Hamilton County Facilities

PBS-A

Paul Brown Stadium
Archive

PBS – Sound System Repair Project

03/21/06 – TEI asked for an engineering change order which covers extra time spent by ThermalTech during the construction phase and occupancy permit time on this project. Joe said he signed it and went on to his boss Eric Stuckey. This project is officially complete.

02/13/06 – TTC finally approved the closeout documents, final pay applications # 6 & 7 and as-built drawings for this project. The only thing left is TE request for additional payment.

12/02/05 – TE requested a revised final payapp reflecting $6200 change order that was approved for the north end zone speakers. All final paperwork and as-builts have been received from Durrell in hard copy and CD. TTC made a copy of this information and is sending all originals to Joe Feldkamp for his use included 3 binders of O&M’s required by spec. TE will have have a hard copy of the 1/2 sized dwgs, just the CD.

11/30/05 – Chris Schaeffer called to inform Terry that the County reached settlement with Ed Simon and his lawyer’s and that a court appearance would not be needed.

11/28/05 – Upon final check the sound system is working, the new speakers are installed and working and the final paperwork has all arrived including the as-builts for this building. TTC has to write an engineering change order for ThermalTech’s Extra Time and WJHW Extra Time on this project and submit it for payment for the year 2005.

11/14/05 – Durrell and TJ’s total change order totaled $6200 ($5600 + $600). Joe Feldkamp approved. TTC confirmed with both contractors. Chris Horrell and Scott have scheduled Durrell’s visit for this Wed 1/16/05. Work to be completed by Thursday. TE shall send out the hard copy paperwork to all vendors.

11/10/05 – TTC was contacted by Chris Schaeffer about a possible court appearance in December over the bidding of this project. TTC discussed County bidding procedures and current ORC requirements for bidding and how the Sound Engineer, Audio Contractor and Electrical Contractor was selected for this project.

09/12/05 – Pay Application #4 is being resent to TE. TTC will approve and send to County for payment. TJ delivered payapp to TE today.

09/08/05 – TTC emailed contractors about closeout for project and punchlist. Sound was excellent last Friday when TTC went to the Colts-Bengals preseason game. TTC sat in section 315 and was impressed with quality of sound and clearness of PA announcer.

08/09/05 – Durrell reported that, Tom and I went over these items and will have most knocked out this week prior to this weekends game. What will be left will have to do with getting QSC down to make the cosmetic changes to the amplifier control system to make it that much more user friendly and correctly control the amplifiers that are being displayed.

08/08/05 – TTC coordinated the final change order amounts with TJ Williams and will modify the change orders for final signing today. Both change orders are complete. TTC will deliver them by hand to PBS tomorrow and try to get Bill Meyer to stop down and sign them. Punchlist was compiled and emailed out to contractors (hyperlink below).

08/01/05 – WJHW and Durrell completed the punchlisting work. Ron Baker is going to send the punchlist to TTC for distribution. TTC talked to Scott Simpson about items that he needed added from his end and left a message for Joe about his items. The consensus appears to be that everything is very nearly complete and everyone is very happy. Hopefully this will lead to a quick closure and a working sound system ready for the season in a very short time period.

07/19/05 – We have reached resolution on the PBS Sound Change Orders. Amy will approve change order #1 8855.00 for the countertops and change order #2: 2,060.74 for restocking fees from TJ. TE will write the new change orders for these amounts and send them to TJ for signatures and then onto JF for signatures by the County. WJHW and Durrell have scheduled the Engineering Commissioning for this project on 07/27 thru 07/29. TTC will be out of town on Wednesday but will assist on Thurs/Fri as needed. Punchlist should be fine as Durrell and Scott Simpson have been working hand in hand during the project. TE and WJHW will supervise and TE will try to set up and Const Mtg on Friday for a final update on progress before we start the as-built drawings for this job. Durrell reported by email on 07/18/05:

Last week Durrell got all the speakers working (with only two exceptions) and wired to the correct amplifiers. The West amp room is complete, all racks laced and cleaned, all amplifiers working. The East we ran out of time Friday, but we have all amplifiers working with the correct speakers, we need to spend one day lacing up and minor cleaning.

We found one 2″ driver not working on the East side that will have to be accessed and one crossover on a full range speaker on top of the north end zone – each will require one day’s work.

The west club area is finished and working and the east is about two hours away (got held up due to a wedding party).

The control room is up and working. We had a MediaMatrix card fail (used backup for tuning) and Scott Simpson has to provide us with info where to mount the two computer screens and the Volume meter, both minor installs. The console and all the other equipment is in a functioning correctly including the software upgrades. We want to rebuild the control block that exist for the control screens for QSControl – some coordination will need to exist between Scott Simpson, Tom Moores and we would like Ron Baker’s input – when the commissioning is done.

Durrell will schedule two days prior to WJHW’s coming to PBS for their commissioning to be sure all of these minor items are finished. We are waiting on Ron Baker for that date (date has been set see above)

07/08/05 – Eric Stuckey, Joe Feldkamp, Diana Craynon and Bill Meyer called today to inform me that the change order has be stopped and no work will be done on it and it is most likely canceled until later. We informed TJ Williams and TTC is supposed to cancel Monday’s field trip to work on it.

07/05/05 – TTC emailed Eric Stuckey the final Change Order #01 cost including the cabling and the countertop for approval. PDF. TTC met Chris Schaeffer, Scott Simpson, Steve Durr, Sam Kinman and Ed Simon and his associates downtown today to supervise a field visit and walk through with the County for the County lawsuit.

06/27/05 – TTC sent out CD’s to HamCo for law suit.

06/23/05 – TJ Williams sent the revised ACO out today. PDF. Terry and Joe asked for TJ to redo the change order to reelect the credit that the County will be receiving in place of the speaker parts that won’t be installed. TTC and JF will then talked to Amy about writing a change order to finish the project off with the cabling upgrade. The Const Mtg verified that many, many of the issues with the speakers were resolved by fixing wiring and termination points. ThermalTech believes that by knowing this it is a fair inference that the 3000 foot cable splices are probably not infallible.

06/22/05 – Const Mtg #02 was held. Durrell reported that all base work is complete except for software upgrade on MM. Durrell offered to do all the CO work except for the cabling for the $50,000 allowance. TTC agreed that this work be a fair barter. We decided to accept the countertop change order from jb schmitt. We will pursue a change order to get the cabling issue taken care of this year and Joe and TTC will talk to Amy about it after TJ provides an update T&M price NTE for the work.

06/16/05 – TTC visited the site earlier in the week with JB Schmitt and they turned in a quote today for the new countertop work at PBS. TTC forwarded the quote to the team for a decision. Countertop = $5695.00 and New Window = $3160.00.

06/06/05 – Durrell sent an email request Topper be added to all correspondences on this project. TE forward to Joe Feldkamp for approval. PDF.

05/31/05 – TE tried to reach WJHW for a conference call to discuss moving forward with additional bidding on Change Orders for this project. CO# 2 and CO# 4 are significant and may have to be bid out separately. TJ Williams called today to see about CO approvals. TTC sent the Allowance email to Bill Meyer. TTC should have sent last week when it was approved but somehow that didn’t happen. TE and WJHW still need to talk to Joe about Club Level work and scope.

05/24/05 – TE issued a recommendation letter to PBS about Change Orders for this project. TE spoke to Durrell and told them they must proceed with scheduling on the assumption that the Change Orders # 2 and # 4 are not approved. The County will issue a formal approval as soon as it can. This may lead to scheduling conflicts later near substantial completion but bidding and change order policies must be adhered to for this project. PDF

05/17/05 – Consultants and JF are in consultation about approving change order request. TE has requested direction from their sub WJHW on what is essential and what is not. First TJ payapp is approved and sent to JF.

05/11/05 – TJ submitted 5 change orders today to the project. PDF TE setup a construction meeting for Thursday at 1:30 p.m. to discuss project progress. TJ contracts are signed and in security for contractor to pick up.

04/27/05 – Contract has been approved by the Commissioners. TTC advised the contractors that the contract and PO would soon be in their hands. TE and WJHW will have subs complete by the end of the week.

04/26/05 – WJHW has submittals for AV work on the job. TE has reviewed the submittals fro EC compliance and found no errors so we will approve them with “No Exceptions Noted” to that end, we have told TJ the same. TJ inquired about contract approval and TE told them Wed at Board meeting, we should know. Please advise us when you hear information about Contract.

04/22/05 – TE received submittals for TJ yesterday. TE is checking for EC items. TE shipped one to WJHW for AV items. TE has delivered all dwgs and specs to TJ for permit application. JF reported that contract is in front of board for approval on 04/27/05. Everyone is still working at their own risk to date. Durrell has sound system working in bowl for weekend draft picks. County Prosecutor asked for some video footage of splice problems in the amp rooms. PBS reported that some have been fixed but other still remain to be documented and that Durrell may know best which ones to document. JF and TTC communicated about this pre-work in email PDF.

04/19/05 – TE sent out an email stating the Durrell may be doing some additional work in the Club levels that is above the scope of work outlined in the contract. Monies for this work shall be determined later.

04/18/05 – TJ sent their employee list into the County for this project. PDF. JF reported that contracts have been submitted and the project is up for Board approval on 04/27/05.

04/12/05 – TE had TJ resign new contracts forms and delivered to Kerry Dowling for approval. Kerry said that she would sign these on 04/11/05 and TE would have City Dash pick up the newly signed contracts and have them delivered back to Joe Feldkamp for submission to the County Commissioners for approval. TE sent 3 sets of dwgs to Dallas for WJHW to sign for TJ to turn into IBI for permit sets. TE and JF told TJ at the pre construct mtg on 04/11/05 that all work done by Durrell and TJ before receiving the contract and the PO is “at your own risk” type work.

02/23/05 – TE delivered contact to Joe Feldkamp. TTC and JF discussed contractor over phone and coordinated paperwork due to prosecutor. JF will submit contract for prosecutor review. TE will hold on notification to contractors until all paperwork is finalized. TTC would like to see 2 week turnaround in contract to keep scheduled intact.

02/22/05 – TE has received all required bid paperwork and finalized the Contract. Contract, Drawings, Spec Books and Drawings will be sent to Joe Feldkamp today.

02/16/05 – County and PBS indicated to proceed with Base Bid and Alternate 2 for this project.

02/16/05 – TTC and WJHW discussed the Alternates from the bids and are basically recommending that the County accept Alternate # 2 at this time and wait on Alternate # 1 because of the unknown variables included with updating the system. TE recommends fixing all the existing problems first before adding a new layer of master control that my contribute new and undiscovered problem of us to troubleshoot in the field plus upgrading to the BIAMP system will add additional dollars to the existing SOSS as this is a scope change for engineering (WJHW is working on an adder price). We will write the contract with Alternate #2 for the time being.

02/08/05 – Bids opened. TJ Williams appears to be the low bidder. TE has contacted contractor for additional paperwork and will begin contract work immediately. County needs to provide a signed bid evaluation form with Alternate recommendations for contract.

01/25/05 – Addendum 3 distributed. Durrell asked a new question for Addendum 4. The bid was extended to February 3, 2005.

01/21/05 – TE coordinated with WJHW and County to extend bid date one week and to send out Addendum 03 on Monday with updated information for bidding and alternate. Purchasing Department instructed TE to contact ICB Audio via email about non-inclusion into the accepted bidder’s list for this project.

01/20/05 – TE distributed Addendum 01 on 01/11/05 and Addendum 02 on 01/20/05. Addendum 03 should come out on 01/21/05. TE has written a rejection letter and given it to Purchasing to give to ICB as they do not meet the Professional Stadium Experience Requirement on this project. The SoundCom qualifications have been sent to WJHW for review and we are currently waiting on SoundCom to confirm a couple of questions about which office will serve this project but they most likely will be approved for bidding as they do meet the quals. TTC asked if the bid should be extended since SoundCom is being added. TE is awaiting the County’s decision. The second prebid was attended by about 8 contractors. Muzak declined to bid and left the prebid after we stated that OEM equipment must be used for repair.

01/19/05 – Prebid is finished. Addendum # 01 wads distributed. Addendum # 02 is going out tonight. Addendum # 03 is scheduled out tomorrow. ICB will not be an approved vendor. TE has to provide a letter to Purchasing for the use, modify and send.

01/14/05 – Joe Feldkamp called to inform TE that because the prosecutor wants a firm number for cost to provide as-built drawings that we can change the bid for to add an alternate to have the AV contractor provide a complete set of as-builts encompassing the entire scope of work at the stadium. TE shall modify the bid form accordingly.

12/24/24 – TE invited Audio Specialist Contractors. Project Manual is on the street, on schedule. Prebid set for January 5th. WJHW will be in town for the prebid. Everything appears to be set for bidding att his time.

11/04/04 – TE found and sent the AV drawings to WJHW today. Final design is still scheduled for final delivery on 12/08/04.

10/25/04 – WJHW sent an informal report from the field trip last week. PDF

10/19/04 – TE, WJHW, PBS and HamCo had a meeting and set the following schedule for this project (see below)

10/19/04 – TE and WJHW met onsite with the owners and ironed out the scope of the project, schedule of the project and the expectations of the project. WJHW will begin design and target first week of December for final engineering documents. TE will release minutes in a follow up email. Contract will be bid to a local EC with a Audio Specialist assigned as a sub.

10/15/04 – TE will meet WJHW onsite on Tuesday for kickoff meeting. WJHW will be onsite late Monday afternoon. They have coordinated their time with Scott Simpson.

ThermalTech solicited consultant bids and wants to team with WHJW from Texas for this project.

Conference call on August 17 between Eric Brown, Bob Bedinghaus, Joe Feldkamp and Terry Cannon with WHJW was held to discuss itemized consultant cost and scope of consultant work on this project.

TE is awaiting a signed SOSS from the County.

The County is awaiting a one page report from WHJW outlining the added benefits of using WHJW on top of the Durrell report.

Project scheduled to be signed in August 04, Designed in Sept – Oct 04, Bid Nov 04, Awarded in Dec 04, Construction Jan 05.

PBS – Sound System Repair Project Read More »

PBS – Occupancy Redistribution Project

03/20/06 – Joe approved TEI’s cost on the ECO for Sound project. This project is officially complete and ready to be archived.

11/30/05 – After speaking with City Permit office they confirmed that TE did pay for these permits. TTC called Randy this morning and told him that these permits were paid for on 10/18/05. TTC is awaiting a call back to clear this up.

11/25/05 – Randy Campion called to inform TE that there is a remaining balance on these permits. TTC called the city to see what that cost was because TE has already paid for the new permits with a check. Once this is cleared up Randy will send new Certificates of Occupancy.

10/18/05 – All revisions have been accepted and approved by the City. New permits costs = $354.00. New occupancies have been set to 1021 (East Club) and 986 (West Club). According to Randy Campion once the permit is paid for, which TTC did today, the permit will close and information will be sent to Fire Dept. They will issue a new occupancy for private club events. to PBS.

09/28/05 – The City received all the information from Cole & Russell but need it properly inserted into the permit dwg sets. TTC will stop at the permit office and manually do this on Friday or earlier if possible.

09/20/05 – After the City sent the letter emailed by TTC to PBS yesterday requesting additional egress information, TTC talked to Cole & Russell about this information. C&R believes that they already have all that information collected from the sliding door project and will call Carl Graeber and discuss directly with him. They can get all that information to the City on Friday or early next week. TTC will check back with city and C&R about progress at that time. We believe the city will accept this and process the permit app immediately thereafter for final inspection.

09/08/05 – TTC contacted city. Permit should be reviewed by 09/13/05. TTC will check back at that time.

08/25/05 – The permit is still being reviewed by the City. TTC will continue to check on status.

0815/05 – TTC met Randy Campion at the PBS site on Monday, Randy approved the 821 and 851 increased occupant load and will sign the CO paperwork and send it to PBS. After the meeting, PBS said that the 30% OA was not a problem so that they want even higher occupant loads. TTC turned in another set of prints with the higher numbers of 986 and 1021. The city made us turn in for all new permits: 2005P06669 and 2005P06670.

07/18/05 – City called with Approved Permit numbers today. Permit was split up into 2 permits 2005P05544 AND 2005PO5589 ($284). TTC will pick-up permit on Tuesday morning. Inspector, Randy Campion has to come to the site to approve and give us a new CO for the space. This will be coordinate with HamCo & PBS in the next couple of weeks.

06/30/05 – TTC got GD to sign occupancy permit drawings in regards to HVAC OA requirements. TTC submitted for permit. Permit # 2005P05544. TTC informed all parties that permit can be checked at www.cincinnati-oh-gov at anytime. Amit was also promoted to Project Manager, so we are unclear if he will review this permit.

06/16/05 – Eric called today and TTC reported that Amit had returned one of his phone calls stating that he was seriously behind in permit reviews. With that knowledge, TTC stated that we should just go ahead and subject a revised CO application and talk to him them as opposed to conferencing in with him early.

06/06/05 – TTC sent an email outlining TE’s field findings to Joe, Sam and Eric. TE need direction from PBS to proceed on next level or work.

06/03/05 – Sam Boehringer of TE collected field data to update actual occupancies of the space.

05/25/05 – Eric Brown setup a meeting with the CFD department about occupancy requirements of the club level space.

PBS – Occupancy Redistribution Project Read More »

PBS – Deep Well Pump Replacement

03/23/06 – TTC spoke to John Wagner of Moody’s today and here is where the problem is: the actual repairs cost $15,573 not $6573, the 6573 +the 9000 already paid = the total cost of repairs on this job. This means that they are still giving you back $4427 on the job. John outlined this in a letter in September which I am having faxed to me. With this information, I will redo the paperwork and send it up to John for use on completing this project. I have to write a new change order, allowance usage and final pay application to make all the numbers work out right.

03/20/06 – TEI received final paperwork on this project today from Moody’s. This will be forwarded to Joe for payment on this project. TEI to begin phase II service contract immediately.

02/16/06 – Moody contacted TEI to request AIA forms. TTC sent them out in US mail for their use. They should complete these, notarize them and get them back for closeout.

02/06/06 – After an inquiry by Sam Kinman, TTC found the payapps sent to ThermalTech for approval. They were approved by Sam on 11/21/05. The problem is that they are not on AIA invoices which means there is no where for TTC approve. Assuming they are approved by TTC on these forms, the Contractor still has not turned in standard county documents for project closeout. TTC will forward a copy to Moody’s and ask for return of these documents. TTC completed a full packet of information required and mailed to Moody’s today via US Mail. TTC will follow up with a phone call today as well.

11/30/05 – Sam Kinman reported today in an email back to TTC that the deep well pump replacement job is complete. Since TE wasn’t used very much during construction, TTC assumes the punchlist is fine and no additional work needs to be done. TTC will archive the project from the database and closeout the project number. TE has never received a payment to approve, nor the final County paperwork to approve for that payment, nor manage any of the allowance monies. All this will need to be done before the project is closed out in the County’s books.

08/08/05 – TTC contacted the County about status of the Deep Well Pump Contracts. The previous entry does not state that the contracts were sent to PBS.

07/18/05 – Bid were opened. Moody was apparent low bidder at about $29,400. $20,000 in Alternates can be taken (ALT #1 and ALT #3). TE has contract written for $49,400 and will give 4 original copies to PBS for approval with Board. Bid PDF

07/05/05 – TTC worked on July 4 to get Addendum 2 complete and sent it out for distribution. PDF

06/27/05 – TE worked on Add01 and it will go out to the Contractors on 06/28/05. PDF

06/13/05 – TE sent out Project Manual for bidding. PDF

06/06/05 – Comments received from Sam and John Wagner of Moody in Dayton. TTC will update Project Manual and prepare for bidding ASAP. PBS talked about including a 3-year service contract on top of the bid. TE has done these in the past and can add this scope to the project if so directed by the County for bidding. This would be an engineering scope change to this project but it makes very good sense to include it now (12 hours x $80 = $960) and that includes the contract modifications for the Alternate bid to take optional years.

06/01/05 – Comment received from Joe and Eric. Nothing from Sam yet.

05/30/05 – TTC sent a project manual out for review over the weekend to PBS and County. Once comments are received, TE will distribute to public for bidding. All dates must still be coordinated with HamCo Purchasing.

05/26/05 – TTC contacted Moody’s for some specific questions about parts replacement. The Project Manual is built for front end. TTC needs to add dwgs and mechanical section. Bid Form needs to be modified for this job.

05/17/05 – The team had serious discussions about project schedule today. PBS re-iterated their concern about flooding. TE provided a timetable for construction that appeared not to be acceptable to PBS. TE had discussions with JF about project and will try to speed up project manual creation significantly to lessen risk. It is TE’s belief that County Purchasing has already decreed that this project does not meet Emergency Status.

PBS – Deep Well Pump Replacement Read More »

PBS – Pro Shop Metering Project

03/29/06 – TTC reviewed the billed KW and KWH to the PBS Pro Shop and the numbers looked good. The pro shop is using less than 1% of the total power consumed at the building.

KW KWH
February

50.91 21,863
January

34.91 28,950
December

79.91 25,448
November

59.28 16,077
October

72.30 14,661
September

63.67 16,528
August

53.30 4,166
02/01/06 – TTC check on the meters and to review monthly billings at the site. The meters appear to be reading in the Megawatts which seems really high at first glance. TTC to reconcile with actual building data.

11/16/05 – TA visited the site today. Reviewed punchlist and determined that Bond Electric has not completed the issues described on the punchlist. TE called Bond to tell that them that can’t get paid until these items and the final paperwork is complete.

11/15/05 – As-Built drawings for this job were turned over to Wayne Trent of HamCo Facilities today.

06/17/05 – Const Mtg was held at PBS. Sam did not attend. Equipment is not on site yet but Bond is ready to get to work as soon as it arrives.

02/28/05 – Purchasing called to inform TE that Bond does NOT have a performance bond or check submitted for this project. We should not let them begin work without this paperwork in place. TA to confer with Jack Boland today and emphasize the need for this check immediately.

02/10/05 – Contracts and Bid Results are in County’s hands. TE awaiting further direction on this project.

11/17/04 – Bid Results

10/12/04 – Project is out for bidding.

Addendum#1 distributed.

Addendum#2 distributed.

Addendum#3 distributed

PBS – Pro Shop Metering Project Read More »

PBS – Deep Well Pump Service Contract

02/02/07 – After many contract revisions, phone calls and problems, the Prosecutor finally allowed preventative only maintenance contract that Kerry wrote and gave back to everyone to use. Other repairs and emergency repairs must be bid our as prevailing wages. TEI does not and will not every agree with this approach. We took prices for many other services to save the County money but those were not accepted as part of this job by Hamco Prosecutors office.

01/10/07 – TTC got Kerry’s new email address and forwarded the revised contract to her for any final changes that she would like to make. Kerry confirmed that the packet was received at her office.

01/08/07 – TTC hand delivered the final contract with Kerry’s marks to security for Jenny and Joe to pick up and resubmit to the Prosecutor’s Office.

12/26/06 – TTC will finalize the deep well pump contract this week.

03/29/06 – TEI has not heard from Daktronics with a registered service repair list yet so I called and got Greg’s email and sent him the request again.

03/21/06 – TEI finished the SOSS and will drop it off at the HamCo Facility Department on Wednesday for this project.

PBS – Deep Well Pump Service Contract Read More »

PBS – Energy Study

03/20/07 – Project ready to archive.

11/30/05 – TTC and GD have to meet internally to review the 10/11/05 findings and energy usage. GD believes there can be savings found in schedules and space control but we will need “buy in” from facility department to implement. TTC has to setup meeting with GD to review other items but County end of year crunch on projects has dampened progress. All work will be done by end of year.

10/11/05 – TTC and GD met on site and reviewed the whole facility with Sam, Joe, Eric and the financial manager.

05/10/05 – Kickoff meeting for project with JF, TTC.

PBS – Energy Study Read More »

PBS – Video Wall Replacement Project

12/19/07 – Nor Comm has provided the AIA closeout paperwork, warranty letter and payapps. TTC signed and City Dashed it to Joe Feldkamp. This project is complete.

09/03/07 – TTC has received and approved the O&M’s. TTC is hand delivering the box of O&M’s and final payapp to PBS tomorrow at 9am at the Deep Well Pump prebid.

08/28/07 – TTC contacted Nor-Com again about final payment via email with a Read Receipt.

08/20/07 – Nor-Com contacted Joe today about final payment. TTC emailed Joe back station what happened to Payapp #2 as listed below. To date, we have not received any additional paperwork.

07/02/07 – TTC has contacted Howard Milkis and Nor-Com several times for closeout on this project. No response to TEI. TTC will try to contact the office directly today and find out how we are going to close out this project.

05/14/07 – PBS did not use TEI service much at all on site during this project. TEI has been in contact with Joe and Scott numerous times during construction as things were going well. TEI contacted owner today for punchlist and closeout items for Nor Comm. As far as TEI knows, this project is complete.

03/30/07 – TE received submittals for review and promised to work on them this week. Nor-Com has a schedule forthcoming.

03/16/07 – Scott and Joe held a kickoff meeting. TTC to follow up and publish some const mtg notes this week. A second Const Mtg is to be scheduled. PBS would like TV in before draft day.

02/13/07 – All contracts and information is in the Prosecutors office for review. Comments have been added and the contract should be approved very soon. TEI provided a copy of the bid results to Kerry Dowling per her request last week. Joe Feldkamp is following up with the Prosecutor Office.

01/30/07 – TEI finished the revised contract and returned it to PBS for use on this project. Now TEI is waiting for approval and signatures to move into a pre construction meeting.

01/10/07 – TTC hand delivered the contract based on the Base Bid cost to Joe for submission to the Prosecutor’s office. TTC included a $2500 allowance in the project after the bids were opened.

12/26/06 – TTC will finalize the deep well pump contract this week.

PBS – Video Wall Replacement Project Read More »

PBS Video Switcher

10/26/09 – Final paperwork is received. TTC approved and mailed to Joe.

09/22/09 – Project is complete. We have approved payapp #2. Once all the closeout paperwork has been received and training is complete. We can close out this project.

08/25/09 – One payapp has been approved. Punchlist has started. Training continues.

07/29/09 – Project has been bid and awarded to Rosco. Work is proceeding and Chris Williams will be able to check in on progress on August 4th when he visits Cincinnati for the Brewers game.

06/23/09 – This project is in contract approval stage at HamCo.

PBS Video Switcher Read More »

PBS Z-Ramp Replacement

09/14/09 – Additional documentation has been sent to Kerry for contract approval.

08/25/09 – Joe needs additional bid information for the project. United needs to provide final bid paperwork to Joe.

0729/09 – Project has been bid. Prices were tabulated and sent to bidders. Final contract was $16,300 and included $500 in allowance monies. TEI has written the contract and given to the County for signing.

06/23/09 – This project is out for small project bidding.

PBS Z-Ramp Replacement Read More »

PBS – Sound System Repair Project

03/21/06 – TEI asked for an engineering change order which covers extra time spent by ThermalTech during the construction phase and occupancy permit time on this project. Joe said he signed it and went on to his boss Eric Stuckey. This project is officially complete.

02/13/06 – TTC finally approved the closeout documents, final pay applications # 6 & 7 and as-built drawings for this project. The only thing left is TE request for additional payment.

12/02/05 – TE requested a revised final payapp reflecting $6200 change order that was approved for the north end zone speakers. All final paperwork and as-builts have been received from Durrell in hard copy and CD. TTC made a copy of this information and is sending all originals to Joe Feldkamp for his use included 3 binders of O&M’s required by spec. TE will have have a hard copy of the 1/2 sized dwgs, just the CD.

11/30/05 – Chris Schaeffer called to inform Terry that the County reached settlement with Ed Simon and his lawyer’s and that a court appearance would not be needed.

11/28/05 – Upon final check the sound system is working, the new speakers are installed and working and the final paperwork has all arrived including the as-builts for this building. TTC has to write an engineering change order for ThermalTech’s Extra Time and WJHW Extra Time on this project and submit it for payment for the year 2005.

11/14/05 – Durrell and TJ’s total change order totaled $6200 ($5600 + $600). Joe Feldkamp approved. TTC confirmed with both contractors. Chris Horrell and Scott have scheduled Durrell’s visit for this Wed 1/16/05. Work to be completed by Thursday. TE shall send out the hard copy paperwork to all vendors.

11/10/05 – TTC was contacted by Chris Schaeffer about a possible court appearance in December over the bidding of this project. TTC discussed County bidding procedures and current ORC requirements for bidding and how the Sound Engineer, Audio Contractor and Electrical Contractor was selected for this project.

09/12/05 – Pay Application #4 is being resent to TE. TTC will approve and send to County for payment. TJ delivered payapp to TE today.

09/08/05 – TTC emailed contractors about closeout for project and punchlist. Sound was excellent last Friday when TTC went to the Colts-Bengals preseason game. TTC sat in section 315 and was impressed with quality of sound and clearness of PA announcer.

08/09/05 – Durrell reported that, Tom and I went over these items and will have most knocked out this week prior to this weekends game. What will be left will have to do with getting QSC down to make the cosmetic changes to the amplifier control system to make it that much more user friendly and correctly control the amplifiers that are being displayed.

08/08/05 – TTC coordinated the final change order amounts with TJ Williams and will modify the change orders for final signing today. Both change orders are complete. TTC will deliver them by hand to PBS tomorrow and try to get Bill Meyer to stop down and sign them. Punchlist was compiled and emailed out to contractors (hyperlink below).

08/01/05 – WJHW and Durrell completed the punchlisting work. Ron Baker is going to send the punchlist to TTC for distribution. TTC talked to Scott Simpson about items that he needed added from his end and left a message for Joe about his items. The consensus appears to be that everything is very nearly complete and everyone is very happy. Hopefully this will lead to a quick closure and a working sound system ready for the season in a very short time period.

07/19/05 – We have reached resolution on the PBS Sound Change Orders. Amy will approve change order #1 8855.00 for the countertops and change order #2: 2,060.74 for restocking fees from TJ. TE will write the new change orders for these amounts and send them to TJ for signatures and then onto JF for signatures by the County. WJHW and Durrell have scheduled the Engineering Commissioning for this project on 07/27 thru 07/29. TTC will be out of town on Wednesday but will assist on Thurs/Fri as needed. Punchlist should be fine as Durrell and Scott Simpson have been working hand in hand during the project. TE and WJHW will supervise and TE will try to set up and Const Mtg on Friday for a final update on progress before we start the as-built drawings for this job. Durrell reported by email on 07/18/05:

Last week Durrell got all the speakers working (with only two exceptions) and wired to the correct amplifiers. The West amp room is complete, all racks laced and cleaned, all amplifiers working. The East we ran out of time Friday, but we have all amplifiers working with the correct speakers, we need to spend one day lacing up and minor cleaning.

We found one 2″ driver not working on the East side that will have to be accessed and one crossover on a full range speaker on top of the north end zone – each will require one day’s work.

The west club area is finished and working and the east is about two hours away (got held up due to a wedding party).

The control room is up and working. We had a MediaMatrix card fail (used backup for tuning) and Scott Simpson has to provide us with info where to mount the two computer screens and the Volume meter, both minor installs. The console and all the other equipment is in a functioning correctly including the software upgrades. We want to rebuild the control block that exist for the control screens for QSControl – some coordination will need to exist between Scott Simpson, Tom Moores and we would like Ron Baker’s input – when the commissioning is done.

Durrell will schedule two days prior to WJHW’s coming to PBS for their commissioning to be sure all of these minor items are finished. We are waiting on Ron Baker for that date (date has been set see above)

07/08/05 – Eric Stuckey, Joe Feldkamp, Diana Craynon and Bill Meyer called today to inform me that the change order has be stopped and no work will be done on it and it is most likely canceled until later. We informed TJ Williams and TTC is supposed to cancel Monday’s field trip to work on it.

07/05/05 – TTC emailed Eric Stuckey the final Change Order #01 cost including the cabling and the countertop for approval. PDF. TTC met Chris Schaeffer, Scott Simpson, Steve Durr, Sam Kinman and Ed Simon and his associates downtown today to supervise a field visit and walk through with the County for the County lawsuit.

06/27/05 – TTC sent out CD’s to HamCo for law suit.

06/23/05 – TJ Williams sent the revised ACO out today. PDF. Terry and Joe asked for TJ to redo the change order to reelect the credit that the County will be receiving in place of the speaker parts that won’t be installed. TTC and JF will then talked to Amy about writing a change order to finish the project off with the cabling upgrade. The Const Mtg verified that many, many of the issues with the speakers were resolved by fixing wiring and termination points. ThermalTech believes that by knowing this it is a fair inference that the 3000 foot cable splices are probably not infallible.

06/22/05 – Const Mtg #02 was held. Durrell reported that all base work is complete except for software upgrade on MM. Durrell offered to do all the CO work except for the cabling for the $50,000 allowance. TTC agreed that this work be a fair barter. We decided to accept the countertop change order from jb schmitt. We will pursue a change order to get the cabling issue taken care of this year and Joe and TTC will talk to Amy about it after TJ provides an update T&M price NTE for the work.

06/16/05 – TTC visited the site earlier in the week with JB Schmitt and they turned in a quote today for the new countertop work at PBS. TTC forwarded the quote to the team for a decision. Countertop = $5695.00 and New Window = $3160.00.

06/06/05 – Durrell sent an email request Topper be added to all correspondences on this project. TE forward to Joe Feldkamp for approval. PDF.

05/31/05 – TE tried to reach WJHW for a conference call to discuss moving forward with additional bidding on Change Orders for this project. CO# 2 and CO# 4 are significant and may have to be bid out separately. TJ Williams called today to see about CO approvals. TTC sent the Allowance email to Bill Meyer. TTC should have sent last week when it was approved but somehow that didn’t happen. TE and WJHW still need to talk to Joe about Club Level work and scope.

05/24/05 – TE issued a recommendation letter to PBS about Change Orders for this project. TE spoke to Durrell and told them they must proceed with scheduling on the assumption that the Change Orders # 2 and # 4 are not approved. The County will issue a formal approval as soon as it can. This may lead to scheduling conflicts later near substantial completion but bidding and change order policies must be adhered to for this project. PDF

05/17/05 – Consultants and JF are in consultation about approving change order request. TE has requested direction from their sub WJHW on what is essential and what is not. First TJ payapp is approved and sent to JF.

05/11/05 – TJ submitted 5 change orders today to the project. PDF TE setup a construction meeting for Thursday at 1:30 p.m. to discuss project progress. TJ contracts are signed and in security for contractor to pick up.

04/27/05 – Contract has been approved by the Commissioners. TTC advised the contractors that the contract and PO would soon be in their hands. TE and WJHW will have subs complete by the end of the week.

04/26/05 – WJHW has submittals for AV work on the job. TE has reviewed the submittals fro EC compliance and found no errors so we will approve them with “No Exceptions Noted” to that end, we have told TJ the same. TJ inquired about contract approval and TE told them Wed at Board meeting, we should know. Please advise us when you hear information about Contract.

04/22/05 – TE received submittals for TJ yesterday. TE is checking for EC items. TE shipped one to WJHW for AV items. TE has delivered all dwgs and specs to TJ for permit application. JF reported that contract is in front of board for approval on 04/27/05. Everyone is still working at their own risk to date. Durrell has sound system working in bowl for weekend draft picks. County Prosecutor asked for some video footage of splice problems in the amp rooms. PBS reported that some have been fixed but other still remain to be documented and that Durrell may know best which ones to document. JF and TTC communicated about this pre-work in email PDF.

04/19/05 – TE sent out an email stating the Durrell may be doing some additional work in the Club levels that is above the scope of work outlined in the contract. Monies for this work shall be determined later.

04/18/05 – TJ sent their employee list into the County for this project. PDF. JF reported that contracts have been submitted and the project is up for Board approval on 04/27/05.

04/12/05 – TE had TJ resign new contracts forms and delivered to Kerry Dowling for approval. Kerry said that she would sign these on 04/11/05 and TE would have City Dash pick up the newly signed contracts and have them delivered back to Joe Feldkamp for submission to the County Commissioners for approval. TE sent 3 sets of dwgs to Dallas for WJHW to sign for TJ to turn into IBI for permit sets. TE and JF told TJ at the pre construct mtg on 04/11/05 that all work done by Durrell and TJ before receiving the contract and the PO is “at your own risk” type work.

02/23/05 – TE delivered contact to Joe Feldkamp. TTC and JF discussed contractor over phone and coordinated paperwork due to prosecutor. JF will submit contract for prosecutor review. TE will hold on notification to contractors until all paperwork is finalized. TTC would like to see 2 week turnaround in contract to keep scheduled intact.

02/22/05 – TE has received all required bid paperwork and finalized the Contract. Contract, Drawings, Spec Books and Drawings will be sent to Joe Feldkamp today.

02/16/05 – County and PBS indicated to proceed with Base Bid and Alternate 2 for this project.

02/16/05 – TTC and WJHW discussed the Alternates from the bids and are basically recommending that the County accept Alternate # 2 at this time and wait on Alternate # 1 because of the unknown variables included with updating the system. TE recommends fixing all the existing problems first before adding a new layer of master control that my contribute new and undiscovered problem of us to troubleshoot in the field plus upgrading to the BIAMP system will add additional dollars to the existing SOSS as this is a scope change for engineering (WJHW is working on an adder price). We will write the contract with Alternate #2 for the time being.

02/08/05 – Bids opened. TJ Williams appears to be the low bidder. TE has contacted contractor for additional paperwork and will begin contract work immediately. County needs to provide a signed bid evaluation form with Alternate recommendations for contract.

01/25/05 – Addendum 3 distributed. Durrell asked a new question for Addendum 4. The bid was extended to February 3, 2005.

01/21/05 – TE coordinated with WJHW and County to extend bid date one week and to send out Addendum 03 on Monday with updated information for bidding and alternate. Purchasing Department instructed TE to contact ICB Audio via email about non-inclusion into the accepted bidder’s list for this project.

01/20/05 – TE distributed Addendum 01 on 01/11/05 and Addendum 02 on 01/20/05. Addendum 03 should come out on 01/21/05. TE has written a rejection letter and given it to Purchasing to give to ICB as they do not meet the Professional Stadium Experience Requirement on this project. The SoundCom qualifications have been sent to WJHW for review and we are currently waiting on SoundCom to confirm a couple of questions about which office will serve this project but they most likely will be approved for bidding as they do meet the quals. TTC asked if the bid should be extended since SoundCom is being added. TE is awaiting the County’s decision. The second prebid was attended by about 8 contractors. Muzak declined to bid and left the prebid after we stated that OEM equipment must be used for repair.

01/19/05 – Prebid is finished. Addendum # 01 wads distributed. Addendum # 02 is going out tonight. Addendum # 03 is scheduled out tomorrow. ICB will not be an approved vendor. TE has to provide a letter to Purchasing for the use, modify and send.

01/14/05 – Joe Feldkamp called to inform TE that because the prosecutor wants a firm number for cost to provide as-built drawings that we can change the bid for to add an alternate to have the AV contractor provide a complete set of as-builts encompassing the entire scope of work at the stadium. TE shall modify the bid form accordingly.

12/24/24 – TE invited Audio Specialist Contractors. Project Manual is on the street, on schedule. Prebid set for January 5th. WJHW will be in town for the prebid. Everything appears to be set for bidding att his time.

11/04/04 – TE found and sent the AV drawings to WJHW today. Final design is still scheduled for final delivery on 12/08/04.

10/25/04 – WJHW sent an informal report from the field trip last week. PDF

10/19/04 – TE, WJHW, PBS and HamCo had a meeting and set the following schedule for this project (see below)

10/19/04 – TE and WJHW met onsite with the owners and ironed out the scope of the project, schedule of the project and the expectations of the project. WJHW will begin design and target first week of December for final engineering documents. TE will release minutes in a follow up email. Contract will be bid to a local EC with a Audio Specialist assigned as a sub.

10/15/04 – TE will meet WJHW onsite on Tuesday for kickoff meeting. WJHW will be onsite late Monday afternoon. They have coordinated their time with Scott Simpson.

ThermalTech solicited consultant bids and wants to team with WHJW from Texas for this project.

Conference call on August 17 between Eric Brown, Bob Bedinghaus, Joe Feldkamp and Terry Cannon with WHJW was held to discuss itemized consultant cost and scope of consultant work on this project.

TE is awaiting a signed SOSS from the County.

The County is awaiting a one page report from WHJW outlining the added benefits of using WHJW on top of the Durrell report.

Project scheduled to be signed in August 04, Designed in Sept – Oct 04, Bid Nov 04, Awarded in Dec 04, Construction Jan 05.

PBS – Sound System Repair Project Read More »

PBS – Occupancy Redistribution Project

03/20/06 – Joe approved TEI’s cost on the ECO for Sound project. This project is officially complete and ready to be archived.

11/30/05 – After speaking with City Permit office they confirmed that TE did pay for these permits. TTC called Randy this morning and told him that these permits were paid for on 10/18/05. TTC is awaiting a call back to clear this up.

11/25/05 – Randy Campion called to inform TE that there is a remaining balance on these permits. TTC called the city to see what that cost was because TE has already paid for the new permits with a check. Once this is cleared up Randy will send new Certificates of Occupancy.

10/18/05 – All revisions have been accepted and approved by the City. New permits costs = $354.00. New occupancies have been set to 1021 (East Club) and 986 (West Club). According to Randy Campion once the permit is paid for, which TTC did today, the permit will close and information will be sent to Fire Dept. They will issue a new occupancy for private club events. to PBS.

09/28/05 – The City received all the information from Cole & Russell but need it properly inserted into the permit dwg sets. TTC will stop at the permit office and manually do this on Friday or earlier if possible.

09/20/05 – After the City sent the letter emailed by TTC to PBS yesterday requesting additional egress information, TTC talked to Cole & Russell about this information. C&R believes that they already have all that information collected from the sliding door project and will call Carl Graeber and discuss directly with him. They can get all that information to the City on Friday or early next week. TTC will check back with city and C&R about progress at that time. We believe the city will accept this and process the permit app immediately thereafter for final inspection.

09/08/05 – TTC contacted city. Permit should be reviewed by 09/13/05. TTC will check back at that time.

08/25/05 – The permit is still being reviewed by the City. TTC will continue to check on status.

0815/05 – TTC met Randy Campion at the PBS site on Monday, Randy approved the 821 and 851 increased occupant load and will sign the CO paperwork and send it to PBS. After the meeting, PBS said that the 30% OA was not a problem so that they want even higher occupant loads. TTC turned in another set of prints with the higher numbers of 986 and 1021. The city made us turn in for all new permits: 2005P06669 and 2005P06670.

07/18/05 – City called with Approved Permit numbers today. Permit was split up into 2 permits 2005P05544 AND 2005PO5589 ($284). TTC will pick-up permit on Tuesday morning. Inspector, Randy Campion has to come to the site to approve and give us a new CO for the space. This will be coordinate with HamCo & PBS in the next couple of weeks.

06/30/05 – TTC got GD to sign occupancy permit drawings in regards to HVAC OA requirements. TTC submitted for permit. Permit # 2005P05544. TTC informed all parties that permit can be checked at www.cincinnati-oh-gov at anytime. Amit was also promoted to Project Manager, so we are unclear if he will review this permit.

06/16/05 – Eric called today and TTC reported that Amit had returned one of his phone calls stating that he was seriously behind in permit reviews. With that knowledge, TTC stated that we should just go ahead and subject a revised CO application and talk to him them as opposed to conferencing in with him early.

06/06/05 – TTC sent an email outlining TE’s field findings to Joe, Sam and Eric. TE need direction from PBS to proceed on next level or work.

06/03/05 – Sam Boehringer of TE collected field data to update actual occupancies of the space.

05/25/05 – Eric Brown setup a meeting with the CFD department about occupancy requirements of the club level space.

PBS – Occupancy Redistribution Project Read More »

PBS – Deep Well Pump Replacement

03/23/06 – TTC spoke to John Wagner of Moody’s today and here is where the problem is: the actual repairs cost $15,573 not $6573, the 6573 +the 9000 already paid = the total cost of repairs on this job. This means that they are still giving you back $4427 on the job. John outlined this in a letter in September which I am having faxed to me. With this information, I will redo the paperwork and send it up to John for use on completing this project. I have to write a new change order, allowance usage and final pay application to make all the numbers work out right.

03/20/06 – TEI received final paperwork on this project today from Moody’s. This will be forwarded to Joe for payment on this project. TEI to begin phase II service contract immediately.

02/16/06 – Moody contacted TEI to request AIA forms. TTC sent them out in US mail for their use. They should complete these, notarize them and get them back for closeout.

02/06/06 – After an inquiry by Sam Kinman, TTC found the payapps sent to ThermalTech for approval. They were approved by Sam on 11/21/05. The problem is that they are not on AIA invoices which means there is no where for TTC approve. Assuming they are approved by TTC on these forms, the Contractor still has not turned in standard county documents for project closeout. TTC will forward a copy to Moody’s and ask for return of these documents. TTC completed a full packet of information required and mailed to Moody’s today via US Mail. TTC will follow up with a phone call today as well.

11/30/05 – Sam Kinman reported today in an email back to TTC that the deep well pump replacement job is complete. Since TE wasn’t used very much during construction, TTC assumes the punchlist is fine and no additional work needs to be done. TTC will archive the project from the database and closeout the project number. TE has never received a payment to approve, nor the final County paperwork to approve for that payment, nor manage any of the allowance monies. All this will need to be done before the project is closed out in the County’s books.

08/08/05 – TTC contacted the County about status of the Deep Well Pump Contracts. The previous entry does not state that the contracts were sent to PBS.

07/18/05 – Bid were opened. Moody was apparent low bidder at about $29,400. $20,000 in Alternates can be taken (ALT #1 and ALT #3). TE has contract written for $49,400 and will give 4 original copies to PBS for approval with Board. Bid PDF

07/05/05 – TTC worked on July 4 to get Addendum 2 complete and sent it out for distribution. PDF

06/27/05 – TE worked on Add01 and it will go out to the Contractors on 06/28/05. PDF

06/13/05 – TE sent out Project Manual for bidding. PDF

06/06/05 – Comments received from Sam and John Wagner of Moody in Dayton. TTC will update Project Manual and prepare for bidding ASAP. PBS talked about including a 3-year service contract on top of the bid. TE has done these in the past and can add this scope to the project if so directed by the County for bidding. This would be an engineering scope change to this project but it makes very good sense to include it now (12 hours x $80 = $960) and that includes the contract modifications for the Alternate bid to take optional years.

06/01/05 – Comment received from Joe and Eric. Nothing from Sam yet.

05/30/05 – TTC sent a project manual out for review over the weekend to PBS and County. Once comments are received, TE will distribute to public for bidding. All dates must still be coordinated with HamCo Purchasing.

05/26/05 – TTC contacted Moody’s for some specific questions about parts replacement. The Project Manual is built for front end. TTC needs to add dwgs and mechanical section. Bid Form needs to be modified for this job.

05/17/05 – The team had serious discussions about project schedule today. PBS re-iterated their concern about flooding. TE provided a timetable for construction that appeared not to be acceptable to PBS. TE had discussions with JF about project and will try to speed up project manual creation significantly to lessen risk. It is TE’s belief that County Purchasing has already decreed that this project does not meet Emergency Status.

PBS – Deep Well Pump Replacement Read More »

PBS – Pro Shop Metering Project

03/29/06 – TTC reviewed the billed KW and KWH to the PBS Pro Shop and the numbers looked good. The pro shop is using less than 1% of the total power consumed at the building.

KW KWH
February

50.91 21,863
January

34.91 28,950
December

79.91 25,448
November

59.28 16,077
October

72.30 14,661
September

63.67 16,528
August

53.30 4,166
02/01/06 – TTC check on the meters and to review monthly billings at the site. The meters appear to be reading in the Megawatts which seems really high at first glance. TTC to reconcile with actual building data.

11/16/05 – TA visited the site today. Reviewed punchlist and determined that Bond Electric has not completed the issues described on the punchlist. TE called Bond to tell that them that can’t get paid until these items and the final paperwork is complete.

11/15/05 – As-Built drawings for this job were turned over to Wayne Trent of HamCo Facilities today.

06/17/05 – Const Mtg was held at PBS. Sam did not attend. Equipment is not on site yet but Bond is ready to get to work as soon as it arrives.

02/28/05 – Purchasing called to inform TE that Bond does NOT have a performance bond or check submitted for this project. We should not let them begin work without this paperwork in place. TA to confer with Jack Boland today and emphasize the need for this check immediately.

02/10/05 – Contracts and Bid Results are in County’s hands. TE awaiting further direction on this project.

11/17/04 – Bid Results

10/12/04 – Project is out for bidding.

PBS – Pro Shop Metering Project Read More »

PBS – Deep Well Pump Service Contract

02/02/07 – After many contract revisions, phone calls and problems, the Prosecutor finally allowed preventative only maintenance contract that Kerry wrote and gave back to everyone to use. Other repairs and emergency repairs must be bid our as prevailing wages. TEI does not and will not every agree with this approach. We took prices for many other services to save the County money but those were not accepted as part of this job by Hamco Prosecutors office.

01/10/07 – TTC got Kerry’s new email address and forwarded the revised contract to her for any final changes that she would like to make. Kerry confirmed that the packet was received at her office.

01/08/07 – TTC hand delivered the final contract with Kerry’s marks to security for Jenny and Joe to pick up and resubmit to the Prosecutor’s Office.

12/26/06 – TTC will finalize the deep well pump contract this week.

03/29/06 – TEI has not heard from Daktronics with a registered service repair list yet so I called and got Greg’s email and sent him the request again.

03/21/06 – TEI finished the SOSS and will drop it off at the HamCo Facility Department on Wednesday for this project.

PBS – Deep Well Pump Service Contract Read More »

PBS – Energy Study

03/20/07 – Project ready to archive.

11/30/05 – TTC and GD have to meet internally to review the 10/11/05 findings and energy usage. GD believes there can be savings found in schedules and space control but we will need “buy in” from facility department to implement. TTC has to setup meeting with GD to review other items but County end of year crunch on projects has dampened progress. All work will be done by end of year.

10/11/05 – TTC and GD met on site and reviewed the whole facility with Sam, Joe, Eric and the financial manager.

05/10/05 – Kickoff meeting for project with JF, TTC.

PBS – Energy Study Read More »

PBS – Video Wall Replacement Project

12/19/07 – Nor Comm has provided the AIA closeout paperwork, warranty letter and payapps. TTC signed and City Dashed it to Joe Feldkamp. This project is complete.

09/03/07 – TTC has received and approved the O&M’s. TTC is hand delivering the box of O&M’s and final payapp to PBS tomorrow at 9am at the Deep Well Pump prebid.

08/28/07 – TTC contacted Nor-Com again about final payment via email with a Read Receipt.

08/20/07 – Nor-Com contacted Joe today about final payment. TTC emailed Joe back station what happened to Payapp #2 as listed below. To date, we have not received any additional paperwork.

07/02/07 – TTC has contacted Howard Milkis and Nor-Com several times for closeout on this project. No response to TEI. TTC will try to contact the office directly today and find out how we are going to close out this project.

05/14/07 – PBS did not use TEI service much at all on site during this project. TEI has been in contact with Joe and Scott numerous times during construction as things were going well. TEI contacted owner today for punchlist and closeout items for Nor Comm. As far as TEI knows, this project is complete.

03/30/07 – TE received submittals for review and promised to work on them this week. Nor-Com has a schedule forthcoming.

03/16/07 – Scott and Joe held a kickoff meeting. TTC to follow up and publish some const mtg notes this week. A second Const Mtg is to be scheduled. PBS would like TV in before draft day.

02/13/07 – All contracts and information is in the Prosecutors office for review. Comments have been added and the contract should be approved very soon. TEI provided a copy of the bid results to Kerry Dowling per her request last week. Joe Feldkamp is following up with the Prosecutor Office.

01/30/07 – TEI finished the revised contract and returned it to PBS for use on this project. Now TEI is waiting for approval and signatures to move into a pre construction meeting.

01/10/07 – TTC hand delivered the contract based on the Base Bid cost to Joe for submission to the Prosecutor’s office. TTC included a $2500 allowance in the project after the bids were opened.

12/26/06 – TTC will finalize the deep well pump contract this week.

PBS – Video Wall Replacement Project Read More »

PBS Video Switcher

10/26/09 – Final paperwork is received. TTC approved and mailed to Joe.

09/22/09 – Project is complete. We have approved payapp #2. Once all the closeout paperwork has been received and training is complete. We can close out this project.

08/25/09 – One payapp has been approved. Punchlist has started. Training continues.

07/29/09 – Project has been bid and awarded to Rosco. Work is proceeding and Chris Williams will be able to check in on progress on August 4th when he visits Cincinnati for the Brewers game.

06/23/09 – This project is in contract approval stage at HamCo.

PBS Video Switcher Read More »

Scroll to Top