29/25 – Barth has redlines, updating as-built drawings
06/25/25 – Record drawings complete. Project ready to close out.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.