Hamilton County Facilities

Colerain – Animal Shelter – (F037)

PM: John Millar/Emily Phillips
01/30/26 – THP issued SOSS for review.
02/17/26 – Hamilton County approved the SOSS.
02/18/26 – THP completed preliminary field survey.
02/26/26 – THP working on repair documents.
03/25/26 – THP finalizing document review set for review with HC early April.
04/27/26 – THP published Owner review documents.
06/25/26 – THP working on Bid Documents.
08/26/26 – THP working on Bid Documents with included demo walkway.
09/22/26 – THP published DD documents.
09/24/26 – Project plans to publish bid documents 9/28/26.
10/13/26 – Prebid meeting occurred.
10/16/26 – Addendum No. 1 issued (prebid meeting minutes).
10/29/26 – Project update – Bids due 11/23/26.