PM: Rycca Thacker, Sam Hofmann
02/22/23 – Bid awarded to Alpha. Contracts are in progress.
03/30/23 – Contracts still in progress.
04/27/23 – Pre-construction meeting held. Submittals incoming.
05/25/23 – Some submittals received and returned. Permit approved. Construction is almost ready to begin.
06/29/23 – Construction ready to begin 2 weeks from notice from Rycca.
07/27/23 – Construction began this week. Most submittals complete.
08/31/23 – Construction ongoing. CO#1 in progress to add minor scope. TTE responded to the plumbing change order work with comments.
09/28/23 – Construction ongoing. CO#1 settled. CO#2 has not been agreed on.
10/25/23 – Construction ongoing. Change Order #2 rejected by TTE. Alpha to rework change and send back to us. Lights have been reworked in current ceiling configuration.
12/07/23 – Work is finishing up. Punch list held on 11/27. Back punch to be scheduled.
02/01/24 – Drinking Fountain cover still not acceptable, TE to work on better cover for the plumbing.
02/29/24 – Back punch items still unresolved. Closeouts in review.
03/28/24 – Waiting on hard copies from Alpha.
04/25/24 – Closeouts received. Check to see why its so large. Three hard copies still required with a thumb drive.
05/30/24 – Waiting on release of liens. TTC repaired the water cooler cover to give it more accessibility.
06/27/24 – No Update. TTC modified the EWC wrap so it’s better than it was.
07/23/24 – TTV replaced the pipe wrap again and it looks better than “better than it was”
08/29/24 – All closeouts received. Final pay app released. Ready to archive.