Hamilton County Facilities

Archived Projects

Archived Projects

A&D – Parkhaus Sump Pump Project

02/19/07 – Change Order for project was rejected by Owner. TTC has received O&M manuals for sump pump from Ginter and they are being sent down to the county for this project. Final payapps have been received and are being sent to the County today.

12/26/06 – Aside from final pay applications being approved the project is complete. All O&M’s have been submitted. Queen City is getting the allowance but no additional monies from the work. TTC archived the project.

11/30/06 – TTC approved Ginter11/27/06 – final paperwork and O&M’s from QCM have been received for this project. QCM submitted a change order over the cost of the allowance. It is my understanding that the County is not willing to pay extra as the contractor were allowed to visit the site during the prebid and were allowed to see the amount of work involved in cleaning the pit out for the new sump.

08/24/06 – Pre Construction Meeting Minutes Distributed. All submittals have been approved. Stiles has been working with contractor on power connections & requirements. PDF

05/25/06 – Project was rebid. Queen City won the mechanical package. Ginter won the electrical package. Contracts were mailed to Mark Hardin today for approval on this project.

04/26/06 – Project will be rebid as two packages. TEI will send out new books for PC right away and building new EC books for their bid ASAP.

04/24/06 – The bids came back. They were much higher than originally budgeted. TTC discussed with Mark Hardin and Mark Donnelly. Because the electrical bids were much higher that $5000, TEI will have to rebid that portion and get new cost directly from the EC’s. TEI will rebid the PC portion to remove the EC subcontractor and get new prices back for that.

04/11/06 – TEI release addendum 01 tonight. The project manual was completely redone. The drawings were also completely redone. The new bid date is April 19th at Noon. The project manual now includes all the electrical as well as the drawings. The plumbing was redesigned to include field findings at the prebid meeting.

03/30/06 – Prebid meeting was held on site. Many new details were uncovered. The electric will have to come from the elevator room over the ceiling and down to the sump pump. TEI has to updated the plans for addendum01. TEI has to relocate the sump on the plans, provide power routing to the sump, add a submersible convenience outlet six feet above the sump location, add the confined space notes (to be reviewed by county), add the safety note that the county will review the winning contractors safety policy for confined space, and add a high water level alarm. TTC does not see a need to extend the bid date or question date for this project. TEI will collect the bids and tabulate them for the owner.

03/20/06 – Mark called today to say that the County won’t provide access into the building for the contractors due to liability issues. TTC called Grady Reed and discussed confined space requirements and Grady suggested that we take away all the safety issues creating confined space and then let the contractors work in the space more like a normal space. One way in/out doesn’t necessitate a confined space but the Owner can assign a more strict requirement than OSHA if they like and the contractor must abide by that.

03/16/06 – TEI met with THP about providing the MEP services for the sump pump. After much discussion, the County decided that TEI could bid out the sump in a small project bid and then get that work done ahead of time.

002/16/06 – SOSS was submitted on 2006 Project Estimate Meeting but no further information has been received.

A&D – Parkhaus Sump Pump Project Read More »

A&D Vestibule Renovation

12/18/06 – Final payment and pay application has been received from Stapleton. TEI is forwarding to Kathy Buschbacher for closeout. This packet does include closeout documents.

11/30/06 – TTC has been working with Stapleton to get closeout complete and the final security key switch complete. It appears the job is ready for closeout. TTC contacted Langdon about closeout documents and payroll today as well. Langdon reported that the final balance report just arrive last week and that O&M’s are probably being completed right now. Kathy has asked for closeout on this project and TEI is trying to get that done in the next 2 weeks. TTC emailed CRA about status of Langdon closeout as well along with allowance usage plan for Stapleton. Allowance Usages for Stapleton: (1) $677.05 – Change Order # 01 – worked on wireless pushbuttons (stapleton bills directly to zeiser for payment from the GC allowance) (2) $410.05 – Change Order # 02 – Install Transmitter, Receiver, Transformer (from stapleton allowance) (3) $567.06 – Change Order # 03 – Access Panel in Ceiling, Fish Door Hardware, Cables to Controllers (from stapleton allowance) (4) $1437.00 – Change Order # 04 – Wireless RF Transmitters with relay and box, Wire door opener, temporary switches for control (stapleton bills directly to zeiser for payment from the GC allowance) (5) $409.85 – Change Order # 05 – Remove Controller, Wire door controls, add relay & transmitter (stapleton bills directly to zeiser for payment from the GC allowance) (6) $598 – Change Order # 06 – Key switch for Security Override (stapleton bills directly to zeiser for payment from the GC allowance)

11/17/06 – TE has performed the punchlist for this project. There are items left on the control of the door hardware for Stapleton to take care of but that seems to be a problem to get finished at this point due to the precarious nature of the control wiring to have the doors work from the standpost and by wireless and then to be able to disable them at night when the building needs to be secured. CRA and TE have put Stapleton in touch with Ingersoll Rand to facilitate the final connections. 11/17/06 was to be the final date this work was to get done. TE approved Stapleton’s #1 and #2 pay applications today and had them City Dashed down to the A&D building for payment.

07/25/06 – Const Mtg today revealed that we have redesigned the door hardware issues that are associated with project. Very little progress has been made except that sprinklers are in, the diffusers are being installed and six lights have been installed. The door hardware issues need to be cleared up so the rest of the job can move forward.

07/14/06 – The coordination and work over the last two weeks includes modifying the plenum such that a continuous sheet metal wall was installed for the plenum air for the boiler room and elbows were added from the existing louvers to the face of the this wall for proper airflow. The ceiling was raised in the space per Dave Woodside desires and this created a clearance problem for the new can lights being installed because our ceiling was too close to the our new ductwork. Mike Stiles resolved these issues with the electrician by relocating the lights into a horseshoe pattern but this also means that the ceiling contractor has to move some of the new studs to make this work. TTC approved Langdon’s #2 invoice on 7-14-06 for payment. Mike and Spencer found a method to resolved the handicap access and power to the new door actuator’s.

05/24/06 – TTC talked to Bill Bauer of Langdon today. They believe that TEI’s new layout is acceptable and will work well in this installation. The new layout reuses the glycol piping for the fan powered box, keeps the existing louvers in place in the lobby and adds a couple of 24×24 lay-ins will provide access into the new ceiling space. All the new parts are ordered and should be here early next week. The HVAC and piping contractors should be down next Thursday to begin this work for the vestibule. I believe that would be June 1. TTC informed all partners.

05/23/06 – TTC provided a PDF file to everyone for review that makes the HVAC work much easier, re-using the glycol heating piping for the VAV box that is subject to cooler air from the return plenum. TTC contacted Langdon again today to see if they are ready to make the changes.

05/16/06 – Store front glass is partially installed. TTC is meeting Langdon on site to coordinate some ductwork above the ceiling tonight at 4:30 p.m.

04/17/06 – TEI received fire protection submittals today for review. TEI reviewed project scope with Bill Bauer at last pre const mtg. Door hardware is pushing back the project 4 weeks.

04/03/06 – TEI sent back the UH submittals today. No Exceptions Noted.

03/07/06 – TEI received submittals today on control valves for this job. TTC gave to Sam to review.

02/24/06 – Jim Lape called to inquire about mechanical submittals. TTC & SRB finished them today and city dashed them to Jim for use on this project.

01/31/06 – We had the pre construction meeting today for this job. Langdon is the MC. Stapleton is the EC for this project. Meeting Notes PDF

01/01/06 – This is a C&R lead project. TEI bid this out with C&R and then had to rebid the electric portion under a separate contract. Now that the project meetings have started we are treating the whole project as one big project with C&R as the lead and Jim Lape at Cole & Russell running the show. TTC is asking that the web journal be kept up to date on this project for record keeping purposes.

A&D Vestibule Renovation Read More »

A&D Cooling Tower Motor Replacement

04/05/07 – TE received final paperwork today from EDI. It will processed and sent to Kathy.

03/30/07 – Project is complete. We have requested closeout documents. New fan motors and air compressor were lifted up to roof on March 17 without incident.

09/16/06 – Security issues have finally been resolved. The new louvers are installed on the building. Door hardware appear to be working. The interior doors have been removed. Interior work should be very close to being complete and the jobs should be getting close to being closed out.

07/10/06 – Bid tabulation was sent to Dave Woodside with EDI as the apparent low bidder. TEI is writing the contract now to include the Alternate since we well under the $25,000 cap. This will provide a permanent platform into the penthouse. TTC also called EDI to discuss bid numbers and how the platform would be created and left on site.

06/23/06 – TEI distributed the prebid meeting minutes to all.

06/20/06 – Prebid meeting was held on site. JFS called after the meeting to tell me that I missed inviting RCME and Siemens. TTC contacted both individuals and gave them the documents for bidding and invited to meet them later on the site. TTC also contacted all vendors to discuss adding these two vendors to the bid.

A&D Cooling Tower Motor Replacement Read More »

A&D – THIRD FLOOR UPS UPGRADE

05/02/08 – After much discussion the UPS project has finally moved forward with Banta winning the bid at 18,100 with a fused disconnect. There was a lot of time spent in emails and discussion on whether this bid was valid and if JFS wanted to accept the fused disconnect offer which came in well under $25,000. Kathy contacted TEI this week to inform us it was. TEI wrote the contracts and mailed them out to Sheila Bass today so they will be in Monday’s mail. The bid tab was sent out to the contracts as such PDF. Banta was informed to send 3 bid packets to Sheila for processing.

12/03/07 – TEI had a meeting with JFS today. Scheme and price seem acceptable. Larry Mitchell asked TEI to forward dwgs to him for giving to County Electrical trades to see if this was work they would want to do. TTC sent these dwgs and specs to Larry, Dale and Bert at 5pm on Monday. If County does work, TEI will get permit for them.

11/30/07 – TEI scheduled a meeting with Dale Crider to go over the final design on the project. Nick V and Nate C have been working on the redesign of this project and have an under $25,000 project ready to bid out for the County for this work.

04/27/07 – Project is still on HOLD.

04/20/07 – Project is still on HOLD.

04/13/07 – Project is still on HOLD.

04/05/07 – Project has bee put on HOLD until further notice.

03/30/07 – Obtaining valid background drawings from Archibus due to other avenues have been exhausted.

03/23/07 – Project is progressing as expected.

03/20/07 – TE trying to obtain electric as-builts for building. TE has acquired architectural backgrounds.

03/07/07 – NR created project journal and filled in back data from previous meetings. Kickoff meeting was held on location. Attendees include Kathy Bushbacher, Charlie Hodge, Dale Crider, Terry Allgeyer and John Penn. Information given to TE; information is being evaluated. TE is trying to obtain electronic copies of the building architectural drawings in order to develop drawings.

A&D – THIRD FLOOR UPS UPGRADE Read More »

A&D Arc Flash Study

04/13/07 – TE has completed their portion of this project.

04/06/07 – Labels are complete and have been delivered. Clarification Report and CD containing pdf’s of the labels has also been delivered.

03/30/07 – Labels have been delivered to the printer. Awaiting return of labels; delivery expected for the first week of April.

03/23/07 – Project is progressing as expected. Completion by the end of March 07 will be met.

03/20/07 – EDSA modeling in continuing. Project will be complete by end of March.

03/14/07 – NR created project journal and filled in back data from previous meetings. Project progressing, model has been developed, final review of modeling is underway. Project completed date of 03/30/07 is not an issue at this point.

A&D Arc Flash Study Read More »

A&D – 3rd Floor Modifications

02/15/08 – CRA followed up with DC and TM regarding status of FP info on 1/28/08 and 2/15/08.

12/06/07 – CRA left voicemail for Dale Crider asking about permit status.

11/13/07 – CRA forwarded permit correction letter to Dale Crider on 11/13/07 and 1/26/07.

11/08/07 – CRA has received the letter form the Plans Examiner requesting additional information for the fire suppression work related to section 903 and NFPA 13. CRA is currently addressing the issue.

10/12/07 – Building permit application was submitted.

10/04/07 – Design review meeting was held. J&FS confirmed that all construction work is to be performed by in-house trades. See Meeting Minutes here.

09/28/07 – Design Phase drawings are being prepared for 10/03/07 Owner review meeting.

09/20/07 – CRA received signed and approved SOSS.

08/27/07 – CRA submitted the SOSS.

A&D – 3rd Floor Modifications Read More »

A&D – JFS 3rd UPS Upgrade REBID

06/23/09 – This project is complete. There were no punchlist items and all closeout documents have been received and sent to Bert.

06/03/09 – We received 2 pay applications today #1 & #2 and signed them and sent them to Bert. We have to write a $5000 deduct change order for the allowance since none of that was used for this project. Closeout documents received and approved by MH and mailed to Bert with the pay apps.

02/26/09 – Submittals are being held pending notification that the unit will fit in space from Ginter.

02/02/09 – Pre Const Mtg was held last week with Ginter.

12/04/08 – Contracts have been submitted for approval.

11/03/08 – Addendum 01 went out to bidders. Some calls were received about scope of work. TEI answered for bidders to match published information.

10/16/08 – Project cancelled and scheduled for rebid on October 28th.

08/25/08 – Pre Const Mtg is schedule for Wednesday. There is serious issues with Banta requesting more money. TTC spend a couple of hours this morning sending and compiling messages to Kathy & Sherry about this issue. Huntwork is handling the meeting.

08/22/08 – Kathy called to say contract is approved and we are ready to start the project. TEI will try to setup a kickoff meeting for next week.

08/04/08 – Kathy B reported contracts have been received. JFS will advise when project is ready to start.

07/30/08 – TEI has been told the contract is complete. Banta has contract and it is in the signing stages.

07/24/08 – Banta has requested additional funds for a delay in project start.

A&D – JFS 3rd UPS Upgrade REBID Read More »

222 – 7th Floor Conference Room Reno

08/11/10 – Schematic Design submitted to owner with cost. Project is canceled due to cost.

05/26/10 – SOSS approved. We will setup fieldwork and kickoff next week. Cost estimate complete. Project put on hold because of pricing.

04/26/10 – Schematic Drawing is complete. Fieldwork is complete for SD. We are working on cost estimate to send with SD.

03/23/10 – Project on hold.

01/26/10 – Bert contacted ThermalTech about permit requirements and was told the mechanical code would require a permit for the new ventilation calc required in a new conference room. Bert has the SOSS for this project.

12/31/09 – Bert contact TEI to work on this project and renovation. TEi owes Bert an SOSS based on the HamCo Scope of Work.

222 – 7th Floor Conference Room Reno Read More »

A&D – Cooling Tower Fill Replacement

12/23/11 -Angela at TP Mechanical says that they sent you the following closeout documents on 10/19/11 – O&M’s which I hand delivered to your office in a box with the payapp 4 that we determined to be wrong. 12/18/11 Signed change order Allowance usage Warranty letter Equipment contact list.

12/28/11 – Change Orders and Allowance sheets were correct, we are deducting $1,864.00 from the original contract amount. Please send 3 originals to TEI for signature and closeout, and also the Prevailing Wage document Bert shared with us. Then we are done.

02/22/12 – Doug Kobman has left TP but all paperwork has been received average and payapps sent to Tony & Bert. County told me they had everything they needed for closeout and archiving.

A&D – Cooling Tower Fill Replacement Read More »

A&D – Bldg Manager Office Renovation

03/06/12 – ThermalTech Prebid finished and Fire Protection bids received.

03/26/12 – Drawings complete for permitting fo mechanical.

03/28/12 – Submit Mechanical and Electrical permits on Friday.

05/29/12 – TTC would like to try to get by with no return for Mike Denton’s office. If he keeps his door open 99% of the time it should be fine. He never had a return before. It that works, using a louver in the door might be a good option. If that is not acceptable, a transfer grille through the wall would require a fire damper. That corridor leads to the elevator and stairwell which makes it an egress path. TTC personally did not change the supply duct through the wall to not deal with that issue.

8/29/12 – Electrical final inspection and approval received week of 8/20/12 from IBI. Close out project.

A&D – Bldg Manager Office Renovation Read More »

CAB 10th Floor Community Development Expansion

2/9/10-Meeting with Bert Watts at Community Development

2/18/10- Issued SOSS to Bert Watts.

2/19/10-Bert questioned GBBN verses TEI scope and permitting costs.

2/22/10-Terry Cannon of TEI issued email with scope, SOSS and permitting resolutions.

3/6/10- Received signed SOSS.

3/8/10- Met with Mike Florimonte to field measure adjacent storage space. Receive directive to eliminate one workstation for a total of 3. The fourth area to become storage.

3/15/10-Received Purchase Order (538771) from Bert Watts.

3/17/10-Susan Walsh approved rotated third workstation.

3/31/10-Final Design Development drawings submitted to Bert Watts for Susan Walsh’s review.

4/6/10- Building Permit Application, Drawings, Electronic Submittal and Check delivered to Cincinnati Buildings and Inspections.

4/21/10- Approved Building Permit paid for and picked-up from Cincinnati Buildings and Inspections.

4/22/10- Approved Permit and Drawings Delivered to Bert Watts.

5/18/10- Inspector Larry Keifer has requested an additional sprinkler head be added in the expansion space.

6/24/10- Sprinkler permit has been filed and still pending.

7/29/10- Bert Watts declared this project closed and ready for Archive.

2/1/11- GBBN completed additional as-built drawing modifications showing the additional fourth workstation in the expansion area.

CAB 10th Floor Community Development Expansion Read More »

Administration – Recorder’s Office Microfilm

03/24/05 – TTC sent the revised change order to ICS for him to sign and prepared it for mailing, stopped them and reprinted them again because Gary called Nancy to schedule the City and Fire Marshal inspection to find that cost is $475 additional to the city fire inspection so now I am advocating that the change order be re-written back up to $1400 to cover the additional charge and Gary will just absorb the rest of the overage from his profits. Larry Keifer has required a FULL BUILDING HORN & STROBE test. Joe called TTC to express his disbelief that a full building test would be required and indicated how difficult that would be to do in one hour. TTC sent an email to Larry Keifer requesting clarification and hopefully explanation on this upcoming test. Tentatively the test is scheduled for Tuesday March 29 at 6:00 a.m.
03/23/05 – ICS finished relocating the fire alarm strobe for our new fire alarm permit. Joe tested the strobe and it works. TTC talked to ICS about painting the wall where the old strobe was moved and negotiated a $450 reduction in the original change order down to $950 and in return the County can touch up the column at their convenience. TTC and JM agreed that this seemed reasonable. TE will rewrite the Change Order and get ICS to sign it for final billing. ICS has to coordinate a final inspection between Larry Keifer and Nancy at the Cincinnati Fire Dept. He hopes it will happen this week, but TE believes this will take at least a week to get scheduled. ICS is to coordinate with Joe Merkt when FA test is actually scheduled.

03/15/05 – ICS submitted a change order price of $1400 to move the strobes for the approved fire alarm permit. Diana approved. TE will now scheduled (we have already called to schedule the work) and assist in the installation of strobes as needed.

03/08/05 – City Permit Office reported today that Fire has approved and they are in the process of setting up the permit. They will call me at TE when ready.

03/07/05 – TTC called the City Permit desk today. Plan Examiner approved on 02/22/05. The Fire Department has the permit now for approval. TTC called 352-4314 and convinced them that the Fire Sprinkler work was completed under Permit # 2004P06759. The Fire Inspector updated the database. Now the city should call us in a couple of days with the final permit price and tell me it is ready to pick up. TTC will call ICS to get them to pay for the work and give us a CO price to do the work for this job.

03/03/05 – TTC contacted the city permit department about status – no word yet.

02/22/05 – TTC contacted the city about permit status – no word received back at this time. We will continue to push for final inspections. TTC authorized ICS to bill for $3500 leaving a $200 balance on the project and whatever this change order turns out to be since all of the original work is complete and punched.

02/14/05 – TTC requested final paperwork from Carrigan again. TTC requested allowance usages from B&J on project for final bookkeeping.

02/11/05 – TTC contacted Preferred about lowering the sprinkler head in the public work area. ICS called to report that the final IBI inspection was today and that everything passed. Final paperwork is en route. Preferred called back and will get it taken care of quickly through Joe Merkt.

02/11/05 – TE submitted the Fire Alarm Permit in person today. The FA permit number is 2005P01862. It will have to be paid for when it is picked up. The review should take under 12 days. TTC asked for Bill Spurling to do the review. TE will keep everyone apprised of progress.

02/10/05 – TE has finished recreated 4 sets of new fire alarm permits for the microfilm area. MS talked to the building department today and we can try for a mini permit but the drawings have to be on 8.5×11’s only. These plans are on 11×17 and stamped and signed so we are going to submit them as a standard FA set and not walk them through as that doubles the cost. ICS will have to move one strobe still to meet the new plans we are submitting.

01/31/05 – TTC talked to Bill Spurling at City plans exam. He did not know where Larry wanted the additional strobe – perhaps the darkroom. He asked me to talk to Larry, so I placed a call to Mr. Keifer and when he calls me back, I will get to the bottom of what we need to do and get it taken care of immediately.

01/27/05 – TE mailed Gary @ Integrated blank final document forms: G706, G706A, G707, Affidavit of Contractor Prevailing Wages and, Affidavit of Original or Sub-Contractor.

01/25/05 – City is now requiring a possible new strobe in the public area which would mean we have to take out a fire alarm permit. Stiles still believes that you can get a TCO for the space and we can pull that permit and get that work done and still make the city happy. TE has placed two calls into William Spurling, the city Plans Examiner, to discuss the issue with him. TE will keep the County apprised.

01/21/05 – Project passed above ceiling inspection with IBI. EC is 95% complete. Larry Keifer may still require a Fire Alarm permit to be pulled for this job although TE doesn’t believe that is necessary. TE coordinate with Preferred to add a sprinkler head in the vestibule as it was shown on the drawings but not to add the one above the microfiche charts as it would tend to get damaged from the anticipated use plus there is not 18″ clearance above the racks.

01/18/05 – Plumbing is finished including vent. HVAC has installed toggle switch for exhaust fan. Auxiliary exhaust fan is burned out so TE instruct B&J to buy a new motor and replace it. B&J has the motor in stock now and will install it on Wed Jan 19th.

01/12/05 – Dennis Grimm of Carrigan & Grimm contacted, requesting 3 additional documents (Affidavit of Original or Subcontractor, Affidavit of Contractor Compliance-Prevailing Wages and Consent of Surety to Final Payment) to complete submission of all final documents. Dennis not sure how to obtain the forms therefore the forms were mailed to Carrigan & Grimm on this date.

12/27/04 – TE contacted ICS about catching up with GC. They said they would be on site this evening at 4:00pm to catch up. ICS will also begin installed lead anchor bolts with 1/4″ #20 eyelets for Communications to hang their J-Hooks for data cable support from. TE advised them not to exceed $640 dollars for this work. Gary Kercher agreed to this pricing scheme. DES can contact Mitch that they will be able to move their cables to the new supports soon as this will need to be done before final inspection.

12/10/04 – TE advised the GBBN can create a wooden soffit around conduit and panel box in vestibule and paint the wood and the cover of the panel and still meet code requirements for the panel. County arranged to have carpenters do the work through a work order. Matthew shall enter a work order into the system.

12/07/04 – Construction Mtg addressed the scheduled as we are about 1 week behind due to holidays and with Christmas approaching, the project is likely to stay a week behind. County asked TE to look at cleaning up existing panel in vestibule for better aesthetics. PC is complete. HVAC will be in on Thursday night to relocated controller for hood fan.

12/01/04 – GBBN & TE resolved the RFI requested by ICS electric in regards to the existing electric panel in Room #201 near the countertop. Microfilm has agreed to redesign the countertop to accommodate the electric panel. GBBN will follow through with 3R and TE will notify ICS that no additional work will be required on their part.

11/24/04 – Rough-in inspection complete. Inspector may request clean up of existing cabling above ceiling. TE to investigate.

11/03/04 – Asbestos Memo was issued to contractors for tile removal by pinnacle communication. PDF. Preferred (Jeff) is confirmed for evening work tonight (11/03/04) and we have coordinated with Joe Merkt for this evening work. TE has contacted all contractors about not working on 11-04-04.

11/01/04 – Carrigan called today to discuss existing piping layout, mixing valves, and hot water heater placement. It appears that some ball valves were added to self regulate temperature at the film equipment. After discussing the situation with Dennis, we believe it would be better to pipe the building hot water into the water heater and have it “boost” that water up to inlet hot water temperature at the mixing valves thereby giving the process room immediate hot water when needed. In it current configuration it backfeeds the building hot water system which would give us unpredictable results. TE will confirm this at tomorrows meeting but in the meantime, we have asked Carrigan to give us a price to replace both temperature mixing valves with new Simmons Temptrol mixing valves that have integral temperature sensors for visual tracking outlet temperatures and piping the water heater in series with the buildings hot water supply to the process area. We will discuss all this at tomorrow’s meeting.

10/27/04 – Fire Permit has been approved: 2004P06759. Carrigan & Grimm schedule of values received and approved.

10/26/04 – Code questions were received by permit office. ThermalTech responded with these answers. PDF

10/25/04 – Carrigan asked to rework the vent arrangement on the sink and equipment in the new area to prevent a flat vent condition on the floor drain. TE has approved this routing of the new vent. Minor change and not cost to the project.

10/19/04 – Const Mtg 2 held. Plumbers, HVAC, Electricians, Fire Protection on board and ready to begin evening work. Scope coordinated through GBBN during project meeting. Owner agreed to allow ceilings to be removed during remodel work and replaced at very end as long as contractors take out the minimum required for each phase.

10/07/04 – Const Mtg held. Carrigan & Grimm was not present. All work appears ready to start on October 18. Phasing and project schedule mostly approved. Preferred needs security checks approved and DES will send them to JJ. We may see additional monies requested from EC for additional permit cost. We may or may not approve these additional funds depending on how the project goes. We can use allowance money if needed and nothing else comes up. TE will post minutes after they are received from GBBN.

09/23/04 – Mtg complete. TE will post minutes after they are received.

Bids opened on August 17.

Mechanical: B&J Jacobs ($12,549), Electrical: ICS ($14,300), Plumbing: Carrigan & Grimm ($17,600)

Administration – Recorder’s Office Microfilm Read More »

Administration – 10th Floor Chiller Upgrade

09/21/05 -This project is being moved to the archive because the whole project is being rebid due to bidding anomalies.

09/15/05 – After much discussion amongst the vendor, the contractor, Tony and Amy in purchasing, it was decided that TE did not use proper bidding procedure on this job and it has to be reibd. TE will provide the new bid documents and prebid and contract time at no cost to the County. TE still has to write an engineering change order for the scope change for the new electrical design (TA to talk to Tony about this new SOSS). The bid and the construction admin will seem to be au gratis from this point forward.

09/07/05 – ThermalTech has received many calls from the vendors on this job mostly in regards to the chiller selection on the project. Trane believes the chiller must be individually test to meet ARI standards and York seems to think that the specifications say that only so many out of 100 need to be test to meet ARI. TTC assured Tony that ThermalTech will review all aspects of the schedule, specifications and bids and provide a written recommendation as to which chiller meets the intent of the specification while maintaining the requirements of the ORC. TTC will ask Tony about getting the purchasing department or prosecutor department to review and provide a decision if needed after the contract is approved. As with any public bid, the bid amount cannot change so the vendors will have to provide the equipment listed to the County at the bid amount or other actions will have to be taken.

09/01/05 – Contracts came back from Prosecutor. TTC to pick up, modify and take back to faculties for approval. Peck and Trane and calling multiple times trying to force us to use the Trane chiller because it is the only to meet the ARI specification. TTC to review ARI 550 and will discuss with everyone after the contracts are signed..

08/24/05 – TTC, TA, AKM and JM talked about how to write the Admin Chiller Contracts and what alternates to take based on our latest discussions with Cinergy and what they are supplying to the building. TTC has the contracts written to accept the EC base bid and Alternate #1 (new service) and for the MC we are taking base bid and Alternate #3 (warranty). TTC stated that the contracts will be dropped off today.

08/08/05 – TE and the County had a meeting today to discuss how to write contracts for this project and what alternates to accept. For the mechanical contractor we will accept base bid and Alternate #3 for 5 year parts and labor warranty. In discussing the scope of the electrical alternates, it was discovered that to accept the new feeder to the 10th floor does not truly provide the full extent of the County desire to have backup power from both grids to building at all times. It is a convoluted situation but basically the building now has 8000 amps to the building from 2 separate grid feeds. If either grid goes down, the building can still maintain power from the other grid. The max usage right now is 3700 on 95 degree OA temperatures. If we only feed the new chiller with the new service, the main building will have no additional power savings. In the end it was decided that the best thing to do was to try to have the contractor provide a new 1600 amp service into the basement from both grids and provide a transfer switch in the basement as well. This will slightly modify the original scope of the Alternate but will handle TE’s misunderstanding of what the County requested in the design process of this job and in no way would have changed the outcome of the bid process. TE will research the changes and advise the County on possible cost and acceptance by Cinergy.

08/01/05 – The bids opened last Thursday. TE is working on which recommendations to accept for this project. The numbers varied for using bus duct in lieu of standard conduit and feeder from a $400 deduct to a $127,000 adder. Because of this TE has to do some research to see what is correct. TE believes that we will be able to accept Alternate #1, Alternate #3 and Alternate #4 and still be under budget for this job. We want to write the contract on either Tuesday or Wednesday of this week.

07/20/05 – Tim Centers from Habegger called to ask about freeze protection on the chiller since we aren’t using glycol at the Admin building. TZ is on vacation but we are using heat tape and DDC alarms to protect the chiller and piping. Ryan Halverson from Trane called to ask about removing the word “Scroll” from the schedule so everyone is bidding “Screw” compressor chillers and TTC will do that in the Addendum.

07/18/05 – TE to work on Addendum 01. Fix the bond issues for purchasing. Move rigging time to full weekend. Move conduit pull to weekend. Add01 should go out on Tuesday.

07/12/05 – The bids are out and the prebid is set for 07/15/05 at 1:30 p.m.

06/15/05 – JM reported that discreet chiller control will be fine for this job.

06/09/05 – TE emailed Tony and Joe about using discreet points to run the chiller plant instead of adding a Trace interface. TE needs to wait for approval from Tony

05/20/05 – TTC dropped off the chiller plans for review. The specs are not complete yet for review and TTC has not decided the best way to bid the chiller (LCC, Alternates or Base and Equals). GD has returned his comments to TTC.

04/27/05 – TTC, TA, TZ, Joe Merkt and AKM met to discuss the project so that TE can design in a way that doesn’t go too far over budget. The cost estimate turned in last year only had $33,000 for electrical upgrade. The plan is to make or use the mechanical scope adjustable so that some additional monies can be diverted to upgrade the electrical. TE has to do more fieldwork to check on the piping arrangement so that TE can fully comprehend the additional return pipe that goes from the 10th floor to the basement. Basically the 3-way valves have a return system that goes from floor to floor UP the building and from the 10th floor back down to the basement.

04/22/05 – This week THP has delivered final structural dwgs to TE for project. TE finalized a control strategy within TE for the new chiller and discussed hydraulic issues of existing piping and pumps. GD gave TZ and TTC direction on sizing the new 10th floor pump. TTC decided that JCI controls can be modified during the upcoming project and that existing control work on 10th floor chiller would have no adverse effects on new system. Chiller S/S and Pump S/S and statuses can be re-used and extended as needed during 10th floor project. Trane sent project info to TE on the existing chillers: Evaporator, 45-55 F, 480 gpm, 2-pass, 26.5 ft wpd, .0005 fouling factor, Condenser: 85-95 F, 581 gpm, 2-pass, 21.7 ft wpd, .0005 fouling factor, CAB-CH-1 TRANE CENTRAVAC CVHE-020B L85B26377, CAB-CH-2 TRANE CENTRAVAC CVHE-020B L85B26376.

04/05/05 – TE coordinated with THP on steel locations and scope for new air cooled chiller. THP will meet onsite with Joe Merkt to field check existing steel conditions this week. THP requested $2000 for fee’s for this project. TE approved. This cost wasn’t in the original scope of fee’s but TE will try to incorporate into project but will save for engineering change order if needed.

03/21/05 – TE kicked off project with a site visit for TA, TTC and TZ. SRB visited the site for equipment and piping takeoffs during the same morning. TE began talking to vendors about equipment weights and chiller selections. TE discussed the cost estimate and various upgrade options at the building for this project.

02/09/05 – Received Signed SOSS

01/12/05 – Project Kickoff meeting with County. TE to begin design.

Administration – 10th Floor Chiller Upgrade Read More »

Administration – DDC Upgrade to Metasys Gen III

02/27/06 – JCI reported today that all final documents are on their way to Tony and they will train the Admin staff on outside access for this project and take care of small punchlist items.

02/23/06 – Final paperwork received. No significant punchlist items other than to answer a couple of questions for us on the control system parameters on the job. TTC will closeout the project. TEI UPS final payapp, closeout paperwork and O&M’s to Tony Matre today. Final Punchlist items included: Item #1: What controls the EF-1 operation? Is it just the rooftop units? That appears to be the only thing telling the fan when to run. The problem is that aside from the OA enable setpoint that EF status should be tied to all the air handlers for relief during economizer mode not just the RTU’s they are almost incidental to its operation. Please clarify. Item #2: The speed drive has been hunting continuously since Mike Asbrock made the latest programming changes. Please investigate and remedy. Item #3: Are you providing a laptop on this project for Joe Merkt? Regardless, we need training to show Joe how to pull the ADS server up from outside the office. Have you coordinated with HamCo IT for internet access or port security control into the building? Does Joe and his staff understand how to view from a remote location?

01/18/06 – Wayne Jackson reported the JCI has been on site working on the punchlist this week. Joe Merkt confirmed they had indeed been at the admin building. The licensed admin software is not on site but JCI will find it and deliver it to Joe. A full backup of the JCI system was completed today. TTC will schedule final punchlist visit for next week to wrap up the job. JCI will provide final documents and billing by end of January.

01/10/06 – TTC emailed JCI to inquire about taking care of punchlist emailed on 12/13/05.

12/13/05 – TTC emailed a partial punchlist to JCI. No response has been received or questions answered yet. AH-6 has been repaired by JCI at this time.

12/06/05 – TTC stopped by the building and began the punchlist today. It is not complete and a second trip will be needed. TTC to schedule in the near future.

12/02/05 – Admin Punchlist has been scheduled for 12/06/05. TTC will distribute soon thereafter.

10/24/05 – JCI is complete and TTC is supposed to contact Joe and setup final punchlist for the project.

10/04/05 – JCI was supposed to complete the job on Friday. TTC will check and find out and will advise the County.

10/03/05 – JCI did not get finished with the DDC project as promised. They believe they will be done this Friday with graphics and 10th floor upgrades 10/07/05. TTC has to follow up with the punchlist as soon as they are complete.

09/19/05 – JCI emailed back and confirmed that the deadline is 10/01/05 and they will be done. TTC told Tony that TE will punchlist the job and get punchlist complete by mid-October.

09/16/05 – TTC emailed JCI about working onsite and meeting the 10/01 deadline.

09/08/05 – JCI emailed to commit to an 10/01/05 completion date on all remaining items on the DDC project. Parts should be in late this week and they can start this week or next. They will contact Joe for on-site work.

09/01/05 – TTC emailed JCI today about final completion again.

08/31/05 – Joe called about getting a final date for completion. This project has gone on too long and Tony wants a completion date that includes the change order cost.

08/24/05 – TTC contacted JCI with all the change order and allowance usage information to get final approval for doing that work. Once complete no allowance money will be left and JCI should bill Joe directly for remaining cost. TE will advise and information comes back.

08/23/05 – JCI and Wayne Jackson have sent in a revised current sensor change order without all low voltage wiring ran in control. The new cost is only $5700. TTC passed along to County for approval. TTC had a voicemail from Mike Asbrock on Monday stating that the hot water pumps were alarmed but not the boilers per say and the only way to know the heating boiler was in alarm was by a decrease in hot water temperature.

08/08/05 – JCI called in response to my inquiry about project status and provided the following report. The project is still about one month away from being complete. Each floor has a reset schedule that they were unaware of that appears to have been added after the original programming and they have to go back and put that into each DX unit. The will have this done in a couple of weeks – their technicians is on vacation this week. The graphics aren’t started yet but they will have their technician do that in a couple of days – but they have to completely wipe the 630 main program off and start over to make it right. They are working on re-pricing the current sensors because their electricians are 100% complete at the building and to bring them back that will cost mobilization, but I told them we still need a price and to coordinate with Joe the scope of what he wanted on the closed feedback controls. Wayne Jackson went on to say that they know they still have a lot of small cleanup work to complete and I told them that and to update the as-builts with all the new sequences.

08/03/05 – Joe called today and asked about revisiting the circuit sensor change order since the chiller job came in under budget. TTC sent JCI and email about final status and about what the cost would be to upgrade the controls and sensors to monitor actual running status of the equipment at the Admin. The old control system had open feedback also – so it didn’t get upgraded during the project. TTC also inquired about the graphics upgrade and when the project would be complete.

06/28/05 – TE received invoice # 01 from JCI but as Pat pointed out, it is not on an AIA form and it doesn’t include the correct paperwork for approval. TTC will contact JCI.

06/15/05 – Joe called today to report that Tony will not be accepting the current sensor change order. JM also reported that JCI was finished with floor 1-8 on all HVAC units. No graphics have been installed to date. TTC said that made sense because that will be the last part that Ed Braemer puts it when he arrives on site for commissioning and downloading.

06/09/05 – TE received update submittals showing the chilled water system for approval.

05/19/05 – JCI is onsite with ACPI on the 8th floor working on the FCU panel. A new DX9100 is being installed and ancillary equipment is being installed before the changeover takes place.

04/22/05 – TE has reviewed submittals and can approve after JCI answers a couple of small questions about AHU-1 and 3. Should leave TE on Monday.

04/06/05 – TE received submittals on controls from JCI. TE will begin review of entire packet for use on the new job. TE is still awaiting direction from the County on whether to accept the CO request for fan status on each air handler.

03/24/05 – Submittals to TE at end of next week. Electrician (ACPI) has pulled the N2 bus around the building. JCI thinks that they will be on site a couple of weeks after that. JCI is still awaiting an answer on circuit sensors.

03/03/05 – JCI turned in a $$9226 Change Order request to add current sensors to all the air handler fans. Apparently the existing system only has open loop control of these fans meaning that if the fans are commanded on, the system shows them as running, if they fail or don’t turn on, the DDC will not show them in alarm. Please advise on how to proceed on this change order request.

01/19/05 – TTC, Ed Braemer and Joe Merkt discussed additional air handler today but couldn’t resolve the numbering issue. We will meet onsite on Jan 24 to resolve. Joe believes that the quote includes all air handlers for this project.

01/12/05 – Joe Shutte called to tell us that an additional air handler on the first floor was discovered during field work that does not appear on any JCI control dwgs or as-builts, therefore it was not included in the state term price given to us for this project. TE informed them to match the existing sequence and give us a price to upgrade it on this job pending a decision from Facilities. We are awaiting the allowance/change order price.

11/05/04 – Pre Construction Meeting

09/20/04 – Tony and Diana requested an SOSS for this project today. TE completed the state term contract for JCI and has already sent it down.

Administration – DDC Upgrade to Metasys Gen III Read More »

Administration – 6th Floor Sink Addition

03/16/06 – Mark reports the sink is compete. I am set to archive this project at the end of the week.

12/28/05 – TTC called Blue Chip to find out the status of the permit application.

12/14/05 – Permit drawings have been signed by ThermalTech and sent to Blue Chip for submissions. Copies will be delivered to the County on 12/15.

12/09/05 – TTC contacted Blue Chip about acquiring this permit for the County. Sam completed a permit drawing for use on this project. TE will get 3 stamped sets of the drawings for Blue Chip if they agree to get the permit.

12/06/05 – THIS PERMIT WAS ACTUALLY FOR THE ADA TOILET UPGRADE. Wayne called to say the scope changed on the project and the only thing they need is a permit for the sink, TTC reported that the permit was pulled by Blue Chip Plumbing already. TTC called Blue Chip and is getting a copy of the permit faxed over to TE. I will scan it and fax it down to Wayne when we receive it.

11/07/05 – The County has decided to the do the work in house and TE will assist in getting a permit for this job and reimburse the cost through Blue Chip for the permit.

10/03/05 – TE sent out a project update but we have not received a signed SOSS for this project yet.

09/23/05 – TTC & MS are meeting the County on site to discuss the scope of the project. We will then write the SOSS for the project.

Administration – 6th Floor Sink Addition Read More »

Administration – Engineer’s 7th Floor Renovation

12/26/06 – This project has been put on hold for so long, it is being archived by TTC.

12/14/05 – TE finalized cost estimates for the new phase I work per Cole and Russell’s revised scope. Archibus is up to date. The HVAC scope remains the same because the areas affected are all within our HVAC scope. The electrical is different and Mike Stiles will update the Phase I cost to reflect the smaller scope.

08/05/05 – Diana sent an email stopping all work on this project until the Engineer’s Office releases everyone to do more work. ThermalTech is nearly done with the design at this stoppage point but will hold all work until further notice.

Administration – Engineer’s 7th Floor Renovation Read More »

ADMINISTRATION – AUDITORS COMPUTER ROOM & RENOVATION

12/26/06 – This project is being moved to the archive until such time as the tenant comes up with the funds to restart the project.

10/01/06 – This project has been put on HOLD till further notice.

09/01/06 – Based on our new chiller design, the expensive computer room unit required for this room could easily be handled by the new/existing 24/7 chilled water system in the building. This may save the Auditor $10,000 whereas the only thing they would buy now is a fan coil unit and the piping from the CHW system to the space. They would be our first tenant to jump on the new system.

07/25/06 – After the County decided to pre-purchase the equipment, TTC has been working with the Liebert rep to decide which equipment would best suit this application so it can be purchased. TEI has not received data from the Auditors office for loads for the new equipment yet.

06/09/06 – TTC sent contracts down for approval on 06/28. Mark Donnelly called today to say that the Auditor would like to pre-purchase the Liebert unit and UPS for the space. TEI will put together a small project pre-purchase spec and bid this out for delivery in November.

06/14/06 – TE and CRA had a meeting to discuss cost estimates with Auditor and even though a miscommunication of what they wanted estimated prevented the meeting from being a total success, there was enough good information to allow us to redo the cost estimates by 06/21/06.

05/29/06 – TTC emailed Liebert about equipment options and budget cost for the upcoming cost meeting. Our fieldwork at the last meeting located the condensing unit on the small roof adjacent to the atrium roof. The architect will have to cut an access door into the wall in the storage room where an old window use to be. Spencer, TTC and Joe Merkt discussed options on this door. TTC stated that when this new condensing unit was installed that the GC will have to install a set of handrails on the outside parapet since the unit will be within 10 feet of the outside roof. Joe seemed okay with the location and this will give us 24/7 cooling without using city water.

05/25/06- Kickoff meeting left TEI with two cost estimates to assemble. #1 leave the computer room on the fourth floor and estimate to the reworking of personnel on 5. #2 move everyone up to the fifth floor including the fire protection system and servers and UPS. We will meet in two weeks to go over cost and issues for design.

05/22/06 – Mark setup a kickoff meeting for this project on 05/25 at 10 a.m. SOSS’s have been signed.

04/07/06 – TTC and GM attended a meeting with the Auditors (Paula Drake, Terry Munz, Stu) and the County (JM, Jim Eby, DES) to discuss the future of this project. DES stated that the job will most likely be incorporated into a 2006 pop up project to move the computer room up to the 5th floor. The Auditor has an offsite computer farm that consists of 6 servers that they are paying $4000 a month. These may be moved into the basement to save money. We will try to design a new project asap to get a 5th floor computer room created. We will reconvene on Monday with Spencer to discuss options.

03/13/06 – Mike Stiles emailed the County for clarification on the scope of this project:

I would like to confirm the items expected under the SOSS and address what it fixes and does not fix. As you know from previous conversations there are several problem with the computer room as it pertains to power. The SOSS written and approved covers some of them but not all, as discussed. The first and most immediate problem is the power strips on the back of the racks failing because of the poor design of the device and loading. The SOSS is to replace the existing power strips, add new power strips on all the racks, and double the amount of circuitry. This will allow for better loading and add redundancy for dual power supply devices.
This will fix the immediate problem but I would like to clarify that this doesn’t to fix the next main problem. The current UPS is loaded to full capacity (82%-95% which is greater the manufacturer recommends). The additional circuitry will fix the loading issue at the power strip but not at the source. No additional devices should be added to the computer room currently even after the additional circuitry, without the UPS being upgraded. There is an option but not a great one. Some of the new circuits could come from building power, not the UPS, and will allow for more devices being added. The down fall of this is the devices connect to these circuits will not have conditioned back-up power. I need to know if the County would like all the circuits to be from UPS power or a mix of building power and UPS power.

ADMINISTRATION – AUDITORS COMPUTER ROOM & RENOVATION Read More »

Administration Electrical Device Identification

02/02/07 – DK has submitted all final paperwork on this job including the final pay application. TTC believes it is okay.

01/17/07 – Debra-Kuempel called the County because they are not turning in correct payapps. TEI will called and send over the final correct pay application for them to turn into TEI for approval. TEI has faxed a final version to DK for use. Alberta received it.

01/10/07 – Project completed in 2006

10/30/06 – Request to cancel change order was accepted. NR returned pay application #5 because of discrepancies in pay amounts. Final pay request should be for the remaining $4,711.14 with no change order.

09/11/06 – TTC contacted Steve Kallmeyer about change order cost on this project. We are trying to get all change order within the $5000 allowance.

07/06/06 – Close-out meeting held on location. DeBra-Kuempel still needs to put the new panel schedules in the panels; the old schedules are to remain in the panels. There were no other open issues. DeBra-Kuempel provided a CD with the panel schedules on them. I will have the drawings together within the next 4 – 6 weeks. TE will have (3) full sized sets delivered to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Joe Merkt). TE will make (3) binders of the panel schedules and deliver them to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Joe Merkt).

06/21/06 – I spoke with Steve Kallmeyer about devices that were not identified. He is sending an electrician out to the jobsite on Friday, June 23, to finish the identification. He is to call me on the following Tuesday to set up a close-out meeting.

05/09/06 – DK sent application #2 with wrong numbers in contract. Job is being closed out this month.

01/09/06 – DK began working on device study in building.

11/15/05 – Contracts have been submitted.

Administration Electrical Device Identification Read More »

Administration – ADA Lighting Upgrade

03/17/06 – TTC walked the site today and saw two lights on the 6th floor being installed. One worked and one didn’t. There appears to be a problem with some of the light fixtures. They may have to be returned for work at the factory.

11/03/05 – TTC sent out the final Addendum for the new bid on this project. TTC took out an ITB since the cost estimate was above $25,000 on this project. The bid is set to open on November 10th. I don’t know why I was rushing to send out addendum today – I actually had till Monday. I reset the estimate to $62,500 after talking to Mark and included a lamp for each fixture as part of the bid. Add01 – PDF

07/20/05 – TA talked to Mark about MS working on the ADA project. MS will provide a new update soon.

02/22/05 – TE is waiting on further direction from the County on any additional work required at the site. Phil and Christine are creating a detail for the additional lights in the lobby area on floors two through six for future use.

02/04/05 – PL visited the site with Brian Meyer and MWH and readjusted some of the lighting in the lobby. PL dropped off the refurbished fixture for the CH too. Rebecca Groppe did not like style and installation of the lights, but TE thinks it looks great. We believe that the space appears open and clean. If there is anything that TE can do to make things better, please let us know.

Phil Lambing has been onsite surveying existing fixtures and will devise a plan to upgrade the lighting appropriately.

Administration – ADA Lighting Upgrade Read More »

Administration – ADA Toilet Upgrade

03/16/06 – Mark reported that they are waiting for partitions to come in right now for installation.

11/02/05 – Blue Chip called to check status of permit. TE stated the invoice could be sent directly to Mark Hardin. TTC does not know current status of doing this work inside the building by trades, but will check with Mark to find out.

09/07/05 – Project is complete. TE has been instructed to assist in the plumbing permit retrieval. TTC contacted Blue Chip who will turn in for the permit for the County. County trades will do all the work. TTC will print out 3 sets of 11×17 drawings provided by Ben at GBBN and give them to Don Grace for city application. Blue Chip will be the county for their time.

Administration – ADA Toilet Upgrade Read More »

ADMIN – RECORDERS OFFICE CUBICLE RENOVATION

03/20/07 – As-Built are here. TE will return this Thursday to MD. Closeout is complete.

03/15/07 – Permits are closing out and job is complete. Ready for Archiving.

12/26/06 – TTC has given all dwgs to contractors and owner for work on this project. The FPC does not need a permit for the limited work and that is to be scheduled directly with Joe Merkt. The IBI was acquired for this job and faxed to Mark Donnelly to give to Jim Eby when need for final inspection.

11/28/06 – TEI was originally working for CRA on this project but the scope got big enough that we took out our own SOSS. Today we reported the J2 fire protection submitted a quote 2 weeks ago for $400 to do this work and that no permit is required to do this work in the space. It is our understanding that J2 can be contacted and coordinated by MD and JM to get this work done in conjunction with County Trades modifying the space. TE submitted for an IBI for this project and scanned the permit and sent it to the County for use on the electrical side of this project.

ADMIN – RECORDERS OFFICE CUBICLE RENOVATION Read More »

ADMIN – 10TH FLOOR CHILLER REBID

05/03/07 – After we found that the existing expansion tank was ruptured we did some super quick engineering and worked it out with PHB to install a new bladder tank Expansion tank on the 10th floor set to 20 psig. After some initial heartache, we found this fix to be working out nicely.

03/15/07 – Joe reported that pump head was extremely high in low load conditions. TE to investigate.

02/19/07 – PHB has finished the pipe bridge work and corrected the reverse return system at the building. First test appear to have everything working correctly. TEI directed everyone to closeout the project.

02/02/07 – PHB is having Bob Gettler’s brother come down to the building next monday to look over remaining work to take Bob’s place.

01/17/07 – TE distributed the punchlist and informed contractors to turn in all closeout paperwork and final pay applications for this project. Punchlist PDF

01/05/07 – TE has to get Trane and PHB to fix a couple of items on the chiller installation and some prices to finish the work including a valve in the pipe bridge and some steps.

12/04/06 – TTC informed contractors to use 10/11/2006 for warranty start date on this project. It was the weekend of the startup and electrical shutdown and will be as good as any to use as the chiller was brought online for service shortly after that. After talking to Joe, we may want PHB to give us some prices for steps and rails up to the chiller control panel as well as the other RTU’s with our allowance money.

12/01/06 – TTC talked to QCE and they will have O&M’s here in a week. TTC has approved payapp #2 for this project for them and sent to Tony.

10/25/06 – PHB Change Order for piping change will come out of allowance of $5000 which has not been used yet (see below). Queen City also confirmed that the $5000 allowance was not used to date.

10/10/06 – TTC check on weekend shutdown and everything seemed to go well. The chiller was not actually started. Today, Bernie told TEI that he believed QCE would have a person down at the Admin building to actual provide power to the chiller. This will allow the chiller to be tested and factory started on Wednesday as planned. TTC may stop down in the morning to check on progress.

10/02/06 – Per everyone’s agreement the chiller will be started on 10/11/06.

09/01/06 – Greg reported today that Duke has been inside the vault and working on the new service. This could mean a completion time of next week. QCE will follow that up with a scheduled shutdown of the building (after talking to Joe) for their tie-in. PHB will be down next week to finalize the piping bridge crossover removal work and then we can really wrap this project up. The new chiller will need to be powered up and tested and the controls (current status unknown by TTC) will have to be checked. Any new computer room system can be added to the system from that point on as long as everyone understands that chilled water will now be available in the building 24/7 either my the main plant or the rooftop plant.

08/18/06 – TTC emailed Joe and Tony costs on converting the system to 24/7 chilled water for computer room units. It can be done with little up front cost to the building and each user would pay for connection to the system. Each computer room unit would get a tap on its associated floor, a check valve, an isolation valve, and an inline pump to provide the chilled water to the unit.

06/29/06 – TTC met Bob Gettler on site to discuss the removal of the bridge connecting the supply and return piping for the CHWS/R. PHB will put a price and time together to do this as Joe and I decided it should be done on the weekend and some equipment should be moved to keep it from getting wet. They will put a price together and send it to us for approval.

06/08/06 -TTC brought all the equipment to the site for field work. We took many readings, some of which don’t make sense. The pressure drop across the flow meter in the basement is showing a chiller gpm flow that is 100 gpm higher than design with or without the auxiliary pump on. The pressure drop at the top of the riser is about 30 psig but the pressure drop across the coil is 1.5 psig. The water temperature at the inlet to the coil is only 57.4 degrees. Cooling is an issue on this floor. The bridge could have something to do with it. TTC requested data from Trane and the balance report to help in resolving the new temperature issues. TZ remembered that during design, this floor had temperature issues during hot weather too so that may be indicative of a long term problem.

06/06/06 – TTC and Joe have been working on AHU-10 serving the 8th floor space since the flow and temperature don’t seem to be exact. Joe also showed TTC a piping bridge that existing on the existing supply and return piping that wasn’t shown on the TEI PID. After consultation with Todd Zurweller and Gary Davies, it was agreed that the new design cannot work without that bridge being removed and blocked. TTC will stop by on 6-7-06 to field verify flows and pressures. TTC emailed Tony with Duke Energy contact for new electric meter application. QCE is negotiating with PHB on roof curb space for new conduits. TTC emailed PHB about removing the 10th floor bridge.

05/26/06 – The steel beam has been moved to its correct location. TTC gave PHB the okay to remove the expansion tank as part of the allowance as long as it is under $1000 as we have a $5000 allowance on this project for the MEP contractor. This expansion tank will no longer be needed on this project but it was not shown as demolished on the plans – it was left as is. TTC contact QCE to have the remove two conduits that are in the way of finishing the demo of the existing chiller.

0523/06 – The chiller lift went very well aside from the new support steel being 1-1/2″ off from where it should have been welded. THP, PHB, TEI and HamCo met onsite to discuss options. TTC instructed PHB to move the steel to the correct location. THP provided a field sketch showing how to use a spacer to keep extra work down to a minimum. PDF. The old chillers were removed and the new chiller set in place with little other incident. PHB pointed out about the expansion tank in the 10th floor. It is not necessary, Joe would like it removed, but the TE dwgs do not show it being demolished. TTC asked PHB for an additional cost for this work. PHB pointed out two conduits they will need removed and TTC said he would get that taken care of by QCE. The electric penetrations for this job were also discussed and TTC said that QCE could use the refrigerant penetrations to save additional roof penetrations and TTC will talk to QCE about this. Lastly, PHB asked about routing the new chilled water lines out of the mechanical room in a different spot closer to the steel. TTC approved this new location as he did not see negatives to the proposed locations.

05/18/06 – PHB and TEI are discussing Saturday Chiller lift. PHB asked about vibration isolators. They do not come with the chiller but TTC would like them to be put under the chiller before it is set on the ground. We asked for a cost. It should only be a couple of hundred bucks.

05/09/06 – Const Mtg 2 was held and mtg notes distributed. The chiller list is scheduled for May 20.

03/29/06 – TTC distributed meeting minutes from yesterdays meeting. We are shooting for do the weekend shutdown over the May 20 weekend if the chiller arrives the week of May 15 like it is supposed too.

03/20/06 – City asked for stamped structural dwgs on this project. TTC had THP stamp their drawings and send it over for PHB to replace in the permit set at the city.

03/15/06 – TEI approved chiller, pump, wiring, mat and switchgear submittals and sent them out to the contractors and owner3/09/06 – Chiller and Electrical submittals have arrived. The chiller selection will be modified for 25% glycol. This does not adversely affect the chiller selection by more than 5 tons. PHB however will need to add some glycol to the system when it is refilled. Also pressure taps on the top of the building should be routed to a drum for collection. These are extra cost to the project that my have to be incorporated. TZ and TTC decided that keeping the electric heat tracing on the piping is still a good idea since it is already included in the project.

02/27/06 – Pre Construction minutes sent to contractors. PHB submittals arrived today. TEI did not select this chiller on glycol. TEI has to contact the manufacturer about derating the chiller for glycol and see what the final tonnage is for this building.

02/09/06 – Pre Construction meeting held.

12/13/05 – Contracts received, corrected and shipped back to the County.

12/01/05 – Trane called to tell everyone that prices were increasing this day and they want a confirmed order. TTC and Tony told Bernie at PHB that they could hold the unit for us while we wait for final contract approval. It was noted that the bid is still valid for 60 days so this price increase should not affect our project. Trane should be made aware.

11/04/05 – TTC, Tony and Bernie finalized bid numbers and some issues with was actually submitted to the County on bid day. Tony gave TE the okay to write the contract for this project. TE will have contract finished by Wed of next week.

10/24/05 – Final Addendum went out last Friday for project. Bid opening is set for this Thursday.

10/14/05 – TTC left a requirement about testing in the spec that has to be removed. Single compressors on each circuit are the only one that York makes so TTC will have to pick that up in the Addendum. The prebid meeting was successful.

10/04/05 – TE has finished the drawings and specs for the rebid and is sending it out for bidding to HamCo Purchasing.

10/03/05 – IBI confirmed today that with the 800A breaker on the 10th floor we can buy the 150-ton chiller as long as the MCA is less than 800A. Our 150 ton chillers are 733A so we can go with the full sized chiller. TTC and MS will finish up the drawings today and will deliver them to the County on Tuesday.

09/27/05 – Tony gave TE the okay to go with a 125-ton chiller if needed. In talking with George Mullins and Mike Stiles today, there may still be a change to stay with the 150-ton chiller because the total cost of the electrical project has decreased from a $105,000 job to a $25,000 project. With this additional money we can upgrade the GE chiller disconnect to 1200A. This will allow us to increase the chiller size back to 150-ton. Mike and George have to setup a field trip with Joe Merkt to verify some electrical data to make this happen. We are still trying to get the rebid done by this Friday.

09/18/05 – ThermalTech began re-engineering the project for buying the chillers on LCC and re-doing the electric design to meet the new standard for providing dual power to all equipment in the building. We want to be complete with the rebid this Friday but are running into some roadblocks where it concerns feeding the new rooftop chiller with an 800A max service or MOCP.

ADMIN – 10TH FLOOR CHILLER REBID Read More »

ADMIN – 7th Floor Engineer’s Office Renovation

08/31/07 – TEI was instructed to put project on hold till next year.

08/08/07 – Project estimated cost seems to be over budget. CRA awaiting direction from Mark Donnelly on scope/cost coordination.

07/30/07 – TE has moved to the design phase of this project.

06/29/07 – TE is awaiting drawings from Cole & Russell. When the drawings arrive TE will put together a cost estimate for the project and present it to Hamilton County Facilities Department.

06/22/07 – TE received word from Cole & Russell that this project is moving forward. TE is now awaiting drawings from Cole & Russell.

06/15/07 – TE is awaiting Joe Merkt, the building manager, to return from vacation so that we can perform the necessary field work to move this project forward.

ADMIN – 7th Floor Engineer’s Office Renovation Read More »

ADMIN – ADA Title I & II Upgrades

12/20/07 – Approved final electrical permit has been received.

11/06/07 – Punchlist completed.

09/28/07 – Pre-Const meeting held 09/18. Signed contract & Notice to Proceed issued. CRA received and approved shop drawings.

09/19/07 – TTC emailed the IBI permit to MD with the paid balance recorded and the permit number.

09/05/07 – Nick Richmond wrote in an email to Mark Donnelly “We have completed the plan review for this project. Mike Huntwork will be dropping of payment for permit tomorrow. On his way back from IBI he will be stopping by your office and dropping off (3) full sets of the drawings for this project. (1)set is for you, (1) set is for Bert, and (1) set is for trades.”

08/06/07 – CRA received Prosecutor comments including comments on Supple Conditions.

07/27/07 – GC Contract (including Alternate #1) sent to Mark Donnelly.

07/18/07 – CRA submitted the Building Permit Application to the City of Cincinnati Buildings and Inspections.

07/09/07 – Bids received. Evaluation complete.

06/29/07 – This project has moved out to bid. Addendum # 01 has been issued.

06/08/07 – TE received drawings form Cole & Russell. This project has moved into the Design Phase. Drawings have been set up and TE has investigated where to get power for the new door openers. TE will perform a site visit early next week.

05/01/07 – 3 drawing packages authorized: signage, trade & bid. CRA issued for Signage and Trades. Existing door closers cannot be adjusted to required closer pressure so eliminated from project.

04/27/07 – TE awaiting drawings from Cole & Russell.

04/20/07 – TE still awaiting notice to proceed.

04/13/07 – TE still awaiting notice to proceed.

04/06/07 – TE still awaiting notice to proceed.

03/30/07 – Meeting was held to assess final requirements. Awaiting notice to proceed.

03/23/07 – Next meeting is scheduled for this coming Monday. Cost estimates will be provided by TE CRA.

03/20/07 – Kickoff meeting complete. CRA building study is being revisited for newer additional ADA. See CRA website.

03/14/07 – NR created project journal and filled in back data from previous meetings. Meeting minutes from the kickoff meeting held the week of March 5 have been issued to project team from Tom Kamphake today via email.

ADMIN – ADA Title I & II Upgrades Read More »

ADMIN – AUDITOR’S 4TH & 5TH FLOOR RENOVATION

04/07/08 – Pre-Award meetings are complete. CRA and TEI sent out copies of the meeting minutes too project members. Letters of recommendation are forthcoming from the partners. CRA is submitting for the HVAC and Building permits today. TEI is submitting for the IBI permit tomorrow. Kevin Maue is supposed to send TEI a release note on the Data Aire unit with Debra Kuempel. A pre const mtg should be scheduled in late April. KM stated that a Notice to Proceed letter should come out on or about May 8th.

03/28/08 – Bid Results are published. PDF

2/07/07 – CRA furniture and move services package ready for issue.

11/30/07 – TEI has the pre-purchase specs on the street for the UPS and the Computer Room AC Unit. These pre-purchase bids are scheduled to be opened on 12/5 at the HamCo Purchasing offices. We have decided to push back a design review meeting until after the equipment is purchased so final design will be exact.

10/30/07 – Meeting was held to review the proposed layouts. See Meeting Minutes here. The next meeting is scheduled for December 4, 2007 at 10:00 AM at 3rd Floor of C.A.B. Auditor’s Office.

10/09/07 – Meeting was held to review the proposed layouts and to discuss project construction phasing. HCFD stated that the project would bid around January 2008. This will allow construction to start around March 2008. See Meeting Minutes here.

10/01/07 – Meeting was held as scheduled. HCFD requested that C+RA, IPM and TEI issue a CD Owner Review Set on 10-05-07. See Meeting Minutes here.

09/28/07 – CRA has a coordination meeting with Mark Donnelly scheduled for 10/01/07.

09/19/07 – TEI had a coordination meeting with CRA on HVAC, Elec and Fire Protection. TEI has to update to CRA latest floor plans and then incorporate the furniture into the project. TEI is behind on finalizing the computer room layout with Stewart but TTC has scheduled a field trip to the space on Friday to go over HVAC changes, fire protection changes and electrical changes to the space. We also have to route chilled water line from the mechanical room to the auditor computer room. MD asked for drip pans under the city water unit and the liebert unit. TK sent a new sent of final floor plans over for our use. TTC gave everything to Chris and Mike to update.

07/26/07 – Restart meeting was held. CRA and IPM are working on re-program and concept layout. Target dates are: August 8 review meeting, September 3 out to Bid.

06/27/07 – Project is on hold but may recommence soon. Awaiting authorization to start.

06/20/06 – Project is on hold due to funding problems.

06/06/06 – CRA Schematic Design documents and estimate have been completed and approved.

05/22/06 – CRA received the signed SOSS.

04/17/06 – CRA submitted the SOSS.

04/07/06 – Kick-off meeting was held. Field verification and photographs were taken.

ADMIN – AUDITOR’S 4TH & 5TH FLOOR RENOVATION Read More »

ADMIN – LOBBY DESK RELOCATION

12/07/07 – CRA sent contracts to BW on 11/29/07.

11/30/07 – The bids have been opened and although, TEI wasn’t at the bid opening, we believe HCG may have won the bid. CRA would have to confirm.

11/15/07 – CRA BW directed to prepare contracts for HGC.

11/12/07 – TTC and MH has sent out Addendum 01 through CRA. The bid opening is 11/15. Zach sent Addendum out for bidders. Addendum included information on relocating and interior light switch and alarm security panel by the EC while the owner has agreed to have the HVAC sensors moved by JCI or by their HVAC team.

10/30/07 – Pre-bid meeting held at C.A.B. first floor lobby at 1pm.

10/19/07 – Bid documents completed. Bid issuance date is 10/23/07.

09/25/07 – Cost estimate entered into Archibus.

09/14/07 – CRA received drawings from TEI. Drawings updated. Awaiting approval to complete and issue for permit.

08/28/07 – CRA issued DD drawings.

08/02/07 – Project being resurrected. Kickoff meeting was held.

ADMIN – LOBBY DESK RELOCATION Read More »

ADMIN -Auditor’s Office – 4th & 5th Floor Renovation

02/08/10 – Payapp has arrived. TEI finished the as-builts drawings. We are shipping the original record markup dwgs, cd’s and final payapp to Bert for closeout.

02/04/10 – Look i can’t take it any longer. This project has to be moved to the Archive. It is just too old. I will update the final QCE payapp when it arrives. It is being moved today.

01/28/09 – TEI contacted QCE but Cavanaugh is out. We have not received their final payapp. As-Builts are almost done with Cad markups by TEI.

12/31/09 -QCE turned in closeout documents today for approval to TEI. TTC received and approved. As-Builts will be updated in 2 weeks by TEI. We need a final payapp from Queen City still for approval which is coming next week according to Mike C. After that this job will be closed out.

09/22/09 – We have contacted Queen City several times about closeout and still have not received the documents.

08/20/09 – QCE payapp has been approved but we have not received their closeout documents yet.

07/29/09 – QCE reported today that they know the O&M’s are due but they have just been too busy on trying to get new work in today’s market to finish them up. TTC told them that they could bill for retainage on this project and leave the closeout document line item at 0% until they submit the O&M’s. Cavanaugh said he might do this but they will work on the closeout docs.

06/23/09 – The final EDI item is the revised sequence which TEI wrote and sent to Data Aire and EDI for approval. The sequence has been approved but TTC is waiting in equipment deadband from DA. This is not critical to finishing the sequence. TTC may just update and send final to Bert. All other project contractors are complete. Get an update on closeout from Bert on EDI, QCE, CDFP paperwork.

05/22/09 – Data Aire Unit is running as designed on both chilled water and DX cooling. The system is changing over quickly and keep the space cool. TEI to write final sequence for the project.

04/15/09 – CR Architecture and Design awaiting final punchlist items to be completed.

04/03/09 – All work and punchlist items have been completed by EDI on this project. O&M’s have been logged in. Final payapp has been received. The payapp #2 was on hold but has now been release to Bert. The CDFP closeout paperwork was signed and sent to Bert yesterday. Queen City still owes us final payapp and O&M’s on this project. EDI still has to use chillers in the building before we know everything works.

02/18/09 – A controls meeting is scheduled for Friday with EDI and Data Aire.

02/07/09 – TTC requested a revised payment from EDI for this project.

02/02/09 – Terry & Mike will be down for project punchlist on Feb 4 for final walk through. The new insulation worked perfect through the cold snap last week. Bert reported no condensation on the unit, even on the the through metal parts.

01/22/09 – EDI is at the site today installing the insulation inside the unit today. All interior surfaces.

12/20/08 – Problems with the Data Aire Unit still exist. Condensation is a real problem. The unit is not insulated. DA said they can fix this problem with insulation. The controls and the chilled water pump are still not interlocked. A JCI N2 card can help the situation. Duft said that would be the easiest to use. TTC said it was going to be provided at no cost from DA on this project.

11/25/08 – TEI is working feverishly with EDI and QCE for final change orders. Hours were spent trying to resolve QCE change order #3 today and it still wasn’t exactly right. Another $317 needs to be written for QCE. ThermalTech must complete final punchlist on this project.

11/24/08 – Project is 95% complete. Final Change Orders need to be in by 11/26. TEI is working on them today.

10/16/08 – Bert reports that Stewart will be making all final computer moves this weekend and by Monday all essential Auditor equipment will be on the 5th floor. Demo of the 4th could start shortly for all contractors. QCE has made more modifications to the plug strip on the server racks and disconnected the 4th floor rack to facilitate its move to the 5th floor. The project is finally making progress towards completion.

09/18/08 – Trying to setup TCO for next week.

09/17/08 – Server must be running by next Tuesday. Fan test not complete. Temporary route condensate to 4th floor hub drain. EDI ductwork not installed. Power outage has delayed final fabrication of ductwork.

09/04/08 – Elevator quote came into today for $3k. Work to be done next Monday with Thyssen Krupp and EDI.

08/2508 – TTC sent out the plumbing Bulletin drawings to Helmes plumbing et al.

08/22/08 – TTC visited the site today for floor drain relocation. UPS is in and being wired. Disconnects are installed. Fire protection is in 5th floor room.

08/08/08 – Const Mtg notes from today include

08/01/08 – GM located new locations for the bus plugs disconnects for the project. One on the 5th and one on the 4th. QCE will have to move an existing disconnect to make the new ones fit.

07/30/08 – Data Aire Unit ship date is August 20. It will arrive 3 or 4 days after that. Quick ship prices were given but overly costly to the project for the minimal gain.

07/17/08 – Const Mtg. We discussed project schedule for this project. Contractors reviewed progress. Demo found a stairwell pressurization fan in the new computer room that must remain as is. EDI will seal ductwork. Computer room unit delivery is 4 to 5 weeks.

05/30/08 – Pre Const Mtg complete. Equip 5 weeks out. Contractors to provide schedule for start of the project.

ADMIN -Auditor’s Office – 4th & 5th Floor Renovation Read More »

ADMINISTRATION 8TH Flr Planning Renovation

08/13/10 – The space looks great. Tenants say they are not used to the new work flow yet but will give it time.

07/23/10- -Work continues. BW is handling the Const Admin of the trades work on this project. No new questions or issues that TEI is aware of.

05/26/10 – TTC will check on progress while at the permit office on Thursday.

05/13/10 – City sent permit receipt to TEI for use on this project. All permits look to be approved at the City Web portal.

05/05/10 – Check on progress with Dave S and Bert W. IBI inspections for rough in are complete. Cindy office is under nightly construction.

04/26/10 – Work has begun. Phasing was taken over by Bert. We check the scale of the drawings on D size prints and it was right, check with Bert on Thursday to see what the issue is.

03/24/10 – Arch permit review is complete. The changes will take some time and we need updated specs from Speer. These should be permitted on Thursday/Friday.

03/23/10 – Permit drawings are being reviewed inside ThermalTech and at the Architects office. We should be acquiring permits by Wed or Thurs this week. We have incorporated all the client comments into the drawings and added specs to the job.

02/24/10 – We had the SD review meeting. Bert asked for a new SOSS for permitting the job and incorporating the changes and Archibus input. Smorey requested a new schedule. TTC will get that completed on Friday.

02/04/10 – We are still trying to get an SOSS worked out with Public Works for this job and Bert is assisting us in this attempt.

01/28/10 – TTC and Bert discussed a new SOSS for County Trades installation and TTC provided it. There is some doubt about how will do this work and how it will get design. TEI will wait for Facility guidance before proceeding.

12/21/09 – TTC, BW and Smorey met on site to go over the changes required in the renovation. TTC got drawings copied for Hamco and TEI and is preparing the SOSS. This project will require electrical, fire alarm, mechanical and general work to complete.

ADMINISTRATION 8TH Flr Planning Renovation Read More »

ADMINISTRATION – 7TH Flr Engr Furniture & Electrical

03/30/11 – Project is complete. Art Smith & TJ Williams invoices has been sent to Pat Day for final payment.

02/22/10 – The initial stage is complete. I believe I am waiting on the County to find some furniture pieces for us to use to fix up the remaining parts. I haven’t heard back from Judy on how well the repairs went.

01/24/11 – We have finished the first pass through on the furniture fix up. I need furniture pieces to have Art Smith fix up the remaining parts to get it as good as it gets for its age. I would like to move to next phase and replace the front counter after we get our contract and counter SOSS approved.

10/25/10 – TJ Williams bid was resent to Judith. Engr needed more information. Ginter has to update their bid and we will forward that along.

09/29/10 – Bids were collected and sent to Bert. The 2 day repair cost is under $2000.

07/28/10 – Need Judith contact info. George Mullins may have to design this project with Susan.

07/23/10 – ThermalTech attempted setup a design meeting for SD and Cost. Judy email bounced back so I need to find her new number.

05/26/10 – SOSS approved. We will setup fieldwork and kickoff next week.

04/26/10 – Schematic Drawing is complete. Fieldwork is complete for SD. We are working on cost estimate to send with SD.

03/23/10 – Project on hold.

01/26/10 – Bert contacted ThermalTech about permit requirements and was told the mechanical code would require a permit for the new ventilation calc required in a new conference room. Bert has the SOSS for this project.

12/31/09 – Bert contact TEI to work on this project and renovation. TEi owes Bert an SOSS based on the HamCo Scope of Work.

ADMINISTRATION – 7TH Flr Engr Furniture & Electrical Read More »

CAB – Access Control Project

09/22/10 – SOSS Approved. Review comments sent and received from Bert.

09/29/10 – Markups corrected from BW. QC check complete. TEI needs to pick up NV marks and send to Purchasing on 10/1.

10/28/10 – Contracts for ICS have been sent to Bert Watts for approval. Project is under budget. No allowance has been added because of a bonding issue.

01/24/11 – Bert and George decided a pre const mtg will be set next week to kick off this meeting.

02/22/10 – Paul Wilson has made good progress on this project. Wiring is ran on upper floors and they are working their way down to the dock.

03/30/11 – Paul Wilson submitted and change order to remedy the power supply issues on the tenth floor. REX needs to be changed so the door does not open at night when approached by security. GM said that the contractor can reprogram this feature. Project seems on track.

04/27/11 – Bert reports that installation is very nearly complete and the system is ready to begin use this week or next.

05/13/11 – Punch list was issued to IPS. Project should be wrapping up.

06/29/11 – IPS has submitted its main pay app, now we need to close out the rest of the project.

08/28/11 – New Signed change order came back. IPS should be doing this work soon, rest of project complete. We can request closeout at any time.

09/28/11 – All work to be completed has been put on hold per TTC.

10/24/11 – The certified payroll for IPS for the dates 10-2 through 10-9 was sent to Hamilton County and TEI.

11/15/11 – IPS requested final payment from Hamilton County in the amount of $4,984.22. TTC responded by saying all paperwork had been sent to Hamilton Co. and IPS should get paid per the Contract.

12/23/11 – This project will be archived for 2012.

CAB – Access Control Project Read More »

CAB – Sheriff’s Re-entry

01/20/12 – Mike B. spoke with Mr. Gaylord Poe, President and Chief Electrical Inspector for IBI regarding the CAB space. Mike explained that there is minimal electrical work being completed on the project, and that the electrical connections will be able to re-use the existing circuits that were removed from the systems furniture when it was disassembled. In order to get a permit, a plan exam is required with IBI. Gaylord and I discussed that the net electrical load on the space will be significantly lower than what was there previously. Gaylord said that if we draft up a letter, and submit it to him directly, he will approve that as a plans examination, and we will be able to then secure the permit. Mike has drafter the letter, and will run the letter with the permit fee to IBI asap. Actual plans, panelboard schedules, single line diagrams, etc will not be produced for this project.

01/30/12 – Mike walked through the electrical permit at IBI, and then dropped off paperwork to Steve Wessels. A final electrical inspection has been requested for Wednesday Feb. 1st. Upon verification of the inspection, Mike will send a follow up e-mail.

03/07/12- Walk-through permit was conducted by GBBN. Permit approved conditionally requiring Mechanical Permit to validate movement of existing linear diffusers to other side of new partition.

05/30/12- Bert Watts requests As-Built drawings to be completed. He indicates the Building Department has given final approval of construction.

CAB – Sheriff’s Re-entry Read More »

LEED EBOM-800 Broadway Study

2/11/10 – HCFD meets at GBBN for USGBC Webinar and issues scope and request for SOSS for this project to be completed by 2010.

3/2/10-TEI submitted preliminary fee costs to GBBN.

3/8/10- GBBN began editing LEED EB+OM checklist based on 2009 LEED EB+OM manual.

4/8/10- Indoor Environmental Air Quality Webinar held in GBBN’s Office. HCFD presents Green Seal Environmental Standards, GS-36 and GS-37 printed literature to GBBN.

4/22/10- LEED EB+OM Checklist and Planning Session held in GBBN’s Office.

4/27/10- LEED EB+OM Checklist with responsibilities sent to HCFD.

4/28/10- Phase 1 Study SOSS to be presented to Bert Watts at monthly partnership meeting.

5/26/10- Signed and Approved SOSS returned.

6/01/10- Internal kick-off meeting with Tony Yunker to initiate the project. Coordination meeting with TEI to be scheduled upon Terry-Thompson Cannon’s return from vacation.

7/06/10- Tony Yunker produces Project Checklist Spreadsheet with lists of construction cost related notes.

7/22/10- Meeting with Bert Watts to discuss final report format and construction cost detail requirements.

8/20/10- Meeting at GBBN with ThermalTech to coordinate study input

8/26/10- Meeting with Darnell Edwards at 800 Broadway.

9/3/10- TEI meeting at GBBN to discuss progress and input into Introduction, Summary and Recommendation sections of the study.

9/30/10- Meeting with Ralph Linne, Bert Watts, GBBN and TEI to review study before final presentation.

10/28/10- Attended HCFD Partnership monthly partner meeting. Delivered LEED EB+OM Study for 800 Broadway

LEED EBOM-800 Broadway Study Read More »

800 – 12th Floor Renovation Project

10/13/05 – Ben sent out some status notes trying to get Arrow to finalize. We are awaiting further direction for our part of the completed work.

09/29/05 – Arrow said they would address the additional items noted at 800 Broadway.

09/29/05 – Additional items were noticed from at 800 Broadway, “This is an F.Y.I. for you regarding the Judge’s bathroom. We had to call the maintenance folks because we ‘heard’ a funny sound coming inside the little access panel on the outside wall of the bathroom located in our kitchen area. When I opened the panel, water was spurting out from two sides of a pipe. The guys came up and turned off the water, I think. Not sure what comes next. However…they mentioned to the Judge that her bathroom sink faucets are on ‘backwards’. You might want to add these situations to your ‘punch list’?? Thanks.

09/27/05 – Arrow responded to punchlist items. PDF

09/23/05 – GBBN issued a revised punchlist with photographs and a directive to Arrow. PDF

09/22/05 – Meeting / Punchlist. GBBN is typing up additional punchlist items, including past unfinished ones, for Arrow to respond to by 09/26/05. At that time it will be decided whether to let Arrow finish, or proceed with hiring another contractor to finish.

09/13/05 – Meeting / Punchlist was cancelled for today. Diana went over to Job Site and is still displeased with Arrow’s Tile work.

09/09/05 – GBBN has scheduled a meeting at the site for 09/13/05 at 7:45 am

09/06/05 – Debbie Poland informed ThermalTech of Judge Grady’s choice of fixtures, and ThermalTech relayed the information to Arrow.

09/02/05 – ThermalTech contacted Arrow and mentioned Pat Murphy at Select Spec Sales, as a possible vendor to obtain a solid toilet seat.

09/02/05 – GBBN informed ThermalTech that the light fixture for over the Mirror has been discontinued, and to specify another one.

09/02/05 – ThermalTech had GBBN forward the following to Arrow: The cleanout and floor drain should be level with the tile and grouted in closely. It should be almost a perfect fit when done right and have a brass cover plate that should look relatively nice. Arrow should adjust the floor flange on the cleanout and floor drain so they are level, if they still can. They may have to bust out the floor and adjust it and then pour a patch around it.

09/02/05 – Judge Grady has made the following requests: Raise the top of the plumbing clean-out to align with the top of the tile. Install a solid toilet seat cover in leiu of the “open” toilet seat currently installed. Install the second coat hook. Install the over – cabinet light fixture. Replace the cracked tile at the “clean-out”. Patch up the plaster adjacent to the sink and cabinet (at door). Provide a finish on the kick-plate of the millwork. Provide shelf in wall cabinet per sheet A201.

08/29/05 – Architectural and Mechanical Punchlist was completed.

08/08/05 – Project meeting postponed for one week.

08/01/05 – Exhaust Fan is not installed yet but is on order. Plumbing is roughed into the wall through the floor space. Electric is roughed into the walls and ready for inspection, insulation and the gyp board. Progress is slow from the MEP side but is going forward.

06/16/05 – GBBN and Arrow are working to resolve a toilet outlet issue. There is a beam below the slab that is interfering with the toilet outlet. GBBN called today to say that they can use a 4-inch filler space to move a wall and thus give the plumber enough room to route the new sanitary line. TE approved this shift in the plumbing.

06/10/05 – TE received insulation, plumbing fixtures and electrical. TE will send out comments on Monday.

06/07/05 – TE sent out submittals on EF, DWV Piping and Vent, Ball Valves and Hangers.

05/10/05 – GBBN setup preconstruction meeting for project on May 24th.

04/19/05 – It was agreed that since Arrow won every part of the bid that GBBN would write an inclusive contract the entailed all items on this project. TE thinks this is great idea and removes all coordination issues between contractors since we will have only one contractor on this job doing all phases of work.

04/15/05 – Bid Evaluation was released. PDF.

04/06/05 – Add01 was released by GBBN and TE. Add01

03/22/05 – Prebid meeting complete. Reupert was only mechanical at Prebid. Sam filled out permit application for HVAC and sent to Brady. GBBN already has all the books and drawings with our stamp. As usual we cannot stamp plumbing drawings because we don’t hold a Master Plumbers license.

03/14/05 – Client review meeting. TTC coordinate with Brady on plumbing items to state the 3-5/8″ wall is fine for our tank type water closet and countertop lavatory.

03/08/05 – TE asked Facilities for direction on copper vs. no-hub cast iron for the sanitary lines on this project in the even they ever entertain waterless urinal systems.

02/25/05 – TE has begun design the MEP on this project. Layout and specs are being compiled.

02/22/05 – TE provided a price of $100 for the gooseneck faucet and $150 for the additional light above the vanity mirror pursuant to the email from the County today.

02/11/05 – DEW advised TE to write the SOSS for this project and submit it to the County for Approval. TE finished and put in the mail on Monday.

01/31/05 – GBBN assembled a complete cost estimate for this project and turned over to the County. We are awaiting further direction from the County. TE noted that GBBN had $3500 too much because TE had front end cost in the estimate and it isn’t required.

01/11/05 – ThermalTech has conducted all fieldwork and assembled a probably cost estimate based on our understanding of the scope of work. We are awaiting a meeting time or notice to proceed. Estimate includes new fixtures, exhaust fan, ductwork, plumbing and electrical work for anticipated scope.

800 – 12th Floor Renovation Project Read More »

800 – Florida Room Renovation

12/26/06 – TTC has decided to close this project and archive it. This project was never contracted or awarded and the work was never done. We believe it was included in another project.

10/14/05 – TE received word that this project is still a “go”, however we have not received any news about the contract status.

10/03/05 – Contracts are turned into the prosecutor. We are awaiting word from the County about proceeding with this project or canceling this project in lieu of a revised EMU project.

09/22/05 – TTC dropped off the revised contacts to Wayne Trent today and gave one copy to Michael Evans at GBBN. All contracts were hand delivered. The County facility group got to meet Kandy today because we stopped in

08/29/05 – Addendum 01 PDF was issued with the new bid form. Job is set to open on September 1st.

800 – Florida Room Renovation Read More »

800 Broadway Electrical Device Identification

11/16/06 – NR visited the site to verify the panel names for the Arc Flash Study. All panels are verified and the single line is complete. The Arc Flash Label information is currently being inputted into EDSA and the labels are being generated. This portion of the project should be completed within the next 3-4 weeks.

09/27/06 – The final drawings were sent out to Queen City to be delivered to Bert Watts so that he could distribute them to the appropriate people. Areas on the 4th and 5th floor will be updated when the Adult Probation Renovation project is completed and ThermalTech receives the as-built drawings. The panel schedule binders were delivered at an earlier date. All other work on this project is complete.

06/27/06 – The close-out meeting was held on location. There were no open issues. Ginter Electric provided (2) CD’s with the panel schedules on them. I will have the drawings together within the next couple of weeks. TE will have (3) full sized sets delivered to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Darnell Edwards). TE will make (3) binders of the panel schedules and deliver them to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Darnell Edwards) .

06/21/06 – Spoke with Darnell Edwards about the EMU area. He informed me that the devices were marked and that he is satisfied with the work performed. Close-out meeting has been schedule for June 27 at 9:00am.

11/15/05 – Contracts have been submitted.

800 Broadway Electrical Device Identification Read More »

800 – JV ISSUE DESK REMODEL

03/20/07 – Check CRA website for closeout documents. Project is ready for archiving.

02/19/07 – Coordinate with CRA for final details. Project is nearly complete.

01/22/07 – Permit drawings have been submitted to the IBI

01/02/07 – TTC and Spencer discussed the project today and TA and TTC will kickoff the project internally on 01/03/07 and push it towards compeltion.

11/10/06 – They installed the desk. Flooring will be installed in the next several weeks.

09/08/06 – Preconstruction meeting held. Things went as planned.

04/05/06 – Review meeting is scheduled for this Friday. Cost estimates have been given to the client. No HVAC or Plumbing work on this job.

03/08/06- Mike Stiles met with the architect on this project for kickoff.

800 – JV ISSUE DESK REMODEL Read More »

800-York Control Panel Replacement

04/26/07 – This project is complete and ready to be archived per the County Partnering Meeting.

01/05/07 – TTC has given the County everything they need to get the PO for this work and it will be done in house on this project. York has provided all the paperwork for sole source and quotes.

10/25/06 – Prebid Mtg today. DK showed up for prebid. TTC built the quotewire package and sent it to purchasing for bidding out just the purchase. TE has to send out an Addendum for bidding changes.

06/27/06 – Tony stated for us to get the electrical requirements together for the trades so they can do the work. TTC said he would get with TA and get this done.

05/05/06 – Mike D and TTC discussed recent information provided by York. Additional scope items and more electrical work that would have to subbed out on the job. TTC talked to service tech’s about doing this work and is trying to formulate a complete scope for the project.

04/26/06 – TTC reviewed the project scope with Tony, Mike Denton, Darnell Edwards, Bill Scholl and Tony Martini. Tony need further proof that this project should not be outsourced because o requirements on County Efficiency Committee.

800-York Control Panel Replacement Read More »

800 – Security Camera Upgrade

11/29/07 – Bert reported today that final pay application has been submitted for. This project could officially be closed out at this point. Bert has confirmed that the County has received the O&M’s and As-Builts sent by TTC at TEI.

11/16/07 – Lori contact TEI today about past due notices. TTC collected information and sent to Nor-Com saying that TEI would do as-builts and write deduct change order of $2000 for the job and Nor-Com has to provide a full warranty letter to HamCo. TEI finished the as-built and made a CD of the dwg. TEI finished the change order for a $2000 deduct. TEI sent both to Nor-Com to return to Bert Watts with the final warranty letter. TEI finished the as-builts and change and mailed to Nor-Com and the County. We are finished with this project.

10/18/07 – TTC opened and sign payapps 3 & 4 and sent final closeout paperwork to Bert for processing. This packet arrived sometime after 09/07 with the wrong zip code. All the certified payroll, closeout documents and payapps appear to be correct. TTC emailed everyone and said the job is ready to close.

06/07/07 – Lori from Nor-Com checked on status of payapps. I emailed back #1 show paid, #2 i need 3 originals and #3 i do not have a copy of.

05/31/07 – Closeout documents have not been sent. They were waiting to use the allowance money. MD directed Nor-com to close the job in an email and TTC forwarded that email to Mike Rolf.

05/30/07 – TEI does not believe they have received close out documents yet for this project. TTC contacted Mike Rolf.

03/30/07 – Punchlist is complete. There are no items from TEI or the owner at this point.

03/23/07 – TTC was on site today and took down punchlist items for Nor-Com. Currently there are no punchlist items for Nor-Com to correct.

03/15/07 – Nor-Com reported that cable work has begun in the space and that unit operation training is complete. 18 people attended including Phil Lambing from TE. Nor-Com will provide a more concrete completion date early next week.

03/14/07 – Nor-com was scheduled to begin work today and Vicom held their master training session for County employees this afternoon.

02/19/07 – Nor-Com is sending a new CD for submittal review on this project. TTC could not find the original.

02/08/07 – TE distributed Const Mtg notes for the pre construction and Const Mtg 01. TTC did not make the meeting in person but attended via a conference call.

02/01/07 – TTC sent MWH dwgs of the space for his use.

12/28/06 – TTC discussed kickoff meeting for this project and sent out another date because all previous dates have conflicts. We are now trying to have a kickoff meeting on Jan 4 at 9am at the 800 BWAY building. Norcomm has already sent in RFI’s on this project and proposed a solution to a DVR problem by downsized the 900 GB harddisk to allow for multiplexing of the signal to the DVR. This will have to be discussed at the kickoff meeting.

12/26/06 – TTC created project journal and filled in back data from previous meetings.

800 – Security Camera Upgrade Read More »

800 – ADULT PROBATION RENOVATION PROJECT

11/16/07 – TEI received a hard copy of the approved QCE change order in the mail today. TTC filed it for archiving with the project folder. Mike Cavanaugh called to inquire about payment of this invoice and TTC referred him to Bert Watts because all invoices should be paid on this job by this point. TTC is ready to archive this project.

11/06/07 – CRA forwarded Change Order #2 to Bert Watts.

10/30/07 – CRA issued Change Order #2 to delete the allowance balance and forwarded to Kramer & Feldman.

10/26/07 – CRA received final closeout documents.

10/18/07 – MD sent back final change order for signatures on 3 originals. TEI printed and sent 3 new originals to QCE for signing.

10/04/07 – TTC and LKV revised CO4 and sent it to QCE for signing. The new amounts were gleaned from the previous emails and signed change orders.

10/01/07 – TTC received, reviewed and signed payapps #5 and #6 from QCE for this project. I read through all the email correspondences and believe these final two payapps to be correct. Assuming that the change orders that the owner had in hand were signed and correct, the amounts of these pay applications should correspond to requested amounts by the Owner. TEI will mail them to Bert Watts for processing today.

09/28/07 – Awaiting final closeout documents. CRA needs As-built drawings.

09/04/07 – Items mentioned in previous entry were sent to QCE this morning.

08/31/07 – Pay application #05 and #06 need to be updated to show CO#04 instead of CO #05 in the work description (there were only 4 CO’s); the dollar amounts shown are accurate. TEI will correct the dollar amounts shown on CO#04 and send 3 originals to QCE for their signature. TEI will also send 3 original copies of allowance clarification #01 for the entire allowance ($2500) to QCE for their signature. When QCE has received and signed all 6 documents they will send them along with the updated pay application #05 and #06 to TEI. All of the above mention documents will be reviewed, sorted, and sent to HCFD. The documents will be sent to QCE on Tuesday, September 4.

08/23/07 – TEI printed 3 more originals for Change Order #5, signed them, and sent them to QCE with instruction to sign them and forward them to HCFD. TEI also sent the O&M manuals along with the final pay application and closeout documents to HCFD Attn: Bert Watts.

08/17/07 – TEI is awaiting the O&M manuals from QCE in order to close this project out. NR contacted Greg at QCE on August 16, 2007 in order to locate these binders. Greg said he sent them to TEI already but we have no record of receiving them. NR will contact QCE today and have them send another copy.

07/31/07 – TTC approved Change Order and PayApp # 5 for this project but asked for backup data for the change order and requested

07/30/07 – QCE is not responsible for completing the ceiling patch work. The remaining ceiling patch work is going to be completed by the Hamilton County trades department. QCE has completed their portion of work. TEI is awaiting the resubmitted final pay application and close out documents in order to close this project out. TTC emailed the County and QCE for closeout documents on this project and approved their last payapp and told CRA the same info.

07/09/07 – TE still awaiting modified change order from QCE.

06/29/07 – QCE has been informed that they will not be paid for the ceiling and wall patching. TE is awaiting a revised change order and final paperwork from QCE.

06/15/07 – Still awaiting response from QCE.

06/15/07 – TE placed call to Queen City Electric about inaccurate Change Order #04. Awaiting response from QCE.

06/08/07 – Change Order #04 was sent to Hamilton County Facilities Department but had inaccurate information. The change order did not reflect the three previous dollar amounts. The paperwork was given to TA of TE in order to straighten the numbers out.

06/01/07 – TE is still awaiting response from contractors about the punch list. New contract dollar amounts between the contractor and Hamilton County Facilities Department are being clarified. This should be resolved in the next couple of weeks.

05/25/07 – TE issued punch list. Awaiting response from contractors stating that all items have been completed.

05/21/07 – TE completed punch list. Issues with lamps have been corrected. Punch list will be issued early this week.

04/27/07 – Fixtures are 99% (one recessed can yet to be installed). TE has visited site on 2 occasions this week. Project is expected to be complete and TE finish their punch list by the end of next week, May 4 of 2007.

04/20/07 – Project is moving along as expected.

04/13/07 – Light fixtures are currently being installed. Project should be complete by the end of the week of April 20 of 2007.

04/09/07 – Phil stopped down at the site on Thursday and resolved some clarification issues on the type of lights the supplier purchased for this job. TE instructed them to send them back and get the correct cuts for remodel 5″ cans to fit into the drywall soffit.

04/05/07 – QCE has begun installing the fixtures into the space and then we can close this job out.

03/30/07 – Fixtures are scheduled to be installed next Wednesday, April 4 of 2007.

03/23/07 – Project progressing as expected.

03/20/07 – Lights are scheduled to arrive next week and be installed next week by Queen City.

02/19/07 – TEI is waiting for Mindy to get back for funding approval but lighting changes are happening now. Check CRA website for details.

01/10/07 – Const Mtg was held but TEI wasn’t in attendance. Project updates are available on the CRA website.

12/26/06 – TTC moved project over to Mark Donnelly and will get an update from Phil and Spencer this week.

02/06/06 – Spencer submitted a revised floor plan with a new sink location in the back corner of the building. TTC and SBO will pipe up the sink and drain while PEL finishes the electric work. We are shooting to have this job on the street by the end of February 20th for this job.

08/04/05 – Had design meeting today. Discussed schedule and typical workstation layouts, phasing of the project and construction times. C+R will issue official meeting notes for the job. They are talking about moving in around November so design documents have to be collected pretty quickly.

06/24/05 – TTC and Spencer visited the site today to look at the lighting and ceiling heights. TTC brought pictures back for Phil.

06/16/05 – Cost estimates were given to client and we are awaiting direction from the County and C+R before proceeding. TE hasn’t heard anything since 03/21 on moving forward with this project. NO HVAC or Plumbing were included in the cost estimate to the client.

03/01/05 – SOSS Written. TA to approve and send to DES.

800 – ADULT PROBATION RENOVATION PROJECT Read More »

800 – VACUUM PUMP UPGRADE

07/09/08 – TTC stopped by the site today and review the project progress with Process. There were several issues with the installation of the equipment that we resolved. Size, location, pipe runs, housekeeping pad, inlets.

12/04/07 – We received a schedule of values today that TTC marked up and sent back to Process. Insulation submittals were received today in the mail. LKV is logging them in for this project and will give them to TTC to review.

11/29/07 – Joe Doxsey and Terry Cannon discussed project schedule and submittals today by phone. Process is going to send their background checks to Willie at the County and are currently working on the submittals. They have not worked on submittals or project schedule yet according to Joe but will get them done now and into the system as discussed with TEI today.

11/16/07 – We held the pre construction meeting with Process and discussed changed scope and timetable for the project. Bert provided an email with the PO attached yesterday. TTC asked for the submittals on the vacuum pumps for the job and saw Rick Huff today and asked him if they were ready. He had no idea about them being asked for so Process must not have told him yet. Laurie finished typing the meeting notes and TTC has to review them and send them out. Process is going to provide a project schedule and SOV for our approval and ThermalTech has printed out and is sending 9 sets of stamped permit drawings (6 for city, 3 for IBI) for Process use on this job. TEI also emailed Process a copy of the spec and the dwgs for their personal use and printing.

08/02/07 – TTC sent out Addendum 02 for the project today PDF. Addendum 01 extended the bid opening to August 7 by Purchasing.

07/31/07 – Bernie and Roger replied with Addendum 01 items for this project. A&M stated that their cost would be about $4500 for this work even though we are adding about 8 points and picking up alarms for the system. Bernie added that the 3″ line sizes were all he needed from the dwgs.

07/30/07 – Purchasing issued Addendum 01 for this project extending the Bid Opening and Due Date to August 7, 2007. TTC will issue Addendum 2 with pipe sizes, control notes and spec revisions.

07/16/07 – TTC sent the same data to Queen City to hold for bidders this morning. TTC has to contact Gina about the advertised price for this project since he changed it after talking to Tony Matre.

07/13/07 – TTC sent the project out for bidding with a bid opening date of July 31, 2007. Rod, Jim and Michael helped complete the project and send it to Gina by 4pm.

06/26/07 – TTC and Rod are going to finish the mechanical design on this project. Michael Huntwork is going to finish the electrical work on the project and TTC has to get project number from Purchasing for this project.

05/30/07 – TTC selected pumps and is finalizing the dwgs and specs for bidding. TTC asked to add the dampers to the back of the combustion air intake while A&M was doing the control work on this job.

05/14/07 – TTC and NR worked on CAD layout and background drawings. TTC will try to have something to review by this Friday. TTC talked to Tony today about using 2 full size vacuum pumps instead of 3 separate pumps. If this works, Tony did not seem to have a problem with the new design.

05/03/07 – TTC visited the site for field work and equipment locations. Meeting notes were distributed to Owner.

04/13/07 – We had second Design Mtg. 3 vendors were selected. We filled out the BOD and DID for the project.

03/15/07 – Tony said the SOSS is approved but TE has not seen it yet.

800 – VACUUM PUMP UPGRADE Read More »

800 – BOILER REPLACEMENT PROJECT

01/22/09 – After making it most of the winter with little problem, the boilers started performing badly last Friday. ThermalTech was on site with the Duke employees to monitor the situation. TTC asked Stoermer and Duke to provide solutions, TTC believes our two options are a new regulator in the boiler room for 14″ or modified regulators at the boilers to handle the boiler pressure better.

03/09/08 – Duke installed a new regulator and it worked good until last Wednesday when there were three low pressure alarms and flame outs on Boilers 2 & 3. TTC sent an email to Duke and SA explaining the latest problems and asked to bring in another expert to look over the entire system.

02/29/08 – Duke installed the 461-S regulator this week and if this works, they will install a larger vent for the regulator to use. We will monitor the boilers over the next few weeks and see if this is the answer.

02/06/08 – Duke Energy replaced the regulator yesterday with the new CL-38-2 but did not use the pilot line. The regulator seems to work okay and settles down in about 2 seconds of a boiler start. TTC sent an email to everyone outlining the results and asked SA to program the boilers one more time with the new regulator in place. The residual static is now up at 47″ with a running static of 27.6″wc. TTC witnessed a dip in pressure down to 17″wc with the new regulator but it recovered quickly and evened out as the boilers started.

02/01/08 – We had a conference call with Duke Energy today. They are willing to try a new gas regulator and meter at the building. We are going to try a CL-38-2 regulator with the new meter next Tuesday at 9am when Duke comes out to install the new meter set. Darnell will coordinate the visit and TTC will stop by to check on progress around noon. They think this meter with the external sensing line and 1.25″ orifice will do the trick.

01/24/08 – Boiler #3 went out on a flame failure last night at 10:30pm. John Gilbert came in to reset the boiler and it has been working fine since then. TTC had emails with Duke & Stoermer to try to get these final issues resolved.

01/23/08 – On 01/18 SA and Duke met on site to work and reset the boilers. What we discovered was that Duke was not comfortable with having the pressure under 1psig because we were testing the boilers at 24 psig and 20 psig. At these pressure the boilers worked pretty well but there are still concerns with Duke regulator. Because of this TTC talked AKM into paying PHB to come on on Sa 01/19 to install a 1″ weld-o-let and valve so that Duke could move the sensing line downstream about 20ft. On 01/21 TTC met Duke back on site and they piped up the regulator sensing line. The regulator is still surging. The boilers are however running great. TTC check the pressure at the inlet to the boilers and it is bouncing around between 19 psig and 29 psig every second. The burnertip pressure however is stead between 7.8 & 8.0 inches. I believe the biggest change in the boilers is that TTC talked SA into changing the low pressure setpoint down to 13″wc and not 19″wc so the boilers are not going out on low gas pressure as much any more. The Sellers regulators seems to be able to handle the incoming gas variations very well and the boilers are firing very smoothly.

01/15/08 – Darnell Edwards called yesterday to say they were having more trouble with the boilers. I met Duke Energy on site today because they responded immediately to a request to test the gas pressure at 15″ wc. It turns out that the boilers can’t be run at the pressure because the low limit on the boilers are set to 19″wc for some reason. Duke set the regulator down to 24″wc incoming for now and the boilers seem to run fine during the day. I am waiting to see how they operate overnight and tomorrow morning. I have talked to Tom Schmidt and Joachim at Duke about this situation too. We are currently trying to schedule Duke and SA back out at the building at the same time to adjust the incoming gas pressure to 20″ wc which should put us right in the middle of the operating range for this boiler. I am also trying to get some chart recorders to log the gas pressure in the main and at the boiler burnertips for testing purposes. When we watched the pressure after the regulators today they were steady at 7.5″wc on BLR-1 and 7.9″wc on BLR-2. BLR-3 is having some startup issues and according to Tony Martini there is sooting on the fire tip inside the boiler. When the boiler cools down, he will clean it off and then it should be back in server as well. I am trying to coordinate a meeting for Friday morning at the 800 Broadway building between TEI, Duke and Stoermer. I am also trying to get chart recorders for history recordings of gas pressures.

01/07/08 – The County called last week with more boiler problems. TTC investigated and found that on November 9, 2007 that the boiler were setup for 37″ of gas pressure on Jan 3, 2008 during our first cold snap the boilers were not running properly and going out on alarm settings. The owner could not keep a boiler running. TTC visited the building on 01/03, 01/04, 01/05 & 01/07 to check on the boilers and the pressures in the main gas line. According to all the readings that TTC took while onsite there is no gas pressure issue with the natural gas piping or Duke regulator. During all test the natural gas system delivered 30″ of pressure to the boilers all the time. At startup or when both boilers were starting at the same time a dip down to 24″ could be seen for a fraction of a second but nothing that could be thought to effect the way in which the boilers are running. TTC, John Gilbert & Will check the boilers at Boiler #1 and at the main building entrance. There is no appreciable loss in the piping system in gas pressure. The new Duke meter seems to be controlling pressure well. Today the temperature was back up to 60 degrees and TTC tested the natural gas pressure with no boilers running and it was found to be at 30″ with both of the domestic water heaters running. Later after they both shutdown the pressure slowly rose to 37″ just like the Duke representative Mike Hoffer said it would. The regulator used back pressure from the high pressure main to ensure positive shutdown of the valve. This means the residual pressure in the gas main is 37″ when no equipment is running and 30″ when anything is on. This correlates exactly to what to Ron Eaton told us by phone last week. The next step is for Sellers to provide a new regulator on one boiler sized for 30″ of static pressure when the boilers are running. This regulator should be able to handle pressures up to 40″ of gas and down to 28″ nominal and even down to 20″ under heavy load conditions or even better if it can go down to 14″, that is what I will make them provide. In my opinion, this is absolutely a boiler regulator issue and not a Duke Energy gas issue. We can hopefully get a new regulator in this week and have ONE of the boiler retrofitted before the next cold snap but your also stand a great chance of the boilers working well right now since they have been adjusted down from 37″ of pressure to 30″ (I think that is just a misunderstanding on Stoermer’s part about what they have at your building).

11/09/07 – Tom Schmidt called today to say that the boilers could not be adjusted so that all 3 boilers run at once. TTC sent an email to the County and Tom stating that all 3 boilers can’t run at the same time. The design is to have one boiler running at a time, at 0 degrees a second boiler can come out to help out but it doesn’t have too. The third boiler does not come on until -20F which really means never because the 6″ gas main isn’t sized for (3) 125 HP boilers to operate simultaneously. TEI had Tom Schmidt come in to discuss the problems and talked to Ron Eaton after he got to the building today about inlet pressures. On Nov 9 the pressure was 37″ and the boiler were adjusted for that pressure. Today the pressure is 29″ and this changes the inlet pressure to the boiler after the Siemens gas train from 8.5″ to 7″ which causes the boiler to run way to lean. Gary and Todd are helping me figure out how to solve these problems for the County. TEI has a conference call with the boiler mfgr at 2pm to work on this some more.

05/19/07 – Duke Energy replaced the gas regulator to the building with the new model specially designed for our load with a tighter tolerance to the outlet pressure.

05/02/06 – Tony called today about flame failure on the boilers at the end of the last season. TTC recapped what has transpired since the 3-22-06 call. TTC has talked to both Stoermer and Cinergy about this problem and it appears to be rooted in the fluctuations of gas pressure not the absence of gas pressure. The building has at least 1 psig of gas pressure which is twice as much as the boilers require but when boilers are running with the water heaters and various units shutdown, there are flame failures in the system. Apparently, the fluctuation of gas pressure on the high side is causing gas delivery problems to the boilers. TEI may recommend having the water heaters moved ahead of the boilers or changing the control sequence so that 3 boilers are never online at any one time. TEI will contact Stoermer, Cinergy and Automation to make sure this problem is resolved going into next heating season. We might need a meeting between TE, Cinergy, Stoermer and A&M to resolve this issue.

03/22/06 – County called about Boilers 1 & 3 going out on flame failure last Thursday and Boiler 2 going out on Saturday.

10/28/05 – County called about erratic boiler controls for gas usage. SA worked on setting the boilers up again with Cinergy regulators.

06/14/05 – TE received and sent out all final paperwork to complete this project for County and PHB.

06/09/05 – TE and PHB discussed final paperwork requirements on this project. TE received a final invoice in January 2005. The final paperwork was received in January also. Now, TE has all the final paperwork in house but can’t find the final application # 5, so PHB is sending over a new original. TE will submit these final documents to County as soon as they are received, copies and signed.

05/03/05 – A&M straightened out the program and released some unpronounced overrides. The provided a little more training for the operators and building manager. The plant appears to be working properly.

05/02/05 – 800 reported some anomalous behavior from the boiler plant. TTC called A&M for dial in assistance and TTC will stop down at building on Tuesday morning to investigate.

04/27/05 – TTC and Tony Martini witnessed the laptop working remotely today. Dennis set it up for home use and left it for Tony to take home for use. TTC observed the entire system while the Free Cooling system was offline because of a condenser water pump rebuild. I found many things in the “override” position. This certainly happens upon occasion but overrides should be release to allow the automatic controls to handle the building most of the time. TTC pointed out that with the boilers overridden off at the DDC through their enable point that this does not disable the feedwater pumps so we actually had 0 boilers running but 3 feedwater pumps running just using up energy. TTC stated that a better way to control the boiler plant “off” would be to lower its enable setpoint below the current OA temperature. The same goes for the Chiller plant which can also be run at lower temperatures when the FREE cooling is disabled to keep temperatures in the building from overheating the space as they were beginning to do today.

04/26/05 – TTC could not get the laptop working from home. TTC delivered to Dennis Brown. A&M called to report the laptop is working and will be dropped off to 800 on Wed morning with training. TTC will stop by to supervise this training. Does the County want Tony Martini and Glenn Wilhoit to attend this laptop training and can they be there at 8:15 a.m.?

04/22/05 – TTC to work on laptop for DDC access. PHB is complete on job. Ron Eaton with Stoermer Anderson made some boiler adjustments today. Cinergy increased building pressure to 2 psig at the meter and in the building. SA said boilers are working fine and building staff is happy with performance at this time. SA also said that PHB had a regeneration line from the water softener to a floor drain that still has to be piped. Everything else appears to be complete.

04/18/05 – TE contacted A&M about 800 boiler items that need to be worked on such as Laptop control from remote location, outdoor air sensor is not calibrated and 2nd floor ventilation CFM issues. TE dispatched SBO to assist in troubleshooting the airflows on the second floor. Sam recommended a change in airflow deflection and balancing and further suggested relocating one of the airflow devices away from the center. Watch changes made and notify TE if you would like to proceed further. A&M will schedule onsite time with John Noyes to work on OA sensor and laptop programming.

03/24/05 – Tom Schmidt reported that all devices are up and running with the Boiler system. Ron reported that a setting was changed on the softener system and that is now running also. This should make all items complete for the 800 Broadway Project.

03/11/05 – PHB delivered the O&M’s to ThermalTech for this project. TE will review and turn into the County for record keeping.

03/07/05 – TTC contacted all contractors to resolve issues at the 800 Broadway Building. (1) Trap on boiler # 1, (2) Sample Cooler on Boilers, (3) Low Fire control on boiler, (4) Draft controls on boilers.

03/01/05 – Tom Schmidt reported that 2 of the 3 draft controls are upgraded and working. The third one has a bad magnahelic. It will take one week to get a replacement mag from the vendor. SA will return to install the final automatic draft control components at that time. PHB will have a pipe fitter to pipe in the replacement sample cooler within a week according to PHB.

02/25/05 – PHB will have a pipe fitter down to install the sample cooler and remove the outlet drain valve within a week. TTC is trying to find out the status of the draft controls upgrade.

02/15/05 – O’Shea patches the concrete yesterday. SA is supposed to be installing the draft controls today.

02/11/05 – Stoermer dropped off the sample cooler yesterday. TTC will contact Peck about installing it. TTC will have Automation setup training next week and upgrade Tony Martini’s Laptop. TTC contacted SA about a $300 service ticket for the water softener as we believe this is only

02/10/05 – Stoermer reported today that the boiler draft controls will be installed on 2/14 or 2/15 with Ron Eaton. Tom Schmidt will personally be delivering a new sample cooler today to the building and he also stated that this type of failure is normally associated with the cooling water to the cooler not being turned on quick enough and an over-pressurization occurs in the shell vessel. This may have been what happened here? Who knows. To be safe, I would advise opening the drain first, then the cooling valve and the test water valve last? I am sure Tony Martini already does it this way anyways, but just in case, I thought I should report what was given to me.

02/02/05 – 800 reported today that the new softener cannot keep up with the water load into the CR tank. TE is investigating this situation and will advise soon.

02/01/05 – TE request updates from contractors for these issues: Water Sampling Station, Draft Controls, Steam Leak at Flange (up high & extra charge) and Concrete Repair.

01/26/05 – TE faxed request for final documents to the attention of Amy Reeves of Peck Hannaford & Briggs. TE coordinated with PHB on fixing concrete flooring in boiler room. TE to discuss with County painters about re-epoxying the floor to match existing red floor previously installed.

01/19/05 – TE faxed back seal pump replacement quotes to Tony for Chiller Room.

01/18/05 – TE talked to Stoermer Anderson about wiring the drafts controls and we still haven’t received new wiring schematics. Tom Schmidt convinced them that just wiring schematics isn’t what we need, so they are sending new internals to the site for installation with new operator manuals that will be up to date and correct so that in the future the wiring schematic will match what is inside the draft control boxes. This work, however, won’t happen until next week at the soonest.

01/03/05 – TE trying to finalized punchlist and get control system backed up on CD format for County. PHB to begin final punchlist work and SA to retrofit draft controls this week according to Tom Schmidt.

12/13/04 – 800 called today because unit heater was not running in electric room and the space was cold. TE advised that the heater should come on anytime the sensor on the interior wall reached 45 degrees. Also, there is no graphic for this heater or control over this heater from Metasys. TE will stop down to check on situation today and help out.

12/10/04 – TE confirmed that SA should be on site on 12/14 or 12/15 to fix the water softener and the draft controls for the boilers. TTC told the building staff that the OA setpoint for the boilers can be used to adjust the start temperature of the plant at anytime. 800 reset the temperature up to 55 degree F.

12/02/04 – TTC stopped at building today and observed that boiler 2 is not running well. He sent emails to contractors for repairs. TTC noted punchlist items that need to be completed and contacted PHB about schedule to finish.

12/01/04 – Automation made final control changes at the site today to fix runtime accumulation modules, labeling the DX-9100 modules and verify the operator control points for lead and lag boiler start. TE forwarded the email received in response to that visit. A&M will update the sequences and get as-builts drawings to TE for inclusion in the final O&M’s for the County soon.

11/26/04 – TTC stopped at the building on Wed (11-24) and Fri (11-26) to verify and watch operation. The boiler plant is running in complete automatic operation at this time and ran appropriately over the Thanksgiving holiday. On Friday, the building was warm and there were no critical alarms on the boiler plant or any manual resets required at either the boiler of the condensate receiver. Todd Zurweller provided the final piping punchlist that will be converted to as-builts drawings that will be turned over to GBBN for inclusion into the CAFM sets. TE will follow up with Peck and Stoermer on the completion of punchlist items within two weeks and TTC will follow up on some control issues and boiler ops issues that he would like to see defined a little more clearly. SA completed the replacement of the solenoids valves, additional strainers in the feedwater system, HOA switch on Boiler #2, and new overloads on the all 3 boilers to prevent nuisance inrush tripping. SA still has to repair the water softener control plate assembly and replace the internals to the draft controllers for all 3 boilers. TE to expedite the remaining items. Remaining items to complete on this project (to TE’s understanding) are: CR water temperature at 150 degrees F (design calls for 190 degree F (SA shall adjust control valve to preheat the feedwater to meet spec), water softener repair, draft control replacement, sump lid replacement, seal replacement on vacuum pumps, seal replacement on cooling plant pumps, concrete repair in boiler room, A&M has to fix the runtime hours display, A&M has to label the DX’s inside the panels for points, A&M has to provide updated as-builts for controls (TE reviewed preliminary submissions with Roger Corbett on 11-24), Peck must install breeching cover must be installed, Peck has to replace or fix the trap on B-3 as it blows by when in normal operation. Glen Wilhoit found a bypass valve open on the condensate receiver, which when closed, fix the steam blow by problem into the floor drain behind the CR unit and stabilized the water level inside the CR immensely, TZ commented that the trap on the CR unit overflow meets the 12″ dwg requirement but TE prefers this trap to be as deep as possible as this is what provides the non-mechanical seal on the CR tank to keep any steam from escaping (we will check back at end of project to see about allowance monies left to increase depth). Peck shall have insulator finish up all insulation on project (lots of insulation work left to do). TE instructed SA to disable the high water level alarm on the CR tank because of nuisance tripping (this alarm is for notification only and requires no user input to fix anything so we just turned it off – the staff reported that the old tank would have high water conditions too but never had an alarm so we will just match the old operation, the tank itself is sized for 4 boilers condensate return so it is of ample size for this plant per Todd Zurweller. The water TDS from the sample coolers has been reading like this this week: at the CR 600-900 micro siemens (this makes sense, city water is about 300-600 normally), the boiler samples have shown 3.6 milli siemens or 3600 micro siemens which is also right in line with what we would want (i think 2500 – 4000 is okay, anything in the 6000 or higher would tend to lead to carryover) and lastly, TTC adjusted the gate valves on the outlet of the boilers to about one hands width of stem showing in an attempt to calm down the surging of the boiler sight glasses, this seems to let the water level stay more consistent and allows the make-up water to keep up with the boil off rate at all conditions, the closure of these valves may be changed when the boiler plant is under heavy load if needed.

11/23/04 – TTC watched boilers all day last Friday. The water controls are such that the boiler plant is too finicky to leave in total automatic operation without expecting nuisance alarms from either low water at the boilers, high and low water at the condensate receiver or overfilling of the boiler vessels through the solenoid valves. SA reports that all components replacements are scheduled for Tuesday except for the draft controls which will be done ASAP. TZ is sick so the TTC & TZ field trip has be rescheduled until Wed at 2:30 p.m. If Glen Wilhoit has any questions please have him call TTC at the office. TTC discovered that the solenoids are letting water bleed past even with a pump on all the time and not the check valves as the water level stayed the same all afternoon with the feedwater valves blocked. In addition the traps on the boilers only drain the boiler vessel when there is a positive pressure inside the vessel, once in a vacuum they are not draining enough water to keep the boiler from overfilling on this day.

11/22/04 – TTC talked to Glen today and we discussed looking at these issues: slope of main steam header towards traps, conduit cover on Boiler # 03, Vent on receiver tank. TE will investigate these issues on Wednesday at the TZ walk through.

11/18/04 – Boiler #1 is overfilling with water. Last time this was due to dirt in the feedwater line blocking the solenoid valve. When the new valves and strainer are installed by SA, this problem should be eliminated. 800 could try to run Boiler #3 instead of #1 to alleviate this problem.

11/16/04 – The boilers are carrying over on startup and shutting down on low water forcing the electric overloads to cut out. SA has to replace the overloads on each boiler to correct this problem, replace the HOA on boiler #2, upgrade the draft controls and install cycle timers into the boilers. This work should be done in one week. All 3 boilers are available for use. At morning startup, Tony Martini may want to turn 2 boilers on and back down the gate valves to 30% of so to allow the plant to come up to working temperature to smooth out this hiccup. Very soon, the boilers can be left on full time. TE is worried about the surging in the CR unit and boiler. The water levels are bouncing around more than we would expect. TE to investigate more.

11/12/04 – All contractors and TE were on site to finish up the project. TE hired Geiler directly to replace the Condensate #4 pump seals because Peck could not meet the schedule. Upon disassembly we discovered that both seals needed to be replaced along with one motor bearing and one motor winding. TE authorized this work to be completed so that the plant can be ran in full automatic on Friday 11-12, Peck service was on site to replaced six sets of seals on condensate pumps CR-1, CR-2 and CR-3, Peck was only able to replace one seal on CR-2 (this work was being done at T&M, TE recommends that we re-evaluate having Peck do all the pumps as we don’t believe there will be enough money left in the allowance to pay 2 days of T&M for each of the 5 remaining pumps, we bought all the seals already which cost $1200, Peck and Cinergy upgraded the gas supply line to 1psig pressure, tested it, installed new regulators and put the system into service. 800 now has a new regulator for the water heaters and for AH-43 on the roof. After purging the system, all the equipment was back in service and burning properly by the end of the day on Friday. We permanently disconnected the garage AH unit that was abandoned, the County CANNOT use this unit unless another regulator is put in the gas supply line (this shouldn’t be an issue since this unit hasn’t been used in 10 years – the gas line has been capped. Stoermer Anderson (SA) finished wiring the draft controls and adjusted all the burners to spec. The draft controls need some different components in the upcoming week as they only work in the wide open position right now. The water softener needs to still be replaced since the Crown Engineering unit was damaged in shipping. The sparge tube and control valve were installed by Peck and adjusted by SA. The unit heater was installed by Peck, wired by Glenwood, and wired by Automation for controls. The unit heater and the exhaust fan worked per spec. The punchlist was commissioned by TTC and will be sent in a separate email where TTC will document remaining items including training which should be given Mon, Tue or Wed of the upcoming week.

11/10/04 – Glenwood will finish up the electrical work on Thursday. Final inspection scheduled for Monday. Please make the accommodations to allow the inspector into the building. All contractors are scheduled for work on Thursday as well. TTC will call automation when enough of the boiler is complete to allow control system to take over control of the boiler plant. Final commissioning and punchlist will happen in afternoon on Thursday.

11/08/04 – All gas pressure work is scheduled for Thursday 11-11-04. The building will be shutdown for Veteran’s Day. Peck, Stoermer, Automation and Cinergy will all be onsite connecting and verifying all final workings of the boiler plant. Terry Cannon will also be onsite to assist in the last minute details. Water softener and unit heater are on site ready for installation (softener has ctrl panel issue). Stoermer has sparge tube in town and hoping control valve will arrive on Tuesday. Stoermer needs to finish wiring the remaining local controls on the boilers. Today’s onsite work proved that one boiler and both water heaters cannot run at the same time without the boiler going out on low gas pressure. PHB assured us that the boiler room door will be installed on 11-09-04. The vacuum pump seals were ordered for overnight shipment and should arrive on Tuesday to Peck. Geiler will be in at 7:30 a.m. on Tuesday to install the seals on the Condensate Pump-4 in the chiller room (ttc coordinated with Geiler and Martini for this work). Outdoor louver needs to be installed. Final insulation needs to be installed. Final control programming needs to be implemented. Training for Tony Martini needs to be provided by Automation (ensure the whole system is demonstrated, optimized control of cooling towers, free cooling, boiler sequences, etc).

11/03/04 – TE confirmed today that the Seller’s boilers can handle and are built for 10 psig inlet gas pressure, at worse case a spring needs to be changed in the regulator and SA will provide that service at no charge. TE instructed PHB to buy two regulators at this point: (1) for the water heaters sized for 2 x 199,000 btuh, 1 inch, 1 psig to 9″ w.c. and (1) for the AH-43, 1 x 160,000 btuh (5″ w.c. nominal, 14″ w.c. max), 1 psig to 9″ w.c. Emergency pressure at inlet to be protected up to 10 psig. As soon as we get the new regulators in we will schedule the work and the shutdown and as TE understands it at this time, Tony Matre has instructed PHB to do this work after normal hours or on a Saturday.

11/02/04 – Remaining project items: insulation, water softener, sample coolers, door installation, damper controls, large louver for combustion air, unit heater, sparge tube, boiler #1 falsely enabled, new regulators for water heater, coordinate pressure test, adjust fuel air mixture, sump lid, chain link fence, seal barometric damper, seals on vacuum pumps, reinstall exit sign. Be complete by November 12 including controls.

11/01/04 – PHB coordinated with TE today on boiler requirements for new venting. Sizing requirements are 17,258,000 btuh connected load (5,620,000 each boiler, 199,000 each water heater, 1 psig inlet pressure (with an emergency inlet pressure of 10 psig), 15 inch w.c. outlet, if a 2″ regulator can meet our flow demands, we won’t need a separate relief valve for the regulator (provided it uses rubber seats), Dead End Lock Up Model type, Main burner and pilot applications, static pressures will be allowed to rise slightly above setpoint, an additional regulator will need to be installed for the water heaters in the 1″ line. We will discuss more at Tuesday construction meeting.

10/27/04 – PHB reported today that boiler breechings are welded in. One louver is installed, the other will be installed shortly, the blank off plate on the other pipe space will be installed next. The new water softener shipped 10/26. Then unit heater should be shipped very soon. Controls are supposed to be ready to go but TE and PHB will confirm. TE would like to meet on Thursday morning at the site and call Cinergy for the gas pressure issues and begin the resolution process.

10/21/04 – Door will be installed on Monday. Stoermer Anderson will be onsite on Friday. Automation will be on site on Friday. Boiler #1 will be in automatic operation on Friday 10/22/04. PHB will have flues welded in by Wednesday 10/27/04. Boiler # 2 & # 3 should be ready to fire for Cinergy test on 10/28 or 10/29. Please make accommodations for everyone to be onsite Thursday 10/28 for this work. Water softener should ship today or tomorrow for installation.

10/18/04 – Stoermer Anderson reported that gas pressure was very low for the boilers at the site. Boilers require 10 inches. Today’s readings showed 7 inches available. TE is investigating how to solve this problem.

10/18/04 – PHB submitted a price of $4106 to reroute the PVC vents from the domestic water heaters. Do you want to do this work or should we keep things as is and let the trades do the work in the future if it becomes absolutely necessary?

10/15/04 – One boiler successfully started today right on schedule. On Monday SA will verify gas pressure in building as it appeared to be low today. SA is on site preparing boiler for startup. Draft control damper is installed. The door to the boiler room will arrive on Wednesday of next week and will be installed on Wed-Thur-Fri. The insulator will be installing 2″ fiberglass on the steam header to match the 2″ piping shoes, the entire breeching will be replaced with new insulation, A&M is on site downloading the new boiler control program this morning, the CR-1 unit comes factory equipped with a low water cutout switch that turns the pumps off on low CR-1 conditions. TE has the DDC system programmed such that it will stay enabled if a feedwater pump goes into alarm so that when the CR-1 unit comes out of alarm the pumps plant will be standing ready to re-engage. Alarms will be issued on the front end documenting the history. The exhaust fan is being installed today. For future maintenance on the new exhaust the facility group will be able to remove the louver and the fan but they will need a lift to access the fan just like the old one. The fan is not removable from the alley (TE doesn’t want vandals being able to mess with the fan)

10/14/04 – Boiler inspector approved ALL boilers for use today. PHB, TE A&M and SA were all on-site for an impromptu construction meeting when we really were meeting to discuss the installation of the sparge tube in the DA tank. Final decision was to move the vent over to the middle 3″ connection and put a vertical then horizontal sparge tube utilizing a double bushing into the open 3″ connection. SA will do much of the work for this and the temperature sensor for the steam control valve and PHB will provide the final connections to these steam heating points. PHB is finalizing piping and B-1 will be started up on friday towards the very end of the day. B-1 will be put into test service on Monday October 18 where 800 can keep an eye on it during its maiden day of work.

10/12/04 – Mike Martini the boiler inspector will be onsite on Thursday at 10:00a.m. ThermalTech, Peck and Stoermer Anderson would also like to be on site that morning about 8:30 a.m. PHB is trying to get all equipment on site and the boilers ready to fire by the 15th as promised.

10/08/04 – Obtained field data on Chilled Water Pumps, in order to get price quote for replacing seals.

09/03/04 – Date Answered: 09/03/04. Question: The Drip Pan Elbows for the boiler relief vents are shown as 3 inch RV’s. The DPL are being supplied as 3.5″ how should we handle? Response: TE instructed PHB that however the DPL’s are delivered to provide a reducer/increaser to 3″ and run the RV’s as 3″ as they are shown on the P&ID. We believe that the 3.5″ might be the OD listing for the 3″ pipe anyways and may be a non-issue.

09/30/04 – Control equipment is on site except for unit heater control valve. Programming will begin at A&M offices on Oct 3. TE has asked contractors to have one boiler online Oct 8 if possible.

09/29/04 – TTC stopped down and told PHB that they can reuse the existing cond header up to the union, TE prefers that the new boiler stack connections be round to round with a saddle at the breeching connection (remove the long skinny rectangular existing connections, TE wants PHB to provide an allowance price to reroute the domestic water heater PVC exhaust vents to the same window outlet as the gas vents are using (TE will provide a sketch to PHB to price), Boiler #2 should be located to miss the existing pit lid, the EOM traps are correctly sized at 3/4″ so bushings from 2″ to 3/4″ are acceptable, one of the intake louvers appears to be 59″ x 59″ the other window will have the EF in it and the vent lines: PHB can build a painted steel or aluminum blank off plate to surround the vents in the remainder of the window – it has to be water tight to prevent rainwater from entering the space (TE to review CA req’s on remaining louver), TE and PHB reviewed CR-1 inlets and agreed where everything goes, Boiler #4 breeching should just be capped as-is, TE told Tony Martini that existing plant is supplied with combustion air without aid of mechanical combustion air: if 4th boiler is ever added, the County can add a forced combustion air fan, increase existing louver size, or provide another opening in the outside air wall (the existing plant CA req’s are sized on 3 boilers connected load per code req’s)

09/24/04 – Glenwood submitted additional cost based on TE request for strobe relocation and alarm conduit relocation of $214.00 and $427.00. Approved by AKM via phone call.

09/23/04 – Boiler are in the rigger’s yard. Peck will deliver them to 800 on October 2. County, please make appropriations to allow PHB in the building for this work.

09/13/04 – Weekend work was exceptional and the large steel tanks was also removed from the premises.

09/08/04 – PHB Advised that first boiler will be delivered and existing boilers will be demolished on 09/11/04 at 7:00 a.m.

09/03/04 – Control submittals have been received.

09/01/04 – TE approved allowances 01, 02 for PHB shown below.

09/01/04 – TE sent a letter to city explaining boiler plant sizing. We sent email with attachment showing fax.

08/31/04 – PHB has submitted door and louver equipment for approval on 08/24/04 – Returned approved. EF needs to be 203V/3Ph version when ordered.

08/27/04 – TE is trying to get final pricing and ok on water softener package for project from PHB and SA.

08/25/04 – Boiler removal and installation scheduled for September 11, 2004.

08/25/04 – CIS will be removing asbestos in the interim.

08/25/04 – Quick ship boiler scheduled to ship on August 31.

08/25/04 – Condensate Water Return system also scheduled to ship on August 31.

08/25/04 – New door has been cut in with plywood secure doors installed.

08/25/04 – Some prefabricated piping has been deposited on site.

08/25/04 | Date Answered: 08/27/04 Question: A conduit shown to be demolished contains boiler and chiller alarm wiring. Should this be kept and maintained?
Response: TE will confirm with John Noyes next week. The alarms provide remote alarming up to the night desk security shack where the on duty security officer is instructed to call John Noyes. The new control system has been installed with alarm paging service which provides the same functionality so this may not be required at all.

08/12/04 | Date Answered: 08/13/04 – Question: For the spool drawings, what is the most important factor for boiler dimensions.Response: TE stated that the boilers are to aligned under the breeching and centered between the columns but the contractor has some leeway with final and exact boiler placements

800 – BOILER REPLACEMENT PROJECT Read More »

800 BROADWAY Vacuum Pump Replacement

05/22/09 – We have turned over all the closeout paperwork from Process on this job to Tony. Joe signed the change order at Tony’s office. We created the as-builts and gave them to Bert in CD format with the original marked up drawing. TTC delivered to Bert’s mailbox on 05/18/09.

02/02/09 – TTC inquired about approving this change order again with Darnell & Tony.

01/05/09 – Process is not budging on the a negotiated settlement for their change order request. TTC talked to Joe Doxsey and Tony Matre and could not arbitrate a settlement. TTC asked Joe to call Tony directly to try to convince him of the extra monies. Tony stated the extra valve cost were fine. The sticking point is the extra labor and material mark-up from last year to this year. TTC mailed in payapps 4 & 5 for this proejct which leaves $1000 for closeout plus the change orders to resolve.

12/18/08 – TTC and Process have sent change order payment request to Tony. TTC requested final payment except retainage from Process.

11/25/08 – ThermalTech sent permit drawings to Ginter. Punchlist to Process Const and Change Order from Process to the County.

11/03/08 – Punchlist is completed. Pumps seem to be working fine when all four condensate pumps are left on to handle the building load. TTC has inquired about operation several times with bldg personnel but no response after visit.

10/16/08 – Vacuum pump testing is scheduled for 10/28. Rod will attend for TEI and do a final punchlist.

08/22/08 – TTC talked to Process about project completion which is about 98% complete. TEI asked that O&M’s include warranty letter, equipment submittals and contact information. Commissioning of system needs to happen after the unit is started up in October. Controls should be complete and main pumps should be working. TEI will want to see automatic backup of the pumps and vacuum pumps operate. Each lead pump should work first then each lag pump should take over if there is a failure on the main pumps. Electrical and Controls still have a little work to finish before TE punchlist. Process is submitting a new pay application for most of remaining budget.

08/05/08 – TTC visited the site today to do a pre punchlist check over. The project looks excellent. Piping is nearly complete. Insulation next and then electric and controls. The project should be a couple of weeks from completion. We are investigating the need for additional disconnects.

07/30/08 – Equipment is installed. Insulation and electrical will be installed over next two weeks. Contractor expects to be complete within one month. Process has experienced material cost increases and pay period increases and will be submitting a change order for our review. There is a question about physical disconnects for condensate pumps. EC says we need them. Mechanical schedule says they are provided with the equipment.

07/09/08 – New pipe routing and equipment locations finalized. Housekeeping pad size selected by owner and coordinated with contractor.

Equipment Ordered

Layout changed based on actual footprint of Skidmore equip.

800 BROADWAY Vacuum Pump Replacement Read More »

800 – Polygonal Pavilion Roof Repair

03-30/12 – THP Reviewed findings with Bert Watts and work complete. THP recommends completing repairs with coating. THP to issue a summary letter.

03/30/12 – THP Reviewed findings with Bert Watts and work complete. THP recommends completing repairs with coating. THP to issue a summary letter.
03/28/12 – THP Reviewed patches during gutter repair project and some patches are cracked. THP to review condition with Bert Wattts.

SSRG completed test patches on west and south elevation. Patches to be reviewed late spring by THP.

800 – Polygonal Pavilion Roof Repair Read More »

630 Main – Community Development Renovation

03/15/05 – Indrolect reported the lamp was replaced with a Philips bulb. We will watch the fixture and see how long it last. If this bulb burns out, then Indrolect will verify ballast and wiring between the two fixtures to see why one is working and one is not.

03/14/05 – PHB delivered the FINAL O&M’s to Thermaltech today. TTC will review, approve and then hand deliver these to the County and in particular Joe Merkt within a

week (i have seen all this paperwork before but now i have it in book format). There are 3 manuals black in color and named Operation & Maintenance 630 Main Building. TTC also talked to John Nagel on status of outside spotlight and they are still working on it. Give them one more day so they can trouble test the wiring as I have asked them to do.

02/18/05 – Greg asked if one of the spotlights can be replaced at 630 as the lighting was not working. Indrolect had Bobby Potter visit the site and replace the bad lamp.

11/18/04 – Peck will be on site this Saturday to remove the internal insulation in AHU-1. This has been coordinated with Joe Merkt and represents that last item to take care of from the punchlist on this project.

11/17/04 – Indrolect and Square D ordered a complete new speed drive for RF-2 to replace the one that burnt up this week. We are hoping this is replaced within a week’s time. No cost to the project and contractors are to coordinate with Joe Merkt on the fix.

10/25/04 – Indrolect & Carrigan & Grimm Substantial Completions are signed and approved.

10/15/04 – TE has requested the PHB provide a price to remove or reword the existing ductwork on AHU-1 that has internal insulation that won’t be acceptable for winter humidification. The insulator was onsite on 10/14/04 with Joe Merkt. The price is forthcoming. All other punchlist items on this project are complete.

10/15/04 – TE has approved Indrolects O&M manuals and is sending one to Greg Smorey for record keeping and one directly to Joe Merkt for record keeping on this project.

10/15/04 – ThermalTech sent all substantial completion documents to the contractors for signing. All were dated for August 8 except for Peck which was dated for October 1, 2004. Four originals were sent to each contractor with instructions for them to sign and send all four to Greg Smorey. Greg was instructed to sign them and return one to the contractor and a copy of one back to ThermalTech.

10/13/04 – Five originals “AIA Certificate of Substantial Completion” documents mailed to each Contractor (Indrolect picked-up).

Temporary occupancy permit has been issued.

Door hardware issue remains to be solved.

Final punchlist and commissioning on controls must be completed.

Final balancing must be completed.

Final humidifier installation must be completed.

Joe Merkt to attend training course in October to meet training requirements of specifications.

630 Main – Community Development Renovation Read More »

250 WHT – Plumbing Division Upgrade

06/14/05 – Phasor turned in a new change order for Fire Alarm additional work at 250. The Change Order cost including all the additional inspections is $967.82. TE will approve and send to Diana for signing. Please return a signed copy to both ThermalTech and Phasor when complete.

06/08/05 – TTC sent final Reupert paperwork to Diana for complete project closeout. Noise issued on floor is being address by Mark Hardin.

05/11/05 – Sound issues arose from the toilet room and accompanying space being too quiet. GBBN made a field visit to investigate and the consultants gave recommendations about white noise or another exhaust fan. The County is to advise on how to proceed from here.

05/10/05 – TE emailed GBBN to advise that toilet exhaust on this project is connected to the main building toilet exhaust. If there is a problem have Tom check the main fan and if that doesn’t work, TE will measure the airflow and check the existing conditions contingent on a future request by the County.

05/02/05 – The building passed it fire alarm inspection this morning at 6:00 a.m. TTC, Jack Lamping, Darnell, Jim McFarland and Darryl Meadows were present and witnessed the test and the paperwork was signed. The City Inspector had issues with the existing system but did not hold up or not pass the test but these are issues, he wishes the County would fix because the system is technically not installed properly. Item (1) any smoke or pull device on the first floor reports as “Smoke & Pull Stations”. The inspector strongly urges that these two actuation devices be separated and report separately when in alarm. Item (2) when in alarm and the “Alarm Silence” button is pushed it disengage all the horns AND strobes on the first floor – this is against code as ONLY the horns should be disabled and the strobes should continue to flash until the system is RESET (it was shown many times during our testing periods that they are not wired properly). Item (3) They questioned the “fail-secure” status of the doors upstairs and downstairs. When the FA system is in alarm all the door holds release as they should and all the security access is disabled so that a key is required to enter the space. I confirmed with TA and MS that this is the correct operation for your building. The people inside can always egress out as there are strike bars or non locking door handles from the inside to the outside so none of that is required to change. Item (4) The first floor system is a “System Sentry” type system which was in place when Simplex received the second contract to renovate the second floor space. They did this by daisy chaining all the existing 4-wire devices through a ZAM (Zone Actuation Module) which is why they all report as the same device back at the Simplex panel. TE would recommend putting in a project right now that upgrades that existing system to 100% Simplex (which is a fully addressable system 4010 model). We estimate about a $23,700 project (30 devices @ $9000, 3000LF @ $9000, 6 ZAM’s @ $3000, Programming @ $1500, Permit and Testing @ $1200). Please advise.

04/28/05 -TE spent most of the day at the building trying to get the Simplex system working in conjunction with the System Sensor system. We tried many custom programs but in the end nothing worked perfectly. TTC has 3 ways to try to get system fixed this morning and will meet Simplex back on site to repair the system. (1) write a custom program that actually works, (2) replace the 4 smoke detectors with authentic Simplex devices, (3) add a UL listed manual reset to reset the 1st and Bsmt floors. TTC will keep DES up to date as we go through the day.

04/27/05 – The project failed the initial Fire Alarm test this morning. Not from device malfunction but the actual FA panel would not reset after receiving an alarm from a smoke head. The system was pre-tested using pull stations and reset fine on Tuesday. Because of this the City did not issue an approval. Phasor, TE and the County contacted Simplex for an emergency call into a technicians to repair or reprogram the main FA panel. Jack talked to Simplex and will be back on site as soon as they arrive today to work on the system to assist in figuring out what is going on and wrong. He believes that he was able to get the technician to understand what was happening and hopes to resolve the issue today. The inspectors agreed to come back this week to approve.

04/26/05 – Phasor bought two strobes locally and will install them today and have everything ready for tomorrow morning. Jack said it was a scramble but he found them and is ready to install. They will be ready for tomorrow’s test. At 2:48 p.m. they reported that everything is set for final FA inspection on Wed at 6:00 a.m.

04/19/05 – Final fire alarm test is scheduled for 04/27/05 at 6:00 a.m. Tom will be on hand from the County for FA issues. TE will attend as Owner’s Rep. Phasor will be EC. Copp stated that all egress issues are resolved and will be working fine for our final test.

04/15/05 – TE contacted Phasor about final completion and inspection by email to make sure everyone is ready for next week.

04/06/05 – TE and Phasor and County are coordinating final inspection details for April 25th. TE waiting on contract interior information from County before confirming

04/05/05 – Project Meeting today. Set new schedule for completion. JB Schmidt scheduled to be complete by April 15. Phasor to be work on 4/15 and 4/18-4/20. Final Inspections to be tentatively scheduled for 04/25/05. TE to contact Phasor for FA inspection coordination with JB. TE to contact Copp about schedule for plumbing space and general building space and to work on resolving software issues. County ES/Facilities to contact Sheriff’s Dept about Panic button for receptionist in ES.

03/25/05 – Reupert delivered some of the final paperwork with no payapp today. TE will contact them about this.

03/15/05 – Portions of the project have been on hold awaiting the replacement of drywall and water sealant. TE received final paperwork and O&M manuals including balance reports from Reupert. The manuals are not bound or copied. TE will copy and make sets for County use and turn them in at the end of the project with final paperwork and payapp from HVAC contractor.

01/31/05 – TE attended last Thursday’s Const Mtg. HVAC is complete. EC is nearly complete. PC is complete with working fixtures. Hot water reached the LAV in under 60 seconds. All fixtures appeared to drain properly. Security is nearly complete but Copp has some final work to do.

01/26/05 – TE faxed one copy and mailed three copies of the Affidavit of Release of Liens to Reupert.

01/24/05 – Jamie of Reupert called TE and indicated that she was preparing final document packet but did not know where to find the Affidavit of Release of Liens forms. TE to mail the Affidavit of Release of Liens to Reupert.

01/18/05 – TTC sent Reupert their punchlist item (balance report) and asked for their O&M’s.

12/27/04 – TTC stopped by the building to coordinate lighting layout with Jack Lamping. Some of the HVAC piping is too close to the ceiling grid and the deep parabolics don’t fit into the grid and below the ductwork and 3-way heating piping and valves. We remedied this situation by moving some lights over a grid space or 2. TTC has a copy of the new locations for as-built purposes. TTC believes the new layout will provide sufficient lighting levels and be a workable layout for the building occupants. The only outstanding issue with the lighting at this point is that the light nearest the column near the restroom can either be swapped out with a shallower fixture like the ones slated for the storage room and the lens be replaced with a paracube or (2) 2×2 fixtures can be used instead of (1) 2×4 fixture. The former would cost the project little or no money, the ladder may cost $200 – $300 out of the remaining allowance. We should have an a final answer later today.

12/20/04 – Ken Reupert out of the office, Jamie will have both of the Affidavit of Original or Subcontractors sent to ThermalTech today or tomorrow (12/21/04).

12/09/04 – Reupert revised Pay Applications 1 & 2 received in the mail. Voice message left for Ken Reupert to disregard earlier message and that the Pay Application will be held for the “Affidavit of Original or Subcontractor” form to be submitted.

12/09/04 – Reupert Pay Applications 1 & 2 Voided due to $600.00 allowance shown on application as a Change Order. Voice message left for Ken Reupert explaining that the Applications were incorrect and will need to be revised.

12/03/04 – TTC talked to Reupert today. All the above ceiling ductwork is complete at this point. The 3-way valves are all piped in. The controls on on schedule at this point. The GC will contact the MC when the diffusers and final connections are ready. The MC has to attach some angles around the fire dampers to meet code and should take of that work next week.

11/22/04 – Reupert called today to discuss the 3-way valves ordered on this project via the submittal change. TE instructed them to pipe the valves in as 3-way valves and use up to $1250 of the allowance for this work and to make the necessary scheduling changes to make this happen. Per our submittals to the MC and CC we changed the 2-way valves to 3-way because this building has constant speed pumps and to prevent dead heading the heating hot water system will require 3-way valves in most installs.

11/18/04 – Reupert called to ask for a size change in the return grill. TE approved a 24 x 12 return opening above the ceiling for this project. TE to verify on site at today’s meeting all their request

10/27/04 – Reupert submitted a $600 allowance request to rework the piping at the bulkhead pursuant to our last construction meeting. TE approved the request from the $2500 mechanical allowance for this project, new balance $1900.

Change order request in approved for security change order and is the amount is not being subtracted from the allowance. TEI issued a revised sketch that corrected the access controlled door locations.

10/21/04 – TE contacted Reupert about missing today’s construction mtg, making the next meeting for sure, submitting their schedule of values, change order pricing for relocating piping and VAV box submittals. Everything is in the works. Reupert is going to send us the schedule, the VAV boxes are already in their shop (we now have to approve them (don’t worry they will be fine)), they will begin working on the change order request.

10/13/04 – AIA Change Order for $1,854.46 mailed to Phasor

10/11/04 – The Plumbing Permit Number is: # 2004P07058.

10/08/04 – TEI to prepare electrical bulletin #1 for 1854.36

10/07/04 – GBBN provided the permit number for the project: The permit number is as follows: #2004P05650

10/05/04 – TEI received devices submittal via email from Phasor.

10/05/04 – DES confirmed that TE sent Lisa the stamped drawings for permit. TE sent them on Thursday 10/07/04.

09/29/04 – Jeanette provided a dimensioned drawing for HamCo plumbing to use for this project – TE reviewed and approved for use, TE to pickup plumbing fixtures from Bo for approval, TE to provide stamped drawings for permit use to Lisa, TE to coordinate revised security (Copp to upgrade entire building including 2 new doors) and TE to write change order for this work to Phasor, Reupert was not at meeting and TTC to confirm that Reupert will be at next meeting, TE requested that GBBN reschedule Oct 20 mtg as it conflicts with CH Archive mtg.

09/20/04 – Ben has asked TTC to coordinate water closet locations with Bo Blank.

09/14/04 – Copp is providing a price to upgrade the whole 250 building, this has to be coordinated through TE and Phasor since our electrical contractor has security money in their bid to do this work.

09/08/04 – Bo advised to remove sanitary so that Reupert can begin construction.

09/08/04 – Pre Construction Mtg completed.

09/03/04 – DES advised that contracts are approved. GBBN will setup pre-construction meeting.

09/28/04 – Lighting submittal approved 9/22/04

10/01/04 – Request for change order pricing from Reupert for Fire Damper

10/02/04 – Reupert gave a verbal price of $375 for the addition of a fire damper

250 WHT – Plumbing Division Upgrade Read More »

250 WHT – Electric Device Study

10/18/06 – Final close-out meeting was held on location. Queen City has completed all contracted work. I have the drawings and will have the information put into electronic format over the next few weeks. I also took the panel index binders. I will have all documents delivered at the same time.

09/19/06 – Construction meeting was held on location. All field work was to be completed by this afternoon. Dick Kuhn of Queen City will be in contact with me when he if finished with his circuit verification. When I have been contacted I will contact all necessary persons to set up the close-out meeting.

08/28/06 – Kick-off meeting held on location.

07/18/06 – Contracts have been submitted.

06/19/06 – Pre-bid meeting was held on location.

250 WHT – Electric Device Study Read More »

250 – SECURITY CAMERA UPGRADE

07/31/08 – Bert reported that the project is finished and final paperwork has been received. Final payment is approved to the contractor.

Broken camera has been fixed. Contractor is awaiting final payment.

07/30/08 – Project is complete. County has all final paperwork.

05/16/08 – Bert sent back changer order and payapp #3 signed by County.

05/02/08 – Stapleton has submitted all final paperwork and sent back a signed change order on this project. TEI has reviewed and approved all closeout documents on this project. They are being UPS to Bert Watts for closeout on this project. The change order has to be signed by the owner and copies sent back to TEI and Stapleton for our records.

03/06/08 – Stapleton and Copp have reached substantial completion. The translator has been installed. Remaining items on the job include: our punchlist (early next week), training for the county, programming at the sheriff’s office, Copp is going to replace one camera that is acting up.

02/08/08 – Stapleton sent the change order cost to TEI for the translator and TEI passed it along to Bert Watts for approval on this project. TEI updated the website with current CO and Allowance costs.

01/23/08 – TTC requested a const meeting for this project this Thursday or Friday.

01/22/08 – MAH met with Dick (Stapleton) and Paul (Copp) about the mounting of the exterior cameras. Copp will supply (3) corner mount brackets for $267 allowance. Stapleton will install camera mounts when they arrive (should arrive 1/23). Also discussed was the data port being included on same plate as existing phone jack in lobby, lobby camera location (NE corner and viewing doors), and location of exterior camera at rear entrance door (will be mounted on adjacent wall approximately 24″ above window to avoid washout from wallpack light fixture).

12/14/07 – Stapleton discovered that the holes in the pole bases are only 2-1/2″ and will not accommodate (3) 1″ conduits as the design calls for. Stapleton requests a $500 change order to install junction boxes in the pole bases to solve this problem. TEI agrees with this solution and the change order amount.

12/12/07 – MAH clarified for Stapleton that the control signal for the PTZ cameras was sent over the coax video cable so no additional control wiring is necessary. Also, siamese RG-59 wire with 18AWG power is acceptable for all interior and building mounted cameras. A separate coax and #12AWG power pair is required for the pole mounted cameras that is wet/direct sunlight rated. Copp Systems submittals are approved and should be sent back 12/13/07.

12/04/07 – Const Mtg #2 was held today and TEI distributed meeting minutes. Stapleton will be staring site work this Friday. Ken Edgell will advise the tenants of the 250 WHT building. Stapleton will be boring the light pole bases and conduit routes this weekend. TEI, Ken and Stapleton pick light pole locations in the field for this work.

11/29/07 – The pre construction meeting was held last week. GM typed up the meeting notes. Stapleton called with questions about submittals, dwgs and const mtg time. TEI setup another const mtg for next week with the owner and facilities. We will discuss the RFI’s about the lamp bases and base diameter. Bert sent out the list of approved employees for this project today which included Barnett, Ronald J., Eckart, Carl, Hammitt, Wayne, Leopald, Mike, Leopold, Douglas A., Stevens, Brian K. Terry Cannon emailed Stapleton to ask about Copp system background checks. Mike Huntwork approved all submittals with No Exceptions noted.

10/03/07 – TTC sent the contract for Stapleton to Bert today via City Dash with an allowance of $2500 added to the project. If acceptable, the County can begin the contract process. Stapleton won the bid with a bid of $90,586.00 + $2500 in allowance money. Our electrical plan review was approved on 09/11/2207 with an application # of CIC0703025. The contractor will now have to pay and pick this permit up when the job begins.

09/10/07 – TEI is submitting plans to IBI for plan review and permit # for this job. TEI will provide permit numbers to County for record keeping purposes when we are complete with this process. It will be the contractors responsibility to pick up and pay for the balance of the permit when one is assigned for this project.

08/27/07 – This project has been sent out for bid with hard copies to Mark Donnelly.

08/24/07 – TEI has been instructed to move forward with this project. This project is set to open for bid on 09/26/07. The pre-bid meeting has been set up for 09/11/07.

08/10/07 – A project review meeting was held at the 250 WHT building on Tuesday, August 7, 2007. Items discussed included camera locations and specifications, new light pole locations, access into building, and budget. TEI is awaiting word from the Hamilton County Facilities Department on when this project will go out to bid.

07/30/07 – The drawings and specs are completed. The package is to be sent out today. There will not be front end or ITB# for this project because construction has been postponed until next fiscal year. When TE is given the go ahead from the Hamilton County Facilities Department on this project they will put together the front end of the project manual and issue for bid at that time.

07/09/07 – TE is finalizing the design. Drawings will be turned over to Hamilton County Facilities Department when complete.

06/29/07 – At the monthly Partnering Meeting with Hamilton County it was decided that the money to perform this work would be budgeted for a 2008 project. TE was directed to complete the design and turn over the drawings to the Hamilton County Facilities Department.

06/22/07 – A new cost estimate was presented to Mark Donnelly. TE is awaiting response on whether or not to proceed with the new latest layout and additional cost.

06/15/07 – Project moving along as expected. Changes per meeting with Mark Donnelly are being incorporated and a new cost estimated is being generated.

06/08/07 – New parking lot lighting and camera layouts were presented to Mark Donnelly along with a cost estimate. TE is moving forward with this project. There are a few slight adjustments; number of new poles, location of new poles, and number of cameras. These modifications will be made and presented again to Mark Donnelly.

06/01/07 – TE will present Mark Donnelly with new parking lot lighting and camera layouts early next week. A cost estimate will be included with the new layouts.

05/22/07 – Project review meeting was held today. Various points were discussed as described in the meeting notes. TE is laying out different schemes of possible lighting and camera layouts with the points discussed in the meeting kept in mind.

05/21/07 – Meeting to review current status is schedule for May 22, 2007 with Mark Donnelly.

04/27/07 – Estimates are complete and will be forwarded to Hamilton County Facilities Department today, April 27, 2007.

04/20/07 – Estimates are near completion and should be turned over the Hamilton County Facilities Department by the end of next week, April 27 2007.

04/13/07 – TE is working on the estimates to be turned over to Hamilton County Facilities Department.

04/06/07 – Review meeting was held today, April 6, 2007. TE is to provide pricing on 2 systems and then await owner’s selection.

03/30/07 – Preliminary layouts have been presented to Hamilton County Facilities Department for review. Review meeting will be scheduled for the first week of April 2007.

03/20/07 – TE met with camera vendor. Parking lot lighting and camera layout is currently underway.

03/20/07 – Design is continuing. Parking lot lighting is under design.

03/14/07 – NR created project journal and filled in back data from previous meetings.02/14/07 – Proposed parking lot lighting and camera locations has been completed by TE. This information is awaiting review by Hamilton County Facilities Department.

02/28/07 – Foot candle readings were taken by Phil Lambing in the evening of this date.

02/27/07 – Kick-off meeting held on location by Phil Lambing of ThermalTech. Attendees include Mark Hardin and Bill Scholl of Hamilton County Facilities Department. IT was decided that TE will collect foot candle readings in the parking lot to get a good idea of what will be needed to ensure personnel safety

250 – SECURITY CAMERA UPGRADE Read More »

250 WHT – Monitoring Room Upgrade

03/30/11 – This project is complete. TEI finalized the HVAC permit and paid for it at the City of Cincinnati so EDI can close out this project.

03/02/11 – TTC checked on braided hose install by EDI on humidifier. Brady said they are working on this. TTC review wall mounted installation and there is no good way to clean this install up with a simple product. TTC asked EDI to closeout project and send in final payapp.

12/30/11 – TEI released the punchlist on the project today.

12/15/10 – EDI on board and working on project towards punchlist completion

250 WHT – Monitoring Room Upgrade Read More »

250 WHT – Phone Switch Room

06/07/11 – Kick-off Meeting at 250 WHT Building. The existing phone switch room at 237 WHT was also visited.

06/15/11 – SOSS delivered to Bert Watts.

06/23/11 – Signed SOSS received with associated Purchase Order.

06/28/11 – Design has begun. There are concerns about the fire suppression on this project already. Wet sprinkler exist in the storage rooms and IT wants to remove them. TEI says that the city would have to approval such a removal. There are discussions about Alternate cost for a clean agent fire suppression system for this space but TEI is also recommending an alternate to that to provide a pre-action system if we have to keep the wet sprinklers.

07/06/11 – Kick-off Meeting with Mike Barth and Mike Folck of ThermalTech. ThermalTech and GBBN held coordination meeting.

07/11/11 – TTC has suggested asking the city if we can remove the spinklers that existing in the storage rooms now that are limited area sprinklers.

07/21/11 – ThermalTech, HamCo facilities, building personnel, and HamCo IT staff met to review progress drawings. HamCo IT group modified plans to change the location of phone racks, phone switches, voice mail server, and associated equipment. The location of the condensing unit was determined and the routing of the line set was planned thru the existing elevator shaft. Several alternates were discussed including a clean agent fire suppression system and removal of the existing freight elevator.

07/29/11 – GBBN found a transfer grille that ThermalTech will have to address in the clean agent alternate before bidding.

08/05/11 – HamCo facilities and HamCo IT review comments incorporated into design. Drawings and specs issued for bidding including clean agent fire suppression and elevator removal alternates.

08/08 /11 -Bid documents released to Purchasing and ARC Reproductions.

08/18 /11 -Pre-bid meeting held at 250 WHT. Deadline for questions: 08/22/11, deadline for answers: 08/25/11, bid opening date 09/01/11.

08/24/11 – Addenda #1 released by GBBN to Purchasing and ARC Reproductions. Issued to bidders for clarification.

09/01/11 – Bid Opening held. Contractors are selected.

09/02/11 – GBBN authors contract for General Trades Contractor (JB Schmitt Co., Inc.)

09/05/11 – TEI suggests revisions to contracts. Bert Watts approves those revisions to be made. GBBN sends modified contract and signature sheet to Bert Watts.03/27/12 – ThermalTech added new panel PP-1 to the Arc Flash model. An Arc Flash label was added to the panel in the field, and a copy of the updated excel file was emailed to Rodney Lofland and Bert Watts.

10/19/11 – Received Contracts and Purchase Orders from Leo J. Brielmaier Co., J.B.Schmitt Co. and Atkins and Stang Inc.

12/05/11 – Pre-construction meeting held with TEI, GBBN, HamCo, and contractors to review status and coordination. GC and EC expected to mobilize tomorrow (12/6), MC to mobilize when completed with background checks.

12/13/11 – Concrete pad size and location within telephone switch room approved by TEI and GBBN. J.B. Schmitt to proceed with installation.

02/22/12 – Project is substantially complete, waiting on close out documentation. There is a need to have a conduit extended from the existing telephone room in the 237 building to the TB clinic. TE to hold on any work associated with this until further notice from Bert Watts. Upon receipt of all closeout documentation from all vendors, TE will forward to County.

02/23/12 – Bert reported that telecom will be changing the way the fiber is running but County telcomm will coordination this work directly with Neyer and Cinbell

02/28/12 – ThermalTech is in receipt of the closeout documents that you were submitted for this project, along with a receipt for final payment. Per the requirements of the project manual, there are items that must be submitted prior to processing the final payments. Upon receipt of the following items, we can process the closeout documents: Punchlist (completed and signed), Notarized statements of warrantee, AIA Document G706 Contractors Affidavit of payment of debts and claims, AIA Document G706A Contractor’s affidavit of release of leans, separate affidavits and waiver of liens for each subcontractor and material supplier, AIA Document G707-consent of surety to final payment, affidavit of Contractor prevailing wages for all contractors or subcontractors supplying labor to the project.

4/4/12- GBBN As-buiilt drawings were sent to Bert Watts.

05/29/12 – As-builts were sent to Bert Watts.

06/26/12 – Mike Barth of ThermalTech contacted Fred Stang of Adkins and Stang to request all final closeout documentation. Fred indicated that Linda McCormick of A&S on vacation this week, but will follow up ASAP.

07/25/12 – Mike Barth spoke to Linda McCormick of A&S. She indicated that she has the entire close out package ready to submit except the as-built. Linda told me that she would get that to submit as soon as possible, and that they realize that the final pay app is still pending.

8/29/12 – Fred Stang of Adkins and Stang emailed on 8/14/12 indicating that closeout documents would be sent by the end of the week of 8/13/12. To date, still pending.

250 WHT – Phone Switch Room Read More »

250 WHT – Boiler Replacement Project

08/13/10 – We are waiting on an approved SOSS to proceed.

09/24/10 – Project was bid out as scheduled. Bid opening scheduled for Oct 14.

10/18/10 – ThermalTech has recommended Feldkamp and Glenwood. Contracts are waiting on Pre Award responses from Feldkamp. There are questions about the controls contractor.

01/24/11 – Contracts are signed. Tony said he is ready to have the pre const mtg.

02/22/10 – Pre Const mtg complete. Electrical submittals have been sent in and approved. Pre Const Mtg notes sent being completed and sent to Contractors. We are waiting on submittals for the boilers. New project schedule must be approved by Owner.

03/30/11 – TEI has sent submittals back on all the mechanical and all the electrical submittals received. We are still waiting on flue piping submittal and controls submittals. Boiler equipment is about 4 to 6 weeks away from delivery.

04/27/11 – Asbestos abatement going on right now on some equipment. Const set to begin June 1. We are waiting for a schedule from Feldkamp and submittals on controls.

05/03/11 – Tony replied with the following “I would add one more item, that would be background Checks. I have received the (4) Local Checks. The remaining personnel on the list of employees that will be working at this site will need to have a background checks? I have not received any more Local Checks or any BCI Checks.
No work can be started until all the background are complete.

05/03/11 – TEI contacted Feldkamp and asked what is the status of this project? We don’t have project schedule, boiler flue submittals, and control submittals? TTC asked Tony to contact Feldkamp about project status.

05/04/11 – Terry wrote to the Team that Feldkamp had submitted their project schedule and it looks like this: June 1-Project start up, June 1-Demo, June 1-Electrical Demo & Work, June 14-15- Set Boilers, June 16-24-Pipe Boilers, June 16-24-Conrols, June 27-Flue piping, June 29-Inspections, June 30-Factory Startup. Basically the project construction side will take one month. To be safe, I would plan on another month to work out construction and control issues and plan on having something ready on July 31 or so.

05/24/11 – Control submittals returned. Const ready to begin in June but I don’t think contractors will have all background checks complete.

06/22/11 – TTC asked Pat Heeney Feldkamp to provide the pump vendor with pump head or whatever he thinks is best and get them the order.

06/28/11 – Feldkamp has made good progress on the demo since starting. We asked for a change order on the chilled water pumps. They said that they would be back this week to cleanup the boiler room and start to get ready for new equipment.

07/11/11 – ThermalTech checked out boiler progress and change order work on the chilled water pumps for this project. Boilers are demo’ed fine. 2 VFD’s have been installed for the HHW pumps, OA has been rerouted. Feldkamp has fitter change and we are trying to setup a const meeting for the week of July 26.

07/21/11 – ThermalTech was on site to review status. New boilers have been set in place, but no connections have been made. No indication of any contractors on site.

07/29/11 – Const Mtg 4 was held last Tuesday. The schedule was updated to have the work completed by Sept 2, 2011. Feldkamp has a new pipe fitter for this job. We discussed change order opportunities for the chilled water pumps. Vendors are giving us prices. Feldkamp has a $5000 allowance, Glenwood has a $2500 we can use. The exhaust vents will be routed straight up from the area well with rain velocity caps.

08/12/11 – TTC spoke with foreman regarding piping layout, discussion is as follows:

1. The old boilers were individually connected to the make-up water supply with no backflow preventer and we did not catch the fact that the piping only had a regulator inline before the boilers. You will need to provide a Watts 009 type domestic water backflow preventer http://www.watts.com/pages/_products_details.asp?pid=895 to meet OPC section 608.3 to meet Code. Please do the work now and give me a price towards the allowance that I need to use.

2. On the pumps the P&ID line sizes here are the updates. The main line size is shown as 6″ but really most of piping at the pump is 4″. I will update the as-built.

3. On the inlet side of the pump to the suction diffuser that is coming down as 4″ piping and will not require a reduce as we show on the dwg as the suction diffuser can bolt right to the pump inlet at 3”.

4. On the outlet side of the pump the flex connectors came in at 4″ but we don’t have 4″ on the outlet. One pump has 3″ pipe and one pump as 21/2″ pipe. The flex connectors will be size to match the existing piping in the field.

5. The triple duty valves that were existing on the old pumps are not shown to be reinstalled on the new pump. This is correct, we are not requiring the triple duty valves because these pumps are being retrofitted with VFD’s. What we are requiring is what is shown on the PID’s as new butterfly isolation with lockout capability strainer and reducer if needed but the suction diffuser takes care of that. The flex connections are on the outlets and get sized to match.

6. Finally HWP-1 and HWP-2 are the same size pump in the new scheme but one has 3″ outlet piping and one has 2.5″, Thermaltech will update the as-built to reflect this change.

7. Feldkamp showed me how they are going to hook up the MER AHU unit back to the heating supply and that looked like an acceptable plan as well.

The gas piping looks great. The HHW piping at the boiers looks great.

08/22/11 – The Power terminations to the equipment at the 250 boiler job is complete. We still have to perform a factory authorized startup on the variable frequency drives. The control wiring does not have to be complete for us to do the startup but there should be a control person present. We require 1 week notice of when we can perform this startup.

08/25/11 -A&M need access to do controls work. Question into Tony about them starting now with the local backgrounds complete.

08/30/11 – Feldkamp provided a price of $45,000 to replace both CHWP-1 and CWP-1 today via a quote from his vendor. We only $5000 in allowance money so I advised Pat that it would be up to Tony Matre but I did not think he would accept this price for these pumps. I suggest we get quotes from other vendors if needed. Feldkamp says state inspector is complete, flow switches need to be added before he will sign off on install. Controls and startup should be complete by 9/8 or 9/9.

09/14/11 – Modbus is up and running per specs, and A&M has installed code to covert form Centrigrade to Fahrenheit. Boiler and Pump controls programming is complete, A&M will be testing it today. DDC Controls are about 95% complete at this time. Duke is supposed to contact TTC about regulator visit to site. Contractors have punchlist items to complete in 14 days from now.

09/15/11 – Duke is going to meter the incoming gas pressure before and after the meter and report pressure trends to TEI. The building is supplied by what is called “standard” gas service which meant 4-7″ pressure most of the time. It can drop lower in cold weather. When the data is received from Duke a decision will be made about what to do. Duke was also asked to check the regulator inside the building and was told his records indicated there was no regulator at this site-which means the regulator that is high on the wall could be an Owner one and not Duke, which means it could be removed and put boiler regulators back on. This could probably alleviate the pressure problem if the house regulator is what is causing the issue. The only problem is to check the pressure for the water heater that the gas line feeds, or to adjust the house regulator to make sure it gets the least pressure drop through the unit as possible. Once Duke is on site, a final decision can be made. Duke will be out Friday or Monday to install the trending device.

09/22/11 – All closeout paperwork has been received by ThermalTech. TTC processed it and is planning on dropping it off to Tony Matre today at our 2pm LEED meeting with GBBN.

09/23/11 – Close out Documents have been received by both Contractors.

09/30/11 – Tony is paying out Glenwood in full minus allowances but holding Feldkamp closeout for boiler resolution.

10/13/11 – Gas pressure and flow should be fine. The Duke readings were 7.9″ at full flow. Several issues to note on this job are:

1. Our boilers are smaller and therefore there is no real way that Duke can say our gas mains are undersized.

2. There is very little gas piping in this building therefore the overall gas pressure drop is very small even if Duke thinks the 1″ lines to the boilers should be 1,5″.

3. Boiler 1 is running and continues to run just fine.

4. The problem is in the BLR-2 machine itself and we should pursue Turton and tell him the gas pressure read by Duke is 7″ and ask him is there any way to soften the low pressure cut out tendancy.

5. Duke talked about having their remodel team come in-that is the people that do replace meters and regulators. TTC has worked with them before. Someone needs to be at the building with them while the boilers light off and show them what is happening. Also ask them to trend the gas pressure in the main, they have a device that does that.

Step 1- TTC will email Turton.

Step 2- TTC has already called Duke and will check back with them.

Step 3-Keep Boiler 1 in lead.

Step 4- A&M is coming out tomorrow.

10/18/11 – A&M fixed the software gliche on the boiler pumps on Friday October 14th.10/19/11 – The lighting board is not in yet and neither is the flame rod assembly but Ballinger will install when they come in. The gas piping has been changed and Boiler 2 went out overnight. Boiler 1 continues to run flawlessly. The errors are either #107 or #108 normally but we are going to send a hand written error log that Hamco has kept on Boiler 2.

10/19/11 – The lighting board is not in yet and neither is the flame rod assembly but Ballinger will install when they come in. The gas piping has been changed and Boiler 2 went out overnight. Boiler 1 continues to run flawlessly. The errors are either #107 or #108 normally but we are going to send a hand written error log that Hamco has kept on Boiler 2.

11/02/11 – Feldkamp had asked for final payment on this job. TTC e-mailed Pat Heeney to let him know that Hamilton County Facilities would not be willing to pay any more billings until Boiler #2 is fixed and acting properly. Currently it is going out every night, but seems to start back up in the mornings. Ballenger’s tech is out of town until Friday, but there was supposed to be an update on the flame rod replacement 2 weeks ago.

11/04/11 – TTC went to jobsite and witnessed the following: Flame rod sensor was changed out in both boilers. The new sensor is longer and thicker than the old one. BLR-2 started working properly as soon as the flame rod was changed out. The ignition start timing was changed to 2000. The low fire firing rate was changed to 1500 on both boilers.

TTC watched both boilers start up properly and it appeared that BLR-1 was back in LEAD and was getting ready to fire again at a setpoint at 150F.

11/07/11 – On Friday FLR-2 had 3 errors. One was error #108 and two were #109. The changes in the flame rod sensor and ignition timings were evidently not the answer. TTC requested a Tech visit and to call Mike Jackson at Hamilton Co. Facilities, he needs to know about the field visits since it is his building. No money will be released until this matter is resolved. Jim Turton with Ballenger Co. has advised Steve of the continuing problems at this site and will be in touch with Mike Jackson soon.

11/14/11 – Ballenger Company ‘s service department ordered a new boiler module for #2 and will install it as soon as it comes in. This should fix the issues. Ballenger will call the customer and schedule a service trip.

11/30/11 – The Boiler Module #2 was replaced on Monday 11/28/11, the combustion checked, and normal operation observed with no fault trips.

12/06/11 – Boiler #2 was out again. It went out on code 108-Flame Lost in Run. It went out yesterday (12/5) also on the same code.

12/09/11 – Steve Schill (service tech for Ballinger) will be at 250 WHT on 12/12 to run some test sequence operations. He has been in contact with Cleaver Brooks product engineers about the problems at this installation, and we will continue to work on a solution.

12/15/11 – TTC proposed a troubleshooting strategy that would allow tracking the boiler pressure at BLR-2 and BLR-1 and see what the differences are between the boilers and track those readings vs. failures vs incoming gas pressure from Duke. Either TEI does this survey themselves or they will hire a third party. If not problem presents itself TTC recommends the following changes at 250 WHT:

Ask to remove the pressure regulator inside the building and increase the pressure to the gas main to the building beyond the standard house pressure of 7-14″. The factory gas pressure regulators can be reinstalled and allow pressure to add one inline regulator on it too so we can drop its incoming pressure down to 14″. We could turn off permanently the natural gas feeding the labs or install a regulator on that line too but those may be out of service. This may be the best solution moving forward. If all agrees with the strategy, a face to face meeting should occur at 250 between Feldkamp, Ballenger, County and TEI.

12/20/11 – TTC spoke with Dave Messmer at Duke Energy and he says they can increase the gas pressure in the building but they would prefer to deliver 2 psig to the building not 1 psig. TTC asked Jim if the factory regulators from CB handle the 2 psig to 14″ wc turndown and if he sees any issue with it?

Assuming all that works, the County has two options at this point. Put in one 2 psig to 14″ regulator after the Duke regulator and make the whole building house pressure again or we can add regulators on each piece of equipment that doesn’t have them. Jim agrees that bringing 2 psig gas pressure into the building and then reducing it with a main step down regulator would be the “cleanest” approach. Instead of dropping the pressure to 14″ we, he suggest maybe consider a reduction of 9″ to 10″ WC in order to have a little safety factor against operating the boiler gas pressure regulators at what He believes is their maximum pressure limit. Ballenger’s service dept. needs to be notified 10 days before increasing the gas pressure.

12/22/11 – Here are the loads: We have two Cleaver Brooks Clearfire High Efficiency boilers, model number CFC-1000, Input 1000 mbh, Output 920 mbh. Only 1 of these boilers should ever run to handle the building load. The other boiler is 100% backup. Does it matter to Duke what the operation is of the boiler plant or do you size for peak load of all connected equipment? One water heater 250,000 btuh. All of these appliances are within 100 ft of the meter. Please let me know what the next step for increasing the pressure to 2 PSIG as you suggested is and what the schedule of that change might be. I have to have some contractors on site to add some regulators onto our equipment because they can only handle 14 psig incoming gas pressure so I have to coordinate that work too. Finally does Duke have a gas pressure trend log? I need to record the gas pressures before and after these changes.

12/29/11 – I have asked Duke to increase the pressure to the building to 2 psig. We will then have to install a new regulator on your house line that takes it from 2 psig down to 14″ but Jim Turton said he doesn’t want more than 10″wc which I struggle with because after we give him 10″ he will say in the dead of winter the boilers are going out on low gas pressure because Duke demand is so high. Anyways, it will probably be 12″. Their regulators can handle 1 psig (28″sc). I had to give all the loads in the building to Duke so they know what “new” regulator to bring out to the building. I have to confirm with Feldkamp that they will be purchasing and installing a new house regulator using the remaining allowance money. I think this will all take a little bit of time and with the holiday, I don’t think Duke is in a big hurry to get it done this week. What will be interesting to see is what happens when the new pressure to the BLR-2 unit is 10-12″. If it continues to g out an alarm then you will have a real case to make Feldkamp or Ballenger reimburse us all the cost or make it a no charge. Feldkamp has offered to swap the inline gas feeds between the boilers for troubleshooting – is that something you think is worth the effort if we are going with the 2spig to 12 psig regulator?

01/13/12 – TTC talked to Feldkamp and confirmed the new regular type and load. They are calling Duke to coordinate install in a week or two when it gets back up in the 40’s.

01/19/12 – The regulator and materials have been delivered to site and depending on the weather will be installed on Monday the 23 or Tuesday the 24. Start time will be around 9 or 10 to give the building time to warm up.

02/03/12 – Ballinger has been trying to get a factory tech in from Cleaver Brooks to resolve the issue. They hope to have this taken care of soon. Ballinger is copying a division head and V.P. on all correspondences.

02/21/12 – According to Jackson, the BLR-1 at 250 WHT made it through the weekend with no reported anomalies. Both boilers had the grounding point and wiring modified so they are both installed exactly the same way now.

03/16/12 – The County has accepted this project as completed. Terry has requested all closeout documents or an update on the status of the closeout process for a timeline for final payments from Pat at Feldkamp Enterprises.

03/28/12 – Terry C sent Pat at Feldkamp an e-mail saying the last payapp needs to be modified and the change order monies be paid. Terry requested the cost of change order for the extra meter at the building. There is $3,500 remaining allowance monies for this project. The previous change order was not valid so that needs to be torn up and Payapp #6 needs to be changed. Also Terry requested the final markups to create as-built drawings to submit to the County.

04/02/12 – The final invoice sent by Feldkamp is not payable through the County Auditor system, TEI will have to reject the entire pay app. Feldkamp needs to send a revised final payapp #6 that asks for the remaining balance including retainage which is $14,650.00. Send 3 originals to TTC notarized and signed for closeout.

Outstanding items that are required:

-AS-Built Markup – have they been submitted to show field changes?

-Final approved permit document from City

-Final payapp with correct billing amount

-Final certified payroll

-Three O&M manuals for Tony Matre

07/09/12 – Feldkamp talked with city inspector and looks like they will be ordering double wall vent pipe, not going to accept the way it is unless the manufacturer backs it up in writing which they won’t du to liabilities. Pretty sure there is no allowance monies left. Feldkamp will get measurements and get it on order.

250 WHT – Boiler Replacement Project Read More »

237 WHT – Hydraulic Elevator Rebuild

10/07/04 – TE has received all final paperwork and a phone conversation record from Harry showing the approval of the allowance for the elevator extra work and it was indeed over $3000 but I told him we wouldn’t pay more than the $3000 and he agreed to assume the overage cost out of his profits. TK also rerouted some hydraulic lines at no cost to the County to facilitate future work on the hydraulic pump in the elevator equipment room. All the final paperwork is coming to you on Friday, October 8.

10/04/04 – We are currently trying to track down documentation that shows the TE approved the $3000 usage for pumping out the pit during the hyd elev pit during the construction. We actually also need an AIA invoice form for final payment.

10/01/04 – TK is dropping off final paperwork to at TE. We will process them and get the down the County ASAP.

09/21/04 – TK checked back in and is compiling the paperwork for this job. They confirmed what all was needed and TE gave the the list of documents. We expect completion in within a week.

09/20/04 – TTC checked back with Harry to see about final billing – Left message, email and voicemail.

09/03/04 – Contacted TK by email and urged completion.

We are awaiting final paperwork to finish this project from Thyssen-Krupp.

Elevator project is complete and new elevator is up and running.

237 WHT – Hydraulic Elevator Rebuild Read More »

237 William Howard Taft – Chiller Replacement

03/15/07 – TTC & Bill Scholl setup a meeting to check VFD operation for next Wednesday Morning.

02/19/07 – Project is complete. Contractors have finished all the punchlist items and the design changes have been fixed. TTC & Bill Scholl will balance the chiller as soon as the cooling towers are filled up and ready to run in 2007. O&M have been received and completed and sent to Tony Matre.

01/24/07 – Triton may start equalizer line on cooling towers. County may start to drain the cooling towers this Friday for this work. TTC and Bill discussed QCE providing power to the VFD but it being manually dialed into a HZ that equals the correct pressure drop across the chiller at full flow. This will be done after Trane confirms the dP and procedure that TTC wants to use to balance the system.

01/17/07 – Tony requested the project be closed out and archived. TEI sent the contractors this imperative. TEI will work to get paperwork completed in one week.

12/26/06 – Bill Scholl reported that the chiller is repaired but now the RM is going off into 3rd stage alarm. We decided just to turn off the RM until A&M can get to the sire to recalibrate the unit and verify it is operational again. This will be done the first week of January along with the new programming of the Chiller plant per last months instructions. The VFD is in town and QCE will be scheduling the install the first week of Jan 2007. QCE may be out earlier to mount the unit and wire it up for the factory rep to program later. BS and TTC discussed and are in agreement with this procedure. Once the VFD and pump are up and running we can manually dial-in the pump to 800 gpm (or a factory agreed PD across the chiller barrel) and then set it and forget it. That should wrap up that project.

12/22/06 – QCE reports that the VFD has arrived. We are scheduling installation immediately. TTC contacted Triton about pump vibration and resolution and will pass along information to County.

12/18/06 – VFD has been ordered. When it comes in, QCE will install. The chiller had a R leak that Trane is fixing. The oil leak to the bearing was found not to be an issued per the local Trane office so the bearing will not need to be replaced.

12/01/06 – Monthly Update. Triton removed the motor from CHWP-1 and sent it out for rebuild. According to Grady, it still vibrates but a lot less. Triton is going to have Weber-Huff come over to see the motor run independent of the system (un-coupled) and prove the motor has a balance issue. We are hoping they either repair or replace the motor. The motor fix is independent of the pumping issue where we have decided to put a VFD on the CHWP-1. AKM has secured a PO for the replacement and TTC has talked to Greg Chambers about ordering the GE VFD and he has. It is a stock item that should only take a week or two to come in. We will then schedule the VFD for installation. Once the VFD is installed, we will balance the constant volume system for 800 gpm through CHLR-1 and mark that position on the chiller, this should be the standard run % of the pump at all times. The remaining allowance usages have been coordinated with Grady at Triton as such: Triton will put the equalizer in between the towers. They will used companion flanges per TEI request and use 6″ SCH 80 PVC piping. The will use minimal elbows on the system to cut down on static but will drop the EQ line to the floor and back up to the basin on both towers. The remaining balance will be paid directly to A&M to have the backup CHLR-2 automated as the backup chiller and amend the economizer sequence such that the chiller plant will stay off line while the air handlers are in economizer mode (currently the chiller is only started by OA temp). The County will move the separator and have A&M pipe fitters provide the taps for the separator. Once all this work is done, the project should be complete. TTC has submitted payapps for the contractors but TEI has to write a change order to QCE for the VFD and allowance usages to Triton for allowances.

10/31/06 – Triton came to the site to check the alignment of the pump sled. By the end of the day they removed the motor for warranty repair. I do not know how long it will be gone but will keep everyone apprised of the dates once they are known. TTC has contacted Triton about adding the flow orifice or the additional balance valve to the job as well. Triton provided a price to do the equalizing line work which is more than expected. TTC passed it on to Tony.

0916/06 – TTC visited the 237 site again on 09/11 to review pump status conditions. I measured the actual ft of hd of the whole system and found it to be 65. TEI sent email messages to Tony, Bill and Dave advising of the existing conditions. There are a couple of things we can do to make the pump better match the existing conditions of the building (e.g trim the impeller, add a VFD, buy a different motor and pump. Weber-Huff reported that just reducing the HP is not a viable option because of the volute on our pump is too big for this small of head in the new system). Tony asked for meeting to discuss the situation and TTC will set that up. Final inspection is complete but the inspector wants to see the refrigerant evacuation system work. TTC advised Triton to coordinate with A&M and get that done for the County. TEI has already seen the system work a couple of times.

09/01/06 – After visiting the site with the Hydrodata meter, TTC contacted the vendors and explained in greater detail the operation of the new pump and chiller. The pump appears to have more head than is needed for this system. At 86 ft hd we have 925 gpm of flow. The design conditions are 800 gpm at 110 ft of hd. TTC offered the County several options on managing the issue. TTC emailed Bill S and Tony M with the recommendations.

07/14/06 – Bill called about training and TTC directed contractors to provide this training and coordinate it with Bill Scholl. Then provide closeout docs to finalize the project. TTC asked for direction from County on using allowance money for project before closeout. TEI would like to close this project and give back extra SOSS money to Dave Woodside before it is used up.

06/27/06 – Tony reported the Bill reported that the new drainage system is working and now water leaks are currently flooding the floor at the building. This good news. We can now close out the project as all other items have also been resolved.

06/26/06 – TTC stopped at the 237 building and put in a new drainage system on the cooling towers consisting of 1″ piping and funnels to catch the weep hole drainage of the cooling towers.

06/06/06 – TTC was on site today to conduct the refrigerant monitor system test. A&M ran the test early and Bill Scholl thought it worked. No one wanted to take a chance of setting off the horns at 7am so we let the early test be the test. TTC witnessed that both sets of pumps backed up the other pumps in about 30 seconds each. The 2nd chiller is truly a backup manual chiller that is enabled and disabled by the front end. The system while rotating chillers runs an extra 10 minutes to remove residual heat from the equipment before completely shutting down. TTC set the triple duty valve to 30% open and brought the CHWP-1 noise to down to a very good level. The pump appears to be running fine with no cavitation sounds and the air handlers appear to be getting enough flow and temperature to work properly. Later during the morning, the RM went into alarm at the second level with strobes on but the front end did not report this 2nd level alarm. Bill Scholl said that this was similar to a previous test where the false readings were from the method the contractor used to test the system. A&M stayed until they fixed the problem with a wiring change and talking to the factory. TTC removed the pans from CT-2 and they were water logged and water was all over the floor anyways. We added some plastic gutter drains for a TEMPORARY TEST to channel the water from the fans to the floor drains. We are not complete and TTC set the fire alarm off in the building by running the shop vac to remove excess water off the floor (that’s a pretty touchy smoke detector). We have to add more plastic drainage to channel the water even more directly to the floor drains. We are trying to dry out the penthouse to pinpoint exactly where CT-2 is leaking from. NOTE: even though the towers have small weep hole leaks like they are DESIGNED TO have by Baltimore Air Coil, my promise that they won’t flood the room from overflowing is STILL HOLDING TRUE.

05/22/06 – TTC visited the site and performed the controls punchlist for the project. Only minor items were found at this punchlist. TEI needs to coordinate a field trip for testing the backup systems on the chillers, pumps, refrigerant monitor system in live action. TEI to coordinate electrical punchlist on this job as well. The equipment is up and running and Bill Scholl seems to have a good handle on how to run the new system as yesterday when it was only 64F outside the new chiller was disabled and the smaller chiller was in service. A&M provided a control point to handle this control.

05/01/06 – TEI has been working to get the Controls finished on the job. A&M wrapped up work last week. Trane and its XIF file is not communicating properly with the front end and once that is complete the job could be finished. CHWP-1 is vibrating too much and Rick Huff believes it must be the pressure drop across the pump as it is readying way too low. TTC will check this out.

04/17/06 – TEI confirmed balancing with contractor on 04/18/06 at the building. Triton, Approved Products and TEI will be on site.

04/11/06 – TTC sent an email out to contractor to inquire about punchlist day, balancing day and controls for project. TTC instructed A&M to modify their existing sequence to match the intent of the specs for the pumping arrangement as the pumps are lead/lag when in reality they are supposed to be matched to the chillers they serve. Pump vibration is still excessive and TTC would like that looked at as well. Tony asked for a control meeting on the cooling towers and TTC gave him Thursday/Friday dates for this meeting.

04/05/06 – TTC talked to A&M about project progress and they reported that the controls can realistically be expected to be complete by April 14, 2006. The electricians and programmers are on site right now completing the work. A&M asked about how to program the refrigerant exhaust fan before or after the local hand/off/auto switch, TEI stated that the RM must be able to turn the exhaust fan on even if the HOA switch is in the “off” position. A placard will be made to designate that if total disconnect of the EF-1 is required, the breaker for the fan must be shutdown and locked out. It should be noted that this will bypass the automatic controls to evacuate the refrigerant from the space in case of leaks but keeps the workers completely safe otherwise. The chiller has been tested under low load conditions. Trane would like to make an secondary visit to the site to test it under full load conditions as the weather permits. TEI will schedule the punchlist work for mechanical and electrical within the next 5 days. TTC will punchlist controls after they are complete. As far as TEI knows at this point, either chiller can be used to cool the building but CHLR-2 is presently being used until Trane makes it return visit. Training is to be coordinated between the County and Vendors as needed at owners discretion.

04/04/06 – Bill Scholl called today to talk about control sequences on new cooling towers. TTC provided the history of the cooling tower plant that he was aware of. Here is the recap: The old cooling tower design allowed for one bank of a cooling tower to run independent of the other, this allowed moisture laden water to re-infiltrate the “off” tower and condensate in the fan housings and leak onto the penthouse floor and then onto the ceiling of the floor below. TEI changed the existing controls to force both banks of a tower to come on together to prevent this from happening (this may have changed when Fosdick modified the control sequence in the AHU job – Bill reported that the cooling towers were no longer coming on as one unit). Our new control sequence calls for actuators to be installed to control the backdraft dampers on the towers to open and close when the towers are in operation. As these are really four towers operating as two, let me use the declarations of CT-1A and CT-1B to represent one cooling tower and CT-2A and CT-2B to represent the second cooling tower. In the new design and sequence, TEI is asking the cooling towers to be put into operation when the chiller is enabled and either one of the condenser water pumps are enabled. Based on the outside air temperature, a reset temperature for the condenser water system will be deemed as a setpoint. As the condenser water temperature rises CT-1A fans will come on and open its cooling tower dampers along with the intake dampers to bring the temp back down to setpoint. If these fans can’t keep up CT-1B fans will come on to keep up and its dampers will open. The operator will select which towers to use in which order as 1,2,3,4 or 2,3,4,1 or 3,4,1,2 or 4,1,2,3 where 1 = 1A, 2=1B, 3=2A, 4=2B. There is no equalizer line between the sets of towers because the size of an equalizer line to let enough water flow between the basins without residual static was either 12 or 14 inches round – not practical PLUS you have a constant volume system, which once balanced shouldn’t have flow problems. The new strainers should keep the tower cells clean and the flow equal between them. Also when checking the design of the towers – they are sized for 600 tons on chillers – we are only using 400 tons – there should not be a problem with condenser water volume. The overflows are now piped directly to the floor drains so if for some reason, the basins overflow, the water should go down the drain, not onto the floor. The backdraft dampers put on the towers at the end of the previous public works project were all that could be afforded at the time of purchase. The actuator system that A&M is adding to the job at this time should automate these dampers one tower at a time (we don’t specifically tell A&M how to automate them, only that they need to be automated, so we will review their design when complete – or they can ask questions if needed). We just want to see them work when complete. If all else fails, you can always block the dampers open like you have been to get full performance if that becomes and issue. Under normal operation, we don’t envision any problems with the cooling tower operation under constant flow. If someone walked up the outlet of the towers and slammed the valves shut and all the CT basin’s overfilled before the pump suction cavitated, maybe there could be an issue – but we don’t see that happening on accident.

03/30/06 – Triton will have a tech at the building to check pump alignment on the new pumps on Friday. The backup chiller system was operational today and seemed to be working fine. The new chiller needs to be load tested under warmer days but was fine when started in the preliminary stages. TEI still wants to see the cooling towers balanced under full flow through the new chiller and pumps. QCE had to come in and change the phases on the chiller before it was started up for testing.

03/29/06 – TTC stopped at building today. Backup pumps and chiller are ready to start. County found a enable switch on an old control panel that turned the second pumps on. A&M is installing the RM system. Jerry Smith was working on that today and reported that the new actuators would soon be wired up on the new chiller. The Trane rep had the modules for the DPS switches in hand was hooking them up. He stated that he may be able to start the chiller today and begin to run it through its initial paces. The temperatures are supposed to be higher on Thurs/Fri so we may need the backup chiller. Mike Iverson from A&M is supposed to stop at the building this morning as well.

03/28/06 – Bill reported today that PSD switches are not installed. TTC sent out Const Mtg notes #4 to team. Chiller might be started this Thursday. TTC checking on status of controls with A&M services. LON cable is pulled, A&M is installing the cooling tower dampers now and they are waiting on some XIF files from Trane for LON integration into the new chiller.

03/24/06 – Bill called today to report that there was a problem with the oil filter on the chiller not sealing. Apparently it was damaged during installation by being stepped on. Later, Trane was able to put the replacement filter on and prove it sealed perfectly. We are on schedule to start the chiller next Tuesday or Wednesday – we have to wait and see when Trane finishes to be sure. TTC will call Tony to let him know when we know. A&M reported today that they should be onsite next week to finish installation and programming.

03/23/06 – Grady reports that chiller should be 100% assembled by end of business today with any luck. TTC asked A&M for controls schedule for completion.

03/21/06 – The County reported today that the Chiller piping is complete and we are filling the system. Triton is waiting on a pressure relief valve for new chiller and then we will fill it. Queen City Electric has the wiring pulled to chiller as of today. They will be back tomorrow to terminate wiring. A&M have been pulling control wire. I am hoping to get power on chiller tomorrow and then call Trane back in to set up chiller. TTC is going to stop at the building on Wednesday to check over the progress. TTC is checking on chiller startup date with Trane and Triton. The chiller will not start up on Wednesday because the DP switches aren’t here yet. Soon.

03/20/06 – TTC emailed A&M back with alarm settings for the Sentech monitor. First phase = LCD on Sentech, Second Phase = Strobes and LCD, Third Phase = Horn, Strobes and LCD.

03/15/06 – TEI spent hours today trying to figure out if the chiller really needs external pressure switches? Once the vendor replies to these questions, TEI will be able to give Triton direction on how to handle this question. Trane emailed me back and either Triton or Trane will provide the PSD on the project, TTC is letting Triton decide.

03/08/06 – Bill called today to inquire about insulation on the evap barrel on the chiller. TEI reported that it should be added after the chiller is put back together. TTC distributed the Const Mtg 03 notes.

02/27/06 – Bill Scholl left a message on my phone today stating that Tony said Facilities will move the light in the penthouse and paint the housekeeping pad at the 237 building as part of this job and Triton will not have to do it. Grady reported that the chiller arrived right on time and has begun its disassembly per the project schedule. We have a meeting this Friday for thsi job.

02/23/06 – Bill Scholl called today to inquire about paint color on the chiller pad pursuant to our last construction meeting. TTC told bill to tell Pat from Triton that the color should be gray and match the floor sealant color the County used when the mechanical room was upgraded. The actual painting of this pad was not in the scope of the project but can be covered out of the allowance money on this project. TTC visited the site earlier in the week and reviewed new valve install with Pat from Triton, we coordinated the on sight drawing for what was actually being installed in the field. Pat and Terry discussed the separator install and Triton agreed to pipe the separator in and out of the condenser water supply pipe and maintain at least six feet separation between inlet and outlet of separator. Triton also pointed out that one of the make-up water valves was damaged and actually “locked” on. There is no telling how long it has been like this but may explain the unusual high water usage at the building last year. TTC asked Triton to provide a cost to replace all 4 valves before we button the towers back up for service. TTC also asked Pat to clean up the drains going into the floor drain so that any overflow from the towers goes inside the existing FD’s and not out onto the floor. Triton was well on their way to having both strainers installed in the header feeding the cooling towers. TTC had to instruct Triton to install spool pieces on each side of the strainers because the strainer interfered with flapper operation on the valves. There is an existing light fixture that is way to close to the strainers and should probably be moved (does the County trades want to move or should I contact QCE about relocated the penthouse light?). Control submittals were received and marked up by TEI and mailed back to Grady Reed today.

02/22/06 – TTC emailed the team to say that A&M’s lockout on the control valves is acceptable. No additional valves are need for this job.

02/16/06 – TTC sent out request for additional valves on chillers per HVAC Trades request. TTC sent out request for decision on separator rework per HVAC trades request and reminded everyone about Friday’s construction meeting.

02/06/06 – TTC rescheduled the next const mtg for for 02/17/06 at 1:30 p.m. ThermalTech received submittals for the strainers, insulation, valves, gages and meters, refrigerant monitor. TTC will work on these this week.

01/23/06 – TTC distributed Construction Meeting # 01 Minutes.

01/18/06 – TTC found out today that the Trane has finalized the ship date of 02/24/06. This basically gives Triton about 2 weeks to install the chiller and meet the 03/15/06 deadline. TTC questioned everyone and is trying to get written buy-in that the project schedule can be met.

01/11/06 – Pre Construction meeting notes distributed. Triton is reporting that chiller won’t be shipped until 03/10/06. TTC has already placed emails and phone calls to see why the date is so late in the year. This is much later than we would care to have for this project and although a backup chiller will be ready to handle the load, we wanted to punchlist this job on 03/01.

01/06/06 – Pre Construction meeting was held. TTC will type up and send out meeting notes soon. The county asked for employee list and security checks. Triton may be on site next Wednesday for field review and to get familiar with building. Contractors want 8 additional sets of dwgs for this project. TE will have sent to contractors.

12/19/05 – TE finished the chiller submittals and sent them to Triton for ordering. After contracts are approved and PO are received, a pre const mtg will be held.

10/14/05 – TE delivered the final contracts to Kathy Bushbacher for the project. The prosecutor marked up and returned and TE reprinted contracts and delivered additional drawings to JFS so that this project could stay fast tracked. TE delivered 8 new contractors within 1-1/2 hours of the phone call and TTC hand delivered to JFS.

10/13/05 – The bids opened on 10/0705 and after much internal work inside ThermalTech verifying the LCC equations, TE recommended the Trane Chiller and Triton Services as the installing contractor. Queen City Electrical was the electrical low bidder on this project. TE is writing the contracts for delivery to Dave Woodside today so that he can turn them in to the HamCo Prosecutor for review.

09/29/05 – Two critical equations are missing from the life cycle cost equation sheet and TE must extend the bid form to allow contractors to enter this data. The bid is being extended one week by Addendum # 02.

09/27/05 – York called today to ask about chiller retrofit on CHLR-2. We discussed how the County will or won’t accept the alternate to change out the refrigerant.

09/26/05 – Addendum 01 has been issued for this project. Bid Opening is still scheduled for this Friday.

09/06/05 – Project was delivered for bidding to Purchasing and Ohio Blue. Prebid is set for 09/16 at 1:30 p.m.

08/31/05 – TTC sent out an email over viewing all the construction and production changes to the final design at the 237 building. The County is seriously concerned about the cooling tower overflow issue and TTC assured Dave Woodside that the construction project will address this issue through cleaning, balancing and repiping the cooling towers. The new system is constant volume and once balanced there should be no more remaining balancing issued between the separate cells on the towers. TE will have the mechanical contractor take care of all these issue during the construction of the cooling tower project.

08/01/05 – TE spent the last two weeks doing field work and finalizing the design on this project. Construction documents should be ready to review at mid August and be ready for bidding. We are going with a 45 degree chilled water temperature and a 12 degree delta T to meet existing conditions at the site and the new ahu coils in use. TE will schedule the final review within the week and go over the final plan for the project and get consensus on all that we are doing.

06/14/05 – TE kicked off a design meeting at the site. We reviewed the scope, bidding process and alternates to the project. See the meeting notes below.

06/13/05 – TE set to meet client for kickoff meeting at site.

237 William Howard Taft – Chiller Replacement Read More »

230 – Humidification in Rooftop Unit

04/22/05 – TTC faxed over a letter stating the deficiencies of Application # 01 on this project. All final paperwork is missing.

03/25/05 – TTC completed punchlist on job. There are no items to fix. Geiler submitted final pay application without any final paperwork. TE will ask for closeout documents.

02/25/05 – TTC asked Geiler for update and if they are ready for TE to punchlist this project.

02/11/05 – TTC talked to MF today. Geiler has the piping complete. The insulation is on the piping now. TTC will perform the punchlist next week on Monday or Tuesday.

02/08/05 – TTC visited the site today with Geiler and MF. Geiler should be wrapping up by end of week. Systems are online. Insulation needs to be completed. Geiler is in cleanup stages of piping work. TE to do punchlist within a week. Valve, steam and humidity control appear to be working.

02/02/05 – TE talked to Geiler today. They will be off the job for a couple of days. They have to soak some unions they are having trouble disassembling for re-use. They will be back next Monday for sure if not earlier (I think Bob wants to stop down to soak the unions tomorrow). Elevator and space access issues have been resolved. We were original trying to finish by 02/07 but I believe it will be at least 02/14 before the changes are complete.

02/01/05 – Geiler has started the project during the evening schedule. TE to follow up the MF this week for progress.

01/26/05 – Geiler delivered tools and piping, but wont’ start project until Monday 01/31/05.

01/25/05 – TE and Mike F. walked the project with Bob Burlege of Geiler. We feel as though they won’t be able to start the project unit Wednesday per Bob’s comments but it could be later than that. We are planning on shutting down the steam once in the evening to weld the thread-o-lets on to each header. Then add an isolation valve to shutdown each header and work on each side independently, keeping the building without humidification to a minimum. The pipe machine will be setup on the dock. Piping will be hauled in the elevator. The 230 staff will stay with Geiler the first night to ensure the boiler plant and steam come back online properly. MF will show Geiler how to shutdown and lockout/tagout the AHU’s when working. 120V welder must be used.

01/17/05 – Submittals received by TE. Walk through scheduled for Jan 24, 3:30 p.m. provided that TE approve the control valve submittals.

01/11/05 – Pre Construction Mtg Complete. Geiler projects this to be a 2 week job maximum. They will begin work and stay on site to complete work throughout the project. Pre Construction Notes added below.

09/29/04 – Original Bid Documents have arrived and TE sent to County via UPS on 09/29/04 for approval.

09/23/04 – TE contacted contractor and we are awaiting original bid documents to submit with final contract (3 copies).

09/20/04 – Contract written. Awaiting for TTC to approve and deliver.

09/13/04 – Bids are compiled. Geiler is low bidder. County please advise how to proceed.

230 – Humidification in Rooftop Unit Read More »

230 – Ninth Floor Microfiche Project

03/14/06 – Bill Scholl and Mike Florimonte have both reported that the systems are working great and permits have been approved. This project is being archived at the end of this week.

01/10/06 – HVAC has work above Julie area’s almost complete. They have scheduled an HVAC inspection with Steve Ossege in the coming days. Exhaust was hard to get routed but they are almost complete.

12/28/05 – The microfiche permit was picked up and emailed down to the County approved for use. TE paid and will reimburse the cost to the County.

12/14/05 – TTC setup a meeting for THP to review the space ceiling construction to approve the ductwork hanging method on this job for 12/15. Aaron Bennett will be contacting Mike Florimonte for access to the building. MF reported that the piping, boxes and louvers are nearly installed so far.

12/09/05 – TTC applied for the permit today at the City. The permit number is 2005P09839. It cost $75 to the application fee today and the remainder will be paid when we pick up the permit. All of this cost is a reimbursable cost to the owner on this project for this work.12/02/05 – County trades can’t put the ductwork in as designed on the plans. MF is going to inspect the above ceiling layout and call TTC with details. TTC will stop by the building and give direction as to the best way to proceed to finish the job. TTC informed Tony of the plan. Terry contacted THP by email to verify ductwork loading won’t overstress the ceiling arrangement.

12/05/05 – Terry meet HVAC trades on site to discuss ductwork routing and relocating light fixtures on this job. It was decided the best and easiest way to fit the ductwork into the room was to rotate the lights 90 degrees and remove the remaining light that is interfering with the light fixture. Carpenters will have to do some ceiling work to patch and paint the areas that are affected by the ductwork and fan supports.

11/29/05 – HVAC called with questions about moving the VAV box in Julie’s office because it was interfering with new ductwork. TE said this was fine. HVAC called with a question about framing the fire dampers in one big angle frame and TTC said this was fine also. In email correspondences today, we believe all issues are up to date and the work in on track.

11/21/05 – TE and the County met at the site to discuss Sam’s HVAC design and coordinate with the tenant and trades for making this work out. Everyone was in agreement that if we could bring both ducts into one corner and just create a matching column in Linda’s office that would be fine. The people in attendance were Mark Perry, Tony Matre, TTC, SRB, MS, Dave S, Bill S, Jim E, Ernie, Mike F, Paul and Jerry.

11/16/05 – TTC and Tony discussed the bidding out of this project and the method in which the money and trades would do the work on this project. Wayne would like more controls11/15/05 – Review drawings were sent to the County today. TE would like to get comments back about this job as the County’s convenience.

11/10/05 – Wayne called and said that the draft design is OK and to proceed with a permit set of drawings, so trades can do the work. He will also contact TE when he has set up a Archibus job number, so we can enter a cost estimate.

11/10/05 – Wayne called and said that he would like trades to do the work. He said that he would check with Mike Florimonte to see if draft design is OK. After final client approval, TE will then put together a drawing set for trades.

11/04/05 – TE sent Mike Florimonte a draft of the HVAC layout to see if Manager of that area is OK with design. Design included exposed ductwork in the Vault to avoid redoing the ceiling, to allow for concealed ductwork.

11/02/05 – TE is putting final design together. Sam and Mike will be making a field trip down to the building on Friday to set routing and check clearances.

10/13/05 – TE and CR met with the client to finalize building and design standards for this project. CR has to submit an SOSS. The equipment will be in the building in about 2 months for this job. TE must do the design immediately for bidding.

08/30/05 – TTC received installation manual from vendor in San Diego. TTC sent pdf to County for their use. Heat and Electrical requirements were provided by vendor. TTC got many other calls from salesmen at Anacomp who because ThermalTech was inquiring believe they were somehow being left out of the purchase loop of the equipment. TTC assured them that the County is in control of purchasing the unit and ThermalTech was only designing the room that the equipment when and if purchased would reside in.

08/25/05 – TTC contacted manufacturer today to collect engineering information on unit for installation including btuh rejection, power req’s, exhaust req’s and mfgr’s installation instructions. I had to leave a message with their main office.

08/22/05 – MF called to say that after talking with some people, the belief is that the vault walls are reinforced concrete and not just metal stud walls. TTC and MF talked about airflows in the room and the floor and TTC believes that the design should most likely be to add one separate VAV box for the microfiche machine and exhaust the entire room. The machine should most likely go into the vault area where the room can be separated from the general airflow of the space.

230 – Ninth Floor Microfiche Project Read More »

230 East 9th Street Electric Device Study

01/10/07 – This project is complete and archived on 01/10/07

08/18/06 – Drawings have been delivered to Hamilton County Facilities. There are no open issues on this project.

06/14/06 – Close-out meeting; no open issues. All work by Queen City has been completed. I will be working on getting the drawings completed within the next several weeks and send (3) full sized sets to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Mike Florimonte). Queen City presented (2) binders, each with copies of the old and new panel schedules. On the new panel schedules the items listed in bold have been verified; the items listed in normal type are transferred over from the old schedules. The binder also includes diagrams of the MCC’s and Switchgear. A CD was also provided which contains all of the new panel schedules in Excel format.

11/15/05 – Contracts have been submitted.

230 East 9th Street Electric Device Study Read More »

230 – Boiler Stack Study

03/05/08 – TTC and Tony figured out the billing issues and TTC sent an email to Grady on how to bill for extra services. The actual project is complete. The County has to fix its own PO to pay Triton but TEI work is complete on this project.

01/25/08 – Tony and I talked today about closeout on this project. Grady is to bill the County the remaining balance as a change order to this job. I will write a change order to match the total amount owed to Triton on this job. The County has a PO invoicing issue on this job (JC bill to this PO).

11/16/07 – TTC talked to Mike F today about project status and sent AKM the following email:

The summer boiler flue temperatures are still no where near 310 F so the fix worked to make things better but we are still probably going to have condensation issues.

The winter boilers are on now and they are slightly better also but we are still not getting 310 F at the outlet of the boiler stack. I told Mike that we should re-smoke test the boiler stack just like we did at the start of the project to see if any drafts are still cooling the boiler stack down as the flue gasses go up.

Mike believes that Triton did a pretty good job buttoning everything on the boiler stack from the job that we bid out and the extra work that you had them do on T&M inside the building. We just aren’t getting as good as results as we would have liked.

The summer boiler is slightly over 2,000,000 btuh which means it would take 4 of the Knight boilers to replace it and meet the same load. We could do this if it was the only problem you still had. The large winter boilers are 5mil btuh so those cannot be replaced by these hot water boilers so we are still kind of faced with some of the same problems with temperatures that you have faced from the beginning in that the outlet temperature at the top of the boiler stack is under 310 F.

and told the County that when they were ready to take the next step to let ThermalTech know and we can help with the design or problem solving.

05/22/07 – Triton submitted their final payapp for the project. There is a $980- change order for the extra camera work. This increases the contract amount and TEI needs approval from the County to pay that. Please advise.

05/14/07 – TEI contacted Triton for closeout documents. Grady said they would send them in ASAP. TEI will return a video copy of the boiler stack video to Grady to closeout the project. TEI has been in contact with MF about the type of brick to replace in the chimney wall to maintain integrity and this would be solid lightweight concrete block according to Spencer at Cole Russell. This project is ready to archive. 12/04/06 – TTC questioned the use of the full allowance today ($5000) and requested an itemized breakdown from Triton for the work completed. The dwgs ask for the the wall to be built by the contractor but that has not been completed to date. The additional work that TEI is aware of is sealing the upper stack and the camera record of the interior. TEI asked for the requested change order to seal the outer stack to be taken from the allowance not as a change order.

11/30/06 – TTC asked about writing a change order to the project for Triton to do the stack sealant work. The project itself is complete. We are moving into the next phase for 2007 where we will address insulation the stack in some way to keep air from overcooling the inner shell. The County is going to open up the wall sections to allow Triton to patch the outer wall of the boiler stack. This can happen right away if the PO gets approved for Tony. TTC asked the County for an update today.

11/13/06 – A lot has happened since the last entry to which i will summarize. Triton has been on site and finished the work. A camera was dropped down between the stacks for a record of how they were built. We discovered that the outer shell had 3 large rectangles removed where spaces were welded to the inner stack. The stack was not support to the outside wall as originally intended. We believe these holes are contributing to the excessive draft up the stack causing a high cooling effect on the boiler flue gas. We instructed Triton to seal the top of the outer stack to the inner stack with a metal seal and put the breeching cover back on seal it air tight with caulk. In the basement Triton sealed the inner stack against the outer stack where the new stack enters the side of the old stack. They did this with steel plates and welds. The temperature sensor is installed and monitoring outlet temperatures and we can only see a 2-degree rise in temperature with the stack being sealed top and bottom. This is not surprising since the are three gaping holes in the outer stack wall on the 4th, 8th and 12th floors that may still be an escape route for air movement. As this is the first stage of the fix it plan being used for investigation as well, we are formulating the second stage now. We want Triton to patch the remaining three holes by change order if necessary. In step two we may try to fill the interstitial space between the stacks with concrete and create a permanent insulation space between the two stacks and this way when the inner stacks rusts out, the concrete stack will remain providing a permanent stack for a long time. We have to get a structural involved at that point to help check the loads on the building.

08/28/06 – We held a construction meeting to get a new handle on where the project stands and to review the R&P chimney stack report. Grady brought one copy of the report and Tony asked for 3 copies to be made and given to the County. The report has basically found that the stack is in FAIR condition. The stack was basically constructed in two different segments, the bottom 130 ft and the top 40 ft. In reviewing the original report from 2001 and the new report from 2006 there is considerable degradation from low temperature condensation and corrosion inside the stack. Photographic evidence was provided in the report to support this claim. The wall thicknesses have decreased and will continue to decrease and the new temperature outlet sensor installed in phase 1 of this project has further provided trending and data to prove that decent outlet temperatures at the boiler flue’s in the basement are significantly reduced in their upward travel to leave the building. Mike Florimonte provided a trend that showed summer boiler leaving temperatures of over 500 F but at the outlet of the stack temperatures were only 210 F. This is a condition that will cause low temperature corrosion. R&P is recommending a spray on coating to protect the interior of the stack. Triton and ThermalTech recommend further investigation into the over cooling effect on the boiler stack. For this much temperature loss to occur, we believe it must be related to the high velocity draft witnessed around the boiler stack at a previous field trip by TE. We have scheduled a Saturday visit with Triton to set off a smoke test inside the boiler stack. We want to witness the path of the released smoke and find the air path that is causing the stack losses. In essence the space between the inner stack and out stack should be dead air space. In addition, Triton will investigate the OA paths surrounding the boiler stack to help ensure that no OA is subjected directly to the boiler stack space. Once this data is resolved, we can isolate the boiler room from the chimney stack and address other “sealant” issues with the new and old breeching. We are scheduled to meet on Sat, Sept 9th. MF will alert the building occupants. AKM requested a synopsis of or plan of attack.

06/16/06 – R&P Industrial Chimney showed up on site. At 2:17 they completed their fieldwork and reported the seems in the stack appear to be the worst off. The took a disposable camera and ultrasonic machine into the stack with them. TTC asked for them to call with a report after they packed up.

05/22/06 – Boiler stack inspection still set for June 19th. Grady is checking on controls and trending.

04/06/06 – Mike called today about getting study complete and temperature sensor in place. Grady replied that the inspection could be the middle of May. The County will need this inspection to be completed either after hours or on the weekend because of hot water reheat. TTC to review and try to find a holiday instead that may work better.

03/09/06 – Pre-construction Mtg was held and notes distributed.

01/17/06 – Wayne reported today that the Bid from Triton did not included a personal property tax statement or a ohio dept statement. TE to check and correct for Wayne.

12/13/05 – Contracts were returned for corrections. TE corrected, printed and returned to the County for submission to the commissioners.

12/01/05 – TTC found the original bids for the job (in sbu’s mailibox) and sent them on to Tony for his use. As soon as contract is approved we can have a pre-construction mtg and get the project moving.

11/08/05 – Tony authorized ThermalTech to write the contract for this work. TE will try to get it done in one day.

10/18/05 – All bids came in and contractors are calling for bid results. TTC gave to Tony and Mike on 10/20 for review. Bid Results – PDF

10/14/05 – No addendum had to be issued. Bids are due next week. TE has received a couple of “No Bids” on this project already.

09/29/05 – Final Project manuals have been created. IES information added for controls. Prebid is set for Oct 6 at 9:30 a.m. TE invited Peck, Triton, Process, Geiler, DK and Langdon to bid the project.

09/09/20/05 – TTC is reviewing Sam’s final drawing and project manual.

08/31/05 – MF reported that with their flow hood the outdoor access door when opened drew 1600 CFM with boiler make-up and exhaust running and 650 cfm with the MUA and EF off. This may contribute to extra cooling down of the boiler flue and TE is investigating welding the outer shell closed during our project. TTC cannot explain the huge draft of air up the shaft at all times

08/30/05 – TTC stopped by the site today to review an access door in the side of the building. There appears to be a huge draft from the outdoors into this access door and it apparently is going up the stack and exiting somewhere that in undetermined. This presents a problem with finalizing our design. We can still go about sealing the basement mechanical room as planned but after we are all done there may still be another step to isolating the inner/outer stacks when we are complete and re-measure the infiltration airflow. In talking with Mike, TE may give Mike the cutout for the future access door. If we cut the whole in the drywall now so we can investigate better how the inner and outer stacks are routed through the building. TTC needs to look at original report and talk to contractor about installation method. There are still unknowns about the original design that are affected an effective solution to this problem.

08/25/05 – TTC sent out final bid manual for review today to MF and AKM. Bid opening might be on 9-7-05.

07/18/05 – TE started the small project manual for bids today. TE has to create a new SOSS because the study used up the first SOSS but since so much of the design is already complete TE only wants to write the new SOSS for $2000 instead of the standard $3500 for bid and contract administration.

06/17/05 – TTC and MF discussed the report today and TTC recommended that we put a small packet together now to close up the air space around the stack. An incremental approach to fixing the problem is best. After the space is enclosed, the stack losses should be re-measured at various conditions to asses the new operating characteristics of the boiler plant. This should be done this year if possible. At the same time, a drywall access hole should be cut to inspect how stacks are anchored together. TE will wait for the County to advise.

06/16/05 – TE sent the final report to Tony and Mike for review and use. TE recommended closing off the bottom of the stack leading into the basement and re-creating a dead air space that can be used for isolation the temperature and creating a thermal barrier.

06/06/05 – TE had a meeting today to discuss recommendations. Our report will be out later this week and 2006 estimate will be estimated based on this report. We plan on discussing with Tony and Mike after Mark Miller sends final report to County. TTC and Mike discussed field findings from last week in an impromptu meeting at B-95 today.

05/24/05 – Mike called today and TTC told him that ThermalTech has not done any construction documents yet on this project and that might be due to the fact that we haven’t given Tony a final report on the condition of the stack (awaiting the re-evaluation from either HC Nutting or the other contractor that MF was going to call into survey the breeching) and TE has not provided a written report to Tony and Mike with recommendations about how to proceed. As MF and TTC discussed the situation though, we decided that if something is to be done this year before heating season, the design and SOSS must begin immediately. TTC will email AKM and ask about how to continue work on this project. TE still has $1172 left from the original SOSS that we do not need to used except to provide a written summary to AKM about our findings.

05/11/05 – TTC gave MF HC Nutting as contact for pipe thickness survey.

03/28/05 – TTC & MM met on site and went over boiler stack calcs and heat losses. Too much heat is being loss going up the stack. We need too look at insulating the stack to keep the heat higher throughout the path.

02/22/05 – TTC and MM reported that initial reports look like stack losses primarily are contributed to the low outlet temperature and condensation issues at the 230 building and not stack sizing or entrainment.

02/10/05 – TE received a signed SOSS and posted it to the website today.

02/01/05 – TTC & Mark Miller visited the site for field investigation and SOSS scope.

230 – Boiler Stack Study Read More »

2020 AUBURN – BUILDING ASSESSMENT

05/03/07 – Hard copy report is finished and being delivered to Mark Donnelly.

04/26/07 – TTC told Mark that he would incorporate Don Benbow’s mark up and update the website and give him 6 new hard copies.

04/18/07 – The only comments that we have received are from Don Benbow. We will update the report for the items we are willing to concede and update and send down final copies to Mark Donnelly if he is okay with this approach.

04/13/07 – Issues in disagreement are being worked out.

04/04/07 – Matre forwarded some comments from Don Benbow. TE may incorporate his suggestions into the report. We however disagree with some of them.

03/30/07 – Email copy has been delivered to Mark Donnelly for markup. TEI will provide 6 hard copies upon receipt of HamCo comments.

03/23/07 – Awaiting notification to provide hard copy of report.

03/20/07 – TTC to input report on Wednesday. Report has been input to Archibus. Review set to be hand delivered on Thursday.

03/14/07 – NR created project journal and filled in back data from previous meetings. Report completed, information to be inputted into Archibus on 03/12/07. Hard copy will be delivered during the week of 03/12/07.

2020 AUBURN – BUILDING ASSESSMENT Read More »

2020 Boiler Replacement

01/24/11 – All punchlist and closeout documents have been sent to Bert for this project. Receptacle was moved by Ginter on water softener.

10/1/10 – All work is complete. Seco has not turned in final closeout paperwork yet.

09/22/10 – Peck has scheduled change order work to start at the end of September. ThermalTech has provided answers to the PHB questions on the Change Order work.

08/13/10 – Peck submittals are approved on water heater and all other change order work. Seco change order was sent out for signing. Seco payapps sent to Bert for payment. Siemens payapps sent to Bert for payment.

07/23/10 – Peck change orders are approved. Folck is working on Seco closeout documents and change order forms. Peck is to schedule change order work starting next week. Bert is trying to get PO for water softener.

06/02/10 – Siemens has provided pricing for OM-1 Actuator Option to convert 2-position valves to modulating. Isolation valves will need to be modulating to avoid damaging system shock.

05/28/10 – Boiler installation has been approved by IBI. There are a few minor issues which Seco will complete next week. PH+B has provided pricing to install blank off orifice plates to convert (3) 3″ flanged 3 way bypass valves to 2-way valves for AHU-1,2,3. Blank off plates are 1/16″ thick with a 1/4″ hole in the center for relief and will be installed between the existing valve gaskets and flanges. CB BLR-3 and BLR-4 have been successfully fired and will continue commissioning by Siemens next week.

05/26/10 – Boiler installation has been approved by the State/City and is ready for startup with CB Thursday and Friday (5/27-5/28).

05/24/10 – We had a construction meeting today for the project. All mechanical and electrical work has been completed. Siemens will be on-site all week to install control wiring and begin controls startup / commissioning. Boiler inspections are scheduled for Wednesday (5/26 – State/City) and Thursday (5/27 – Electrical). Boiler startup with CB is scheduled for Thursday and Friday (5/27-5/28).

05/21/10 – HWS/HWR and NG piping have been completed. Condensate drain line and relief valves will be installed Monday (5/24). Combustion air intake has been modified to eliminate 45 degree elbow around conduit rack. All electrical work has been completed including VFD’s, pump, and boiler feeds. Current transformer has been fixed temporarily until new transformer is installed on Monday (5/24). Control panel has been installed and conduit for control wiring was run to boilers and pumps. CC will be on-site all next week (5/24-5/28) to install control wiring, thermal wells, and begin programming with Chris Neff.

05/18/10 – Combustion air and exhaust have been installed for Boiler #3 & #4. (1) 45 degree elbow was used on intake air to avoid conduit rack. TTE recommends (2) 90 degree elbows vs (1) 45 degree elbow for a more appealing installation. To avoid compromising the security bars and make installation more simple, combustion air intake was not installed thru existing louvers. Boiler piping has been started and will be completed by Monday (5/24). Balancing valves or triple duty valves will not be used for this installation. Copper was considered for condensate drain lines to avoid damage by foot traffic, but is not an option due to possible erosion from acidic condensate. If problems occur in the future, condensate drain lines could be changed to sch 80 pvc or stainless steel. Electrician has moved (2) of (4) VFD’s near pumps and will complete installation Wednesday (5/19). Siemens will be on-site Thursday (5/20) for controls.

05/14/10 – Project schedule was updated and meeting notes were sent out from construction meeting on Monday (5/10). All demo has been completed for boiler #2. New Boiler #3 & #4 are currently in the assembly process and will be completed on Monday (5/17). Included boiler legs have been shortened 5″ to accommodate overhead clearance requirements. Boiler #3 & #4 have been positioned on existing concrete pad as shown on TTE drawings. Included boiler exhaust was installed opposite of drawings by factory and will be changed to match TTE drawings. Boiler piping will now be routed between boilers as approved by TTE. HWS valve has been relocated near existing HWS tie-in. TTE considering the addition of balancing valves or triple duty valves for Boiler #3 & #4. Boiler combustion air, exhaust, and piping will be installed next week (5/17-5/21). Electricians will be moving VFD’s near pumps on Tuesday (5/18) to satisfy line of site concerns. Replacement transformer is scheduled to arrive Wednesday (5/19).

05/10/10 – We had a construction meeting today for the project. Peck will begin demolition on Tuesday. Controls and Electricians will be reported next week to start their next phase of work. TTE will work on schedule and meeting notes this week.

05/07/10 – We setup a const mtg for next week on Monday to kick off the demolition on this job and to coordinate the construction issues. The permit has been approved by IBI and City. The real work begins.

04/29/10 – We continue to work on schedule with Peck. PHB came on Wednesday to begin coredrilling for the new vents. The city has the permit held up on 3 issues that TEI sent responses down for reconciliation. The electricians and Siemens are working on a disconnect issue with the VFD’s. Boiler is scheduled to be demolished on May 10 which has been approved by Don Benbow.

03/24/10 – Siemens payapp has been received but the schedule of values is not acceptable. TTC will contact Siemens. Peck payapp has been approved.

03/23/10 – All submittals have been received. All submittals have been returned. We clarified an issue with the boiler vent piping. It can be single wall with personnel protection on this job. A controls meeting is scheduled next week to work on sequences with 2020 and the Siemens. Gary Davies will attend for TEI.

02/22/10 – No word on Siemens. TEI created permit drawings sets for the contractors, as soon as they are stamped and signed, we will give to contractors. Small modifications to venting per the 02/12 visit.

02/12/10 – Met with Peck on site and reviewed project with Foreman. Contact all contractors for submittals. Neff said he could call Siemens for me to find out where their subs are.

01/19/10 – The preconstruction meeting was held on site. TEI has approved the boiler submittals but wants better paperwork. Siemens did not attend the precosnt meeting. PHB and Seco were in attendance and are working on submittals as TEI works on permit drawings for the project.

12/31/09 – Contracts are signed but the BOCC have to approve them before we start. Siemens state term contract is ready. Peck asked for and received an extension on the project completion date. Ballinger informed us through Peck that boiler prices will increase in 2010 if we don’t order in 2009. That is a problem since the contract won’t be approved because of winter hours for the BOCC.

10/19/09 – Bid came in for the project. Peck appears to be the lowest bidder. I confirmed the prices with Bernie. His labor looks low but they are willing to do the project for the price. I know have to look at the LCC for the boilers and see which is best and look at lead times on the equipment.

09/18/09 – Final bid documents were sent to Purchasing and Queen City. The Bid Opening is October 19th. The Prebid is Oct 1. Chris Neff called and wants to go over some drawing details. The controls contract will be given to Siemens under a state term contract. TEi turned over the pdf’s to Siemens but we have not heard any comments from the CC yet. Gary is in the office this week so we need to organize the final details.

08/25/09 – Control schemes are finished. SOSS is approved. TEI is working on design. We need to go back and do more fieldwork for verification and start the design on paper. We are bidding 3 alternates for boilers: Clearfire, Fulton, Sync.

07/28/09 – TTC & TZ visited the site and did the preliminary field work. TTC created and sent Tony an SOSS for the project. TTC will hand deliver the SOSS to Bert at the County Partnering Meeting.

2020 Boiler Replacement Read More »

2020 – Boiler Replacement Phase 2

08/13/10 – We are waiting on an approved SOSS to proceed.

09/24/10 – Project was bid out as scheduled. Bid opening scheduled for Oct 14.

10/25/10 – Contract for Peck has been sent to Tony for approval. Tony said he was going to pay for Boiler #1 repair this year and install the new boilers in Spring 2011.

01/24/11 – Contracts are in approval stages. Waiting for pre const mtg. Labor will start after heating season, March 2011.

02/22/10 – Pre Const Mtg Complete. Mtg notes being sent to contractors. PHB has submitted boiler paperwork for approval. The original rain caps have been removed on the boiler stacks to prevent ice puddling below the stacks. PHB is looking at installing thimble caps on all new vents. New venting and project schedule must be approved.

03/30/11 – Peck is working on boiler order and delivery. Boiler submittals and electrical submittals have been returned to Peck. We are currently trying to work out a change order on the control valves, actuators and flow meter. The project will begin in May-June 2011. We should be finished by the time summer is over.

05/12/11 – Peck is working on new background checks. All change orders have been sent through. Boilers are ordered.

06/07/11 – Boilers are at PHB and the flues should be there in a few weeks. PHB still needs to get background checks back from the State before they proceed.

06/20/11 – PHB is ready to start some sheet metal demo in the boiler room next week, also finalizing the project schedule for this job.

Item #2 – There are a couple of issues with the control equipment that we need to discuss. The acuator and valve by Keystone apparently is out of stock. They have offered a replacement that we can get, it is slightly bigger than the one we specified. The problem is TTC can’t find this model on their website. Asked Chris who they contacted locally for prices and model #’s.

Item #3 – TTC asked if Siemens or someone else preferred make the paddles wheel flow meter needed. Bernie was looking for a local manufacturer that sells the Badger flow meter, but was not aware of any yet. Did Siemens offer the one we get easily?

07/07/11 – Peck is on site performing demo. Chris has been sharing controls and wiring with the Peck for purchase through Seco.

07/21/11 – Pipefitters are complete with their work. Sheet metal guys are waiting for a fitting for the flues, and will continue as soon as they get the rest of their materials. SECO Electric will be on site Monday 7/25. Start up is scheduled for August 12th, that will give enough time to get everything complete and the boilers inspected. ThermalTech has to provide a punchlist and discuss controls with Chris Neff.

08/05/11 – TTC sent out an email punchlist to Peck from a site visit last week. Bernie said they can get this done.

08/08/11 – Peck submitted payapp #1 but the change order paperwork is not signed yet. TEI asked them to modify their payapp so they can bill more quickly on this project.

08/25/11 – All work is complete except for metal pans on louvers. Boiler alarms not part of new boilers, Bill is working on a separate change order for that. Ready to closeout. Chris is writing sequences now.

09/28/11 – Pay App #1 was resubmitted by PH&B. Approved by TTC 3 copies were sent to Tony Matre on this date.

09/30/11 – We resolved Payapp #1 issues and asked PHB for closeout documents. Tony paid the $102,600 invoice already so we voided the later invoice and asked for a #2 for closeout. The change order was signed on May 13.

10/24/11 – Payapp 2 (labeled 3) arrive and was paid. Payapp 3 (retainer arrived and was held for closeout docs). TTC advised PHB the closeout documents are due before final payment can be made.

12/23/11 – This project will be archived for 2012.

02/22/12 – Chris reports all boilers are working great but there is still some programming left for him to change or update. This project is ready to be archived. All closeout and pay applications have been sent to Tony.

2020 – Boiler Replacement Phase 2 Read More »

Elevator Maintenance Bid

01/10/06 – TTC completed the escalator contract per Kerry’s comments and merged with previous comments. TA will hand delivery 4 copies to PBS today at 1:30 p.m.

01/09/06 – TTC delivered PBS elevator to PBS and bid tabs for their use.

01/06/06 – TTC delivered 230/800 contracts to Tony at the 237 WHT pre const mtg.

01/04/06 – Kerry returned electronic copy marked up. TTC to check over and approve.

12/21/05 – TTC returned electronic copy to Kerry for revisions.

12/12/05 – Contract revisions arrived from Kerry Dowling. TTC to make changes and send out ASAP.

12/09/05 – Kone called today to inquire about new contracts and cancelling old contracts for buildings they did not win under the new bid. Terry told them that new contracts should be forthcoming for official use by end of next week.

11/21/05 – TTC answered questions from the County about contracts. Everything appears to be in order.

11/17/05 – All contracts have been given to County for approval. TTC noted that there is no real need to have a supplementary conditions with the project manual as that is all outlined in the maintenance contract and we don’t use AIA contracts with this type of bid.

11/16/05 – TTC finished the elevator contracts for 230, 800 & PBS and sent them to Joe and Tony for distribution. This time, we coordinated issues like termination clauses, contract amounts with the combined bid savings and decided to split the savings 50/50 between the PBS and Facilities.

11/03/05 – After an initial scare that Addendum 01 did not get posted, Gina realized that the bid doesn’t open until 11/08 and therefore Addendum 01 is posted to demandstar and already has been sent from Ohio Blue.

11/01/05 – TTC is writing the Add01 for escalator project. This job should open next Tuesday. The SOSS has been signed for the escalator change order part of the job.

10/25/05 – Abell/Irvine called today to say that their office has been on Colerain Avenue since 1986. They have got their questionnaire answered and turned in with their bid. TTC ask Purchasing to fax a copy of it over to ThermalTech for review. TTC told everyone that the bid spec stated up to 5 buildings with 5 years experience. Tony called and discussed with TTC the new elevator contracts.

10/24/05 – Bids were opened. Fujitec did not bid the job. Kone didn’t their bid bond, Schindler withdrew their bid after TK’s opening bid, ThyssenKrupp and Abel/Lincoln turned in appropriate bids. TTC contacted both vendors for qualifications. TK provided a fax with all the documentation today. I have not heard from A-L but their number turned out to be long distance so I don’t consider that a good thing.

10/18/05 – The escalator bids immediately went back out on the street because no bid against Kone. Joe and Terry set the new bid estimate based on past numbers for the work in an attempt to make sure Kone didn’t try to overbid as they may be the only one entering bids on this project.

10/14/05 – The final addendum was issued to the contractors that dealt with questions from the prebid and mostly insurance and indemnity. TTC incorporated answers from the HamCo prosecutors office and risk managers for those issues. Also there is concern that one of the vendors does not have a full time office in the City as required by the bid. They also have not met the 5 project requirement of the specifications. This will have to be followed up on in the interview process.

10/03/05 – This Wednesday is the prebid meeting. I will meet Tony and Mike at 230 at 10:30 a.m.

09/21/05 – Project Manual completed and sent out for public bid. Bid opening scheduled for Oct 19th. Prebid mtgs scheduled on Oct 5th per everyone’s attendance request. Project budget estimated at $650,000.

09/20/05 – TTC completed the bid manual and sent out for review. All comments came back, TTC incorporated them into the manual and sent back to Maureen for advertising dates and SBA %. TE will turn over to County on Wednesday for bidding.

08/31/05 – Tony emailed today to say that TE is to keep the original insurance requirements from the original bid.

08/30/05 – Finalizing the bid process. Insurance requirements for Kone are final question before setting up public bid forum. Waiting on word back from Todd Dalton at Kone and AKM.

07/18/05 – Meeting went great. TTC has some work to cleanup old bid. AKM to inform TTC about 2020 building. Kone had some verbiage changes to contract. TTC has to modify bid form for combination bids.

07/12/05 – TTC setup a meeting with Tony and the elevator vendor for Friday.

07/05/05 – Project manual built by Sam. TTC has to get new information from Kone on new testing requirements. TTC talked to Sam Kinman today at PBS while on a walkthrough at PBS and was told that October’s escalator work is going to be an additional $30k on top of the standard contract. TTC will talk to Kone about new scope and testing for this bid and project manual.

Elevator Maintenance Bid Read More »

ADAS – Due Diligence MEP Study

11/03/05 – TTC contacted THP for coordination and kickoff on this project. We will wait till they contact us to start working directly with Wes Miller at the site. According to Mike Stiles, the building could certainly use an electrical upgrade that could be upwards of $1mil in cost.

10/25/05 – TTC and Wes Miller setup a walk through today for Sam and Mike to gather info for the SOSS for this project.

10/24/05 – TTC contacted Wes Miller, THP and Diana Supe about finalizing the SOSS for this project. It appears to be much larger than originally thought. KLH has already visited the site and did a walk through with the Facility Director Wes Miller. TTC will re-contact and set up a field trip for TE to build the SOSS by Wednesday.

ADAS – Due Diligence MEP Study Read More »

Energy Manager Project

01/16/07 – TTC compiled new format energy report and sent to Tony & Ralph. After December bills come in, TEI will present year end Energy report for Tony and Ralph.

06/01/06 – TTC sent Governors Award Application out for review. Markups will be incorporated and sent out UPS on June 2, 2006 to ODOD.

05/22/06 – TTC and Tony discussed the Governor’s Award for Energy that is due on June 02, 2006.

05/18/06 – Talked to Compass Energy about being an authorized buying agent for Hamilton County. There are so many things I like about this approach. I typed up and email to Tony to outline his benefits. We are awaiting approval to move forward.

05/05/06 – Strategic is very interested in bidding County work but mostly PBS. TTC sent the indemnity clause to them that County always requires and they want a conference call on 05/16/06 to discuss Q&A.

04/05/06 – After a second conference call, Tony has requested a write up from TTC outlining the possible cost and savings for bidding our dereg electric. TTC shall get this complete in a week.

03/23/06 – TEI sent Tony & Ralph the CCAO Report for 2005 updated with all the latest numbers. TEI sent Tony & Ralph the 2005 Monthly Report through December with the final CCAO numbers included. Next on TTC’s agenda is to update the yearly master and then the 2006 report for CCAO gas cost.

03/20/06 – Terry requested the Nov/Dec CCAO bills again as the latest packet doesn’t have them. TTC also contacted the CCAO for the information and talked to Amanda and she said she would fax them down to TTC but as of 3:40 p.m. they have not arrived. TEI cannot reconcile 2005 gas without this information.

03/15/06 – Talked to Joe Ewing today about Electric Deregulation Bid for county. We setup a conference call next week to discuss possibilities. TTC reconciled the 2006 Cinergy Rate schedule with an actual JC bill for February. This is a very big accomplishment towards reconciling the bills each and every month.

02/27/06 – TTC has to sign up for energy conference in Columbus. TTC and AKM discussed today on phone. TTC will drive up on Wed morning.

02/16/06 – TTC delivered the final report to Tony Matre and Ralph for use a couple of weeks ago but made one final change to the pie chart today. TTC is now working on deregulated electric and updating the individual building charts for a meeting with the bldg managers.

12/28/05 – TTC entered all the 2005 Gas data and got it input into the main spreadsheet for the County. TTC also began answering the CEC questionnaire.

12/09/05 – TTC discovered a billing anomaly in the CCAO billing for FT rate. It is a question that TTC can’t explain. The CH burnertip price is about $2 higher than the rest of the buildings for the same gas (it is all FT from the CCAO). Tony and Terry called the CCAO about the situation and left a message for assistance.

12/02/05 – TTC received the Energy Report packet today from the County that we will use as a template for LCC and this year’s report.

09/27/05 – Tony called and Terry sent our all 2004 Utility Data to Tony for his use. We sent a PDF and and excel file.

09/21/05 – First pass at Energy Star application yielded a grade of 33 for the 230 building. Passing is 75. TTC reviewed all data that Sam put into website. We believe that although we have additional data for additional months, this only hurts the ES score. Sam is removing extra months. The new score was in the mid 40’s. TTC manual calculated the buildings kbuth/sf to be 64.5 which is still lower than required for an Energy Star rating. TE is learning as we go on the application process for this website.

09/20/05 – Sam is currently entering 2004 data for 230 East Ninth.

09/16/05 – Set up user account at Energy Star for Hamilton County. We will be entering data for 230 East 9th Street for qualifications.

07/20/05 – TTC and Tom Kennedy met with Tony Matre and Mike Florimonte to discuss a proactive approach to getting the 230 East Ninth building LEED-EB certified. TE is to put together a business plan to make this work for the County

07/20/05 – TTC received the Alliance To Save Energy rejection letter for our March 2005 submission on the IT rate at the Courthouse. TTC forwarded the letter to Tony Matre.

07/19/05 – TTC finished the electric utility reports up through June 2005 and distributed to the County. TTC will work on reconciling the gas utilities next.

07/13/05 – Tony sent the CCAO summary to TTC for inclusion in to the energy files.

06/03/05 – TTC submitted the 2005 Governor’s Award to the State of Ohio. PDF. TTC submitted all 2004 energy data to Ralph for reporting.

05/26/05 – Downtown Six Pack Cinergy bills should started to arrive today at ThermalTech. There is no need to continue to copy Cinergy bills for EM work. I know will receive all the bills I need to do the monthly tracking. This should save Pat and Donna some work each week. If by chance I am missing one or two, I can request those manually.

05/20/05 – TTC has spent the better part of 3 days re-writing the TE software to accept all the new Cinergy Market Generation Riders so that I can correctly calculate and reconcile the energy bills for 2005. I estimate 2 more days of work before they are approved for use.

05/10/05 – TTC picked up Energy Authorization letter and will request data from Bill Fleisnner.

04/27/05 – TTC requested a County release for new energy data and to be authorized for the e-clips program to see Cinergy bills online, plus receive duplicate bills for the main 6-pack of buildings. The County should provide this letter.

03/31/05 – TTC sent in “Stars in Energy Alliance Application” PDF

03/25/05 – TTC startup monthly charts showing electric and gas, usage and cost and plotted on column graphs. TTC synchronized data with Tony’s local disk.

02/25/05 – TTC completed all the 2004 Energy Pulse Data Input. Graphs printed for 6 pack buildings. I am started to reconcile data vs. pulse data. A lot of energy bills are missing from 2004 and I have to contact Cinergy to get the actual bills for comparison. That request should be made on Tuesday.

02/18/05 – TTC attended the 9th Annual Ohio Energy Conference in Columbus and tabulated the 2004 237 WHT Energy Data.

02/11/05 – TTC will be working from TE and attending the Ohio Energy Conference next week for 2 days.

02/10/05 – TE registered TTC for the Ohio Energy Conference today. See you in Columbus next week.

02/08/05 – TTC collected more bills and is having Laurie at TE re-organize the bills by year, building, then service for easier updating..

02/04/05 – TTC got 230 E9th electric input for 2004. Looks like building has started using more energy and more 24/7 hours. TTC pointed out on graph to AKM.

02/02/05 – All 2004 bills have been tabulated. TTC and AKM set a schedule of having Energy Star program applied for by May 2005, having LEED-EB applied for by May 2005 and having Deregulated Electric bid on street by May 01, 2005. Cinergy has provided ALL 2004 interval electric data in an email today.

01/28/05 – TTC organized bills collected from 2004 for water, gas and electric.

01/2 1/05 – TTC organized bills collected from 2004 for water, gas and electric.

01/14/05 – TTC created water spreadsheet for 237 WHT. There are unexplained phenomena that need further investigation.

01/07/05 – TTC requested data from all current registered Cinergy Suppliers for Deregulated Electricity for County Bidding Purposes.

Energy Manager Project Read More »

XPEDX – DUE DILIGENCE STUDY

05/21/07 – The team presented the both phases of the Due Diligence study and the BOE move in programming and cost to Jeff Alluto, Diana Supe, Kevin Maue and John Michel and Bill Stautberg today. We went over existing conditions and possible future costs if the BOE takes occupancy of the building. Phasing plans and cost were turned over to the owner for this report. MEP wise the building is in good shape and will work for this and future needs.

05/14/07 – TE has DK on site for mechanical HVAC testing. TEI visited the site last week to get more FPC, EC and PC information. Report is due for review this Friday with MD and partners.

04/27/07 – TE awaiting signed SOSS.

04/18/07 – TE got prices from one contractor to perform Due Diligence on the AHU’s units at the site for $1900. We have a couple of request still pending.

04/17/07 – TTC & TA visited the site with CRA and THP and County Officials to take pictures, look at equipment and assess the requirements to prepare the Due Diligence Report.

XPEDX – DUE DILIGENCE STUDY Read More »

BLACKOUT/VULNERABILITY STUDY

04/27/07 – The final report is going to be delivered to Hamilton County Facilities Department today, April 27, 2007.

04/20/07 – TE received word from Hamilton County Facilities and are currently working on the final report.

04/13/07 – TE awaiting word from Hamilton County Facilities to proceed with final report.

04/03/07 – TA turned over draft copy report to Mark Donnelly by hand for review.

03/30/07 – Project progressing as expected.

03/23/07 – Hillcrest and Patrol Hdqtrs are complete. 800 Broadway is scheduled for next week.

03/20/07 – Patrol Hdqtrs fieldwork is complete. Hillcrest is scheduled in the next couple of weeks. Whole project is scheduled to be completed by end of March 07

03/14/07 – Patrol Headquarters, 800 Broadway and Hillcrest Campus have been added to the list of buildings to be evaluated. Field work for Patrol Headquarters and 800 Broadway has been performed. Hillcrest will be completed next week.

02/28/07 – 5 out of 6 original buildings have the report completed and turned over the Hamilton County Facilities Department.

02/19/07 – TEI will wrap up this project. 3 buildings are left to complete. CH, CAB, River City, Coroner’s Office are complete.

02/02/07 – The write up is very nearly complete on this project. TA is hoping to finish today.

11/03/06 – Write up is progressing

09/29/06 – Field trip is scheduled for week of 10/02/06

09/22/06 – Field trip is scheduled for the week of 9/25

09/15/06 – 5 out of 6 buildings are complete. Working on 6th next week.

BLACKOUT/VULNERABILITY STUDY Read More »

2010 COST ESTIMATES

07/24/09 – The cost estimates were finished on Wed 07/22 but Bert found several that needed more work or were empty. We finished these today. TTC reviewed every project new and old for completeness. The LEED portion was difficult and I an not 100% sure the data will be totally usable by HamCo fo its 2010 needs but it is the first step towards getting greener buildings. The projects are complete. CRA will be printing manuals for the next 5 days.

06/23/09 – TTC reviewed the Rebuild America and ECM Screening Tool with Tim and issued the original cost and scope documents to the team for updating our scope items for the cost estimate project. I have found several projects that are duplicates and especially have some questions about the Hillcrest site where they appear to be repeated twice and maybe three times. Terry will call Bert to discuss.

06/19/09 – The SOSS is approved and we have begun visiting the buildings. Terry and Mike have been to the 250 WHT building. The remaining projects are being coordinate by several TE employees for field trips next week. For this project we will have Terry, Tim, Andy and Mike Folck performing mechanical estimates. Mike, Danny and George will be performing the electrical estimates. Today we had our internal TEI kickoff meeting and internal Archibus training for input.

2010 COST ESTIMATES Read More »

BOARD OF ELECTIONS Third Floor Renovation

10/16/08 – Bert reports the BOE is very happy and has given Facilities a kudos for the work.

08/22/08 – Permit is in County hands for IBI. Bert said city permit was also received.

08/08/08 – According to City Permit Tracker Website this project is APPROVED.

08/01/08 – TEI has submitted three drawings to IBI for permit for this project.

09/05/08 – Permit approved in August. TEI submitted final payment for permits so final inspection can be scheduled.

BOARD OF ELECTIONS Third Floor Renovation Read More »

FIRE ALARM & FIRE SUPPRESSION MAINTENANCE BIDS

02/02/10 – Cintas submitted paperwork for a change order cost to the JC work for 2010 based on building count inaccuracies. TEI may review? No word on Tony on what he needs.

12/31/09 – The only development aside from all contract being approved is that JCI will not agree to the contract published with the project. The Admin bldg is going to have to be inspected outside the scope of this project. TTC recommended Hamco take out a change order on SA Communale contract and get them to do the building for 2009. A separate agreement will have to be reached with one of our vendors to get the 2009 testing complete. Tony is working on final contracts.

09/11/09 – TTC sent final contracts to Tony for delivering to Kerry for review. We have 5 contracts on this job and everything is under budget. SA Communale got most of the buildings, Cintas, JCI and Simplex each got one of the buildings.

08/25/09 – Addendums 1-5 have been sent out and extended the bid to Sept 4. One company protested the bid and forced Addendum 5 and we published the actual service contract with the last addendum for their use.

07/29/09 – We have collected almost all of the building summary sheets for the project back from the building managers. TTC & DPC are working on the new spec, combined bid forms, etc for the large Addendum.

07/15/09 – Addendum 01 went out to bidders and extended the bid opening date to August 19th.

06/23/09 – Today was the first prebid meeting and it was less than stellar. The addendum on this project will be quite large and we have to get better equipment counts in all the buildings. The printouts that were provided do not have all the equipment the contractors want to see for an accurate bid. We will most likely extend the bid opening by one month, detail the scope of work better, combine the bids, rework the building summary sheets, take combined bids for better pricing, add an alternate for the five year required testing and add an alternate for the County workers to self perform all the weekly and monthly testing.

FIRE ALARM & FIRE SUPPRESSION MAINTENANCE BIDS Read More »

ELECTRICAL DEREGULATION 2009

01/28/10 – Talk to PBS & Tony. All paperwork should be in. There are some lingering questions about contract signee’s and interval meters at several locations. As these get solved to the satisfaction of DERS these accounts will be brought on line too.

12/31/09 – Contracts are being signed. Interval meters request have been sent out. TTC forwarded the emails to hamco directors for signature and suggested everyone accept option 2 where the cost $446 each of the interval meter be rolled into the monthly bills for 24 months. Bill Fleissner is our contact at DEO for this. There was significant conversation between Matre and Cannon about us believe the entire cost was under $1000 for interval meters. DERS indicated 11 accounts required them. TTC rebuffed that by providing interval data on 9 of those accounts. DEO came back with another 19 that required it because peak demands were over 100kw not 1000kw as TTC believed. In the end written documentation is clear that the threshold is 100kw. PBS has already signed and faxed their approval to DEO. Final contracts and insurance have been worked out between Kerry, Tim and DERS. TEI provided backup savings calcs for the groups approving DERS savings estimates at significantly lower numbers (DERS numbers include cost savings and cost avoidance savings as one lump number).

10/20/09 – We have about five vendors registered and we have extended the contract question phase. We are opening the project on Nov 19. We have no contract questions yet on this project.

09/22/09 – Tony and Terry discussed insurance requirements with Tim Grabenstein for this contract. TTC sent the final copy for review to Tim. TEi asked for comments back by Friday.

09/21/09 – Contract comments came back from Tony and Kerry. Jim and Terry merged them into a final contract. We received the ITB-92-09 for this project. TEi will issue the final documents for public distribution on Oct 1. Contract questions and comments will be due Oct 15th. Bids are due in November.

08/19/09 – We completed our meeting with the Prosecutor’s office RSM will write a preliminary contract. TEI will write the end. 6 certified suppliers will be invited. Ralph will present to the commissioners for their review. Ralph, Tony, Kerry and myself have agreed to the plan.

07/20/09 – TTC sent Tony a revised SOSS for bidding out electrical services for the County. Ralph also asked about the Voltage Guard hardware which TTC and NV replied that TEI was very weary of this technology. We are doing more investigation.

06/23/09 – The report is approved and we have presented the results to the Commissioners. There are a few projects for energy savings that we should pursue in this year.

ELECTRICAL DEREGULATION 2009 Read More »

Archibus Drawing Updates

6/18/10-Met with Jack Randle of In4 and Michelle Ray of Hamilton County Facilities Department to discuss In4 scope of work verses Architectural Partnership scope of work. First Floor of Alms and Doepke mentioned. Michelle to investigate status.

6/21/10- Received email from Bert Watts with attachment documenting building drawing red-marks for correction.

6/22/10- Verified with Bert Watts the First Floor of Alms and Doepke is to be added to list of drawing corrections.

6/23/10- Submitted SOSS to Bert Watts at monthly Partner Meeting.

6/29/10- Approved SOSS delivered to GBBN.

7/02/10- Drawing updates completed and reported to Bert Watts.

Archibus Drawing Updates Read More »

2011 Project Request Estimating

4/26/10- Bert Watts discussed Estimating Project at Monthly Partner Meeting

5/8/10- Bert Watts email with attachments listing Partner and Project Manager Project List received.

5/12/10- GBBN received estimates for services from Mike Strine at Pinnacle Engineering for Asbestos Abatement Services.

5/13/10- GBBN submitted SOSS to Bert Watts.

6/23/10- Met with Walt Heckel of THP to coordinate all projects involving “All Partners”.

6/23/10- Conference call with Susan Barrett of IPM to discuss Communications Building Projects estimated earlier by IPM.

6/24/10- GBBN submits proposal requests to vendors for printing and assembly of project binders.

7/01/10- GBBN met with Bud Wells at Parkhaus Garage to discuss vegetative roof project request

7/02/10- IPM/GBBN visited Communications Center to discuss two project requests.

7/03/10- GBBN visited 2020 Auburn to discuss and document two project requests.

7/18/10- QCR delivers final binder tab revisions to GBBN to allow for final binder assembly.

7/19/10- Deliver project request binders (9 sets) to Bert Watts at the Courthouse.

7/20/10- Record set of Binders delivered to MEP Partner TEI.

7/22/10- Bert Watts delivers revisions to Binder Summaries for GBBN to insert into sets for partners.

7/23/10- Record set of Binders delivered to structural Partner THP.

7/27/10- Bert indicated the binders are to be slightly realigned from GBBN’s submission. Bert will take the 9th set of binders and realign them for GBBN’s reference. GBBN’s current office copy set of binders will be delivered to IPM for their records.

7/29/10- GBBN to received 9th set of binders from Bert Watts at the monthly partnering meeting.

2011 Project Request Estimating Read More »

Workforce Investment Board Vestibule Renovations

Current Comments (5/26/2010)

Project complete. Working on closeout documentation. CRA completing work.

Past Comments

Masonry repair work in progress.

Vestibule removed and new vestibule under construction.

New piers anticipated next week.(2/24/10)
Contractor completed demolition of vestibule.(2/24/10)
Sink Hole investigation:
Dug test well to footings and no fill below footing.
Pumped 5 yards of flash fill into void.
Plan to complete second test well on adjacent wall.
All phases of work approved.
THP subconsultant to CR Architects.

Workforce Investment Board Vestibule Renovations Read More »

2012 Project Cost Estimates

06/27/11 – Project 1208 was updated. Barth already had the cost separated as Bert wanted.

06/24/11 – Project estimates are complete. We are currently putting final touches of the estimates for this year.

05/24/11 -started field work on most estimates. Several have been input. Added one based on field work.

04/27/11 – We will be kickoff off this project next Monday and doing the work in May 2011.

2012 Project Cost Estimates Read More »

Emergency Generator PM Bid

06/29/11 – Tony reported today that the contract is approved.

05/03/11 – ThermalTech turned over final paperwork to Blaine for contract writing.

04/27/11 – Engineer’s office is writing a one year contract, Comm Center asked me to looked at three year bids and Tony asked me to write a contract for five years for the Facility buildings.

03/30/11 – Bids are due Thursday at 11am. TTC will attend. Three Addendums have been sent out on this job. We are taking prices on base bid, alternate and unit prices.

02/25/11 – Project is out for bidding. Prebid Mar 11, Bid Opening Mar 24. Note: TTC has to fix bid form for more clarity on bid day.

02/22/10 – Tony and Mike have approved the project manual and TEI will be sending to Jill Williams for bidding on Friday Feb 25.

Emergency Generator PM Bid Read More »

ENERGY MANAGER 2011

08/25/11 – Ameresco work is in final stages for contract negotiations. More controls meetings are schedule. Ameresco is presenting final report early Sept.

07/29/11 – 10 color copies of the final report have been mailed to Ralph per his request. The 2010 Report is complete.

07/07/11 – Energy Star bills have been entered for 230, Admin, and 800 Broadway. Field trips were scheduled for 230 and Admin, but have to be moved back to July 26 to coordinate with Florimonte vacation.

06/24/11 – Ralph said that he is sending Jeff’s questions over for final changes.

05/04/11 – Deliver 2 hard copies to Tony & Ralph today. Ralph said that if Jeff Aluotto approves this report, we can print these in color and be done. Also for 2011 report, he would like Hillcrest added, 237 WHT removed and the water data expanded.

04/26/11 – Delivered the final report to Ralph for 2010 including water from 2009 and 2010 completed for all major buildings. In 2011 we will add water for the remaining buildings and try to back date that information to 2007. We are trying to update the Energy Watchdog website before the final import at the end of May. It is nice to report that we saved over $1,000,000 in 2010 on our 3 major energy conservation measures.

03/30/11 – TTC finished inputting water bills. Thursday Amy will integrate into the report. Friday, Terry will finish the report.

03/14/11 – Duke has confirmed that ThermalTech has correctly included all the Administration Bldg electric into the Energy Star website. With this information, we are going to move forward with Estar approval.

03/01/11 – TTC has to add the deregulated electricity calcs to the report.

02/22/11 – TTC gave Ralph and Tony their final copy to review. Comments are back and TTC will finalize to give to Ralph for review by EOB on Friday.

01/24/11 – Folck has entered all bills that have been received. Terry and Amy are starting the Energy Report this week. Hopefully to be completed early February.

09/29/10 – All bills ThermalTech receives have been input into Watchdog. Next week have to do the bills kept at the CH.

07/28/10 – We are working on the new HamCo RFP with a couple of ESCO. RFP’s are due Aug 16.

05/26/10 – We received the 237 bills. Folck will input them. We will then generate the April bill.

05/06/10 – We modified Energy Watchdog to allow us to start entering electric commodity for Hamilton County ins 2010. Folck will enter all bills to date starting this afternoon.

04/26/10 – We delivered 10 copies of the final report to Ralph last Thursday. We delivered an updated electronic copy with the years of each project added to the Appendix today per Ralph’s request. We will continue to update bills in Energy Watchdog.

03/22/10 – Ralph and Tony have returned the Energy Report with comments. TTC will compile the final report. All previous reports uploaded to web.

03/05/10 – ThermalTech sent the final report to Ralph and Tony for commenting. TEi will compile the final report when comments are returned.

02/24/10 – Attended the 14th Annual Ohio Energy Conference with Tony & Ralph. Got the Energy Report about 50% complete. We are adding new buildings this year which means fixing the baseline model from 1997 and forward. It is harder than expected and taking longer.

02/22/10 – We have collected all utility data for 2009 and input into our worksheets

02/04/10 – Energy Watchdog data is input for 2009 for all buildings except for missing CCAO bills for Courthouse. We are working on the 2009 report and trying to finalize all the bills.

01/28/10 – Terry and Amy will be updating the report in Feb 2010. Andy is putting in the Watchdog data and Energy Star data this week.

12/31/09 – More bills are being input. The energy watchdog website should be up to date by mid January.

09/22/09 – Some bills are missing. TTC contacted Tony about Coroner’s gas bills. Jackson called about Coroner’s office water usage. TTC emailed the 2010 cost estimate report and explained the cost and program to reduce water usage.

08/19/09 – We completed our meeting with the Prosecutor’s office RSM will write a preliminary contract. TEI will write the end. 6 certified suppliers will be invited. Ralph will present to the commissioners for their review. Ralph, Tony, Kerry and myself have agreed to the plan.

07/20/09 – TTC sent Tony a revised SOSS for bidding out electrical services for the County. Ralph also asked about the Voltage Guard hardware which TTC and NV replied that TEI was very weary of this technology. We are doing more investigation.

06/23/09 – The report is approved and we have presented the results to the Commissioners. There are a few projects for energy savings that we should pursue in this year.

05/22/09 – The final report was turned over to the commissioners and we attended the commissioner meeting on 05/18. Mike Folck is updating all the water bills from 2009 and 2009. All data has been entered into Energy Watchdog through April 2008. We are not updating our monthly sheets until next year.

04/05/09 – The report is ready for TTC to review. I will get this done this week. I emailed Ralph & Tony about working with Ameresco on the 2009 energy projects.

01/26/09 – TTC & MAF finished the ECM Summary table and sent to Ralph Linne & Tony Matre. Ralph forwarded it to Jeff Aluotto for use. We are awaiting and update on how to write the SOSS for the work.

ENERGY MANAGER 2011 Read More »

2012 Project Estimates

Current Comments (9/28/2011)
Past Comments

Project complete.

THP added 250 William Howard Taft assessment into Archibus.

June 6 THP updated Archibus entries for 1431 and 1432.

Project estimates completed and loading into Archibus June 3, 2011.

THP reviewing project estimates, deadline for data entry into Archibus is June 3.

May 5, 2011 SOSS approved.

THP developing SOSS.

March 31, 2011 requested SOSS to complete 2012 project estimates.

2012 Project Estimates Read More »

2012 Project Request Estimating

03/31/11- Kick-off Meeting with Bert Watts during regular monthly Partnering Meeting. Tabulation Lists to be issued to all partners.

04/28/11- SOSS delivered to Bert Watts at monthly partnering meeting.

05/16/11- Met with Scott Lemond of ARC to discuss printing schedule and deliverables.

05/12/11- GBBN and IPM visited with Greg Smorey of the County Engineer’s Office to discuss the CAB 8th Floor Phase 2 Renovations.

05/18/11- Met with Greg Smorey of the County Engineers Office to review scope of project request for the Phase 2 renovation of the 8th floor not renovated in Phase 1.

05/31/11- Meeting with Greg Gelhaussen of the County Engineer’s Office at Ripple Road Engineer’s Garage.

06/14/11- All project Request Estimating is closed and completed.

06/23/11- Bert Watts email indicating three Project Requests have been eliminated.

06/27/11- Bert Watts email indicating one additional Project Request has been eliminated.

06/30/11- Deadline for all consultants to complete any requested revisions to Project Requests.

07/05/11- Delivery of electronic files and lists of projects to ARC printing

07/27/11- Binders received from ARC printing. Bert Watts accepts delivery from GBBN

07/29/11- GBBN delivers and installs corrected spline and cover slipsheets.

08/05/11- GBBN delivers partner sets of binders to THP and IPM.

08/25/11- GBBN delivers partner set of binders to TEI and CD’s of 2011 and 2012 to all partners.

2012 Project Request Estimating Read More »

2011 General Services – GBBN

01/14/11-SOSS submitted.

01/21/11- Bert Watts forwarded the new Contractor Safety and Health Specification section that is to be included in all future HCFD project manuals.

01/24/11-SOSS signed by BOCC and issued to GBBN along with Purchase Order.

01/25/11- Modified Standard Bidding Documents to indicate Christian Sigman as Interim County Administrator.

01/27/10-Attended HCFD Partnership monthly partner meeting.

01/27/11- GBBN forwarded to the other Partners the revised Master Specification Table of Contents and Legal Wrap showing the inclusion of the new Contractor Safety and Health specification section.

02/04/11- The meeting with Amy Hoh to kick-off a new project to modify the existing office partitions was cancelled.

02/14/11-Kick-off meeting with Sean Winfield of CAGIS to initiate an estimate to enlarge the CAB 10th Floor Conference Room.

02/15/11- Bert Watts agreed to perform the CAGIS work under this contract in lieu of a SOSS.

02/18/11- Drawings and estimate for CAGIS project sent to Bert Watts.

02/24/11- Attended the regularly schedule Partnering meeting at the Courthouse.

03/12/11- Met with Bert Watts to review the as-built conditions at Parkhaus Retail spaces. GBBN took measurements and photographs of space

03/15/11- GBBN sent as-builts to Bert Watts for review. Additional MEP input to be performed by GBBN due to lack of involvem,ent by ThermalTech.

03/25/11- Meeting with GBBN, ThermalTech and Duke Energy to discuss potential energy savings and partnering programs.

03/31/11- Attended the regularly schedule Partnering meeting at the Courthouse.

04/28/11- Attended the regularly schedule Partnering meeting at the Courthouse.

05/11/11- Interior Project Management performed background checks at the Justice Center. GBBN delivers results to Diana Supe.

05/12/11- GBBN staff performed background checks at Justice Center. GBBN delivered results to Diana Supe.

05/26/11- Attended the regularly schedule Partnering meeting at the Courthouse.

06/23/11- Corrections for new County Administrator made to standard front-end specifications.

06/30/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated after Partnering Meeting.

07/06/11- Meeting with ThermalTech to review Courthouse Courtroom Ceilings for redesign of the soffits and ceilings with Tony Matre.

07/29/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

08/25/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

09/29/11- Attended the regularly schedule Partnering meeting at the Courthouse.

– Website updated before Partnering Meeting.

2011 General Services – GBBN Read More »

2013 Project Cost Estimates

06/06/12 THP submitted SOSS.

06/07/12 SOSS Executed.

06/29/12 THP updated Archibus with project estimates for 1469 and 1471. THP, TTE, and GBBN working on estimate for Revit modeling (1467).

09/17/12 – TTC checked in with Partners to ensure that website is updated with final cost for Bert and it was agreed that we had all of our consultant time entered to do the ThermalTech provided 3D modeling presented at Partner meeting in July with THP and GBBN support for building frame structures done at base level.

09/06/12- GBBN meets with Tremco Roofing on site to finalize the remaining roofs that require restoration or replacement. This is a result of the Project Request Estimate that was cancelled due to inaccurate roof designations for estimating.

2013 Project Cost Estimates Read More »

2012 General Services – GBBN

12/14/12 – SOSS submitted.

12/23/1 1- Signed SOSS returned by Bert Watts to GBBN.

01/26/12 -Attended HCFD Partnership monthly partner meeting.

02/23/12 – Attended HCFD Partnership monthly partner meeting.

03/29/12 – Attended HCFD Partnership monthly partner meeting.

04/26/12 – Attended HCFD Partnership monthly partner meeting.

05/16/12 – Bert Watts requests GBBN investigate CAB 6th Floor security upgrade project.

05/17/12 – BOCC CAB-6th Floor Security Modification estimate presented to Bert Watts.

05/31/12 – Attended HCFD Partnership monthly partner meeting.

05/23/12 – Bert Watts forwards the list and schedule for the 2012 CIP projects.

05/29/12 – Bert Watts sends letter of Critical Project SOSS requests.

05/16/12 – Bert Watts requests GBBN investigate CAB 6th Floor security upgrade project.

06/28/12 – GBBN attends monthly partnering meeting.

07/26/12 – GBBN attends monthly partnering meeting.

08/30/12 -GBBN attends monthly partnering meeting and performs website updates.

09/23/12- Bill Scholl of 2020 contacts GBBN about flooring replacement information. GBBN suggests contacting Spectra Flooring for State Term options.

09/27/12- GBBN attends monthly partnering meeting.

2012 General Services – GBBN Read More »

2012 General Services – THP

LEED Partner: THP
Current Status: SOSS
SOSS: F32
Contract Date:N/A

Status: N/A

As-built:

Status:

03/29/12 THP completed initial review the book case load assessment on the 9th floor in the Administration building. Initial assessment was inconclusive; either drawings are needed or testing is required.

THP Staff submitted information to Sheriff on January 30, 2012. Sheriff’s office noted background check can take six to eight weeks.

SOSS submitted; waiting on approval.

04/25/12 – THP working Administrative building load assessment field work to be scheduled with anticipated answer by mid-May. Drawings do not exist, so THP is complete a field survey and tests.

4/30/12 THP provided summary letter of Administrative Building load assessment to Bert Watts.

5/23/12 County provided Capital project list with proposed schedules. THP agreed with the proposed schedule.

5/29/12 County requested SOSS for the following projects: Memorial Hall, 800 BW Roof, and 250 WHT windows and concrete repair. SOSS due June 1, 2012.

2012 General Services – THP Read More »

2012 General Services – TEI

09/17/12 -Joann Cramer sent a new PW packet without the Terrorist statement included. TTC will udpate and distribute.

09/26/12 – SOSS-F056 Approved. TTC received, reviewed, updated and sent out the revised Prevailing Wage packet for Hamilton County Purchasing. Several edits were made by TTC. TTC updated the website for the new design with all buildings in facilities, black bar titles and updated projects for use and unloacked all building files for others to work on.

2012 General Services – TEI Read More »

Master Space Plan

Partner: GBBN

Status: Inactive

Status:

04/12/10- An email from Bert Watts requested a Kick-off meeting with Bud Wells in Courthouse B-90. First Phase of three to be performed in2010 requiring SOSS submittal.

04/15/10- Kick-off Meeting held with Bud Wells and Bert Watts. Handouts included Survey Form, Project Activity Timeline, Charter for Space Utilization Study and Buildings to be incorporated into study.

04/27/10- Clarification emails from Bud Wells and Bert Watts answered questions related to SOSS.

04/28/10- SOSS to be submitted to Bert Watts at Monthly Partnering Meeting.

05/21/10- Signed and Approved SOSS returned. Email from Bert Watts indicates schedule is to commence 6/24/10- Archibus Drawings to be updated are sent to GBBN from Bert Watts. Progress is on hold until In4 completes all Archibus polyline revisions and Michelle Ray completes all reviews.

08/04/10- Attended kick-off meeting to change this SOSS to another masterplan for the 237 Internalization study.

Master Space Plan Read More »

Master Plan Internalization Study

Partner: GBBN

Status: Inactive

Status:

08/04/10- Attended Kick-off meeting with Ralph Linne and Diana Supe.

08/18/10- Internal Kick-off meeting with Keven Speece, Thomas Rottinghuas, Jack Herbet Ralph Linne and Diana Supe along with Craig Landers and KEvn Maue of DDS.

08/30/10- Meeting with Ralph Linne and Diana Supe to discuss changes to the scope of this project. Project will now contain five options for relocation.

08/31/10- Met with Tony Matre and Bill Scholl at 237 WHT to walk the entire building and field verify the existing drawings.

09/01/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to discuss all the various options, including those generated by GBBN, and decision affecting data to be considered.

09/01/10- Meeting with Craig Landers and Kevin Maue of DDS to discuss programming issues and schemes for possible relocation to 237 WHT for their existing employees in lease facitlities.

09/09/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to discuss variations in options to be considered including possible tenants into 237 WHT.

09/17/10- GBBN met with Ralph Linne and Diana Supe to restructure the options to be investigated for the study. A report was requested to summarize the options and all data to be considered for the approval of the options to be developed further.

10/25/10- Kick-off Meeting with Ralph Linne and Diana Supe. SOSS requested for additional Options for Jeff Alutto to review for Masterplanning Studies.

11/03/10- Meeting with Jeff Alutto, Ralph Linne and Diana Supe to review report and options documented in Partner study.

Master Plan Internalization Study Read More »

Scroll to Top