PM: Bert Watts, David Toombs, Terry Cannon
04/02/21 – SOSS approved. Waiting for contacts from County to begin programming.
05/27/21 – No Update.
06/17/21 – Toured City and County facilities.
06/23/21 – Site planning concepts sent to Bert for input. Input received the same day.
07/16/21 – Review meeting with County Commissioner, City Council Member, County Administrator, and representatives of Hamco Sheriffs and City of Cincinnati Police.
07/26/21 – Final rendering and diagram packet sent to Bert.
08/25/21 – SOSS Submitted to County
10/28/21 – No Update.
12/14/21 – No Update.
01/26/22 – No Update.
02/22/22 – Champlin presented at Residents Meeting in Colerain Township.
02/24/22 – Elected officials outnumbered the residents who were in attendance at the meeting and Champlin presented the project. 5 residents were in attendance, sheriff, county, other people were there. Concerns: Acoustic study, traffic study, and site environmental range. Even though it’s a firing range now.
04/27/22 – Champlin sent kickoff meeting invite for May 10.
05/10/22 – Kickoff meeting with County Cincy Champlin and Kleingers held. Reviewed program and concept
05/24/22 – Progress meeting with County Cincy Champlin and Kleingers to review floor plans and ancillary buildings.
06/30/22 – Progress meetings ongoing. SD package to be completed on schedule
08/25/22 – Final SD package sent to HC. Estimate breakdowns to be finalized.
09/29/22 – No Update.
10/27/22 – No Update.
01/26/23 – Meeting held with County and City to discuss funding. Estimate is being broken down by item to value engineer the project.
02/03/23 – THP – Champlin requested SOSS for structural services.
02/09/23 – THP provided an SOSS to Champlin for review.
02/22/23 – SOSS received for DD-CA.
03/08/23 – THP and Champlin have executed contract.
03/30/23 – Site survey is complete. Developing Topo basemap to be complete middle of next month. the Acoustical Engineer has completed existing condition sound testing.
04/27/23 – Draft of Acoustics report received. Champlin had questions and is finalizing a report. Topographic survey complete and base map received. Champlin and Kleingers are coordinating scope of work.
04/28/23 – Moved project out of Champlin General Services to Satellite Offices for future updates.
05/21/23 – TTE attended DD development meetings wiht Champlin & Kleingers for site work.
05/25/23 – Site package sent to County for review. Drawing to begin development.
06/29/23 – DD page turn held 6/23. Hud environmental assessment exhibit materials are due to Bert by friday June 30. Flood plane exhibit sent 6/27. Final acoustics report is ready to send upon request. Design team has reworked architectural site plan with the temporary building location moved.
06/28/23 – THP coordinating with Champlin on Phase 1 documents in July.
06/29/23 – Septic Engineer will be onsite Jully 6 for site survey and cores for their work. The Water Test from Veolia is on hold for supply issues with our test kit, but we hope they can also be on site the week of July 7.
07/20/23 – ThermalTech met SCS engineers onsite for septic design ground samples and septic tank locations.
7/24/23 – Champlin sent email: Phase 1 design coordination with structural (THP) is expected start this week for CD due end of August.
07/26/23 – Veolia water testing scheduled for August 1 with Ian, TTE, and Veolia.
07/27/23 – Meeting held with Sheriffs. Program and plan confirmation for temporary range and ancillary structures locations occurred at that meeting. Expect phase 1 CD submission for end of August. Geotechnical work is ongoing.
08/31/23 – Schedule for bid package 1 and 2 distributed to all consultants 8/28. Coordination is ongoing. Bid package 1 completion date is 9/22.
08/31/23 – THP no project updates.
09/28/23 – Meeting held with CPD. Cincinnati had scope requirements to continue involvement with the safety center. County is working on an agreement.
09/29/23 – THP issued Phase I bid review documents.
10/25/23 – Revised estimate submitted to County for review. Waiting on meeting to be scheduled with CPD to answer some outstanding questions. EPA issue has not been resolved.
12/07/23 – Meeting with Cincinnati, CPD, Sheriff, and Hamilton County held to discuss status on 11/6. US EPA review comments continue and we are providing answers as required.
1/24/24 – THP – No update. Paused.
02/01/24 – EPA questions submitted answered. HC continues to have meetings with the EPA. We will most likely require some sort of testing wells for this site to monitor content in the aquafer. Currently this project is on a design hold until these administrative tasks are complete.
2/28/24 – THP – Phase 1 is on hold. Expected official response 3/1/24 and issue bid document 30-45 days. Design is done. Phase 2 is on hold with no date planned.
02/28/24 – Met with Morgan and Anson on Feb 23 to discuss approach to hiring engineering for water main extension. City of Cincinnati determined that GCWW was OK with not hiring the design as long as standards are met. All agreed it made sense to have Kleingers due the work because of head start on project understanding. USEPA verbal commitment to have a letter by March 1 has slipped to mid March.
02/29/24 – Bert asked for operational cost, environment, utility cost and lab test.
03/28/24 – Land swap negotiations nearing completion. Zoning variance for sniper lanes to be submitted in near future. Coordination between architectural and civil to wrap up this week.
4/23/24 – Phase 1 Bid Review set submitted on 4/12/24. Phase 2 on hold with no date planned.
04/25/24 – 95% review set submitted to the County 4/18. Cost estimates are being developed. Zoning meeting scheduled for 5/22.
05/30/24 – Board of zoning appeals voted to approve the required variance on 5/22. Bid set sent to purchasing 5/23. City comments on phase 1 received with no impact to phase 1 drawings.
06/27/24 – Project is out to bid. Pre-bid held, Addendum #1 is issued.
07/24/24 – Bids were opened and five underbudget bids were received
08/28/24 – Phase 1 Bids in. Phase 2 on hold with no date planned.
08/29/24 – Bid review complete. Project in contract phase.
09/23/24 – ThermalTech sent “Issued for Permit” drawings sent to Champlin for distribution and submission for this project.
09/25/24 – THP – Pre construction meeting with Monarch next week. Phase 2 still on hold.
10/31/24 – Groundbreaking ceremony held last Friday. Phase 2 to begin.
12/11/24 – in CA. submittal reviews. Phase 2 still on hold.
01/30/24 – Phase 1 – Site work to start ramping up due to weather. Zoning and Permit issues are close to resolved. Phase 2 – SD plan approval received from Cincinnati and Hamilton County. DD development ongoing.
02/26/25 – Phase 1 – we have returned adn submitted all the OEPA permits to keep the permitting phase of the job moving forward, the contractor is getting close to running out of work on Phase 1 I think, we need to get permitting on place. Phase 2 work for DD is due March 3. TTE working on Revit model updates and working on cost estimates as well. We have been meeting with David Toombs regularly on MEP updates.
03/25/25 – We have multiple DD design meetings with Champlin this month. Bluebeam studio being used for markups, DD drawings and cost due this week to Champlin for Final DD tear-off set. MEFP and Architectural design being tweaked for final DD adjustments. Phase 1 submittals are being received and returned as they come in, submittals are acceptable. The Septic permit is still elusive but we continue to work towards resolution, SCS says most of the paperwork is already submit, but he needs to fill out one more new electronic form.
04/24/25 – THP update – County requested changes to the design. THP provided pricing for additional services to be included in Champlin’s request.
04/24/25 – DD for phase 2 is complete. Revised estimate submitted to county. Phase 1 work ongoing.
05/29/25 – Project schedule shared for phase 2. Phase 1 work in progress.
06/25/25 – DD submittal in Apr. Team is waiting for approval to proceed into CD.
08/04/25 – We received an Anti-Degradation email from Bert and forwarded that to Dan Brennan SCS engineers to handle. SCS sent a memo to Glenn per their request but will call him back to make sure that is all they need. We also got the approval to send in the revised submittal drawings from the contractor for Monarch. TTC passed all this information on to Bert and David.
08/26/25 – Construction continues on site. Pilot holes are being drilled to assist in figuring out how to get under the roadway. Soils change order being developed. Bulletin 6 issued to Monarch for pricing and coordination.
08/27/25 – on Phase 1 the large retention system walls are nearly complete, and the Phase 1 temporary range was completed last week. The Ph1 grounds building cladding is in progress and the staging to raise the parking lot grading has also started. On Phase 2 the Design Team received DD approval and is proceeding with CD Phase. Over the last 3 weeks all remaining in-person owner meetings for Security, Technology and Interior Design have been completed.
10/30/25 – 90% documents for phase 2 will be submitted to county tomorrow. Phase 1 work continues and on target for January completion. Retaining wall movement has been rectified with additional wall in front of original retaining wall.
12/11/25 – 90% set is under owner review. Ohio EPA approval is still in process. Grounds building is complete and sheriffs are moving in. Existing building Demo to begin shortly. Phase 1 work on target for completion in January.
02/26/26 – Project complete. Punch work ongoing.
03/26/26 – One site issue still outstanding. Kleingers is working on a solution.
04/30/26 – Guardrail posts being installed next week. Closeouts outstanding.
05/28/26 – No Update.
07/30/26 – Monarch sent closeout documents, Partners have been commented on them this week. Concrete joints and curb issues being addressed.
08/27/26 – OK to Archive.