PM: Matt/Trades, Terry Cannon
Closeout: Terry Cannon, tcannon@davieseg.com
06/25/24 – Proposal from ANS sent to Bert Watts for review.
07/24/24 – Submitted for 2025 budget. County may know in Q4 about viability.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold.
01/17/25 – SOSS Requested.
02/26/25 – Kickoff meeting on hold while TEI researches additional technologies.
03/19/25 – Preliminary conditions meeting held with EMA on SOSS modifications. TTC submitted revised SOSS with additional scope same day.
04/23/25 – MCP sent a very high proposal in to assist on this project. TTC to follow up with Nester on next steps.
05/28/25 – TTE release PO to ANS for Siren Assessment, scheduling the first kickoff meeting June 30 or July 2, this request out to Mike D at ANS. ANS says they will need about 45 days to perform the onsite analysis. MCP quote came back very high, looking for other specialist contractors to assist with assessment.
06/25/25 – ANS cannot make the July 2 date, TTC to pick another date.
07/18/25 – Kickoff meeting held at 525 with ANS and EMA. Project set to kickoff August 4.
07/27/25 – Nick commented that third party vendor not required for future recommendations of system and we can concentrate on the siren conditions first.
07/30/25 – Additional scheduling taking place, project set to kickoff August 11 onsite at Siren #414. EMA, TEI, HCDF and ANS.
08/28/25 – ANS has made two deployments to the County so far. Zone 4 was completed the first week of August. Zone 5 was addressed this week. We are not sure how far ANS will get this week but shadowing ANS, each siren was about one hours to 90 minutes of work with travel. We have questions out for what constitutes a FAILED siren, especially in regard to test 3.1.4 on the Audit worksheet. The Siren Tracking sheet was created and updated and implemented by ThermalTech and put to use in the OneDrive. The OneDrive folder is available for use on this project. We are on schedule for targeted completion.
09/24/25 – Vendor meetings continue. Zone 6 is complete. 26 audits have been uploaded, no failures for this group. Several sirens were skipped for access and traffic control. Joe is in town for Zone 1&2 at this time.
10/29/25 – ANS has completed their initial visit to all sites in all zones. ANS returning November 3 for Traffic Control sites. The traffic control sites and daily order was released today to all team members. Friday November 7 is a backup day to pick up remaining sites. Facilities has followed behind ANS nicely fixing and putting UNSAT sirens back into service.
12/12/25 – Traffic Control and Access impeded sites have been visited. DEG checks with ANS every day for final audits. We have received 8 of the final 37. TTC must submit 25% Draft Report by Friday.
12/31/25 – Draft report sent to Hamilton County Facilities & EMA for review.
01/12/26 – Received final 17 Audit reports from ANS and incorporated them into the report.
01/15/26 – Reviewed report with EMA and tabulated all siren conditions from ANS and presented these numbers to EMA as well.
01/25/26 – Updated report being sent to the EMA this week for second around of reviews.
02/25/26 – Rev-5 sent to the EMA for comment. This version includes the Acoustic Model from ASC. No comments received from Rev-4 yet.
03/25/26 – No comments received yet.
04/16/26 – Met with the EMA on comments on the report. They are extensive comments. DEG will begin working through the changed.
04/27/26 – DEG continues working on report updates. We’ve gotten though some of the proposed cost changes, most of the editing is complete, inventory changes picked up and now TTC has to contact Federal Signal and get their information for the report.
05/21/26 – Met with EMA and Facilities and sent back next revision of report to EMA for approval and review.
06/25/26 – TTC checked back with Morgan on comments or progress, no update yet.
07/30/26 – No updates on markups to final report.
08/26/26 – No updates, saw Nick at Sharonville Life Safety event, he didn’t mention.
09/23/26 – No updates but we are starting two siren relocations with Ben, Keith, and Zach.
10/26/26 – Waiting on next review meeting with EMA. Project is in closeout.