PM: John Nester, Terry Cannon
03/25/21 – SOSS submitted.
04/21/21 – SOSS approved. Terry, Coty, Ryan will work on this project.
04/29/21 – Contract sent to QCM for signature. Check on progress. Okay to do fieldwork during city water main shutdown.
05/26/21 – ThermalTech secured the services of Mike the plumber from Triton (same guy that installed the work at the CH) for the plumbing survey at 800 for one daytime and two nighttime visits). We will probably do this work in June.
06/09/21 – Met with County, walked the building, started reviewing existing installation.
06/25/21 – Updated drawings since 6/9 meeting, almost ready for field work.
07/27/21 – Day 1 Night Fieldwork with Terry, Coty, Danny, Triton, Tom. Basement, First, Second, 14,15,16 floors were completed.
07/28/21 – Day 2 Night fieldwork with team complete for the rest of the building. We have to return to finish the basement, access the drug testing labs and some judge’s private RR. Very little galvanized piping found. The building appears to be in good shape for plumbing piping materials.
08/26/21 – Existing drawings slightly updated from fieldwork. We will be on this in earnest the second week of September. There is limited scope to change based on what we found in the field. Our basement fieldwork will coincide with the city water main work on QCM Saturday.
09/30/21 – Drawings are complete and ready to TTC review. Study report started, TTC going to let Coty have a shot at it first and then will edit for final submission.
10/28/21 – Working on Fire Department design this month and did not make a lot of progress on wrapping this up yet. We could send drawings in for review.
12/13/21 – Project completion pushed to the end of December for this work. TTC coordinating with Coty on putting the final touches on this work. The laminated CH placards drawings were emailed to the County.
01/22/22 – Drawings are being completed now.
02/22/22 – Plumbing schematic ready for review, floor plans mostly completed and on final review and editing.
03/31/22 – Final Draft report complete, TTC will send today.
04/28/22 – Plumbing report and recommendations were sent to the County. Design SOSS requested.
05/25/22 – Design SOSS is almost ready. It’s a simple one but I need to finalize it and get it to John. We did meet with QCM this week and tell them we’d like their help.
06/30/22 – TEI has a field trip setup next Tuesday at 800 to final water shutdown plans and finalize valve locations.
07/27/22 – TEI performed additional fieldwork and found more valves and useful locations for valves. We’ve schedule another field trip to wrap up final details next week.
08/24/22 – Two additional field trips were held this month for finalizing changes. Updated drawings and revised report will be ready 8/30.
09/22/22 – Coty has prices back from QCM, they are revising and sending back for final scope on Monday. Some more valves were fixed during the last walk through.
10/26/22 – New pricing submitted by QCM. They called twice wondering which way we are going to go with the change order. I told Drew, we are probably just doing a material purchase and a fire detector restock.
10/27/22 – JN sent change order to TTC for review.
12/15/22 – Change order awarded to QCM. Drawings are updated for final scope, limited rework in the building is necessary. OK to close and archive this project.