Hamilton County Facilities

Dane-A

Dane – Phase 2 Renovations

PM: Bert Watts, Mike Murphy, Terry Cannon
06/29/23 – Opened for tracking.
07/27/23 – Cad plans are ready per request.
08/31/23 – New SOSS requested and will be submitted this week.
09/01/23 – Sent SOSS to Champlin for use on 152 and 157 Kennel options. TTE started working on a zoning and load calc for any future dehumidification unit we may need.
09/28/23 – Small Project flooring replacement ready for bid. Project will be sent out 10/3.
10/25/23 – Bids received for Epoxy Flooring Installation. Bid vetting in progress. Trench drain scope in progress.
10/26/23 – TTE requested design meeting with owner to review HVAC requirements for this space. Temporary vs new conditions, reusing existing equipment, locations of new equipment.
12/07/23 – User meeting held to discuss phase breakdown. Phase 1 = Epoxy Flooring. Phase 2 = Plumbing Improvements. Phase 3 = HVAC Improvements. Phase 3 = All other improvements. Phase 1 has contract signed and flooring installation scheduled for 1/29. Phase 2 to be submitted for owner review 12/15.
01/31/24 – TE submitted Plumbing and HVAC review drawings for this project concerning the trench drains and air conditioning systems for this phase of upgrades. We are still exploring most economical ways to build these trenches at the Dane St. site.
02/29/24 – Request for availability for final phase II meeting sent out. Waiting to hear back from Cares. We can be ready for bid end of March. Wait until next Wednesday and set the meeting with available data.
03/28/24 – Final review meeting held. Cares requested consultant to review the plan. Shelter Planners of America have been brought on and will conduct review.
04/25/24 – Consultant brought on board for industry standard advice. Updated plan presented to CARES. Champlin to incorporate changes and determine new phasing plan.
05/30/24 – Drawings have been updated to reflect plan changes for Phase 2. Final estimate to be submitted this week. BW said to go ahead and include the kennel cost in the Phase 2 work. Phase 3 cost due end of June to County as well. Coordinate with structural for final design and cost.
06/27/24 – Phase 2 and 4 cost submitted to Bert. THP investigated structure options for Phase 3. It was determined that the best option is to put the mechanical units on a platform behind the building that will later serve as the sallyport structure. Goal is to have Phase 2 & 4 ready for bidding by July 17. Phase 3 to be purely HVAC scope and okay to include platform & roof now in this phase. OK to pour slab during this phase. Stairs and ramps can be done later. TE will put power in for Portable HEPA to hold us over until the new units are installed on the new platform in Phase 2.
07/12/24 – Phase 2 & Phase 3 cost submitted to Champlin for rollup to County and Cares.
07/23/24 – Phase 2 + 4 Issued for Bid with additional work included as alternates with latest request from owner and tenant.
08/29/24 – Phase 2 bid opening 9/3. Acoustical vendor bids came in and Universal had the lowest bid for this project.
09/26/24 – Phase 2 bids awardable. Contract returned. First submittals received.
10/31/24 – Contract finalized. Scope may change slightly due to record center work. Holding off on permit submission until changes are finalized. JN said pick a new material for the walls and change them to something less permanent. We discussed phasing for Dane vs Records at this meeting and the fast timeline of preparing space for Phase 2 work for the dogs.
12/12/24 – Bulletin #1 issued addressing scope change requests. Submittals are in process. Kickoff meeting scheduled for next week.
01/30/24 – Bulletin #1 was rescinded. Bulletin #2 issued with minor changes to account for the cancellation of Phase 3. Applying for a change of use in Zoning is ongoing. Application has been sent to examiner for review. Once his comments are received, we can apply for a conditional use review. Permit will be held up until zoning is complete.
02/26/25 – Bulletin #2 and #3 have been issued. Zoning hearing scheduled for March 12. Work ongoing.
02/27/25 – City zoning link was sent to Rycca and Champlin and Nester, not allowed to share, but BW will join with JN. Other witnesses can request access 24 hours in advance.
03/27/25 – Zoning conditional use was approved. Building department has not issued the permit yet and the building department has ordered a halt on all work until a permit is approved.
04/24/25 – Permit has been approved and work resumed. Kennels were delivered on site. We are still on schedule to be complete by end of June.
05/29/25 – Phase 1 punch scheduled for 6/2. Phase 2 work complete by end of June.
06/26/25 – Fire alarm and electrical issues pushed back turn over of phase 1. Phase 2.1 punch complete.
07/31/25 – All punch work is complete. The exterior ramp begins next week. Closeouts to be submitted by Graybach.
08/26/25 – Project is complete. TTC working with Ian and Chris on Wi-Fi thermostats. RTU-7 does have issues but wasn’t part of project. Ian getting . Entrance ramp poured incorrectly. Corrected railing detail to be provided to Graybach.
08/28/25 – Ian getting prices to replace RTU-6,7 given the issues. JN said CVW met with CARES on the security camera, JN to get AIA, TTE to send XBE forms, keep this moving ASAP.
09/25/25 – Multiple issues with all washers. Supplier and plumber met onsite to discuss issues. They are being replaced. Railing work outstanding. Graybach to submit closeouts in next 2 weeks. Security Camera project to be in to John for review by Monday.
10/30/25 – Railings installed. Punch list sent to Graybach and work completed. Back punch to take place in near future. Closeouts received but have not yet been reviewed.
12/11/25 – Railing punch items addressed. Closeouts reviewed. Graybach to provide missing items.
02/26/26 – Closeouts delivered to County.
03/26/26 – No update. County to review closeout documents.
04/30/26 – Final items to be delivered to County.

Dane – Phase 2 Renovations Read More »