DDS – Franks Center Roof Restoration

01/07/20 – Hamilton County requested SOSS for roof restoration project.
01/13/20 – Meeting setup up, but cancel by County.
02/11/20 – THP and County walked the site for a SOSS.
02/18/20 – THP issued SOSS to County for review.
04/15/20 – County review documents issued.
04/21/20 – THP received summary WTI moisture analysis reports.
04/24/20 – Bid documents issued.
04/29/20 – Alternate No. 1 issued.
05/13/20 – Alternate No. 2 issued.
05/20/20 – Bids received and Imbus Roofing is the apparent low bidder.
05/28/20 – THP issued a bid summary letter and draft contract to the County.
06/15/20 – Contract have been processed.
07/07/20 – County issued PO.
07/30/20 – Roof work anticipated to start mid-August.
09/21/20 – Gravel removal started.
10/2/20 – Gravel removal completed. THP and Imbus located 400 S.F. of unit cost repair items.
10/7/20 – Unit cost roof repair items being complete.
10/15/20 – Located (2) poor areas of roof installation at RTUs. Imbus to provided a follow up repair of the installation.
10/29/20 – Project update: 40% of surfacing installed and 90% of unit cost repair completed.
11/17/20 – Bulletin No.1 issued for pricing.
11/25/20 – Imbus submitted pricing for bulletin No. 1.
12/01/20 – Bulletin No. 1 pricing approved via email. Change order being processed.
12/04/20 – Change Order No. 1 issued for processing.
12/10/20 – THP received Change Order No. 1 from Imbus. THP forwarded to the County for final execution.
12/10/20 – Project update: 95% of project base bid work complete.
01/12/21 – Project punch list completed. A few small items noted.
01/18/21 – Imbus submitted January pay application (minus retention). THP processed it and sent to Hamilton County.
01/18/21 – Imbus submitted draft project manual.
01/22/21 – Imbus reported all punch list work completed. THP and Tremco to verify final installation.
03/04/21 – Final closeout documents sent to the County. All closeout documentation approved. THP to deliver hard copies to DDS and Facilities.

DDS – Franks Center Roof Restoration Read More »

DDS – Security Upgrades

11/28/19 – DDS contacts GBBN by telephone to discuss project and Architectural involvement.
11/29/19 – DDS forwards the four facilities Security Reports from Risk Management to TEI and copies GBBN.
01/09/19 – TEI informs GBBN the approved SOSS and Purchase Order were recieved from DDS.
01/15/19 – GBBN and TEI met with DDS Administration to discuss scope and direction for project.
01/16/19 – TEI and GBBN send updated budgetary information to DDS for Budget Analysis.
01/22/19 – DSS sends to TEI and GBBN the Proposed Security Assessment Budget for review and input.
02/08/19 – GBBN contacts bullet resistant glazing and frame contractors to discuss material and system selections.
02/11/19 – GBBN meets DDS at Fairfax School to discuss issues and options for the Receptionist renovations after reviewing the original renovation drawings for this earlier renovation area.
02/15/19 – GBBN forwards preliminary Scoping Drawings, for eaach floor of each of the four facilities to DDS for review and comment.
02/18/19 – DDS requests meeting with Administration to review scoping drawings and Optional Plan Layouts for the Support Center Receptionist area.
03/13/19 – GBBN communication estimated fee and scope to TEI for Owner requested Life Safety Plan updates.
04/05/19 – Owner review meeting with TEI and GBBN is held. Opinion of Probable Costs are reviewed. Owner indicates scope and estimated Construction Costs are per Owner’s needs and wihtin budget. Design team is approved to proceed with next phase SOSS for services.
04/18/19 – DDS confirms new door hardware on existing restroom doors is to be of a locking type.
04/23/19 – GBBN recieves confirmation from Owner that new Support Center Receptionist Layout and Safe Harbor Rooms are to be added to the Life Safety Evacuation Plans.
04/24/19 – Owner review documents are sent to DDS for review, of the LIfe Safety Evacuation Plans.

DDS – Security Upgrades Read More »

DDS – Rost and Franks Re-Paving and Sealcoat Project

04/27/18 – DDS and GBBN hold kick-off meeting to discuss project scope of work and services.

05/23/18 – DDS and GBBN hold first project and document review meeting.

07/19/18 – DDS and GBBN hold final review meeting before release of contract documents for bidding.

07/23/18 – Preliminary Bidding Documents sent to ARC for review and comment.

07/24/18 – Final Contract Documents posted to ARC and Purchasing.

08/14/18 – Pre-Bid Meeting held at Rost School.

08/21/18 – Addenda #1 posted.

08/23/18 – Bid Opening held. Three bids were received. Westside Paving & Excavation, Inc. was the apparent low bidder.

08/24/18 – GBBN holds bid interview meeting with Westside. GBBN issues letter of recommendation to DDS in favor of Westside as low and responsible bidder.

08/27/18 – GBBN completes authoring of AIA contract for Westside and delivers to DDS.

09/14/18 – Notice to Proceed sent from DDS to Westside.

09/17/18 – Contracts delivered from DDS to Westside.

09/21/18 – Pre-Construction Meeting held at Rost School. 10/3/18 established as the contract date.

09/24/18 – Schedule of Value Preliminary received by GBBN from Westside

09/26/18 – Schedule of Values and Mix Design Approvals sent back to Westside Paving.

10/17/18 – Logistics meeting held with WPI, GBBN and DDS Directors and Facilities Manager. Schedule agreed to in principal, with dependency on weather.

10/22/18 – WPI starts with Site Mobilization.

10/23/18 – Milling and parking block removal are started. By end of day all milling at Franks up to Rost service drive are completed.

10/24/18 – Paving is completed at all areas. Striping should be completed by 10/27/18.
04/15/19 – DDS Facilities Manager requests status of close-out repairs remaining. Indicates painting of speed bumps has beeen completed by Owner.
04/16/19 – GBBN and Facilites Manager meet on site to finalize the remaining close-out repairs required. GBBN transmits findings to Westside Paving.

DDS – Rost and Franks Re-Paving and Sealcoat Project Read More »