525 – HVAC Retrocommissioning (No ITB)

PM: Rycca, Terry
Closeout Contact: Will Fisher wfisher@davieseg.com


02/24/26 – SOSS submitted for CX work.
03/25/26 – No updates.
04/29/26 – SOSS received last week. Internal kickoff meeting yesterday. Client kickoff meeting scheduled for Friday.
05/13/26 – DEG on site for initial fieldwork and discovery meeting.
05/20/26 – Internal meeting with Emcor & Habegger for RTU retro commissioning at 525. Commissioning is set for 5/28/ and 5/29 with Will Fisher, Emcor and Habegger.
06/25/26 – Bison currently repairing RTU-4, Triton currently upgrading economizers for RTU-2,3. Once complete CX will continue. Graphics updated to match other buildings.
07/30/26 – Bison repaired their units. Parts delayed on Triton units until 8/5. After economizers are programmed CX continues.
08/26/26 – Final parts came in yesterday and Triton is scheduled on site 8/27 to install missing parts for these units, then final commissioning will begin.
09/23/26 – DEG and Emcor met earlier this month and finalized the commissioning for this building and set final report to HC. Outstanding item are the exhaust fans in the main warehouse which are owner items to troubleshoot and repair.
10/26/26 – All work is complete the retro-commissioning is complete, final report sent to the County.