Hamilton County Facilities

Colerain – Kitty City Electrical Upgrades

PM = Megan, Mike Barth

01/28/26 – HamCo request SOSS for Electrical Upgrades for Kitty City. DEG submits SOSS. DEG receives approved SOSS and PO on 01/28/26. DEG coordinating meeting with Duke.
02/25/26 – DEG meets with Duke to discuss power options. DEG proceeding with load calculations to send to Duke for service sizing.
03/25/26 – DEG develops drawings for electrical upgrades. Final field work scheduled for 03/31 at 7:30 AM to confirm final details.
04/29/26 – DEG submits 100% review drawings and OPCs to HCFD for comment/approval. Upon receipt of comments, ITB will be submitted.
05/27/26 – DEG meets with bldg mgr – adds a couple of alternates for additional outlets and also replace thru wall fans with new with humidistats.
06/23/26 – Drawings sent to HCFD for review.
07/29/26 – Upon receipt of HCFD review comments and/or approval, ITB package will be finalized and issued.
08/26/26 – Meeting scheduled for 08/28/26 with CARES to review and receive approval. Goal setting worksheet submitted (pending approval).
09/23/26 – Project issued for bidding. Prebid meeting occurred on 09/23. Bids are due on 11/12.
10/28/26 – Project in bidding phase. (1) addendum issued.