12/28/17 – THP publish SOSS to Hamilton County as requested.
01/25/18 – Hamilton County approved SOSS.
03/06/2018 – THP completed ground survey of façade.
03/29/2018 – THP to schedule rappelling survey early April.
04/26/18 – THP schedule rappel the facade.
05/21/18 – THP completed draft of Cincinnati façade ordinance report and published.
5/31/18 – County reviewing report.
6/26/18 – THP submitted drafts of the Envelope Assessment Report and City Report
07/26/18 – THP finalized and published Cincinnati façade ordinance report. Signature by Ralph Linne’s required before THP submits report to City of Cincinnati Buildings & Inspections.
08/24/18 – THP received letter from City of Cincinnati acknowledging the submitted report.