Hamilton County Facilities

[CLOSEOUT]

This category is where we will move projects in between Active Status and Archive Status.

111 – Employee Break Shelter (No ITB)

PM: Rycca, Eryn
eeagle@elevar.com;

04/30/26 – SOSS provided for CA.
05/28/26 – Awarded to Tumlin and Elevar receiving initial Div 01 submittals.
06/25/26 – No update.
07/30/26 – Submittals complete and unit moved into production planning. Contractor will provide stamped drawings soon.
08/27/26 – Contractor will provide stamped drawings soon with Elevar to follow up. Anticipated unit installation in Oct.
09/24/26 – Contractor provided stamped drawings. Anticipated unit installation in early Oct. Elevar/HCFD/GC to meet onsite prior to installation.
10/29/26 – Unit installed. Need closeout docs from GC.

111 – Employee Break Shelter (No ITB) Read More »

525 – HVAC Retrocommissioning (No ITB)

PM: Rycca, Terry
Closeout Contact: Will Fisher wfisher@davieseg.com


02/24/26 – SOSS submitted for CX work.
03/25/26 – No updates.
04/29/26 – SOSS received last week. Internal kickoff meeting yesterday. Client kickoff meeting scheduled for Friday.
05/13/26 – DEG on site for initial fieldwork and discovery meeting.
05/20/26 – Internal meeting with Emcor & Habegger for RTU retro commissioning at 525. Commissioning is set for 5/28/ and 5/29 with Will Fisher, Emcor and Habegger.
06/25/26 – Bison currently repairing RTU-4, Triton currently upgrading economizers for RTU-2,3. Once complete CX will continue. Graphics updated to match other buildings.
07/30/26 – Bison repaired their units. Parts delayed on Triton units until 8/5. After economizers are programmed CX continues.
08/26/26 – Final parts came in yesterday and Triton is scheduled on site 8/27 to install missing parts for these units, then final commissioning will begin.
09/23/26 – DEG and Emcor met earlier this month and finalized the commissioning for this building and set final report to HC. Outstanding item are the exhaust fans in the main warehouse which are owner items to troubleshoot and repair.
10/26/26 – All work is complete the retro-commissioning is complete, final report sent to the County.

525 – HVAC Retrocommissioning (No ITB) Read More »

800 – HVAC Controls Upgrade (STS)

PM: Terry Cannon, Tony Matre
Closeout: Joe Bulach, joe_bulach@emcorgroup.com, Dayna O’Brien, dobrien@davieseg.com

 


08/19/25 – Kickoff discussion with Emcor.
11/18/25 – Emcor running low voltage at the building for new DDC network.
12/09/25 – Const Mtg and meeting minutes distributed.
01/08/26 – Const Mtg. Emcor making progress on equipment in the basement and on the first floor. They need help with access to some rooms that are under HCSO control.
01/20/26 – Const Mtg and new schedule released. Emcor gearing up for Chiller plant programming in March. Joe says they will take care of the 6th floor network cable. AM reports it is still not in the right place. The switches are in place and ready.
01/21/26 – Emcor shared missing submittals with DEG on VFD’s.
02/25/26 – Work continues as Emcor is planning on working on the chiller plant in March.
03/25/26 – Work continues, chiller plant programming in progress. Emcor ready to commission when building starts the chilled water plant for the season.
04/28/26 – Const progress meeting with Emcor held with DEG, Tom and Emcor. Small progress being made on new controls. Emcor asked to start boiler plant this week, it was decided to wait because of cold weekend temperatures. Tom had issues with chiller operation, Emcor found chiller in manual and released it. Emcor did some training with Tom to show him how to use new system but Graphics are not complete yet and the chiller plant is not fully programmed yet. Emcor to work on graphics, updated chiller programs and preparing for heating plant integration.
05/25/26 – Const Meeting held adn Emcor reported they started the boiler plant upgrades and they are making good progress. The communication infrastructure is in place for the future upgrades and the 800 Tower units can be added to it.
06/25/26 – Const meeting held last Tuesday, working out graphics updates and final controls work. Tom requested training.
07/30/26 – Project nearing completion, chiller sequences being updated.
08/26/26 – Project is complete and in commissioning. PCHWP-2 has an issues that DEG will be on site troubleshooting on Thursday.
09/23/26 – DEG met onsite to review chiller operations. DEG recommends to follow DK recommendation to replace thermal overloads on PCHWP-2. Tony said that Craig could perhaps replace these since they are less than $100. That is our recommendation as well. DEG updating the PID to new conditions after replacement of CH-2.

800 – HVAC Controls Upgrade (STS) Read More »

SPHQ – Fall Protection Upgrade (F026)

PM: Matt Butz, Paul Bellman

04/01/25 – County requested SOSS for Fall Protection upgrade to the existing roof.
04/24/25 – THP to publish SOSS for review.
05/21/25 – SOSS approved.
06/25/25 – THP requesting roofing plans to start layout.
07/30/25 – THP working on DD drawings and plan to send draft to HC late next week.
08/27/25 – THP finalizing DD drawings and plan to send to HC at the end of the week.
09/24/25 – THP working towards CD drawings. Need to schedule a review meeting with HC.
10/15/25 – Documents issued for bid on 10/15/25.
10/29/25 – Pre-bid meeting held 10/27/25.
11/19/25 – THP issued summary letter to HC recommending NR Lee Restoration.
12/11/25 – HC finalizing paperwork for Contract approval.
01/14/26 – HC issued fully approved Contract to HR Lee Restoration.
01/27/26 – Preconstruction Meeting held virtual.
01/28/26 – THP issued Preconstruction Meeting Minutes.
02/19/26 – Preconstruction Meeting held On-site.
02/20/26 – THP issued Preconstruction Meeting Minutes.
03/25/26 – HR Lee is scheduled to deliver telehandler forklift 3/26 or 3/27 and material on 3/31. Work scheduled to begin shortly after.
04/08/26 – THP and HC reviewed on site substantial completion by HR Lee.
04/20/26 – HR Lee submitted Change Order for requested additional railing at small roof. THP to review with HC.
05/26/26 – HC issued signed and approved CO for additional railing. HR Lee placed order and updated schedule requested. Closeout documents in progress.
06/25/26 – THP is scheduling a final walk-thru with all parties. Closeout documents in process.
07/14/26 – On site final walk.
08/21/26 – THP sent CO #2 for requested safety line and final punch items to HR Lee for signature. Signed CO#2 returned to HC.
09/22/26 – On site review of final punch list items. HR Lee to schedule remaining work by next week.
10/08/26 – HR Lee completed final punch list items and THP and HC reviewed and approved.
10/15/26 – HR Lee submitted final closeout docs.
10/29/26 – HR Lee submitted paint touch up procedures from manufacturer for warranty work and would like to schedule paint touch up of bases.

SPHQ – Fall Protection Upgrade (F026) Read More »

Central – Office Consolidation Phase 1 & 2

PM: Bert, Mike M, Terry, John Millar
05/30/24 – ThermalTech submitted SOSS to Champlin for SD & Cost.
05/31/24 – Champlin sends TTE background material to start working on this project.
06/26/24 – Design Meeting started, Champlin sent agenda and latest drawings.
07/02/24 – Board Presentation Day.
07/10/24 – Fieldwork at site.
07/17/24 – Fourth Floor layout sent from Champlin to TTE.
07/25/24 – JFS Computer Room fieldwork setup for TTE.
07/31/24 – Bond Hill Due Diligence SOSS request sent.
08/01/24 – SD & Cost sent to Hamilton County for this project.
08/21/24 – Due Diligence SOSS questions came back from Champlin. Be ready to move on due diligence quickly if approved.
09/19/24 – THP update – Champlin/County request THP provide building envelope and garage restoration due diligence assessments.
09/26/24 – Due Diligence kicked off. Architectural, MEP and environmental site visits complete. Survey happening today. Structural and civil scheduled.
10/02/24 – Due Diligence – THP update – THP published proposal to Champlin.
10/03/24 – THP update – Champlin/County request THP provide structural footing design for the garden fencing as part of the larger project.
10/07/24 – Due Diligence – THP update – THP field teams completed building envelope and garage surveys.
10/10/24 – Due Diligence – THP update – THP completed roof thermal scans.
10/11/24 – THP update – THP published proposal to Champlin.
10/23/24 – Met onsite with Facilities, Environmental Services, Ameresco and ThermalTech on Netzero energy opportunities.
10/25/24 – Due Diligence – THP update – THP published building envelope and parking garage due diligence assessment to Champlin.
10/31/24 – Due Diligence draft submitted to county. SOSS for DD-CA submitted. DD review meetings have begun. Documentation ongoing.
12/12/24 – DD to be submitted for review on 12/23. Estimate to be submitted 1/6. Meetings ongoing.
12/23/24 – THP update – THP issued DD fence and moveable wall structural details.
01/27/25 – ThermalTech finalizing fieldwork at the site to continue design for HVAC, Plumbing, Electric, and Fire Protection beyond the DD phase into CD. We have received the server survey from Telecomm and have updated our calculations for each IDF and MDF room, we hope to have floor plans updated by end of this week with proposed rack locations and HVAC needs. We are on pace to make the CD deadline of February 28, 2025.
01/30/25 – Final meetings with each department ongoing. CD’s being developed. Bid review set to be submitted for review on 2/21.
02/27/25 – Review set submitted to county. Tentative bid issuance date is 3/6. DDS has been removed from bid package to be issued as a separate project.
03/27/25 – Drawings are ready for bid. Updated Estimate to be submitted this week.
04/24/25 – Bid phase ongoing. Pre-bid had light attendance. Bids open May 23.
05/29/25 – Graybach is apparent low. Bid vet to be scheduled when bid is determined acceptable.
06/26/25 – Bid vetting in process. A305s provided to county for consideration.
07/31/25 – Graybach will be awarded the bid. bid vet meeting held. contract has been signed and will be going in front of the board next week. Const meetings start week of August 11.4
08/28/25 – Graybach has mobilized and began demolition. Furniture move services bid issuance on 8/26. RFI received on plumbing and HVAC are being answered as they come in. We have officially access controls, but it has been resubmitted as individual components and AV cable, fiber and Cat6 is approved. Now we need to discuss what to do about the security camera system. We reinforced with the field foreman that we are pulling every cable back to the IDF rooms so it landed by floor. TTE to send IDF coordinate drawings to John for ordering and coordination ASAP.
09/23/25 – TTE met with DK yesterday on proposed HVAC changes at Bond Hill. DK has already performed all the work on the first floor, we negotiated changes and discuss field engineering changes methodology with Dustin and Dave. We agree on the material cost but feel strongly that the labor is more than what is needed to make the requested changes (as it was estimate at three additional men for one month). TTE suggested that this change order is enough to cover not only the 1, 2, 3 floors, but the entire building.
10/02/25 – THP – Champlin requested field support for cutting holes in precast panels.
10/23/25 – THP – after site trips and coordination with Champlin, THP issued field sketch for precast hole support.
12/11/25 – Graybach still confident they will get done by mid January with TCO in mid January for Phase 2. TCO expected next week for Phase 1 as most inspections are done for the TCO work. Design team still issuing Bulletins for changes for GC, EC, and low voltage. AT A&D they are getting ready to move to the new building. HC has weekly move meetings for coordination, Veteran Services move being coordinated. Osterman working with HC and Graybach coordinate move items. HC seeking additional funding for extra asks at the building and the low voltage items.
01/28/26 – Punch walk through completed. Exit sign issue has been solved.
02/26/26 – JFS has moved in to the first 3 floors. minor punch work ongoing. Floors 4 and 5 are ongoing. DDS awarded to Triton. Demo is complete for DDS.
03/26/26 – Floors 4 and 5 in progress. Punch tentatively scheduled for 3 weeks from now. Furniture scheduled to be compete 5/1. DDS portion is ongoing.
04/30/26 – Project to be complete in 2 weeks. Punch scheduled for next week. Move in mid may.
05/28/26 – Punch work nearly complete on 1, 2, & 3. Punch walk through on 4 & 5 minus DDS happened last week. Everyone (minus DDS) should be moved in by end of next week.
10/29/26 – Closeouts ongoing.

Central – Office Consolidation Phase 1 & 2 Read More »

EMA – Tornado Siren Conditions Assessment (No ITB)

PM: Matt/Trades, Terry Cannon
Closeout: Terry Cannon, tcannon@davieseg.com


06/25/24 – Proposal from ANS sent to Bert Watts for review.
07/24/24 – Submitted for 2025 budget. County may know in Q4 about viability.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold.
01/17/25 – SOSS Requested.
02/26/25 – Kickoff meeting on hold while TEI researches additional technologies.
03/19/25 – Preliminary conditions meeting held with EMA on SOSS modifications. TTC submitted revised SOSS with additional scope same day.
04/23/25 – MCP sent a very high proposal in to assist on this project. TTC to follow up with Nester on next steps.
05/28/25 – TTE release PO to ANS for Siren Assessment, scheduling the first kickoff meeting June 30 or July 2, this request out to Mike D at ANS. ANS says they will need about 45 days to perform the onsite analysis. MCP quote came back very high, looking for other specialist contractors to assist with assessment.
06/25/25 – ANS cannot make the July 2 date, TTC to pick another date.
07/18/25 – Kickoff meeting held at 525 with ANS and EMA. Project set to kickoff August 4.
07/27/25 – Nick commented that third party vendor not required for future recommendations of system and we can concentrate on the siren conditions first.
07/30/25 – Additional scheduling taking place, project set to kickoff August 11 onsite at Siren #414. EMA, TEI, HCDF and ANS.
08/28/25 – ANS has made two deployments to the County so far. Zone 4 was completed the first week of August. Zone 5 was addressed this week. We are not sure how far ANS will get this week but shadowing ANS, each siren was about one hours to 90 minutes of work with travel. We have questions out for what constitutes a FAILED siren, especially in regard to test 3.1.4 on the Audit worksheet. The Siren Tracking sheet was created and updated and implemented by ThermalTech and put to use in the OneDrive. The OneDrive folder is available for use on this project. We are on schedule for targeted completion.
09/24/25 – Vendor meetings continue. Zone 6 is complete. 26 audits have been uploaded, no failures for this group. Several sirens were skipped for access and traffic control. Joe is in town for Zone 1&2 at this time.
10/29/25 – ANS has completed their initial visit to all sites in all zones. ANS returning November 3 for Traffic Control sites. The traffic control sites and daily order was released today to all team members. Friday November 7 is a backup day to pick up remaining sites. Facilities has followed behind ANS nicely fixing and putting UNSAT sirens back into service.
12/12/25 – Traffic Control and Access impeded sites have been visited. DEG checks with ANS every day for final audits. We have received 8 of the final 37. TTC must submit 25% Draft Report by Friday.
12/31/25 – Draft report sent to Hamilton County Facilities & EMA for review.
01/12/26 – Received final 17 Audit reports from ANS and incorporated them into the report.
01/15/26 – Reviewed report with EMA and tabulated all siren conditions from ANS and presented these numbers to EMA as well.
01/25/26 – Updated report being sent to the EMA this week for second around of reviews.
02/25/26 – Rev-5 sent to the EMA for comment. This version includes the Acoustic Model from ASC. No comments received from Rev-4 yet.
03/25/26 – No comments received yet.
04/16/26 – Met with the EMA on comments on the report. They are extensive comments. DEG will begin working through the changed.
04/27/26 – DEG continues working on report updates. We’ve gotten though some of the proposed cost changes, most of the editing is complete, inventory changes picked up and now TTC has to contact Federal Signal and get their information for the report.
05/21/26 – Met with EMA and Facilities and sent back next revision of report to EMA for approval and review.
06/25/26 – TTC checked back with Morgan on comments or progress, no update yet.
07/30/26 – No updates on markups to final report.
08/26/26 – No updates, saw Nick at Sharonville Life Safety event, he didn’t mention.
09/23/26 – No updates but we are starting two siren relocations with Ben, Keith, and Zach.
10/26/26 – Waiting on next review meeting with EMA. Project is in closeout.

EMA – Tornado Siren Conditions Assessment (No ITB) Read More »

JC – Selective Cell Door Replacement 2024 (Ph. 4)

PM: Matt Butz, Sam Hofmann
03/28/24 – SOSS received. Sheriffs to locate doors included in this project.
04/25/24 – No update.
05/30/24 – Sheriffs provided doors to be included. Work in progress.
06/27/24 – Work in progress.
07/25/24 – No Update.
08/29/24 – Owner review set submitted. project to be bid in next couple weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Cornerstone is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project in contract phase.
01/30/25 – Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff scheduled for 3/31.
04/24/25 – No Update.
05/29/25 – Submittals received.
06/26/25 – Submittals to be returned and a schedule provided by Cornerstone.
07/31/25 – Submittals returned. Cornerstone to schedule mobilization.
08/28/25 – No update.
09/25/25 – No update.
10/30/25 – Cornerstone to mobilize Monday to finish phase 3 work and begin phase 4.
12/11/25 – Phase 1 complete. Moving to phase 2 after the new year.
01/28/26 – Project ongoing.
02/26/26 – Project is ongoing. 2 pods left until completion.
03/26/26 – Project ongoing. second to last phase has been started. Final phase to pause for 1 month until Triton completes phase 2 work.
04/30/26 – No update.
05/28/26 – Cornerstone to complete this project after tritons project is complete.
06/25/26 – No update.
07/30/26 – Final pod is ongoing.
08/28/26 – Work is complete. Closeouts in progress.
09/24/26 – No update

JC – Selective Cell Door Replacement 2024 (Ph. 4) Read More »

JC – Lobby Ceiling Replacements

PM: Matt Butz, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Field verification complete. Project in progress. ThermalTech has been onsite and updated mechanical drawings for the potential future pans. Sam to setup kickoff project for this job.
06/27/24 – Kickoff to be scheduled in near future. BW asked to add the North Bldg Lobby to be added as an Alternate to this job, lower ceilings etc.
07/25/24 – Meeting held to discuss scope. Field visit to North building will take place soon. Bid set will be ready for owner review by end of August.
08/29/24 – Owner review set submitted. Project will be issued for bid in the next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Triton is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project is in contract phase.
01/30/25 – Contract is still in process. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract finalized. Kickoff to be scheduled in near future.
03/27/25 – Kickoff held. Submittals in progress.
04/24/25 – Submittals still in progress.
05/29/25 – No update.
06/26/25 – No Update.
07/31/25 – Submittals returned. Triton to schedule mobilization.
08/28/25 – Pre-mobilization meeting to be scheduled. Duration schedule received.
09/25/25 – Background checks approved. Triton mobilized this week. Demo to begin next week.
10/30/25 – Demo complete in both buildings. Installation has started.
12/11/25 – Plumbing and drain pan rework saved cost and simplified the system. Ceiling grid and pads to begin in North Lobby next week.
01/25/26 – Diffuser RFI answered earlier this month, should be an easy install. DEG reminded the county that they were working on Geiler replacing bad p-traps at ceiling before new ceilings are going back in. Fire dampers accessible only through this ceiling should be getting done by NKYHC (see Tony).
01/28/26 – North Building insulation tested for asbestos and came back negative. Triton providing pricing for insulation and mastic removal.
02/26/26 – CO#1 approved to remove insulation and mastic. Work is ongoing. Scheduled to be complete March 5th. Fire damper work is complete. Plumbing repairs being finalized. Fire alarm worker can use Triton lift to facilitate progress.
03/26/26 – Ceiling installation ongoing. CO Trap work to begin next week. Project tentatively to be complete mid april.
04/30/26 – Electric sub never got plan review approval. Issue has been resolved and inspections can be scheduled. Once inspections are passed, padding out ceilings will be final step.
05/28/26 – Final inspection passed. OKI to be on site for pad installation this week. Punch to be scheduled week of 6/8.
06/25/26 – Punch complete and final work to be complete this week.
07/30/26 – Punch work complete. Closeouts ongoing.
08/28/26 – Back punch complete. Closeouts received.
10/29/26 – No Update.

JC – Lobby Ceiling Replacements Read More »

TPC – Reentry Expansion

PM: John Nester, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in. We need the PO by mid-November and the project must be complete by 11/1/25, they are moving out of the lease space.
05/30/24 – Kickoff held with Thermaltech, County, Reentry and Champlin. Some minor redesign will be explored.
06/27/24 – New options will be provided to Trina this week.
07/25/24 – New options presented. Final plan confirmed. CDs in progress. Owner review scheduled for 8/14.
08/29/24 – Final owner review meeting held. Project will be issued for bid in next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 9/30.
10/31/24 – Triton is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project is in contract phase.
01/30/25 – Contract still in process. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract finalized. Kick off to be scheduled.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Submittals in progress. Kickoff meeting scheduled for next Wednesday.
06/26/25 – Demo for Phase 1 in progress.
07/31/25 – Demo complete for Phase 1. Re-entry to move to 4th floor space to give Triton full access to project area.
08/28/25 – Phase 2 demo is complete. Triton met with County and Champlin to discuss change orders. Adjusted COs provided. HC reported today that they would like to Triton to be completed in October 2025.
09/25/25 – Project on schedule to finish end of October. All change orders settled. Work continues.
10/30/25 – Project nearing completion. Furniture delivered to site. Triton will most likely get TCO approval early next week. Fire sprinklers are being added in a couple of pockets. We are keeping the window washing sprinklers heads as-is but Preferred will have to update their permit drawings after the TCO is approved.
12/11/25 – Fire protection work took longer than expected. Inspection to be scheduled for next week. Final CO expected before Christmas.
01/28/26 – Inspector will not provide CO until the exterior stair door is fixed. Trades is fixing the door starting on 2/2. Bulletin 2 for window shades and power issued and waiting pricing.
02/26/26 – Bulletin 1 pricing received. Work outstanding.
03/26/26 – Bulletin #2 pricing has been received and approved. Triton to begin electrical work.
04/30/26 – Blinds installation outstanding. All other work complete.
05/28/26 – Closeouts received and returned. Triton to submit outstanding items.
06/25/26 – No update.
07/30/26 – Hardcopies to be delivered to County.
08/28/26 – Hardcopies delivered. Access control programming complete.
10/29/26 – No update.

TPC – Reentry Expansion Read More »

CH – Law Library Stained Glass Window Repair

PM: Megan, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Initial field verification complete. We will need a second trip to take dimensions.
06/27/24 – Second trip complete. CDs in progress.
07/25/24 – No Update.
08/29/24 – Owner review set submitted. Project will be issued for bid in next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 9/30. ITB sent to multiple stained glass vendors.
10/31/24 – Bids received. One vendor had a bond issue, one bidder did not fill out XBE paperwork properly. Purchasing to provide direction.
12/12/24 – Project is in contract phase.
01/30/25 – Contract is still in progress. Kickoff to be scheduled in near future.
02/27/25 – Contract Finalized. Kickoff to be scheduled.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Phase 1 windows are removed and taken back to the shop for refurbishment.
06/26/25 – Progress meeting at the shop scheduled for mid July.
07/31/25 – Windows still in progress.
08/28/25 – Phase 1 windows to be reinstalled in september. Phase 2 windows will be removed during the same time. Tentive completion date of end of october.
09/25/25 – Reinstallation of phase 1 began this week. Removal of phase 2 in progress.
10/30/25 – All storm windows have been installed. Stain glass installation of phase 1 to begin shortly. Phase 2 to be complete by end of november. County to request change order related to the plaster repair at window jambs.
12/11/25 – One section of stained glass installed. Second half of windows are still under repair. Background checks for installers have been over 90 days. County allowed stain glass to be reinstalled all at once when phase 2 windows are ready.
01/28/26 – No update.
02/26/26 – No update.
03/26/26 – Breilmeyer to mobilize this week. Installing half of glass and taking the other half to their shop.
04/30/26 – Half of stained glass is installed. Tentative completion at end of may.
05/28/26 – Breilmeyer to mobilize 6/8 to install the second half of the glass.
06/25/26 – Second half install ongoing.
08/28/26 – Installation complete. 1 punch item outstanding.
09/24/26 – No Update.
10/29/26 – Punch item complete. closeouts outstanding

CH – Law Library Stained Glass Window Repair Read More »

SPHQ – Arc Flash Remediation 2024

PM = Matt, Barth

04/24/24 – TEI submits SOSS for approval.
05/29/24 – Project Pending SOSS approval.
06/26/24 – TEI receives signed SOSS and PO.  TEI has conversed with building manager re existing system and electrical needs.
07/24/24 – Project in progress.
08/28/24 – TEI to meet with building manager to discuss updated model and options.
09/25/24 – TEI meets on site with building manage and Matt Butz. A list of possible upgrades developed. TEI sends schematic dwg and costs to HCFD for review and direction.
10/30/24 – TEI issues project for bidding. Prebid meeting scheduled for 11/12/24 at 11:00 AM.
12/11/24 – Bids open at 11:00 AM on 12/12/24.
01/29/25 – No bids received. HCFD to advise if re-bid funds are available.
02/26/25 – No updates on rebid funding.
03/26/25 – No updates on rebid funding.
04/23/25 – No updates on rebid funding.
05/28/25 – No updates
06/25/25 – No updates
07/30/25 – No updates on rebid funding.
08/27/25 – No updates on rebid funding
09/24/25 – Project pushed to 2026 project.
01/28/26 – DEG to submit SOSS for re-package and rebid for 2026 project.
02/25/26 – DEG submits SOSS for approval.
03/25/26 – Project pending approval of SOSS
04/29/26 – DEG receives signed SOSS and PO. Reaching out to bldg mgr to confirm scope.
05/27/26 – DEG meets with Ian Zellner – confirms scope. Finalizing drawings and OPC for HCFD review.
06/23/26 – DEG to submit 100% review set to HCFD by end of June.
07/29/26 – Per HCFD – Project on HOLD until further notice.
08/26/26 – DEG to update labels and apply then close out the project.
09/23/26 – No updates
10/28/26 – All labels have been applied to the gear on site. Project complete.

SPHQ – Arc Flash Remediation 2024 Read More »

JC – Fire Pump Replacement (085-24)

PM: Matt, Terry Cannon
Closeout: Haeli Johnson, hjohnson@tritonservicesinc.com, Dayna O’Brien, dobrien@davieseg.com

 


01/24/24 – Post created for tracking.
02/01/24 – TE to submit SOSS for this project.
02/23/24 – Coty will be working on this job.
03/22/24 – Initial fieldwork started this week. SOSS submitted. Electrical review scheduled for next week to ensure fire pump feeders meet current code. Life safety code updates may apply to this upgrade.
04/08/23 – Met with our electrical group this week to discuss the power feeders to the fire pump. We decided the best course of action that saves the County the most money is to let the Emergency Power project go first and update the MCC disconnects to isolate the fire pump disconnect in its tub so that it meets current code. Once that work is complete, we can bid out the replacement of the fire pump with out running into issues with the new NEC requirements for feeders in concrete or the fire pump being fed first before ancillary equipment.
04/24/24 – The preliminary drawings are ready for TTC review.
05/29/24 – TTC marked up drawings for owner review. TEI working with Fire Marshal on component required for replacement versus new NFPA code. This has to be bid this year even though it will be installed after the Emergency Gen update.
06/26/24 – Final drawings are ready for review, changes have been made from our field trip with Andy earlier this month. CFD not willing to provide pumper truck for weekend, we are checking on rental fire pumps and fire watch. SA believes a fire watch can be used.
07/24/24 – We were waiting on the JC Emergency project to be awarded so we could move forward with bidding our design out. The FPC will provide the fire watch as needed to make these piping changes and replace the pump vs using the CFD. I have not seen any CFD response in writing to our design request.
08/28/24 – Final internal review scheduled Friday.
09/24/24 – Project is out for bid. Prebid scheduled for Oct 8 at 9am. Bid Opening is Oct 30.
10/30/24 – Bids opened with four bids under budget, two of which were non-awardable due to a bond issue. TTE to interview KFI on Friday for compliance to bid specs.
12/12/24 – Triton was the low bidder via the base bid and Alternates accepted, we await the contract and PO to have the kickoff meeting.
01/30/25 – Contract going to commissioners tomorrow for approval.
02/26/25 – Contract is back, we are setting up Pre-Const meeting.
03/25/25 – Pre Const meeting was held and meeting notes distributed. Schedule, SOV, and equipment submittals have been requested.
04/23/25 – Construction Meetings started. Stamped permit drawings have been sent to Triton for submissions. Submittals have been requested. Other project startup documents have been requested.
05/28/25 – ThermalTech received written direction on suction valve controller which is not required on this replacement as long as we have the low suction cutoff report as a supervisory back to the FACP. We are approving the Fire Pump Controllers and rejecting the Fire Pump and Jockey pump due to under sizing and rotation issues.
06/25/25 – Equipment ordered and waiting on equipment delivery. The latest ship date is September 18, 2025.
07/30/25 – Pump submittals are finally approved. Bulletin #1 drawings sent for pricing to fix test header.
08/28/25 – Latest update is that the fire pump will arrive 9/19. Triton to coordinate replacement with Owner.
09/24/25 – Work being scheduled now including fire watch requirements.
10/29/25 – The fire pump has arrived. The test header was repaired by SA Comunale, now the wall and patching work needs to be completed. A new test ring needs to be installed on the outside FDC. Quality Fire has two people badged, checking on TJ Williams badged contractors. We need to iron out Fire Watch details with Triton.
12/12/25 – Triton and Quality ready to begin the project. Final fire watch details being negotiated. Inspection test header has been repaired, outdoor placard spacing is loose.
12/22/25 – Construction meeting held, we are working out details of shutdown, fire watch and submittal approvals.
01/12/26 – Const Mtg, finalizing shutdown details, fire watch, and schedule for work. Fire Watch must be provided by Triton for non-secure areas, DEG to issue drawings for scope. Electrical shutdown may require Courthouse to provide steam for Justice Center based on weather.
01/21/25 – Adding additional details and scope to the shutdown and next phase of work. USPA does not have background checks complete for fire watch yet. Electrical changes submitted to IBI. Feb 3 will be electrical emergency crossover and Feb 10 will be the primary crossover. Pump replacement scheduled for Feb 23.
02/25/26 – Emergency power is connected. Normal power has become a power struggle between Duke and IBI and DEG is working through those requirements and obstacles with both parties. the pump install will be coordinated after the power requirements are resolved.
03/25/26 – Normal & Emergency power are connected and ready to go. CFD required paperwork submitted & 3 of 4 FDC did not pass inspection. March 23rd replacement rescheduled until FDC are repaired. SA coming in on Friday to begin repairs and assessment.
04/29/26 – 3 of 4 of the FDC are repaired. The fourth FDC is currently under repair but SA is having trouble sourcing an access panel for the wall opening. TTC asked to open the wall now and repair the FDC which should only take a day, temporarily install a wall covering to keep the fire pump job moving along. The fire pump is currently scheduled to be replaced May 18-22.
05/18/26 – Replacement started on the fire pump today. Triton and DEG providing 24/7 fire watch.
05/19/26 – Repairs and fire watch continues.
05/20/26 – Repairs and fire watch continues. 99% of electrical and mechanical work is complete. Corporate equipment pre-inspected the fire pump installation and it passed. We are trying to move up final inspection to Thursday at 1:00PM.
05/21/26 – Replacement complete. Fire pump tested at 1:00PM with full water test, manual and automatic starts with City of Cincinnati and Cincinnati Fire Department in attendance. All system passed, the new fire pump was put online about 4:00PM and the fire watch was completed.
05/27/26 – DEG provided the punchlist for the project and will distribute later this week.
06/25/26 – Project in closeout.
07/30/26 – Working on latest change orders for this project. COR-1.
08/26/26 – Change Order #2 in the works? Working on other closeout documents.
09/23/26 – Change Order #2 COR #1 data all updated and sent in for approval to County.
10/26/26 – Final change order approved and signed the project is in closeout. TTC reached out to Triton to get all closeout documents by 10/31.

JC – Fire Pump Replacement (085-24) Read More »

JC – LC Server Rack Upgrades 2023

PM = Matt Butz, Mike Barth
12/06/23 – TEI receives approved SOSS.  Project kick off meeting to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet on 01/30 to discuss project objectives and kick off the project.  Network switches for the Kiosks and Camera systems shall be put in a lockable rack that will prevent local CO’s from tampering with them.   The outlets that serve the overhead rack and the floor mounted Telecor Intercom racks will have lockable covers over them such that they can not be unplugged.
02/28/24 – Project is ongoing.
03/27/24 – Project is ongoing with documentation.
04/24/24 – Review set to be sent to HCFD upon completion.
05/29/24 – no updates
06/26/24  –  TEI selects lockable racks.  TEI recommends racks with solid doors (versus glass doors), but the glass doors are slightly less costly.  ($100-$150 per rack).
07/24/24 – TEI to deliver review set to HCFD end of week of 08/05.
08/28/24 – TEI submits documents to HCFD for review and comments. Project will be issued for bidding upon receipt of comments.
12/11/24 – HCFD and TEI meets with HCFD to review documents. Final comments to be incorporated and project issued for bidding first of year.
01/29/25 – Small projects bid to be issued on 01/31/25
02/26/25 – Project in bidding phase.
03/26/25 – Received (2) bids. Dunn Electric and DK. Dunn apparent low bidder. TEI vets Dunn bid.
04/23/25 – Project in contract phase with prosecutors office.
05/28/25 – Project in contract phase.
06/25/25 – Project in contract phase.
07/30/25 – Const KO to be scheduled with Dunn and HCFD.
08/27/25 – HCFD, HCSO and DEG have const kick off with Dunn Electric. Materials roughly a month out.
09/24/25 – DEG approves submittals. Dunn Electric orders equipment. Dunn sends an email to DEG re equipment cost increase from bid time.
12/10/25 – All LC racks are installed, except G22. Ceiling by rack needs to be raised for the proper NEC clearances for the existing solenoid panels.
01/28/26 – Waiting for HCSO to move their equipment to move ceiling to wrap up the G22.
02/25/26 – Waiting for HCSO to move their equipment to move ceiling to wrap up the G22.
03/25/26 – Triton on site moving ceiling 03/25. Dunn to install new enclosed rack upon completion of ceiling work.
04/29/26 – All work completed. Punchlist completed. Contractor to submit closeouts.
07/29/26 – Project in closeout. DEG discusses with EC closeout docs needed.
08/26/26 – no updates.
09/23/26 – Project complete – pending closeouts.

JC – LC Server Rack Upgrades 2023 Read More »

JC – Selective Cell Door Replacement 2023 (Ph 3 Cornerstone)

PM: Matt Butz, Sam Hofmann
02/22/23 – SOSS received. Kickoff to be scheduled soon.
03/30/23 – Kickoff held on site. Sheriffs chose 7 doors for base bid and another 4 as an alternate. They will provide a few more doors to be added into the scope as alternates.
04/27/23 – Still waiting on additional doors from sheriffs.
05/25/23 – No update.
06/29/23 – List of doors and alternates has been provided. Drawings can be complete by end of month.
07/27/23 – Drawings will be complete by end of August.
08/31/23 – Drawings will be complete by end of September.
09/28/23 – Meeting held with Captain Wilson to confirm scope. Project will be out to bid 10/10.
10/25/23 – Project is out to bid.
12/07/23 – Bids returned. Cornerstone is lowest bidder. Bid review meeting held 12/5. Project now in contract phase.
02/29/24 – Cornerstone to send submittals in near future.
03/28/24 – Still waiting on submittals from Cornerstone.
04/25/24 – No Update.
05/30/24 – Submittals received and returned.
06/27/24 – Cornerstone field verification completed this week. Doors to be ordered.
08/29/24 – No Update.
09/26/24 – Cornerstone placed order. Pre-con meeting to be scheduled in near future.
10/31/24 – No Update.
12/12/24 – Cornerstone has material in hand. Coordinating best time with sheriffs and ongoing lock project work.
01/30/25 – Work to be scheduled in line with lock project corrections.
02/27/25 – No update.
03/27/25 – No Update.
04/24/25 – First Pod began. All frames installed but doors did not fit. New doors shipped immediately to finish the first pod. The rest of the doors will ship end of May.
05/29/25 – Pod complete and back punched. Next pod to begin next week.
06/26/25 – Next phase punch scheduled for tomorrow. Final phase to begin in 3 weeks.
07/31/25 – Next set of frames and Phase 4 frames to be manufactured together. 12 week lead time for delivery.
08/28/25 – Frames to be delivered mid september.
09/25/25 – Frames will be delivered next week.
10/30/25 – Cornerstone to remobilize monday.
12/11/25 – Phase 2, 3 and 4 have effectively merged into one project. All material is on site. Scope has been scheduled per unit with phase 2 and 4.
01/28/26 – Work Complete. Closeouts outstanding.
02/26/26 – No update.
03/26/26 – No update.
04/30/26 – No update.
05/28/26 – No update.
06/25/26 – No update.
07/30/26 – Closeouts reviewed and missing items requested.
08/28/26 – No update.
09/24/26 – No update.
10/29/26 – No update.

JC – Selective Cell Door Replacement 2023 (Ph 3 Cornerstone) Read More »

525 – EMA/JFS/513 Office Renovations

PM: Bert Watts, Mike Murphy, Paul Bellman, Terry Cannon

01/25/23 – SD and Cost complete.  Created new category and started tracking EMA renovation.  CD documents have been started.  THP and TTE starting overhead door early project.  BW sent information for design.
02/22/23 – User meetings complete. DD in progress from user meeting changes.
03/30/23 – Met with JFS last week. Need to get approval on design from users.
04/27/23 – Meeting on site with JFS scheduled for 5/5. Design development to proceed after that. Update old estimate with new cost for revised design. Cost is due in two weeks. Champlin to send revised plans. Include owner required items in the new cost including blue brick screen wall that is coming down, new sidewalk, plus other owner items.
05/11/23 – Champlin requested updated opinion of probable cost with updated scope of work.
05/17/23 – THP provided updated opinion of probable costs for structural scope of work.
05/17/23 – THP provided SOSS for DD through CA services based on new scope of structural work.
05/21/23 – ThermalTech DD cost updated in Archibus and shared with the team. Drawings are being updated this week.
05/25/23 – Drawings and estimate have been uploaded to Archibus. Landlord improvements have been marked with a (C).
06/12/23 – THP – Champlin returned executed Contract for DD-CA Services.
06/29/23 – No updates from THP.
06/29/23 – Final plans have been approved by users. follow up information to be provided to County this week. CDs in progress.
07/27/23 – 95% Review set submitted to County. Page turn with users to be scheduled.
08/09/23 – THP updated structural work and fees to the Archibus project estimate.
08/31/23 – Updated department breakdown plans and estimate. User page turn to be scheduled in near future.
09/27/23 – THP waiting to hear from Champlin about the page turn meeting with Hamilton County.
09/28/23 – Review meeting held with EMA. minor changes to plans made. JFS and 513 meetings to be scheduled.
10/25/23 – THP sending bid set to Champlin. Meetings held with all users. Final owner review sent to County for landlord approval.
11/22/23 – Building owner has approved the Phase 2 renovation plans. THP to send Bid Set to Champlin once bid date has been set.
12/06/23 – THP to send Bid Set to Champlin for 12/15/23 issuance.
12/07/23 – Received final approval from landlord and County. Bid issuance on 12/15.
01/04/24 – Project advertised to Bid.
01/18/24 – Pre-bid meeting on site.
01/25/24 – Addendum #1 issued.
01/29/24 – THP sent stamped permit set to Champlin.
02/07/24 – THP Addendum #2 issued. Unit prices and details for CMU tuckpointing and CMU replacement were included.
02/22/24 – THP – Bid Opening. 4 bids received (Alpha Construction, John P. Tumlin & Sons, Leo J. Brielmaier, and Triton Services). Champlin to evaluate bids.
03/28/24 – Contract phase ongoing.
04/19/24 – THP – Approved construction contract approved by the Board of County Commissioners and sent to project team.
04/23/24 – THP – County issued PO for the project to the team. Pre-construction meeting tentatively scheduled for 05/03/24 afternoon.
04/25/24 – Contracts finalized. Project kickoff tentatively scheduled for 5/3.
05/03/24 – Pre-construction meeting with full team at project site.
05/30/24 – Kickoff held. Submittals in progress.
06/27/24 – Pre-mobilization meeting scheduled for 7/12. RTU submittals have been rejected, TEI trying to get submittals on approved manufacturers.
07/12/24 – THP reviewed front entry slab drainage issue with Hamilton County.
07/12/24 – Pre-mobilization meeting with full team at project site.
07/25/24 – Construction to begin Monday.
08/28/24 – THP returned structural shop drawings to Champlin.
08/29/24 – Construction ongoing. More abatement to be completed next week. Demo almost complete.
09/26/24 – Construction ongoing. Main sewer line underslab is damaged beyond use. Tumlin to report on extent of damage. CO2 is being discussed and finalized. THP will return approved Masonry Lintel shop drawings to Champlin on 9/26. Water test is complete and Fire Protection calculation underway.
10/29/24 – THP responded to Champlin regarding Masonry repairs. Hamilton County to determine extent of repairs.
10/31/24 – Construction ongoing. Change order 2 and 3 approved for sanitary line work and fire protection changes.
12/06/24 – THP visited the site to coordinate supplemental steel with Thermal Tech and Tumlin to help with the response to RFI 23. THP issued a field report for review by Thermal Tech.
12/12/24 – Work ongoing. Forest Park has provided report stating that any combustible material will need to be removed. We believe the wood studs would be grandfathered in compliance. Champlin to investigate.
01/27/25 – Work progressing, Tumlin stated they would be complete at the end of February. ThermalTech (TTC) trying to schedule a coordination meeting between Emcor, Bison, and KW about final controls scope between project and state term work. Rooftop units not onsite yet but should be arriving soon. Plumbing rough-in mostly complete. Forest part has approved our fire protection permit and Preferred Fire should mobilize soon to the site for sprinkler work. According to Tumlin, we will not have to move all the trucks parked in the warehouse for the sprinkler work (all sprinklers in the Northeast Warehouse must be replaced with 11.2 sprinkler head).
02/26/25 – Work continues in space. GC, MC, EC, FPC are all on site performing work daily. PC coming back soon when the fixtures will be installed. TTE bringing Wi-Fi plan to Friday meeting. Several COR have come in this week, HC asked for the Fire Pit cost too, the permit needs to be amended for the additional inspection. We will get a scheduled update this Friday.
03/11/25 – HVAC Engineering Change drawing sent to Tumlin for their submission to FP for the return air openings on the first floor.
03/23/25 – TTE returned another set of controls submittals to Emcor for the ALC controls. Bison has not confirmed if we can get BACnet thermostats or now. ALC planning on interfacing through the SystemVu controllers in the RTU units.
03/25/25 – Plumbing Engineering change drawing set to Tumlin to give to Carrigan to give to FP for the natural gas adjudication letter received last week. ThermalTech continues to answer questions from the contractors working towards permit approvals.
03/27/25 – Pricing for Bulletin#3 received. Substantial completion date set at May 9th.
04/24/25 – RTUs delivered a month ahead of schedule and have been installed. Fire pit work ongoing. Railings will not be delivered and installed before May 9. Signage quote approved.
05/19/25 – THP visited the site to review supplemental steel.
05/29/25 – Punch list sent last week. Railing scheduled for delivery this week. Tumlin to schedule final inspection. Signage to begin install tomorrow.
06/24/25 – ThermalTech onsite this week working on HVAC issues. We are scheduled to come back for troubleshooting with MC and CC Friday at 7am. Emcor video was sent out from Ben.
06/25/25 – Final inspection complete. CO will be signed when Rafic returns. Ribbon cutting tomorrow.
07/31/25 – Ribbon cutting ceremony held. Several punch items still outstanding. Tumlin to begin closeouts. As-Builts not received yet. Emcor controls out this week for finalizing the new DDC controls..
08/28/25 – Tumlin confirmed all work is complete. Back puch to be scheduled. Closeouts outstanding.
09/25/25 – Backpunch complete. As-builts received. closeouts outstanding.
10/30/25 – Closeouts outstanding. Official CO received.
12/11/25 – No update.
01/28/26 – Closeouts in review.
02/26/26 – Waiting on closeout corrections.
03/26/26 – No update.
04/30/26 – No update.
05/28/26 – No update.
08/28/26 – Tumlin provided update on missing items.
09/24/26 – No Update.
10/29/26 – Closeouts received

525 – EMA/JFS/513 Office Renovations Read More »

525 – Warehouse Doors and Ramp (F072)

PM: Rycca Thacker, Paul Bellman
12/07/22 – THP submitted SOSS to Hamilton County.
01/08/23 – THP spoke with City and have verbal confirmation a new curb cut is allowed.
01/10/23 – THP proposed initial layout to Hamilton County.
01/19/23 – THP and Thermal Tech met Hamilton County and EMA personnel onsite to review site layout and get field measurements.
02/10/23 – THP sent owner review documents to Hamilton County.
02/21/23 – Owner has approved the warehouse improvements. Hamilton County getting funding put in place.
02/24/23 – THP and Kleingers meeting with Hamilton County and EMA personnel to measure vehicles for final ramp layout and design.
03/16/23 – THP sent bid documents to Hamilton County Purchasing Department.
03/20/23 – Bid Documents released by Hamilton County Purchasing Department.
03/29/23 – Prebid meeting completed.
03/30/23 – Project opening scheduled for 4/13/23.
04/13/23 – Bid opening occurred with John P. Tumlin & Sons being the apparent low bidder and under budget.
04/21/23 – THP published a bid summary letter, recommending the County proceed with Tumlin.
05/21/23 – Permit drawings created and sent last week.
04/21/2023 – THP published a bid summary letter, recommending the County proceed with John P. Tumlin & Sons.
05/15/23 – HC sent contract to John P. Tumlin & Sons and requested their insurance certificates.
05/31/23 – HC waiting on Board of Commissioners for contract approval.
05/31/23 – John P. Tumlin & Sons working on schedule of values, schedule, site specific safety plan, material submittals, background checks, etc.
06/29/23 – THP receiving submittals from John P. Tumlin & Sons.
07/12/23 – HC notified THP that the construction contract will be presented to the Commissioners at their public meeting on 07/27/23.
07/27/23 – TTE returned the PTAC submittals again (second time) for changes.
07/28/23 – HC sent approved contract, PO, and Notice to Proceed to THP and Tumlin.
08/22/23 – Pre-Construction meeting set for Wednesday, August 30.
08/30/23 – Pre-construction meeting with THP, Hamilton County, Tumlin, ThermalTech Engineering, and Kleingers.
09/27/23 – Tumlin submitted construction schedule. Tentative date for mobilization set for October 2.
10/02/23 – Tumlin mobilized to site to begin construction.
10/25/23 – Interior overhead doors installed, masonry repaired at office, PTAC installed in office, interior slab on grade has been removed and replaced, interior man door has been installed, steel framing and masonry work at exterior door openings has started. Gas line has been relocated and additional gas line repairs have been approved via change order.
11/27/23 – Steel framing and masonry work for exterior openings has been completed. Both exterior overhead doors have been installed. Electric work and painting continuing inside. All mechanical/gas line repairs associated with this project have been completed. Exterior ramp (grading, forming, rebar/mesh, etc.) has been started. Concrete ramp pour scheduled for the week of 11/27/23.
12/06/23 – Electric work continuing inside. First two concrete ramp pours completed on 11/30/23 and 12/06/23.
01/02/24 – Last concrete pour for ramp completed.
01/24/24 – THP, ThermalTech, Hamilton County, and Forest Park met onsite to walk through and discuss required life safety items to get temporary certificate of occupancy for Phase 1. Team to address issues.
01/26/24 – Punchlist Walk Through with Bert Watts. Sent list to Tumlin.
01/30/24 – Additional Overhead Doors in back of warehouse started to get installed.
02/26/24 – THP, ThermalTech, and Champlin met onsite to review the vehicle layout. Champlin and ThermalTech to update Life Safety drawings and Electrical drawings, respectively, for in place vehicle layout with egress, emergency and exit lighting, etc to address issues that were discussed with Forest Park Building Department and Fire Department.
04/18/24 – THP received updated electrical drawings with emergency/exit lighting from ThermalTech. Request for change order pricing and updated drawings sent to Tumlin for installation.
04/24/24 – THP waiting to receive change order pricing from Tumlin. Installation of emergency/exit lighting required to close out phase 1 and building permit.
05/10/24 – Change Order for Emergency/Exit Lighting approved.
05/14/24 – Fully executed Change Order sent to all parties.
05/21/24 – Emergency/Exit Lighting submittal received. Waiting on review from ThermalTech to send approval. Installation to follow after submittal approval.
06/26/24 – ThermalTech reviewed Lighting submittal – Approved as Noted.
08/29/24 – Safety electrical items being installed.
09/26/24 – Pay Application #7 received for review.
10/11/24 – THP returned Pay Application #7 to Hamilton County.
10/31/24 – Closeout Process needs to be initiated.
12/11/24 – Closeout Process needs to be initiated.
01/23/25 – Closeout Process initiated with Tumlin.
02/26/25 – Closeout Process in progress by Tumlin.
03/26/25 – THP to follow-up with Tumlin on Closeout.
04/08/25 – THP sent Tumlin email on Closeout documents.
04/22/25 – Tumlin responded to email and indicated another request was sent out to subcontractors for closeout documents.
05/16/25 – Fire Alarm testing caused a short in the new fire alarm control panel. A fire watch was required for this weekend and was provided by a third party firm. TTE helped HamCo on first session until fire watch company arrived.
05/20/25 – Cin-Day installed the new FACP and replaced one address module, tested the existing system and found it to be working with no Trouble. We still need to work out warranty requirements.
05/19/25 – THP received close-out documents from Tumlin.
05/28/25 – THP started review of close-out documents.
06/25/25 – THP to return comments on close-out documents to Tumlin.
07/30/25 – THP reviewed close-out documents and sent Tumlin final comments/documents.
08/27/25 – Tumlin is sending final closeout documents to Hamilton County.
02/20/26 – Preconstruction Meeting held for Generator Plug-In Relocation.
02/23/26 – THP issued Preconstruction Meeting Minutes.
03/11/26 – On-site meeting held to review logistics of panel relocation.
03/24/26 – THP verified panel had been removed from the existing Blue Ash location. Status of permit drawings, IBI Inspection, closeout?
04/28/26 – Tumlin is working on final PW info for HC for Closeout Documents.
05/27/26 – County said do not archive until we get all closeout documents.
06/25/26 – Tumlin submitted requested Closeout Documents.
07/30/26 – Need IBI Inspection report for Closeout Documentation for Plug-in Electrical relocation. Davies to submit.
08/20/26 – THP sent project Meeting Minutes to HC.
08/27/26 – Rycca believes they have paid out this project.

525 – Warehouse Doors and Ramp (F072) Read More »

CH – HVAC Control System Replacement (081-22)

PM: Matt Butz, Terry Cannon, Will Fisher
Closeout: Joe Bulach, joe_bulach@emcorgroup.com, Dayna O’Brien, dobrien@davieseg.com


02/19/22 – ThermalTech submitted SOSS for the project.
03/04/22 – Met with Emcor on Ameresco pricing and scope exercise.
03/09/22 – Met with SBS on new technology and ALC interfacing capabilities
03/10/22 – TEI has created all the background drawings and base specifications for the project in the new CSI format.
03/11/22 – SOSS received and work begins. TTC setting up kickoff meeting on this project.
03/15/22 – Met with Honeywell onsite today and reviewed scope of Chiller controls and scope of this project in more detail. Two new corporate guys met us onsite and review past history and what they plan going forward.
03/22/22 – TTE met and review the action item list for bidding this out in 2022. We need to get background checks complete, BDS coming down tomorrow for BGC, Fisher has his badge, Constable BGC is complete and needs his badge. We’ve agreed to meet with Honeywell and JCI as the additional manufacturer’s for this project. We also want some time to sit with the con
03/23/22 – Started specs in new CSI format. Set up meeting with Honeywell for April 8 and JCI for April 11. We are trying to meet with Barth to review acceptable communication paths in the CH. We will schedule fieldwork soon.
03/31/22 – Meeting updated with JCI for 4/7. The badge process is started for 3 guys.
04/15/22 – Final controls meeting with vendors held this day. All said they can bid this job and meet the requirements.
04/28/22 – Project design schedules distributed. Fieldwork and design in April, May, June, July. Bidding in August, September. Award and contracts are October, November. Fieldwork started last Tuesday with Bracken and Matt. Basement, sub-basement, and roof equipment was verified.
05/25/22 – ThermalTech has been on the building finalizing equipment locations and needs for the last month. Our review drawings for all the equipment including VAV boxes will be out the County on June 3. We are also developing airflow diagrams for the control sequences based on our findings and Honeywell existing information. We are on schedule to bid in August.
06/30/22 – This month we finished up equipment takeoffs and sent them back to the County for review. Comments came back in a day and we have scheduled another field trip to check out additional equipment. JN asked for us to check our equipment against the archibus database, however, I cannot see the equipment database in archibus yet. Ask HC for help at meeting.
07/27/22 – A full equipment set of drawings was submitted to the County for review. TEI scheduling another field trip for final equipment information next week. We want to be on site with Randy so we can finalize sequences on standalone equipment and missing equipment in the sequences.
10/26/22 – Out for Bid. Prebid complete, Addendum 1 & 2 issued. Bid was extended to Nov 15. At least one more addendum before bid opening.
12/15/22 – Bids were opened on schedule and the apparent low bidder is Debra Kuempel. A full pre award meeting was held and the recommendation sent to the County for Base Bid and several Alternates for this job that were still under the published estimate. Project is moving forward, Emcor called for an update yesterday.
12/20/22 – County sent the contract to Emcor for signature.
01/24/23 – Contract was sent, not sure if the PO is back yet. Ready for kickoff.
01/30/23 – John checked back with Steve on contract status.
02/23/23 – Project is in front of the board for approval. DK putting together their project team and was instructed to run all communications through the County PM.
03/29/23 – All contracts are in place and we are ready to have pre-const kickoff meeting. TTC to schedule and reach out to ZH commissioning for their background checks.
04/25/23 – The Pre-Const meeting was help and Emcor was introduced to the project team. After the meeting, we walked one AHU and DK spent time on site surveying the existing building and equipment. We are in submittal and background check phases.
05/21/23 – It Meeting was help this month. DK putting together proposed network locations for our review. The County is working on ordering 7 network switches for the new Control VLAN inside the Courthouse.
06/28/23 – DK continues to work on background checks. Initial network switch location rejected, looking for new locations. TTC & MCB to suggest locations, then will give to DK to review, we may need additional network switches.
07/26/23 – Emcor still working on getting staff background checked for this job. Net network locations reviewed and sent to County for their review. We may potentially meet and go over them at Partner Meeting on Thursday. TTC invited IT and Telecom.
08/16/23 – Met with DK and have new prices for the fiber backbone change order. Steve Yockey sent them to TTC who will review and send to County.
09/27/23 – We are very close to finalizing the change order for the fiber infrastructure for this job. TTE will create a final room location drawing for DK after we receive comments from Jack, Steve and the County. Any issues with what is on the our change order markups for VE options? Controls Submittals have arrived for TTE review.
10/25/23 – Background and LEAD checks underway. DK working with JN. Network location finalized with County and Debra and Change Order #1 for network infrastructure sent to DK for signatures, we are accepting the Value Engineering proposal for this work. Controls submittals returned to DK Revise and Resubmit. We’ve incorporated ZH commissioning comments, WF, BDS and TTC comments into specifications. DK and TTE have coordination meeting on Thursday to review in details to ensure resubmittal is correct.
11/03/23 – Bi-Weekly Construction meetings begin. Emcor working on schedule. TE working on submittal review. Team working on network infrastructure. Jack can’t make Friday meetings until 2024.
11/17/24 – Const Meeting. Working on Background Checks and LEAD checks. Emcor low voltage working on cable runs.
12/01/23 – Const Meeting. Start working on deficiency report format, LEADS checks, low voltage routes.
12/15/23 – Const Meeting. Continue with Submittals work, background check and low voltage routes.
12/20/23 – Submittals returned for equipment and sequences. We still have a couple of outstanding items.
01/05/24 – Const Meeting. Work continues and is making progress.
01/19/24 – Const Meeting #6. Emcor and DK working on after hours progress, TE working on missing piece of equipment and getting ZH in Leads checks program.
01/26/24 – Deficiency List and Honeywell Scope meeting in Room 608.
02/23/24 – Const Mtgs continue. DK running new fiber continues. Deficiency list is begin worked and updated. Honeywell contacted for their portions. Emcor pricing up actuator replacements from deficiency report. Submittals are being updated, penthouse controls are being updated.
03/22/24 – Biweekly meetings continue. This month Honeywell got the chiller plant online, the secondary chilled water pumps VFD’s are online and working, Bacnet has been added to three of the four chillers. DK submitted change orders for four pneumatic upgrades to four units. TTE reached out to Honeywell for pricing on these same four units plus their deficiency list items. Emcor has many of the fibers ran to the server room, they need to repair the walls where they brought items into the room and finishing punching down the cabling. The DDC server is installed in the Rack.
04/24/24 – Next Const Mtg tomorrow is this Friday. Will is out this week and Bracken will cover the meeting. Emcor is being pushed to provide a best guess schedule. AH-52 has been submitted. TTE is reviewing sequences for the new equipment, we will have a design meeting with Emcor to go over sequences and make sure they can do what we have asked for in the Project Manual.
04/25/24 – Biweekly meetings continue. The fiber and CAT6 installation is scheduled to be finished by April 30th. The new network and front end are scheduled to be online during May and equipment changeover to the new controls system shall begin immediately afterwards. Emcor will begin with changing smaller equipment in the basement that is less disruptive to everyday operations. Emcor is beginning to work on replacing the approved pneumatic valve actuators that were deficient.
05/28/24 – Biweekly meetings continue. Low voltage wiring will be completed in the next 2 weeks, only the fourth floor remains incomplete. The new ALC controls database will be uploaded to the old server by Emcor this week. The database will then be transferred over to the new server once HAMCO brings the new server online. Emcor will be starting the first equipment change overs next week, once the database is uploaded. Emcor will begin with the smaller equipment in the basement that is less disruptive to everyday operations. CO#3 has been approved to add AHU-52 to the scope of the project, changing that unit to ALC controls. Emcor and ThermalTech have reviewed the controls sequences and are working to finalize the sequences.
06/24/24 – Biweekly meetings continue. Low voltage wiring on the fourth floor will be completed this week and the new network switch will be installed. Emcor has uploaded the new ALC controls database to the new server. Emcor has begun bringing materials to the site and are planning to begin work in the next 2 weeks to change over equipment in the basement. ThermalTech, Emcor, and ZH are working to finalize the controls sequences based on the latest comments provided by ThermalTech.
07/22/24 – Biweekly meetings continue. Emcor has begun to change over equipment in the basement to ALC controls. Emcors graphics department has begun work on the graphics for the front end. CO-01 is nearing completion, ThermalTech will be creating a punchlist to close out the work. Emcor and ZH Commissioning are coordinating to commission the equipment that’s been changed over. ThermalTech is coordinating a controls sequence meeting with ZH and Emcor. ThermalTech is also coordinating a deficiency list review meeting to close/address any open deficiency list items.
07/24/24 – Met with Dale and Ben today on sequences, they should be finalized before end of next week. Met with ZH commissioning today and ALC not ready with graphics for them to star CX, so we are pushing them back a week.
08/26/24 – Biweekly meetings continue. Emcor continues to change over equipment in the sub-basement and basement to ALC controls. Emcor has changed over the south central VAV’s on the first floor, further work on the first and second floor will begin in the next 2 weeks. Emcor continues to develop the graphics, expecting to complete them by the end of August. A preliminary BAS training took place this month to get Tyler Laws and his team familiar with the new system; another training will be scheduled once the graphics are complete. Commissioning by ZH Commissioning will take place once the graphics are completed. Controls sequences have been finalized by ThermalTech and Emcor, the sequence submittal is expected to be submitted by Emcor within August. Work for CO-01 is almost complete, Emcor will provide a punchlist and ThermalTech will verify it. The deficiency list is nearing completion, with a few items being addressed by HAMCO and a few items still to be investigated by Emcor.
09/23/24 – Biweekly meetings continue. Emcor continues to change over equipment in the basement and first floor to ALC controls and has begun work on the second floor. Emcor continues to develop graphics with an expected completion at the end of October. A BAS training session will take place on October 1st to review the graphics in more detail with Tyler Laws and his team. Commissioning by ZH Commissioning has begun starting with the basement equipment. The fiber and CAT6 installation is nearly complete; Emcor has turned over a punchlist that ThermalTech has started to review. The deficiency list is nearing completion with a few items being addressed by HamCo and some items requiring Honeywell assistance.
10/28/24 – Biweekly meetings continue. Emcor continues to change over equipment on the second and third floors to ALC controls. Emcor continues to develop graphics with an expected completion at the end of October. A BAS training session has taken place on October 1st to review the graphics in more detail with Tyler Laws and his team. Commissioning by ZH Commissioning is ongoing and currently focused on the basement equipment. The fiber and CAT6 installation are complete. Once the record network submittal drawings are received, ThermalTech and HAMCO will review and walk down the punch list items. The deficiency list is nearing completion with the last few items being addressed by HAMCO once the steam system is turned on for the winter.
10/29/24 – ThermalTech scheduling change order review meeting with HamCo. We need to work out some scope issues on the drawings vs reality of what is in the space.
12/12/24 – Emcor is mostly complete with the basement and moving up through the building to floors 1 thru 4 as well. They are onsite every day and working towards the April deadline. ZH commissioning has started creating an CX list that Emcor will have to help correct the CX issues as we move forward and complete the work. VPN seems to be working.
12/23/24 – Biweekly meetings continue. Emcor has completed all changeovers on the second floor and third floor. Emcor continues to change over equipment on the fourth and fifth floors to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement, basement, and first floor. Emcor has a few small items to update in the BAS per HAMCO preference. Commissioning by ZH Commissioning is ongoing and currently focused on the first and second floor equipment. The fiber and CAT6 installation are complete. Record network drawings have been received from Emcor. ThermalTech and HAMCO will review and walk down any network related punch list items. The deficiency list will be checked again in January, no deficiencies have been checked on in December. Change order #2 work for AHU-21, AHU-22, OAHU-1, and AHU-B2 has begun. All of the AHU’s mentioned previously have new valves installed per CO#2, only the damper work remains to be completed.
01/27/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, and third floor. Emcor continues to change over equipment on the fourth and fifth floors to ALC controls; these floors should be completed in January. Emcor will begin the sixth floor in early February. There is a small amount of equipment left to be changed over in the sub-basement and basement. Commissioning by ZH Commissioning is ongoing and currently focused on the first and second floor equipment. Most equipment in the basement that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network related punch list items. The few remaining items on the deficiency list should be closed out in February. Change order #2 damper actuator replacement work for AHU-21, AHU-22, OAHU-1, and AHU-B2 should be completed in January, closing out CO#2 work. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 82, 85) have been changed over.
02/24/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, and fourth floor. Emcor continues to change over equipment on the fifth and sixth floors to ALC controls. The fifth floor should be completed in February. There is a small amount of equipment left to be changed over in the sub-basement and basement. Chiller plant changeover will begin in February. Commissioning by ZH Commissioning is ongoing and currently focused on the third and fourth floor equipment. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network related punch list items. The one remaining item on the deficiency list should be closed out in February. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going and should be completed in February, closing out CO#2 work. AHU-52 has been changed over, closing out CO#3. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 82, 85) have been changed over.
03/24/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to change over equipment on the sixth floor as well as wrapping up the equipment in the basement and beginning on the chilled water system and large AHU’s. AHU-82 is the first large AHU that has been changed over to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement and basement. Chiller plant changeover is on-going. Commissioning by ZH Commissioning is ongoing and currently focused on the third and fourth floor equipment. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going. AHU-52 has been changed over, closing out CO#3. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 85) have been changed over. March will focus on the large systems in the courthouse, the chilled water system and the remaining large AHU’s.
04/23/25 – Work is progressing with about about 84% of the project complete. Emcor has asked for a two month extension for completion. ZH is following behind Emcor and catching up on commissioning. The County has some decent request for front end modifications that Emcor needs to work through. The large AHU’s are being converted now. The Chilled Water plant is current under integration and Emcor has been asked to provide a boiler plant integration cost outside of the scope of this project (see TTC & AKM).
04/28/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to work on the sixth floor, seventh floor, and the chilled water system. All large AHU’s (AHU-68, 75, 82,85) have been changed over to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement and basement (Pending deficiency item repairs). Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning will be next. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going. A schedule extension change order is in progress. May will focus on completing changeover of the remaining items and resolving any commissioning deficiencies identified by ZH Commissioning.
05/27/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to work on the few remaining items and the chilled water system. The following are the remaining items to be changed to ALC controls for the project: Chilled water system, AHU-B, AHU-B16, EF-71, and misc. (4) condensing units. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HAMCO and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is on-going. Change order #4 is closed. Change order #5 has been signed, extending the schedule to June 13 and adding in the changeover of FCU-8 and AHU-B to full ALC controls. June will focus on completing changeover of the remaining items and resolving any commissioning deficiencies identified by ZH Commissioning.
05/28/25 – Emcor did not submit a payapp for January. Payapps 12, 13 and 14 are wrong. We are working on corrections. We received corrected copies of 13 & 14 today but 12 is still wrong.
06/23/25 – Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. Emcor has completed all changeovers except for the chilled water system and (4) misc. condensing units, which are on-going. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HamCo and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network (CO#1) related punch list items. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is on-going. Emcor is back checking all of their work, currently expecting to be done and ready for ThermalTech to punchlist on August 1. Basement, first, and second floors are largely complete and functioning correctly. HamCo is coordinating directly with Emcor to resolve any issues that are identified in the day to day building operations. July will focus on checking all equipment and resolving any commissioning deficiencies identified by ZH Commissioning to prepare for August 1 punchlist.
07/25/25 – Const Mtg held with HamCo, TTE, and Emcor. ZH not present.
07/28/25 – Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. Emcor has completed all changeovers except for (4) misc. condensing units in the basement, which are on-going. The chilled water plant is now changed over and running in automatic mode. Emcor is focusing the majority of their time back-checking the commissioning items found by ZH and resolving any issues with the large AHU’s (85R has some pressure sensor issues being worked on). All change order work is completed. CO#6 is being drafted to give credit to HAMCO for systems that have been removed from scope and to extend the schedule. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is completed. State contract work is on-going for misc. repairs. Commissioning by ZH is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HAMCO and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network (CO#1) related punch list items. Emcor is back checking all of their work, revised date for ThermalTech to begin punchlist is now August 15. Basement, first, and second floors are largely complete and functioning correctly. HAMCO is coordinating directly with Emcor to resolve any issues that are identified in the day to day building operations. County wants to make sure that DK is doing the t-stat touch up plates. Make sure the County knows when.
08/25/25 – The project has entered the punchlist phase. Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. The chilled water plant is continuing to run in automatic mode. Emcor is focusing the majority of their time backchecking the commissioning items found by ZH and resolving any issues with the large AHU’s. All change order work is completed. CO#6 is being drafted to give credit to HamCo for systems that have been removed from scope and to extend the schedule. State contract work is on-going for misc. repairs. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HC and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network (CO#1) related punch list items. Punchlist walk with ThermalTech and HC is scheduled for early September.
08/26/25 – We are having a hard time narrowing down the graphics for the generators in the Courthouse. EGEN is the emergency generator in the basement. GEN-1 is the standby generator on the platform.
09/22/25 – The project is in the punchlist phase. Punchlist was developed during a one-day site walk with HAMCO and ThermalTech. Draft punchlist was supplied to Emcor, punchlist will be submitted to Emcor as final once ZH’s commissioning is completed. Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. The chilled water plant is continuing to run in automatic mode. Emcor is focusing on completing items on the punchlist or checking the commissioning items found by ZH and resolving any issues. All change order work is completed. State contract work is on-going for misc. repairs. Commissioning by ZH Commissioning is nearing completion. All equipment (except for heating equipment) has been commissioned. ZH has commissioned the chilled water plant. ZH is coordinating with HamCo and Emcor to resolve any issues found. The Punchlist has been issued, and we are ready to enter the closeout documents phase.
10/29/25 – The second training session was held earlier this month with the operators. I think it started our rough but was better received by the end of Training. More use will make the end user more comfortable with the new product. The Project punchlist still being completed. ZH Commissioning has a few days left to complete their work on the deficiency list for this project. We found that the free cooling HTX was not on the graphics yet, DK fixed yesterday and the heating plant is not working correctly yet, DK to assist Tyler in making this right.
12/12/25 – Functional testing deficiencies list meeting held today to review progress from Dec 3-5. Some items complete, many are not. DK needs to devote resources and technician to site to complete the CX work. DEG will have to setup owner internal review meeting later this week to review our outstanding resolution items. TTC pushing for 02/28/26 drop dead date for all the outstanding work, requested basic progress scheduled for DK too address final items.
12/22/25 – Punchlist completion is on-going. Site visits in December discovered that there are numerous open items on the resolution tracking form to be resolved. Resolution tracking form items are planned to be resolved by the end of February. HAMCO has given a PO to Emcor to replace HX-1 and HX-3 steam valves to DDC on state contract terms. Weekly meetings have been scheduled to check on the progress of the resolution tracking form items.
12/23/25 – HTX-4 Meeting scheduled for Jan 7 with County, DK and Davies.
01/25/26 – Emcor and DK making good progress, we are hopeful that this project will complete by the end of February. Ethan making good progress knocking out all final items and coordinating with HamCo and ZH Commissioning. VPN access requested for Will Fisher, Anthony said they will send him application. Smell and temperature on sixth floor better but not gone all the way that I know of. Weekly meeting continue with DEG, Emcor, DK and Facilities.
02/25/26 – Weekly Const meetings continue. Emcor has completed the TE punchlist and ZH resolution tracker except for the chiller plant which they are working on this and next week. The HTX will be taken apart and tested in March or April. TTC reached out to Emcor for a full PW download directory as requested.
03/25/26 – Emcor working on Chiller and Cooling tower plant controls. Emcor commissioning ready to start as soon as chillers are started. DEG and ZH met on commissioning deficiencies. DEG issued Punchlist #2, ZH working on revised resolution tracker worksheet. We are scheduled to inspect the HTX next month.
04/20/26 – Emcor, DEG and ZH reported for final commissioning and worked through the final punchlist and functional testing markups this week.
04/28/26 – Checked in with Tyler and everything seems to be working well.
04/29/26 – Tyler reported this morning at the cooling tower overflowed with water this morning and the penthouse was flooded. Investigation showed that some equipment was commanded off and a second condenser water pump started causing the overflow condition. DEG asked Emcor for an additional logic step to prevent this from happening in the future. Emcor also asked that equipment be release to operated in automatic mode so this does not happen.
05/27/26 – All punchlist and resolution tracker work is reported as complete. DEG requested closeout documents from Emcor for project closeout.
06/25/26 – Project in closeout.
07/30/26 – Working on closeout documents. Emcor collecting OM’s and paperwork. We check back every Friday.
08/26/26 – Almost all closeout documents received including releases. We are working on full closeout.
09/23/26 – After months of work, coordination, and emailing Emcor, we have the final closeout documents and TTC will hand delivery to Ted and Mat ton 9/24. We have requested final payapp for processing.
10/26/26 – Project is in Closeout.

CH – HVAC Control System Replacement (081-22) Read More »

CH – Bronze Door Repair

PM: Matt

02/15/22 – Signed SOSS received.
03/31/22 – Field investigation completed. Preliminary drawings completed. We have been in contact with several historic door restoration companies.
04/28/22 – Drawings at 75% complete. Need to schedule a review meeting.
05/10/22 – Review meeting with Rycca. Determined more documentation per door is needed.
06/30/22 – Bid package to be finalized and submitted for final review.
07/28/22 – Additional site visit performed. detailed scope photographs added to drawing set.
08/24/22 – 95% check set sent to HC.
09/29/22 – Project out to Bid
10/27/22 – Olek won bid. West doors and Cleaning awarded. Contracts in progress.
12/15/22 – Contracts signed and returned. Kickoff meeting to be scheduled
01/26/23 – Call with Olek, County and Champlin to discuss details of kickoff meeting. kickoff meeting to be scheduled by end of February.
02/22/23 – Kickoff meeting to be scheduled in near future. Champlin has reached out to Olek twice for dates.
03/30/23 – Kickoff held on site. Preliminary schedule received. Olek to provide firm dates as we near demolition.
04/27/23 – Doors have been removed and sent to New Jersey for refurbishment.
05/25/23 – Doors have been taken apart and analyzed. Doors are in better shape than anticipated. Submittals to come soon.
06/29/23 – Photographs received. Work in progress.
07/27/23 – Restoration ongoing. restoration revealed that the door pulls were originally nickel plated. Change order to nickel plate the door pulls in progress.
08/31/23 – Olek to return to site 9/11. Test fit of closer complete.
09/28/23 – Olek cleaned existing bronze and prepped hardware installation. No crocs in sight.
10/25/23 – Construction ongoing. County requested pricing for additional bonze cleaning.
12/07/23 – Installation scheduled tentatively for march. Olek returned pricing for all items requested.
02/29/24 – Change orders approved. Several doors are complete. Still on schedule for late March Install.
03/28/24 – Doors to be installed first week of April. Site and prep work will continue into the following week.
04/25/24 – Doors to be installed in may. Firm dates to be determined.
05/30/24 – Olek is on site. Two doors are in. One Torchiere was blown over in a storm. Olek is shipping damaged parts to their shop.
06/27/24 – Work on site complete. Olek will need to come back for punchlist work. Matt ask Murphy to review final retainage payment submit.
08/29/24 – Olek needs to come back out to complete punchlist.
09/26/24 – No Update.
10/31/24 – Olek was back on site for the punch work. They did not complete the list and will need to come back.
12/12/24 – Olek came back for the back punch work but did not complete their work. They will be back for the punch and for a closer warranty issue.
01/30/24 – Olek still has punch work to complete. close outs to be submitted.
2/27/25 – Scott reached out to olek to request closeouts and a timeline for punch work. The closeouts are in progress. The punch work will be done in tandem with the first phase of the north and south doors.
03/27/25 – No Update.
04/24/25 – No Update.
05/29/25 – No Update.
06/26/25 – No Update.
10/30/25 – No Update.
12/11/25 – No Update.
01/28/26 – Olek to complete punch work when on site next.
02/26/26 – Olek onsite March 9th to finish punch work.
03/26/26 – Olek is onsite. Punch work is in progress.
04/30/26 – Work is complete. Closeouts nearly complete.
06/25/26 – No update.
07/30/26 – No update.
08/28/26 – No update.
09/24/26 – No update.

CH – Bronze Door Repair Read More »

800 – Fire Alarm System Upgrade

PM: Matt Butz, Mike Barth
08/26/21 – HCFD sends TEI signed PO and SOSS. TEI contacts HCFD PM to schedule design kick off meeting. Date pending.
10/26/21 – TEI has begun the design process by setting up the CAD file drawings and using archive data to begin the demolition drawings. Once kick off meeting occurs, the field investigation will be scheduled and the design will proceed.
12/13/21 – TEI has taken the as-build documents to create demolition drawings.  Next step is to field verify/document the existing conditions.  Field work to be scheduled with building manager.  design kick off meeting occurred with HCFD and building manager.
01/25/22 – TEI fieldwork pending return of background checks for James Smiddy and Alex Woods.
02/23/22 – Background checks approved and badges approved.   TEI and HCFD to schedule field work with building manager.  Note – there was an issues with the existing Simplex FA System panel (dialer power supply) and JCI sent a quote for a complete panel replacement.   TEI and JCI investigating a more cost effective fix until a time when the system is replaced.
04/27/22 – TEI hires MobilComm to provide survey of signal strength for FF radios (per CFD requirements).   Upon receipt of report from MobilComm, recommendations for BDA may be included in design specifications.  TEI fieldwork complete.   Existing conditions  documented and moving forward with new work drawings.
05/26/22 – MobilComm reports back that the building has a non compliant system.  New BDA system will be installed.  TEI Meeting with Fire Marshall on 06/07/22 with 90% complete documents for review/input.
06/28/22 – Project deign near complete – Pending Barth review, documents will be sent to HCFD Week of 7/4/22 for review and comments.   ITB will be issued upon receipt of review comments.
07/27/22 – TEI sends drawings to Hamilton County facilities for review.  Upon receipt of review comments, the package will be issued for bidding.
08/24/22 – Project being sent to purchasing on 08/26/22 for bidding.  Available to bidders on 08/30/22.  Prebid scheduled for 09/14/22 and bid opening scheduled for 09/28/22.  ITB # 075-22.
09/26/22 – Project bidding.   Bids Due 9/28/22.
10/26/22 – Bids received and opened.  DK apparent low bidder.  JCI/Simplex vender in bid.  TEI vets bid and makes recommendation for award.   Project to commence upon contract approval and PO to DK.
12/15/22 – DK signs and returns contract to HCFD.  Once PO is issued, pre-construction meeting to be scheduled.
01/25/23 – DK receives contract and PO.  HCFD and TEI working to schedule preconstruction meeting to kick of construction.
02/23/23 – Preconstruction meeting completed.  JCI developing submittals.
03/29/23 – TEI speaks with JCI about submittal package.   JCI estimates that the submittals for the 800 building will be completed and turned over to DK in the next 2-3 weeks (Mid April-ish).
04/27/23 – TEI follows up with JCI, submittals nearly complete.   JCI indicated that the submittal package should be sent to DK on or before 05/01/23.  TEI to review upon receipt.
05/23/23 – TEI receives, reviews, and returns submittals with minimal marks, asks for schedule from DK for commencement of work.  JC sends photo of material that was shipped to DK for project.  TEI to schedule pre-construction meeting first week in June.
06/28/23 – TEI requests schedule again from DK.  Upon receipt of schedule, construction to commence pending procurement of materials.
07/26/23 – construction kickoff meeting scheduled for 7/28.
08/24/23 – DK to mobilize to project site and start construction on 9/5/23.  Josh Querry from DK to PM/site Super the project.
09/26/23 – Construction has began.  DK installing backbone of the system.
10/26/23 – Backbone installation complete.  DK has started on upper floors and at the construction meeting on 10/25/23 stated that 18, 17, 16 and part of 15 is complete.  DK also working in basement and installing devices there.   Rooms are being identified that require either  LEADs clearance or special access.  DK to schedule work in these areas during day shift.
12/06/23 – Construction progressing.  Working on installs in LB, B 1,2,3,3M.  LB and B ready for change over.  2 will be by Christmas.  1, 3 and 3M will be nearly complete if not complete by Jan 1.
01/30/24 – DK submits CO request for portion of work changes.  The beam detector CO still pending.
02/28/24 – Beam detector CO still pending.
03/27/24 – Beam detector for 3 beam detectors received ($41k).  HCFD to determine if it is accepted or not.  Smoke purge CO under review.
04/24/24 – Smoke purge CO verbally approved to DK at const meeting.  Beam detector CO not approved at the meeting.  Work continues through the building.
05/29/24 – The smoke purge CO has been approved and sent to DK.  DK and JCI working on Drawing updates and will progress to install as soon as the revised install drawings from JCI complete.  JCI indicated that all parts are readily available.
06/26/24 – No updates from JCI on this project.
07/24/24 – DK same staffing issues – staff being moved from 800 to JC and back. CO verbally approved (HCFD waiting on PO increase) for formal approval.
08/28/24 – JCI submits revised drawings wot city for approval. JCI states that there is no way (on existing system) to repair the amplifier card for the upper floors. TEI and HCFD directed JCI that the New system shall be turned on immediately and use the new devices for audio on the upper floors.
09/25/24 – TEI, DK and HCFD meet with inspector (Jeff Hinkel) to discuss inspection process and 3 and 3M. Inspections will proceed similar to CH and TPC, where we will have multiple teams and multiple inspections. Looking at options for the 3 and 3M area – inspector sympathized with the task and we developed possible workable solutions.
10/30/24 – The switchover of floors to the new system in the tower (top down) has commenced. Anticipate tower work to be completed in approx 2-3 weeks. then move to low rise floors. TEI recommends scheduling inspection of tower floors once tower complete.
12/11/24 – HCFD, CFD, CBD, JCI, DK and TEI participate in the first acceptance inspection at the building. Floors 7-18 were inspected and accepted, with minor tweaks. Construction continues, with the crews starting on 5th floor week of 12/16.
01/29/25 – Crews working on 2 right now. Next inspection scheduled for 02/12/25 at 5:00 PM. Planning for inspections of floors 2-6.
02/26/25 – Inspections for 2-6 went well. First floor complete and working in basement. Will be ready for next inspection in about a month. Then there will be the Flow/Tamper inspections, then AHU/smoke control inspections, then Elevators. Need resolution of elevator issues for the non-functioning elevators.
03/26/25 – Inspection for SB, B and 1 scheduled for 04/16/25. The tamper/flow inspection to be scheduled 2-3 weeks after the inspection on the 16th.
04/23/25 – All floors inspected for smokes, pulls, heats and AVs. Door holders were inspected. Tamper/flows inspection next – to be scheduled TBD.
05/28/25 – Tamper flow inspection occured and passed. Next is air handlers. Inspector allows the magna-helic results from the pre-test to be written on the covers for the inspection night.
06/25/25 – Installation nearing completion. Elevtor and Air Handler inspections scheduled for 07/16/2025
07/30/25 – Freight elevator and final air handler inspections scheduled for 07/31/25 at 0700. This is final building and fire and elevator inspections pending no issues during the inspections.
07/31/25 – Early morning inspection went well this morning. Three small electrical items are required to be updated to get the AHU-45 and Smoke Fans 14 & 15 did not start. The elevators are approved and the Chief Inspector approved the current smoke detector layout.
08/27/25 – follow up visits with CFD and CBD to inspect and approve the repairs made by HC. All inspections completed (other than IBI). IBI to be scheduled once the Bldg Dept and FD upload all their paperwork.
09/24/25 – All inspections passed. HCFD and DEG to schedule final punchlist for project.
10/29/25 – Punchlist completed and issued punchlist to DK.
12/10/25 – project tied to Justice Center PO. Closeout pending completion of JC FA project.
01/28/26 – Project tied to the JC FA PO, Closeout pending completion of JC FA project. Anticipated completion April/May of 2026.
02/25/26 – No Updates.
03/25/26 – No Updates.
04/29/26 – No Updates.
06/23/26 – DEG directs DK to assemble and submit closeout documents for 800 building.
07/29/26 – Project completion pending closeout documents.
08/26/26 – Project complete pending closeout documents.
09/23/26 – Project complete pending closeout documents.
10/28/26 – Project complete pending closeout documents.

800 – Fire Alarm System Upgrade Read More »