PM: Bert, Mike M, Terry, John Millar
05/30/24 – ThermalTech submitted SOSS to Champlin for SD & Cost.
05/31/24 – Champlin sends TTE background material to start working on this project.
06/26/24 – Design Meeting started, Champlin sent agenda and latest drawings.
07/02/24 – Board Presentation Day.
07/10/24 – Fieldwork at site.
07/17/24 – Fourth Floor layout sent from Champlin to TTE.
07/25/24 – JFS Computer Room fieldwork setup for TTE.
07/31/24 – Bond Hill Due Diligence SOSS request sent.
08/01/24 – SD & Cost sent to Hamilton County for this project.
08/21/24 – Due Diligence SOSS questions came back from Champlin. Be ready to move on due diligence quickly if approved.
09/19/24 – THP update – Champlin/County request THP provide building envelope and garage restoration due diligence assessments.
09/26/24 – Due Diligence kicked off. Architectural, MEP and environmental site visits complete. Survey happening today. Structural and civil scheduled.
10/02/24 – Due Diligence – THP update – THP published proposal to Champlin.
10/03/24 – THP update – Champlin/County request THP provide structural footing design for the garden fencing as part of the larger project.
10/07/24 – Due Diligence – THP update – THP field teams completed building envelope and garage surveys.
10/10/24 – Due Diligence – THP update – THP completed roof thermal scans.
10/11/24 – THP update – THP published proposal to Champlin.
10/23/24 – Met onsite with Facilities, Environmental Services, Ameresco and ThermalTech on Netzero energy opportunities.
10/25/24 – Due Diligence – THP update – THP published building envelope and parking garage due diligence assessment to Champlin.
10/31/24 – Due Diligence draft submitted to county. SOSS for DD-CA submitted. DD review meetings have begun. Documentation ongoing.
12/12/24 – DD to be submitted for review on 12/23. Estimate to be submitted 1/6. Meetings ongoing.
12/23/24 – THP update – THP issued DD fence and moveable wall structural details.
01/27/25 – ThermalTech finalizing fieldwork at the site to continue design for HVAC, Plumbing, Electric, and Fire Protection beyond the DD phase into CD. We have received the server survey from Telecomm and have updated our calculations for each IDF and MDF room, we hope to have floor plans updated by end of this week with proposed rack locations and HVAC needs. We are on pace to make the CD deadline of February 28, 2025.
01/30/25 – Final meetings with each department ongoing. CD’s being developed. Bid review set to be submitted for review on 2/21.
02/27/25 – Review set submitted to county. Tentative bid issuance date is 3/6. DDS has been removed from bid package to be issued as a separate project.
03/27/25 – Drawings are ready for bid. Updated Estimate to be submitted this week.
04/24/25 – Bid phase ongoing. Pre-bid had light attendance. Bids open May 23.
05/29/25 – Graybach is apparent low. Bid vet to be scheduled when bid is determined acceptable.
06/26/25 – Bid vetting in process. A305s provided to county for consideration.
07/31/25 – Graybach will be awarded the bid. bid vet meeting held. contract has been signed and will be going in front of the board next week. Const meetings start week of August 11.4
08/28/25 – Graybach has mobilized and began demolition. Furniture move services bid issuance on 8/26. RFI received on plumbing and HVAC are being answered as they come in. We have officially access controls, but it has been resubmitted as individual components and AV cable, fiber and Cat6 is approved. Now we need to discuss what to do about the security camera system. We reinforced with the field foreman that we are pulling every cable back to the IDF rooms so it landed by floor. TTE to send IDF coordinate drawings to John for ordering and coordination ASAP.
09/23/25 – TTE met with DK yesterday on proposed HVAC changes at Bond Hill. DK has already performed all the work on the first floor, we negotiated changes and discuss field engineering changes methodology with Dustin and Dave. We agree on the material cost but feel strongly that the labor is more than what is needed to make the requested changes (as it was estimate at three additional men for one month). TTE suggested that this change order is enough to cover not only the 1, 2, 3 floors, but the entire building.
10/02/25 – THP – Champlin requested field support for cutting holes in precast panels.
10/23/25 – THP – after site trips and coordination with Champlin, THP issued field sketch for precast hole support.
12/11/25 – Graybach still confident they will get done by mid January with TCO in mid January for Phase 2. TCO expected next week for Phase 1 as most inspections are done for the TCO work. Design team still issuing Bulletins for changes for GC, EC, and low voltage. AT A&D they are getting ready to move to the new building. HC has weekly move meetings for coordination, Veteran Services move being coordinated. Osterman working with HC and Graybach coordinate move items. HC seeking additional funding for extra asks at the building and the low voltage items.
01/28/26 – Punch walk through completed. Exit sign issue has been solved.
02/26/26 – JFS has moved in to the first 3 floors. minor punch work ongoing. Floors 4 and 5 are ongoing. DDS awarded to Triton. Demo is complete for DDS.
03/26/26 – Floors 4 and 5 in progress. Punch tentatively scheduled for 3 weeks from now. Furniture scheduled to be compete 5/1. DDS portion is ongoing.
04/30/26 – Project to be complete in 2 weeks. Punch scheduled for next week. Move in mid may.
05/28/26 – Punch work nearly complete on 1, 2, & 3. Punch walk through on 4 & 5 minus DDS happened last week. Everyone (minus DDS) should be moved in by end of next week.
10/29/26 – Closeouts ongoing.