PM: Matt, Terry, Elevar
03/26/26 – Original SOSS rejected, need XBE on this job. DEG got proposal from Elevar last week and resubmitted on 3/25. Robert approved but need LOI for Elevar. DEG to provide and resend SOSS.
04/29/26 – More fieldwork completed last week with Tom and we have selected which units will be replaced. DEG working with Habegger on new unit selections and putting background drawings together. We will have a kickoff meeting in May with Elevar on electrical work for these units.
05/27/26 – Unit selections are made, we will be ready to meet with Elevar for electrical kickoff first week of June. No real surprises with new units other than they are all converted VVT to VAV units now. ALC controls kickoff meeting discovered that they cannot reuse any of the JCI VFD drives on this project.
06/25/26 – HVAC design progressing, Electrical kickoff meeting held with Elevar, more fieldwork next week. Owner planned end of July.
07/30/26 – Met with owner on design scope. Design continues, Owner review set still planned for end of July. Working on coordination with Emcor and Elevar on scope for VFD’s and electrical needs.
08/26/26 – Another field trip and final design concepts updated for several AHU. We have meeting with Facilities Thursday afternoon to discuss budget, final scope, and asbestos abatement. Then we are ready to bid.
09/15/26 – Project Issued for Bid. Bid opening scheduled for 11/12/26.
10/26/26 – Addendums issued bid opens on 11/12/26. Addendum 1 issued. No additional questions have been received as of 10/26.