A&D – Critical Façade Repairs (F104)

12/28/17 – THP publish SOSS to Hamilton County as requested.
02/15/18 – Hamilton County approved SOSS.
02/20/18 – THP published review documents.
03/09/18 – THP published bid documents.
03/15/18 – Prebid meeting completed.
03/29/18 – Bids received. American Façade Restoration the apparent low bidder.
04/3/18 – THP sent a letter of recommendation after a phone interview with AFR.
04/4/18 – THP sent draft AIA County / AFR contract to the County for review.
04/26/18 – County prosecutor reviewing the contract.
06/06/18 – Hamilton County and AFR under contract.
06/28/18 – AFR reported they plan to start work mid to late July. Work should take about two weeks.
7/23/18 – Preconstruction meeting completed.
7/26/18 – Anticipated start of construction will be 8/6/18 with work expected to be completed 8/31/18.
08/30/18 – AFR actively working on North, South and West elevations. Concrete and stone patching repairs 90% complete. South Elevation pilaster repair 50% complete.
9/5/18 – AFR substantial completion reached. THP reviewed work and generated a punchlist.
9/11/18 – AFR completed punchlist work.
9/27/18 – AFR working on closeout documentation.
10/25/18 – Project complete and closeout documentation complete.