Hamilton County Facilities

250 WHT – Plumbing Study

PM: John Nester, Terry Cannon
02/23/23 – Fieldwork complete. Report has been started. No dissimilar metals were found.
03/15/23 – Additional fieldwork conducted to confirm missing piping.
03/29/23 – Report is being updated.
04/25/23 – Being reviewed now and should be sent to JN before Thursday.
05/21/23 – Final Report sent this evening including final drawings.
06/28/23 – Final Report delivered in hard copy.