800 – Probation EMU Office Expansion
PM: Matt, Eryn
10/29/26 – SOSS to be awarded soon. Elevar to work on drawings to provide Gen. Trades with take-offs.
800 – Probation EMU Office Expansion Read More »
800 Braodway
PM: Matt, Eryn
10/29/26 – SOSS to be awarded soon. Elevar to work on drawings to provide Gen. Trades with take-offs.
800 – Probation EMU Office Expansion Read More »
PM: Matt, Terry, Elevar
03/26/26 – Original SOSS rejected, need XBE on this job. DEG got proposal from Elevar last week and resubmitted on 3/25. Robert approved but need LOI for Elevar. DEG to provide and resend SOSS.
04/29/26 – More fieldwork completed last week with Tom and we have selected which units will be replaced. DEG working with Habegger on new unit selections and putting background drawings together. We will have a kickoff meeting in May with Elevar on electrical work for these units.
05/27/26 – Unit selections are made, we will be ready to meet with Elevar for electrical kickoff first week of June. No real surprises with new units other than they are all converted VVT to VAV units now. ALC controls kickoff meeting discovered that they cannot reuse any of the JCI VFD drives on this project.
06/25/26 – HVAC design progressing, Electrical kickoff meeting held with Elevar, more fieldwork next week. Owner planned end of July.
07/30/26 – Met with owner on design scope. Design continues, Owner review set still planned for end of July. Working on coordination with Emcor and Elevar on scope for VFD’s and electrical needs.
08/26/26 – Another field trip and final design concepts updated for several AHU. We have meeting with Facilities Thursday afternoon to discuss budget, final scope, and asbestos abatement. Then we are ready to bid.
09/15/26 – Project Issued for Bid. Bid opening scheduled for 11/12/26.
10/26/26 – Addendums issued bid opens on 11/12/26. Addendum 1 issued. No additional questions have been received as of 10/26.
800 – Tower AHU Replacements Read More »
PM: Matt, Terry Cannon
Engineers: Coty Groeschen, Wesley O’Hara
08/27/25 – Prebid held today, bids are due in September. Owner furnished equipment includes fire pump, jockey pump, low suction controller and fire pump controller.
08/28/25 – Issued for Bid 8/13 and bids open 9/24.
09/24/25 – Bid Opening today at 11AM.
10/03/25 – Post bid meeting held with Alpha and they are recommended for the project. Base bid no alternates accepted.
12/12/25 – Jesse reported contracts close to being sent to contractor for signature.
01/25/26 – Contract should have went to BOCC on Jan 19, no updates. Sending Permit Drawings Tuesday 2/3. Electrical RFI received and in the process of being answered.
02/12/26 – DEG starting pre-construction work with Alpha and subs.
02/25/26 – Contracts are back. DEG coordinating with Duke and IBI on power installation requirements for the MI cable. Alpha EC vendor being weird about MI cable requirements and cost.
03/25/26 – Alpha arranging EC vendor for this job. DEG working on necessary CFD details before work begins.
04/22/26 – FDC testing complete and 800 passes inspection. DEG checking with Alpha on starting this project and getting permits to begin. A project schedule should be ready to share with the owner in a couple of weeks.
05/27/26 – SOV was approved today. We are ready to set up the Pre-Const meeting. DEG sent mechanical drawings for permitting to Alpha last week adn IBI drawings are already in for permitting.
06/25/26 – Kickoff meeting held with contractors. IBI permit approved, City permit under review. Electric change order under review. Schedule, SOV, Site safety documents received and under review.
07/30/26 – Had meeting with vendors on electric change order. Third meeting scheduled today at 1PM. Prices are coming down but not going away. Met with CFD and received their thoughts on allowing the high rise fire pump to provide temporary service for both low and hi rise, they are amendable provided we provide a letter stating it will work. Griffith sent us that letter.
08/26/26 – CO-1 sent and signed by DEG and Alpha, returned to County for approval. Planning on scheduled work to begin in October after Duke power is stable.
09/23/26 – 9/26 shutdown pushed back to Veterans Day. Alpha agreed to January 2027 startup without the project incurring any additional cost.
10/26/26 – JTL requested site visit to start working on the electrical portion of the job. DEG informed them to coordinate with Facilities on access adn that we wanted to be cc’ed on all visits so we can stop in and check progress.
800 – Fire Pump Replacement Read More »
PM: John Nester, John Millar
01/02/2 – Champlin reached out to THP to provide SD services for the new Animal Shelter.
02/25/25 – THP provided an SOSS for SD Services.
03/26/25 – Elevar pending approved PO. Truescan started scanning the building from the interior.
04/23/25 – Design team had internal kick off meeting. Project update – Scanning complete and THP working on base Revit model for the project.
05/28/25 – Elevar has site walk scheduled for 05/30 to review windows. THP completed initial surveys and plans to rappel 5/29 and 5/30.
06/26/25 – Elevar investigating window replacement vs restoration and window cleaning products.
07/31/25 – Window drawings are progressing and a set will be provided to THP for inclusion in the next checkset to HCFD.
06/30/25 – THP completed aerial platform surveys of the lower section of the building and interior surveys of the façade 6/30 to 7/3.
07/17/25 – Stone stabilization proposals received and AFR is the low bidder.
07/22/25 – THP sent 800 Broadway review set to County. Set included windows and fall protection.
07/30/25 – AFR installing supplemental anchors on north elevations. Anticipate being complete by 7/31/25.
07/30/25 – AFR completed installation of supplemental anchors and THP confirmed the work.
08/27/25 – THP published share file with SD review drawings. Drawing included stone, window, and safety package.
08/28/25 – Summary documents and initial estimate planned for week of September 2.
08/28/25 – Window SD set provided to THP 08/15.
09/25/25 – Elevar provided ROM estimate to THP.
10/30/25 – Review mtg with HCFD scheduled for 11/06.
10/23/25 – THP issued opinion of probable cost for all work.
10/30/25 – County review meeting scheduled for November 6th.
12/11/25 – Review mtg held with HCFD. Revised estimates and design schedule to be provided.
12/01/25 – Schematic Design meeting occurred. Scope, budget and next steps presented.
12/23/25 – HC requested an SOSS – DD through Bidding.
01/19/26 – THP published SD report for County project planning.
01/29/26 – THP/Elevar working on SOSS.
01/31/26 – THP and County working through project scope and design team services.
02/25/26 – THP published SOSS for review.
04/09/26 – HC approved SOSS.
04/30/26 – THP working through initial design phase planning.
05/27/26 – Design Kick off meeting completed.
06/08/26 – Project summary for security meeting published.
06/17/26 – Project placed on hold.
07/29/26 – THP published summary of conditions for use by the County.
09/24/26 – Project on hold.
10/25/26 – Project on hold
800 – Façade Repair SD (F022) Read More »
PM: Matt Butz, Eryn Thamann
01/29/25 – Met onsite 01/27 to review scope and SOSS requested.
02/25/25 – SOSS provided for Elevar/TEI. Pending approved PO.
03/26/25 – Pending PO approval. Onsite meeting with City AHJ is scheduled for 03/27 to walk spaces and review for any AHJ concerns.
04/24/25 – Elevar had site visit walk-thru AHJ to review life safety concerns. City concerns sent out in meeting minutes with sketches. HCFD needs to confirm additional scope as indicated by AHJ. Elevar will work on stair scope only for now.
05/28/25 – Elevar provided drawing backup to TEI on 05/28. After MEP design is DD level, a design review meeting will be scheduled with HCFD. Elevar to provide design schedule and will need to meet with HCFD to review Div 01 requirements.
06/26/25 – Design review meeting scheduled for 06/30 to review CD set.
07/31/25 – HCFD has 95% set. Waiting on approval prior to preparing final bid set. Elevar to provide clarification on fee per MB’s request.
08/28/25 – Discussing remaining fee with MB/TEI.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Uploaded to Archibus.
12/11/25 – No update.
01/29/26 – Elevar met with HCFD to review 90% set and provided overview sheet for security committee. Waiting on security committee approval before proceeding with CDs. Project needs to be bid/award in 2026.
02/26/26 – Waiting on security committee approval before proceeding with CDs. Elevar has picked up internal revisions and ready when HCFD obtains approval.
03/26/26 – HCFD to setup security committee approval before proceeding with CDs.
04/30/26 – On hold pending HCFD approval of bidding costs.
05/28/26 – Out to bid now with bids due June 30.
06/25/26 – No update.
07/30/26 – Contractor recommendation provided to HCFD and contracts are in process with Purchasing.
08/27/26 – In final stages of contracts with Purchasing.
09/24/26 – Contract was finalized.
10/29/26 – Procurement starting but no submittals yet.
800 – Exit Stair Security Cages Read More »
PMs: Sarah, Terry Cannon, Eryn Thamann
01/17/25 – SOSS Requested.
02/25/25 – SOSS submitted to HCFD. Pending approved PO.
02/26/25 – Awaiting approved SOSS.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. We will follow Elevar lead on first design meeting. TEI scope is in the basement and the 6th floor area. Elevar hasn’t received approved PO.
04/24/25 – PO provided and awaiting design kick-off meeting with Court Admin/team.
04/23/25 – Project setup and internal meetings underway. Elevar and ThermalTech setting up kickoff meeting.
05/28/25 – Awaiting kickoff meeting with Elevar and County. TTE ready to mobilize for design.
06/25/25 – Kickoff meeting in July.
07/30/25 – Drawings received from Elevar, ThermalTech working on MEP design, submitted questions about need for MSB in new restroom. Additional fieldwork done last week for basement repairs.
07/31/25 – Drawings are progressing for a bid review set Aug 8 and a bid set to HC Purchasing Aug 15. TTC changed name and assigned to Elevar and merged Plumbing Repairs and 6th Floor Reno.
08/28/25 – Project scheduled for bid advertisement on 08/29.
09/25/25 – Bids due 10/10. Last addendum due out 09/26 with final questions.
10/30/25 – Lowest bid was Triton and under advertised cost. Vetting mtg occurred and Elevar has recommended Triton for award.
12/11/25 – Project awaiting final contract award from purchasing.
01/29/26 – No update.
02/26/26 – Contract was approved but Elevar has seen no submittals or correspondence. Elevar to schedule construction kick-off mtg.
03/26/26 – Contract was approved but Elevar has seen no submittals or correspondence.
04/30/26 – Have reviewed some general trade submittals.
05/28/26 – Possibly complete with submittals but low on Triton’s priority list.
06/25/26 – No update as it’s low on Triton’s priority list. Not received change order pricing for flooring add.
07/30/26 – Construction kickoff meeting held 07/20. Recurring progress meetings scheduled.
08/27/26 – Triton likely back onsite now after ACM removal. Regular progress meetings to resume next Mon. We will keep the floor drain in the project based on today’s conversation.
09/24/26 – Working thru slab change order.
10/29/26 – New pricing is expected soon for slab work.
800 – 6th Floor Reno & Bsmt Plumbing Repairs Read More »
PM: Matt Butz, Terry Cannon
01/17/25 – SOSS requested.
02/26/25 – TTC still needs to submit this SOSS, this is the last one on my list to submit.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. Our first design meeting to be in April.
04/23/25 – Project underway. We have completed our first field trip to the building. TEI running load calculations to verify sizing, setting up existing drawings and working on ventilation calculations. After we get the preliminary design complete, let’s meet and discuss project particulars.
05/28/25 – We held a kickoff meeting with the Facilities in the last month and made another round of field trips to the building for additional information. We are trying to prove HVAC AHU sizing from original job and collect factory information from original install of the low rise units to verify coil sizing, heating and cooling loads and whether or not air side economizers make economic sense during this replacement.
06/25/25 – ThermalTech doing additional fieldwork to lock down actual ductwork in the mechanical rooms. We should be ready for bidding next month.
07/31/25 – Project submitted for Owner Review. Project Manual didn’t make it through TTC review, will be sent later. Look for prebid third week of August.
08/26/25 – Prebid meeting Wednesday 8/27. TTE invited many.
09/24/25 – Addendum 1 previously released. Bid opening today at 11AM.
10/29/25 – Project on hold pending official bid award. TTC answered Nester email inquiry this morning about award status. TEI/DEG has not advised either bidder the project has been awarded yet.
12/12/25 – in contract approval stage. TTC notified contractors that Triton received the bid and Alpha did not.
01/25/26 – Sent before BOCC on Jan 19 for approval. We are awaiting notice to proceed.
02/12/26 – Contracts are back. Pre-Const meeting being set up now.
02/25/26 – Triton has been awarded the project. We are scheduling the project kickoff meeting soon. We do need to discuss what are we going to do with AH-71 and it’s proximity to the parapet wall.
03/25/26 – Submittals coming in, no kickoff meeting scheduled yet.
04/26/26 – DEG working on change order request drawing to relocate AHU-L71 to farther away from parapet wall. Once complete we will get a price from Triton for the change.
05/27/26 – DEG sent revised AHU-L71 location to Triton for pricing to rotate away from parapet to get 10 foot clearance.
06/25/26 – Awaiting project kickoff. AHU-71 change order not received yet.
07/30/26 – Pre Construction meeting held with Triton. Working on submittals, sent permit drawings to Triton, working on getting project n place for January start so unit can be replaced over long County weekend.
08/26/26 – Reviewing submittals preparing for January start.
09/23/26 – Still on track for January start, no new submittals in September from Triton.
10/26/26 – Had meeting with Triton and Emcor on HVAC Controls. We are awaiting the resubmittal of the controls package to DEG for full review. The controls have not been approved for this project yet. AHU submittals including curbs are approved. We are verifying current lead time for equipment.
800 – Low Rise AHU Replacements Read More »
PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after first walk of 230 bldg.
04/24/25 – Walk-thru not scheduled yet but is next in line.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
06/26/25 – Ready for review with Champlin/HCFD.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.
800 – Fire Door Repairs Read More »
PM: Rycca Thacker, Mike Barth, Lauren Schmitz
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (5) elevators in 800 Broadway. TEI and Elevar meet to discuss rolls on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar provided SOSS to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO. TEI and JE perform initial walkthrough of all of the elevator machine rooms.
01/29/25 – TEI/Elevar/HC met and TEI has design schedule. Field work is ongoing now.
02/25/25 – Elevar performed all field work and work is ongoing.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting was scheduled with HCFD. SD review meeting shceduled for 04/02.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team waiting on HCFD to schedule courts committee for design review.
06/25/25 – Team meets with Court Admins – get direction on security and finishes. TEI to submit updated schedule.
07/23/25 – THP – Davies, Elevar, County and THP met to review possible options for getting the elevators in 800 Broadway.
07/30/25 – Team sends proposed schedule and RFIs to HCFD for direction.
07/29/25 – THP sent a proposed summary of elevator access plan and THP scope of work for review.
08/13/25 – THP sent an SOSS to Davies for review.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/08/26 – THP issued bid documents.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Low bid being vetted by design team.
04/30/26 – THP sent questions for GC post-bid review in March.
04/30/26 – Contract in process with HC Purchasing.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027. The contract phase and procurement deposit caused the delay. Due to the obsolescence of the R-410A refrigerant, the Liebert units for the machine room cooling anticipated ship dates are 52+ weeks. The Skill-Aire alternate ($42k deduct) is 16-18 week ship time.
800 – Elevator Modernization Read More »
PM: Matt, Mike Barth
01/25/23 – TEI Submits SOSS. Project pending SOSS approval and PO.
02/23/23 – Project pending SOSS approval and PO.
03/29/23 – TEI receives signed SOSS and PO. Project kickoff to be scheduled with TEI and HCFD.
04/27/23 – TEI performs preliminary review of existing model. TEI and HCFD to meet to discuss next steps.
05/23/23 – TEI to set up meeting with HCFD to discuss next steps. Proposed time of 9:00 AM, on 6/8.
06/08/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC.
07/26/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC.
08/24/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC
09/26/23 – TEI develops drawings and submits to HCFD for review.
10/26/23 – TEI issues project for bids. Prebid meeting occurred on 10/25/23. Bids are scheduled to open on 11/22.
12/06/23 – Bids received and opened on schedule. Stem Electrical is apparent low bid. TEI vets bid and submits letter of recommendation. Contracts are at prosecutors office for approval.
01/30/24 – Project awaiting BOCC approval
02/28/24 – Stem Electric receives signed contract and PO. Preconstruction meeting to be scheduled in the next couple of weeks.
03/27/24 – Pre-construction meeting scheduled for 04/15/24
04/24/24 – Pre construction meeting occurred. submittals receieved , and approved. Project pending procurement of materials (approx 12 month ship date). Stem electric to confirm shipping schedule.
05/29/24 – Project pending material procurement. TEI requests Stem Electric to send in Ship date.
06/26/24 – No Updates. Project pending material procurement.
07/24/24 – No Updates.
08/28/24 – No Updates, project pending procurement of materials.
09/25/24 – Project pending material procurement.
12/11/24 – Project installation pending material delivery.
02/26/25 – Project installation pending material delivery.
04/23/25 – Project installation pending material delivery.
05/28/25 – No updates.
05/25/25 – No updates.
07/30/25 – Stem electric and DEG and HCFD meet to KO project. Gear has arrived and DEG certifies at Crane yard.
08/27/25 – Stem to begin the construction phase of this in first week or two of September.
09/24/25 – Gear is rigged into place. Outage/tie in to be coordinated.
10/30/25 – MCB to call Stem to schedule a shutdown meeting.
12/10/25 – DEG to follow up with Stem again to schedule the shutdown.
01/28/26 – Stem ready for the outage. John Nester requested pricing on refurbish breaker in the main gear. Stem is sending email of availability to DEG for meeting to discuss/schedule outages.
02/25/26 – Stem to send in proposed schedule and timelines.
02/25/26 – Stem sends in multiple proposed dates in May for tie in schedule. DEG, HCFD, Tech Svrcs, and Juv Courts to meet to discuss outage plans and select date.
04/29/26 – DEG and HCFD meet with all building tenants and discusses power outage plans. Tentative dates for outages are 5/30 for the 2nd floor and 6/19 for the sub-basement gear.
05/27/26 – 5/30 outage cancelled due to the contractor not having BGC staff. 6/19 outage still on the schedule.
06/23/26 – Second floor switch tied in on 06/19. TJW Electric provided staff that had current BGC and badge to perform the work. Basement level work to be scheduled.
07/29/26 – DEG has a virtual meeting with HCFD and Stem Electric. A list of possible Saturdays was emailed to HCFD and Stem to coordinate the next outage. HCFD to confirm the procurement of bad breaker for the distribution panel serving the computer room to be replaced by trades during the outage.
08/26/26 – HCFD states that the replacement breaker has been purchased by trades. Stem has confirmed 09/26/26 date with ESI, still pending confirmation from TJW. DEG states lets work towards making outage #2 happen on 09/26/26 so not to delay other projects. Stem to confirm with TJW and finalize the date.
09/23/26 – 9/26 date was postponed due to staffing issues with Stem Electric. New Date is 11/11/26 – starting at 07:00 AM. Pre-outage conference call scheduled for 10/28/2026.
10/28/26 – Outage is scheduled for 11/11/26. Meeting held with courts, HCSO and HCFD to discuss outage on 10/28/26.
800 – Arc Flash Mitigation 2023 Read More »