Hamilton County Facilities

BOE-A

Board of Elections
Archive

BOE – Fire Alarm System Modifications

10/23/18 – BW contacts ThermalTech about pricing for additions required by the City of Norwood to the existing fire alarm system at the BOE. ThermalTech, HCFD and DK meet at the site to develop budget pricing for HCFD. BW to advise next steps upon approval of funding.
1/28/18 – Signed SOSS and PO received to complete the work. ThermalTech receives Drawings from Notifier (RP Biederman) and there are additional devices from what was priced. TEI has DK call RPB to question where/why these devices were added (where did the direction come from?) DK to respond back to TEI with RPB response.
01/29/19 – There are doors at the facility that the BOE has asked to have door hold opens on that did not have closers. Also – due to door and rack configurations, there are doors that only open 90 degress so an alternate closer/hold open device was suggested. DK submitted a CO request, but BW stated that it needed to come from Tumlin since Tumlin holds the contract. TE contacted Tumlin and DK to request the CO appropriately, and it is still pending.
02/26/19 – HamCo Signs CO for the additional door closers for the project (there were doors that had doors that BOE requested hold opens that had no closers). Door hardware scheduled to be delivered first week of March and then installation will be scheduled immediately upon receipt.
03/26/19 – All equipment has been installed and pre-tested on 03/21/19. Final inspection scheduled with Norwood on 03/28/19 at 1:30 PM. After the final inspection, ThermalTech to perform final punchlist and project closeout documents can be completed.
04/24/19 – ThermalTech and Facilities performs and issues punchlist. DK completes their portion of punchlist and waiting on Tumlin for a few items on the punchlist.
05/29/19 – ThermalTech waiting on final closeout documents from Tumlin to close out the project.
06/26/19 – ThermalTech waiting on final closeout documents from Tumlin to close out the project.
07/24/19 – ThermalTech reviews and certifies final pay application and submits to Bert Watts. DK submits close out documents to Bert Watts.
07/25/19 – BW says after PW Rates arrive we can close this job out.

BOE – Fire Alarm System Modifications Read More »

BOARD OF ELECTIONS – RELOCATION SERVICES ESTIMATING

Lead Partner: GBBN

Current Status: Active- Project Closeout

01/22/16 – County requested availability for kick-off meeting with Board of Elections.

01/27/16 – Meeting date established for Kick-off Meeting at 824 Broadway Building. Kick-off meeting held at BOE Offices.

01/28/16 – IPM and GBBN visit existing Warehouse for site investigation and photographing of existing conditions.

02/04/16 – GBBN receives approved SOSS from Facilities.

02/09/16 – Facilities directs GBBN/IPM to use estimate number 1835 in Archibus for the estimating efforts.

02/10/16 – GBBN/IPM receives first space planning design from Owner’s Reality Agent.

02/23/16 – IPM visits proposed building site with BOE for the site investigation for the purpose of estimating the move services.

02/24/16 – GBBN and Facilities agree on concept for estimating electrical disconnect services to be placed into the estimate.

02/24/16 – IPM begins estimating input for the move services.

03/02/16 – IPM/GBBN confirm with Facilities that the Move Services will require a public bid if over $49,000.

03/03/16 – TEI communicates information about the Data Room/Network relocation component of the relocation services. Facilities responds to inquiry about inert gas/fire suppression systems.

03/07/16 – Facilities responds to additional requests for information about phone switch and data/I-T questions.

03/10/16 – TEI provides Network/Data/I-T relocation estimating data and cost figures.

03/11/16 – GBBN and IPM finalize estimating in Archibus with the exception of phone/I-T relocation pending input from BOE.

03/23/16 – GBBN/Facilities/HamCo Telecommunications/BOE meet to discuss I-T/Network/Phone relocation component of move services estimating. Telecom to provide estimate to BOE for running new data wiring at new facility. BOE to inquire with CBTS and Building Owner related to Inert Gas Extinguishing and Phone provisions in lease and services agreements for Telecommunications.

04/19/16 – BOE instructs Facilities that revisions to new facility space planning are not completed, by other Architectural firm, so data outlet location drawing have not been completed, for sending to Hamilton County Telecommunications Department for completion of their Opinion of Probable Costs for the data/telecommunications component, for insertion into GBBN overall Opinion of Probable Cost.

05/19/16 – GBBN attends Kick-off Meeting with RFP Team.

05/20/16 – Facilities requests SOSS from GBBN for the Moving Services Scope of Work.

05/24/16 – IPM meets with Sally Krisel to discuss scope and overall project delivery dates.

05/26/16 – GBBN submits SOSS to Facilities at monthly Partnering Meeting.

06/02/16 – GBBN and IPM attend BOE RFP Construction update meeting.

06/07/16 – GBBN and IPM attend BOE Design Services Kick-off Meeting.

06/08/16 – IPM completes BOE on site existing furniture/equipment field verification.

06/16/16 – GBBN and IPM attend BOE RFP Construction update meeting. IPM releases final furniture and equipment layouts to BOE for final approval.

06/30/16 – GBBN and IPM attend BOE RFP Construction update meeting.

07/14/16 – GBBN and IPM attend BOE RFP Construction update meeting.

07/21/16 – GBBN and IPM meet with BOE to review Moving Services Bid Package with BOE Directors.

07/28/16 – Next scheduled BOE RFP Construction update meeting with Developer, Building Team, BOE and Facilities.

08/15/16 – BOE Move Services ITB #061-16 Issuance of Bidding Documents.

08/23/16 – BOE Move Services ITB #061-16 Pre-Bid Meeting held. 824 Broadway was toured first, followed by 3600 Red Bank Road Warehouse and concluded at the 4700 Smith Road Facility.

08/30/16 – Final Day for Bidding Questions. GBBN receives one set of questions from Purchasing Department for Addenda.

09/01/16 – GBBN issues Addenda #1 to Purchasing and ARC.

09/08/16 – GBBN attends bid Opening for BOE. Two bids received and Purchasing releases copies of both bids to GBBN.

09/15/16 – GBBN and IPM meet with Planes Moving and Storage Inc to discuss bid, scope and validity of bid documents. Planes agrees to honor bid and agrees in principal to enter into contract with Hamilton County for this project.

09/19/16 – GBBN authors a Meeting Minute summary for Facilities with GBBN and IPM recommending Planes be awarded the contract.

09/26/16 – GBBN and Facilities discuss status of Meeting Minutes, recommendation and contract authoring. Subject of accepting Alternate Bid to be determined with conversations with the Board of Elections.

10/03/16 – GBBN authors AIA contract for Planes Moving and Storage. Delivers to Facilities.

10/05/16 – GBBN and IPM tour construction site to field verify critical furniture installation dimensions. Critical dimensions are found to be acceptable.

10/15/16 – Wessells Moving and Storage emails GBBN about the return of their Certified Check. GBBN emails Facilities about it immediately.

10/17/16 – Wessells calls GBBN to personally inquire about the return of the Certified Check. GBBN calls Facilities to inquire but no answers are available. GBBN calls Purchasing to obtain more information and obtains answer. GBBN calls Wessells back to inform them the bid recommendation has not been officially accepted by the County therefore check can not be returned until that time by Purchasing.

01/17/17 – IPM reports roof leak in new Warehouse area will delay move of elections equipment to new facility. Building Owner to have roof repaired.

02/22/17 – IPM reports to GBBN that move is progressing very well and move should be completed soon. BOE is very happy with progress by Planes Moving.

03/16/17 – GBBN authors and delivers Additional Services SOSS for IPM services due to delays related to roof leaks and delayed move-in of the Warehouse Elections Equipment.

03/17/17 – Planes issues request for additional services to be allocated from the Allowance built-in to the contract. GBBN requests that Planes re-issue request with additional cost break down including material and labor.

03/22/17 – Planes revised request received. Facilities approves request and authorizes GBBN to author Change Order #1 reflecting revised request.

03/23/17 – GBBN issues Change Order #1, with Architects signature, to Planes via mail.

03/27/17 – GBBN authors and mails Change Order #1 Revisions as requested by BOE.

04/20/17 – GBBN informs Planes that AIA Documents are required to submit any Application for Payments to the County per the Project Manual.

04/26/17 – GBBN coordinates completion of AIA Documents with Planes.

BOARD OF ELECTIONS – RELOCATION SERVICES ESTIMATING Read More »

BOE – Training Center Renovation Build-Out

11/10/17 – Facilities requests SOSS be prepared by GBBN.11/14/17 – GBBN authors and delivers SOSS to Facilities.
11/13/17 – TEI submits MEP scope of services to GBBN.
11/14/17 – GBBN authors and delivers SOSS to Facilities.
11/15/17 – BOCC approves BOE Training Center Build-Out project to proceed.
11/29/17 – GBBN and TEI attend Client project kickoff meeting on 11/29/17. Discuss schedule, budget, and design parameters. Additional Field Verification done and photographs taken.
11/30/17 – Next review meeting for IT is 12/13. The SD presentation meeting is scheduled for 12/20. TEI does not need a site plan, roof plan or underslab drawing for this work. GBBN will send us updated plans next week. GBBN can also send section and wall cuts soon.
01/25/18 – Review sets given to BOE for review by BOE and Bldg Owner. We are waiting on comments back and then we will bid this project out. GBBN will update specs and bid dates
02/09/18- Oswald supplies carpet and toilet accessory selections from recent renovation for use in replicating the same in the new build out.
02/16/18 – BOE requests small vision lights be added to Training Room doors for visibility into rooms from Lobby.
02/20/18 – ThermalTech to complete bid sets to send to GBBN for 02/26/18 issuance.
02/20/18 – GBBN distributes ITB information. ITB#021-18 selected by Purchasing. Existing Prevailing Wage Rates will be used due to no new substantive changes made recently. BOE approves 3/7/18 at 10:00 am as Pre-Bid Meeting date.
03/07/18 – Pre-Bid Meeting held at 4700 Smith Road. Meeting Agendas prepared by GBBN are issued and Minutes Recorded along with a Sign-In-Sheet filled out.
03/13/18 – Addenda #1 with Pre-bid Meeting Minutes was issued.
03/15/18 – Addenda #2 issues by ARC and Purchasing.
03/22/18 – Bid opening extended to 3/28/18. Addendums 1-4 released and update the budget and scope to take mechanical deduct alternate for a different control packages.
03/26/18 – GBBN meets Dorn Fire Protection to tour building and contract site.
03/27/18- City of Norwood Building Department was contacted for information on Permitting requirements and logistics.
03/28/18- TEI contacts Hamilton County Plumbing Department about submissions for Permitting.
03/29/18- Bid Opening to be held at 11:00 AM at CAB, Room #507. Apparent low bidder is John P. Tumlin and Sons, LTD.
04/04/18 – GBBN holds Bid Interview with Douglas Tumlin. Meeting Minutes and recommendations send to Facilities. Facilities issues decision to proceed with the contract authoring to John P. Tumlin and Sons, Ltd.
04/05/18 – Facilities reviews and approves final AIA Contract copies to be printed and delivered to Facilities.
04/12/18 – Facilities informs GBBN that the contracts have been approved.
04/18/18 – GBBN submits permit applications for Building and Mechanical Permits to the City of Norwood.
05/01/18 – Plumbing and Fire Protection stamped and signed drawings sent to GC for permitting.
05/08/18 – GBBN/TEI send Plumbing CAD drawings to contractor.
05/08/18 – GBBN forwards tax exempt form to Contractor via Facilities.
05/09/18 – GBBN forwards CAD reflected ceiling plan to Electrical Contractor.
05/10/18 – GBBN forwards Oswald Keying and Wood Door finish information to Contractor.
05/10/18 – TEI forwards Plans Examination language to GBBN for Revision letter.
05/10/18 – Door Hardware Submittal returned from GBBN to GC.
05/11/18 – TEI forwards MEP Revision Draiwngs to GBBN.
05/11/18 – GBBN sends Construction Change Directive (CCD) #1 to GC.
05/11/18 – GBBN coordinated revised door swings, locations and hardware with Facilities, BOE and Door Hardware Consultant. Plan Revision letter finalized.
05/17/18 – City of Norwood notifies GBBN that Building and Mechanical Permit are approved. Owner and GC are notified.
05/22/18 – Certified Letter from Becker Electrical forwarded from Purchasing to Facilities and GBBN. GBBN forwards Plan Revision Letter and documents to General Contractor. GBBN completes and forwards revised Door Submittal to GC. TEI sends approved Light Fixture Submittals to GBBN, then forwarded to GC.
05/23/18 – Pre-Construction Meeting is held at BOE Offices. City of Norwood informs GBBN that specification books were not included in permit approval package picked up by GC. Tumlin notified. HVAC and Plumbing Fixture Submittals returned by TEI and forwarded to GC. TEI informs resubmittal will follow for Pressfit.
05/24/18 – Electrical Stamped and Signed Drawings given to Electrical Contractor for IBI Permit. First of Tumlin Background Checks have cleared the Local stage.
05/29/18 – ThermalTech attended pre-const meeting with project team and has completed submittal review for the plumbing and HVAC for this project. TTC will try to complete the Fire protection review by 5/31. Plumbing press-fit fittings were approved for use on this project.05/30/18 – GBBN distributes Pre-Construction Meeting Minutes to all attendees. Plumbing Re-submittal approved by TEI and distributed by GBBN to GC. TEI reviews Fire Protection Submittals and indicates “Revise and Resubmit”. GBBN forwards to GC.
05/31/18 – Fire submittal was asked for revise and resubmit and returned to the contractor. Electrical still needs to see conduit and feeders and lights. Flooring samples are approved.
06/06/18 – Construction Meeting #1 is held at BOE. Site investigation and photos are taken. Wood Door stain approval is hand delivered.
06/13/18 – Construction Meeting #2 is held at BOE. Site investigation and photos are taken.
06/20/18 – Construction Meeting #3 is held at BOE. Site investigation and photos are taken. It was determined the plumbing for the restrooms are were switched. Plumbing inspection was held
06/27/18 – Construction Meeting #4 is held at BOE. Site investigation and photos are taken. Change Order #1 originals, signed by the Architect, are delivered to JPT for signatures.
07/11/18- GBBN issues Construction Change Directive #2.
07/20/18- Signed copy of Application for Payment #2 is received by GBBN from Facilities.
07/24/18 – GBBN resends permission letter from BOE to Tumlin, copied to LaForce and Kleine and sons, concerning the lock core bit number/key for new core keying.
07/25/18 – Construction Meeting #5 is held at BOE. Site observation and photos are taken. Punchlist date to coincide with Construction Meeting #7 on 8/8/18. TTE followed up on some plumbing, fire and hvac items with the contractors. GBBN also completed Architectural/GC Punch List.
08/01/18 – Construction Meeting is held.
08/08/18 – GBBN and TEI conduct Punch List inspection. Construction Meeting is held afterwards.
08/15/18 – GBBN receives Application for Payment #3 (after requested revisions from Pencil Copy Review).
08/16/18 – GBBN resends all door keying information from bidding to Tumlin to be forwarded to LaForce once again.
08/17/18 – GBBN forwards approved Application for Payment #3 to Facilities.
08/24/18 – Build-Out review meeting with BOE personnel. TTE completed back punchlist of MFEP items and submitted back to GBBN for distribution for the project. GBBN submits all Punch Lists and Back Punch Lists to Facilities for all disciplines.
08/25/18 – GBBN receives from Tumlin the completed and signed Punch Lists including the completion of the Fire Protection Record.
08/28/18 – GBBN receives via email Change Order Request #3 from Tumlin.
08/29/18 – Pursuant to the Counties directive the Construction Change Order Request from Tumlin is rejected.
09/07/18 – GBBN approves pencil copy of Application for Payment #4.
09/11/18 – GBBN signs and delivers Application for Payment #4 to Facilities.
09/17/18 – GBBN receives Warranty and Close out Manuals from Mayers Electric via transmittal from Tumlin.
09/27/18 – GBBN turned over electrical closeout documents to TTE for review and approve. BOE confirmed the access controls are done, cleaning is scheduled, supplies are ordered, training is scheduled for next week. HVAC training still needed.
10/02/18 – GBBN receives Mayers Electric Signed Completed Punch list.
10/08/18 – GBBN signs and delivers Final Application for Payment #5 to Facilities for Processing.
10/23/18 – TEI reviews electrical close out documents and delivers to HCFD for archiving. ThermalTech sent all plumbing field work to Bert for clogged drain issue.

1/21/19 – GBBN recieves closeout documents from Tumlin. MEP portion distributed to TEI for review. Closeout AIA documents sent to Facilities.

1/18/19 – TEI acknowledges approval for MEP closeout documents. Still awaiting as-built drawing from MEP Subcontractors.
02/26/19 – GBBN recieves inquiry from Tumlin concering closeout of Application for Payment #5.
02/27/19 – GBBN meets with Facilities to review all closeout documents in possession of both GBBN and Facilities. A final list of the missing items is inventoried and reported back to Tumlin.

03/26/19 – Final fire alarm inspection scheduled to be performed at 1:30 on 03/28/19. Project closeout will be completed after the final inspection.

BOE – Training Center Renovation Build-Out Read More »