PM: Terry Cannon, Tony Matre
Closeout: Joe Bulach, joe_bulach@emcorgroup.com, Dayna O’Brien, dobrien@davieseg.com
08/19/25 – Kickoff discussion with Emcor.
11/18/25 – Emcor running low voltage at the building for new DDC network.
12/09/25 – Const Mtg and meeting minutes distributed.
01/08/26 – Const Mtg. Emcor making progress on equipment in the basement and on the first floor. They need help with access to some rooms that are under HCSO control.
01/20/26 – Const Mtg and new schedule released. Emcor gearing up for Chiller plant programming in March. Joe says they will take care of the 6th floor network cable. AM reports it is still not in the right place. The switches are in place and ready.
01/21/26 – Emcor shared missing submittals with DEG on VFD’s.
02/25/26 – Work continues as Emcor is planning on working on the chiller plant in March.
03/25/26 – Work continues, chiller plant programming in progress. Emcor ready to commission when building starts the chilled water plant for the season.
04/28/26 – Const progress meeting with Emcor held with DEG, Tom and Emcor. Small progress being made on new controls. Emcor asked to start boiler plant this week, it was decided to wait because of cold weekend temperatures. Tom had issues with chiller operation, Emcor found chiller in manual and released it. Emcor did some training with Tom to show him how to use new system but Graphics are not complete yet and the chiller plant is not fully programmed yet. Emcor to work on graphics, updated chiller programs and preparing for heating plant integration.
05/25/26 – Const Meeting held adn Emcor reported they started the boiler plant upgrades and they are making good progress. The communication infrastructure is in place for the future upgrades and the 800 Tower units can be added to it.
06/25/26 – Const meeting held last Tuesday, working out graphics updates and final controls work. Tom requested training.
07/30/26 – Project nearing completion, chiller sequences being updated.
08/26/26 – Project is complete and in commissioning. PCHWP-2 has an issues that DEG will be on site troubleshooting on Thursday.
09/23/26 – DEG met onsite to review chiller operations. DEG recommends to follow DK recommendation to replace thermal overloads on PCHWP-2. Tony said that Craig could perhaps replace these since they are less than $100. That is our recommendation as well. DEG updating the PID to new conditions after replacement of CH-2.