Hamilton County Facilities

Archived Projects

Archived Projects

230 – Ninth Floor Microfiche Project

03/14/06 – Bill Scholl and Mike Florimonte have both reported that the systems are working great and permits have been approved. This project is being archived at the end of this week.

01/10/06 – HVAC has work above Julie area’s almost complete. They have scheduled an HVAC inspection with Steve Ossege in the coming days. Exhaust was hard to get routed but they are almost complete.

12/28/05 – The microfiche permit was picked up and emailed down to the County approved for use. TE paid and will reimburse the cost to the County.

12/14/05 – TTC setup a meeting for THP to review the space ceiling construction to approve the ductwork hanging method on this job for 12/15. Aaron Bennett will be contacting Mike Florimonte for access to the building. MF reported that the piping, boxes and louvers are nearly installed so far.

12/09/05 – TTC applied for the permit today at the City. The permit number is 2005P09839. It cost $75 to the application fee today and the remainder will be paid when we pick up the permit. All of this cost is a reimbursable cost to the owner on this project for this work.12/02/05 – County trades can’t put the ductwork in as designed on the plans. MF is going to inspect the above ceiling layout and call TTC with details. TTC will stop by the building and give direction as to the best way to proceed to finish the job. TTC informed Tony of the plan. Terry contacted THP by email to verify ductwork loading won’t overstress the ceiling arrangement.

12/05/05 – Terry meet HVAC trades on site to discuss ductwork routing and relocating light fixtures on this job. It was decided the best and easiest way to fit the ductwork into the room was to rotate the lights 90 degrees and remove the remaining light that is interfering with the light fixture. Carpenters will have to do some ceiling work to patch and paint the areas that are affected by the ductwork and fan supports.

11/29/05 – HVAC called with questions about moving the VAV box in Julie’s office because it was interfering with new ductwork. TE said this was fine. HVAC called with a question about framing the fire dampers in one big angle frame and TTC said this was fine also. In email correspondences today, we believe all issues are up to date and the work in on track.

11/21/05 – TE and the County met at the site to discuss Sam’s HVAC design and coordinate with the tenant and trades for making this work out. Everyone was in agreement that if we could bring both ducts into one corner and just create a matching column in Linda’s office that would be fine. The people in attendance were Mark Perry, Tony Matre, TTC, SRB, MS, Dave S, Bill S, Jim E, Ernie, Mike F, Paul and Jerry.

11/16/05 – TTC and Tony discussed the bidding out of this project and the method in which the money and trades would do the work on this project. Wayne would like more controls11/15/05 – Review drawings were sent to the County today. TE would like to get comments back about this job as the County’s convenience.

11/10/05 – Wayne called and said that the draft design is OK and to proceed with a permit set of drawings, so trades can do the work. He will also contact TE when he has set up a Archibus job number, so we can enter a cost estimate.

11/10/05 – Wayne called and said that he would like trades to do the work. He said that he would check with Mike Florimonte to see if draft design is OK. After final client approval, TE will then put together a drawing set for trades.

11/04/05 – TE sent Mike Florimonte a draft of the HVAC layout to see if Manager of that area is OK with design. Design included exposed ductwork in the Vault to avoid redoing the ceiling, to allow for concealed ductwork.

11/02/05 – TE is putting final design together. Sam and Mike will be making a field trip down to the building on Friday to set routing and check clearances.

10/13/05 – TE and CR met with the client to finalize building and design standards for this project. CR has to submit an SOSS. The equipment will be in the building in about 2 months for this job. TE must do the design immediately for bidding.

08/30/05 – TTC received installation manual from vendor in San Diego. TTC sent pdf to County for their use. Heat and Electrical requirements were provided by vendor. TTC got many other calls from salesmen at Anacomp who because ThermalTech was inquiring believe they were somehow being left out of the purchase loop of the equipment. TTC assured them that the County is in control of purchasing the unit and ThermalTech was only designing the room that the equipment when and if purchased would reside in.

08/25/05 – TTC contacted manufacturer today to collect engineering information on unit for installation including btuh rejection, power req’s, exhaust req’s and mfgr’s installation instructions. I had to leave a message with their main office.

08/22/05 – MF called to say that after talking with some people, the belief is that the vault walls are reinforced concrete and not just metal stud walls. TTC and MF talked about airflows in the room and the floor and TTC believes that the design should most likely be to add one separate VAV box for the microfiche machine and exhaust the entire room. The machine should most likely go into the vault area where the room can be separated from the general airflow of the space.

08/19/05 – TA & TTC met Tony on site for field work.

230 – Ninth Floor Microfiche Project Read More »

230 East 9th Street Electric Device Study

01/10/07 – This project is complete and archived on 01/10/07

08/18/06 – Drawings have been delivered to Hamilton County Facilities. There are no open issues on this project.

06/14/06 – Close-out meeting; no open issues. All work by Queen City has been completed. I will be working on getting the drawings completed within the next several weeks and send (3) full sized sets to Hamilton County Facilities (Attn: Bert Watts, Jim Eby, Mike Florimonte). Queen City presented (2) binders, each with copies of the old and new panel schedules. On the new panel schedules the items listed in bold have been verified; the items listed in normal type are transferred over from the old schedules. The binder also includes diagrams of the MCC’s and Switchgear. A CD was also provided which contains all of the new panel schedules in Excel format.

11/15/05 – Contracts have been submitted.

230 East 9th Street Electric Device Study Read More »

230 – Boiler Stack Study

Journal:

03/05/08 – TTC and Tony figured out the billing issues and TTC sent an email to Grady on how to bill for extra services. The actual project is complete. The County has to fix its own PO to pay Triton but TEI work is complete on this project.

01/25/08 – Tony and I talked today about closeout on this project. Grady is to bill the County the remaining balance as a change order to this job. I will write a change order to match the total amount owed to Triton on this job. The County has a PO invoicing issue on this job (JC bill to this PO).

11/16/07 – TTC talked to Mike F today about project status and sent AKM the following email:

The summer boiler flue temperatures are still no where near 310 F so the fix worked to make things better but we are still probably going to have condensation issues.

The winter boilers are on now and they are slightly better also but we are still not getting 310 F at the outlet of the boiler stack. I told Mike that we should re-smoke test the boiler stack just like we did at the start of the project to see if any drafts are still cooling the boiler stack down as the flue gasses go up.

Mike believes that Triton did a pretty good job buttoning everything on the boiler stack from the job that we bid out and the extra work that you had them do on T&M inside the building. We just aren’t getting as good as results as we would have liked.

The summer boiler is slightly over 2,000,000 btuh which means it would take 4 of the Knight boilers to replace it and meet the same load. We could do this if it was the only problem you still had. The large winter boilers are 5mil btuh so those cannot be replaced by these hot water boilers so we are still kind of faced with some of the same problems with temperatures that you have faced from the beginning in that the outlet temperature at the top of the boiler stack is under 310 F.

and told the County that when they were ready to take the next step to let ThermalTech know and we can help with the design or problem solving.

05/22/07 – Triton submitted their final payapp for the project. There is a $980- change order for the extra camera work. This increases the contract amount and TEI needs approval from the County to pay that. Please advise.

05/14/07 – TEI contacted Triton for closeout documents. Grady said they would send them in ASAP. TEI will return a video copy of the boiler stack video to Grady to closeout the project. TEI has been in contact with MF about the type of brick to replace in the chimney wall to maintain integrity and this would be solid lightweight concrete block according to Spencer at Cole Russell. This project is ready to archive. 12/04/06 – TTC questioned the use of the full allowance today ($5000) and requested an itemized breakdown from Triton for the work completed. The dwgs ask for the the wall to be built by the contractor but that has not been completed to date. The additional work that TEI is aware of is sealing the upper stack and the camera record of the interior. TEI asked for the requested change order to seal the outer stack to be taken from the allowance not as a change order.

11/30/06 – TTC asked about writing a change order to the project for Triton to do the stack sealant work. The project itself is complete. We are moving into the next phase for 2007 where we will address insulation the stack in some way to keep air from overcooling the inner shell. The County is going to open up the wall sections to allow Triton to patch the outer wall of the boiler stack. This can happen right away if the PO gets approved for Tony. TTC asked the County for an update today.

11/13/06 – A lot has happened since the last entry to which i will summarize. Triton has been on site and finished the work. A camera was dropped down between the stacks for a record of how they were built. We discovered that the outer shell had 3 large rectangles removed where spaces were welded to the inner stack. The stack was not support to the outside wall as originally intended. We believe these holes are contributing to the excessive draft up the stack causing a high cooling effect on the boiler flue gas. We instructed Triton to seal the top of the outer stack to the inner stack with a metal seal and put the breeching cover back on seal it air tight with caulk. In the basement Triton sealed the inner stack against the outer stack where the new stack enters the side of the old stack. They did this with steel plates and welds. The temperature sensor is installed and monitoring outlet temperatures and we can only see a 2-degree rise in temperature with the stack being sealed top and bottom. This is not surprising since the are three gaping holes in the outer stack wall on the 4th, 8th and 12th floors that may still be an escape route for air movement. As this is the first stage of the fix it plan being used for investigation as well, we are formulating the second stage now. We want Triton to patch the remaining three holes by change order if necessary. In step two we may try to fill the interstitial space between the stacks with concrete and create a permanent insulation space between the two stacks and this way when the inner stacks rusts out, the concrete stack will remain providing a permanent stack for a long time. We have to get a structural involved at that point to help check the loads on the building.

08/28/06 – We held a construction meeting to get a new handle on where the project stands and to review the R&P chimney stack report. Grady brought one copy of the report and Tony asked for 3 copies to be made and given to the County. The report has basically found that the stack is in FAIR condition. The stack was basically constructed in two different segments, the bottom 130 ft and the top 40 ft. In reviewing the original report from 2001 and the new report from 2006 there is considerable degradation from low temperature condensation and corrosion inside the stack. Photographic evidence was provided in the report to support this claim. The wall thicknesses have decreased and will continue to decrease and the new temperature outlet sensor installed in phase 1 of this project has further provided trending and data to prove that decent outlet temperatures at the boiler flue’s in the basement are significantly reduced in their upward travel to leave the building. Mike Florimonte provided a trend that showed summer boiler leaving temperatures of over 500 F but at the outlet of the stack temperatures were only 210 F. This is a condition that will cause low temperature corrosion. R&P is recommending a spray on coating to protect the interior of the stack. Triton and ThermalTech recommend further investigation into the over cooling effect on the boiler stack. For this much temperature loss to occur, we believe it must be related to the high velocity draft witnessed around the boiler stack at a previous field trip by TE. We have scheduled a Saturday visit with Triton to set off a smoke test inside the boiler stack. We want to witness the path of the released smoke and find the air path that is causing the stack losses. In essence the space between the inner stack and out stack should be dead air space. In addition, Triton will investigate the OA paths surrounding the boiler stack to help ensure that no OA is subjected directly to the boiler stack space. Once this data is resolved, we can isolate the boiler room from the chimney stack and address other “sealant” issues with the new and old breeching. We are scheduled to meet on Sat, Sept 9th. MF will alert the building occupants. AKM requested a synopsis of or plan of attack.

06/16/06 – R&P Industrial Chimney showed up on site. At 2:17 they completed their fieldwork and reported the seems in the stack appear to be the worst off. The took a disposable camera and ultrasonic machine into the stack with them. TTC asked for them to call with a report after they packed up.

05/22/06 – Boiler stack inspection still set for June 19th. Grady is checking on controls and trending.

04/06/06 – Mike called today about getting study complete and temperature sensor in place. Grady replied that the inspection could be the middle of May. The County will need this inspection to be completed either after hours or on the weekend because of hot water reheat. TTC to review and try to find a holiday instead that may work better.

03/09/06 – Pre-construction Mtg was held and notes distributed.

01/17/06 – Wayne reported today that the Bid from Triton did not included a personal property tax statement or a ohio dept statement. TE to check and correct for Wayne.

12/13/05 – Contracts were returned for corrections. TE corrected, printed and returned to the County for submission to the commissioners.

12/01/05 – TTC found the original bids for the job (in sbu’s mailibox) and sent them on to Tony for his use. As soon as contract is approved we can have a pre-construction mtg and get the project moving.

11/08/05 – Tony authorized ThermalTech to write the contract for this work. TE will try to get it done in one day.

10/18/05 – All bids came in and contractors are calling for bid results. TTC gave to Tony and Mike on 10/20 for review. Bid Results – PDF

10/14/05 – No addendum had to be issued. Bids are due next week. TE has received a couple of “No Bids” on this project already.

09/29/05 – Final Project manuals have been created. IES information added for controls. Prebid is set for Oct 6 at 9:30 a.m. TE invited Peck, Triton, Process, Geiler, DK and Langdon to bid the project.

09/09/20/05 – TTC is reviewing Sam’s final drawing and project manual.

08/31/05 – MF reported that with their flow hood the outdoor access door when opened drew 1600 CFM with boiler make-up and exhaust running and 650 cfm with the MUA and EF off. This may contribute to extra cooling down of the boiler flue and TE is investigating welding the outer shell closed during our project. TTC cannot explain the huge draft of air up the shaft at all times

08/30/05 – TTC stopped by the site today to review an access door in the side of the building. There appears to be a huge draft from the outdoors into this access door and it apparently is going up the stack and exiting somewhere that in undetermined. This presents a problem with finalizing our design. We can still go about sealing the basement mechanical room as planned but after we are all done there may still be another step to isolating the inner/outer stacks when we are complete and re-measure the infiltration airflow. In talking with Mike, TE may give Mike the cutout for the future access door. If we cut the whole in the drywall now so we can investigate better how the inner and outer stacks are routed through the building. TTC needs to look at original report and talk to contractor about installation method. There are still unknowns about the original design that are affected an effective solution to this problem.

08/25/05 – TTC sent out final bid manual for review today to MF and AKM. Bid opening might be on 9-7-05.

07/18/05 – TE started the small project manual for bids today. TE has to create a new SOSS because the study used up the first SOSS but since so much of the design is already complete TE only wants to write the new SOSS for $2000 instead of the standard $3500 for bid and contract administration.

06/17/05 – TTC and MF discussed the report today and TTC recommended that we put a small packet together now to close up the air space around the stack. An incremental approach to fixing the problem is best. After the space is enclosed, the stack losses should be re-measured at various conditions to asses the new operating characteristics of the boiler plant. This should be done this year if possible. At the same time, a drywall access hole should be cut to inspect how stacks are anchored together. TE will wait for the County to advise.

06/16/05 – TE sent the final report to Tony and Mike for review and use. TE recommended closing off the bottom of the stack leading into the basement and re-creating a dead air space that can be used for isolation the temperature and creating a thermal barrier.

06/06/05 – TE had a meeting today to discuss recommendations. Our report will be out later this week and 2006 estimate will be estimated based on this report. We plan on discussing with Tony and Mike after Mark Miller sends final report to County. TTC and Mike discussed field findings from last week in an impromptu meeting at B-95 today.

05/24/05 – Mike called today and TTC told him that ThermalTech has not done any construction documents yet on this project and that might be due to the fact that we haven’t given Tony a final report on the condition of the stack (awaiting the re-evaluation from either HC Nutting or the other contractor that MF was going to call into survey the breeching) and TE has not provided a written report to Tony and Mike with recommendations about how to proceed. As MF and TTC discussed the situation though, we decided that if something is to be done this year before heating season, the design and SOSS must begin immediately. TTC will email AKM and ask about how to continue work on this project. TE still has $1172 left from the original SOSS that we do not need to used except to provide a written summary to AKM about our findings.

05/11/05 – TTC gave MF HC Nutting as contact for pipe thickness survey.

03/28/05 – TTC & MM met on site and went over boiler stack calcs and heat losses. Too much heat is being loss going up the stack. We need too look at insulating the stack to keep the heat higher throughout the path.

02/22/05 – TTC and MM reported that initial reports look like stack losses primarily are contributed to the low outlet temperature and condensation issues at the 230 building and not stack sizing or entrainment.

02/10/05 – TE received a signed SOSS and posted it to the website today.

02/01/05 – TTC & Mark Miller visited the site for field investigation and SOSS scope.

230 – Boiler Stack Study Read More »

250 WHT – Asbestos Study

Project Lead: GBBN

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sens list of buildings to be included in Asbestos Abatement Reporting.

02/06/12 – Pinnacle Engineering requested drawing files for the purpose of documenting findings.

02/07/12 – GBBN sent drawing files to Pinnacle Engineering in PDF form.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

01/26/13 – BRG confirms entry of ACM data into Archibus is completed.

01/28/13 – GBBN conducts spot review and confirms data entry is accurate.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

02/24/14 – GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/WebCentral is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14 – GBBN sends another email and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

8/29/14- Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications to finalize the remaining invoices to close out these projects.

250 WHT – Asbestos Study Read More »

250 WHT – Plumbing Division Upgrade

06/14/05 – Phasor turned in a new change order for Fire Alarm additional work at 250. The Change Order cost including all the additional inspections is $967.82. TE will approve and send to Diana for signing. Please return a signed copy to both ThermalTech and Phasor when complete.

06/08/05 – TTC sent final Reupert paperwork to Diana for complete project closeout. Noise issued on floor is being address by Mark Hardin.

05/11/05 – Sound issues arose from the toilet room and accompanying space being too quiet. GBBN made a field visit to investigate and the consultants gave recommendations about white noise or another exhaust fan. The County is to advise on how to proceed from here.

05/10/05 – TE emailed GBBN to advise that toilet exhaust on this project is connected to the main building toilet exhaust. If there is a problem have Tom check the main fan and if that doesn’t work, TE will measure the airflow and check the existing conditions contingent on a future request by the County.

05/02/05 – The building passed it fire alarm inspection this morning at 6:00 a.m. TTC, Jack Lamping, Darnell, Jim McFarland and Darryl Meadows were present and witnessed the test and the paperwork was signed. The City Inspector had issues with the existing system but did not hold up or not pass the test but these are issues, he wishes the County would fix because the system is technically not installed properly. Item (1) any smoke or pull device on the first floor reports as “Smoke & Pull Stations”. The inspector strongly urges that these two actuation devices be separated and report separately when in alarm. Item (2) when in alarm and the “Alarm Silence” button is pushed it disengage all the horns AND strobes on the first floor – this is against code as ONLY the horns should be disabled and the strobes should continue to flash until the system is RESET (it was shown many times during our testing periods that they are not wired properly). Item (3) They questioned the “fail-secure” status of the doors upstairs and downstairs. When the FA system is in alarm all the door holds release as they should and all the security access is disabled so that a key is required to enter the space. I confirmed with TA and MS that this is the correct operation for your building. The people inside can always egress out as there are strike bars or non locking door handles from the inside to the outside so none of that is required to change. Item (4) The first floor system is a “System Sentry” type system which was in place when Simplex received the second contract to renovate the second floor space. They did this by daisy chaining all the existing 4-wire devices through a ZAM (Zone Actuation Module) which is why they all report as the same device back at the Simplex panel. TE would recommend putting in a project right now that upgrades that existing system to 100% Simplex (which is a fully addressable system 4010 model). We estimate about a $23,700 project (30 devices @ $9000, 3000LF @ $9000, 6 ZAM’s @ $3000, Programming @ $1500, Permit and Testing @ $1200). Please advise.

04/28/05 -TE spent most of the day at the building trying to get the Simplex system working in conjunction with the System Sensor system. We tried many custom programs but in the end nothing worked perfectly. TTC has 3 ways to try to get system fixed this morning and will meet Simplex back on site to repair the system. (1) write a custom program that actually works, (2) replace the 4 smoke detectors with authentic Simplex devices, (3) add a UL listed manual reset to reset the 1st and Bsmt floors. TTC will keep DES up to date as we go through the day.

04/27/05 – The project failed the initial Fire Alarm test this morning. Not from device malfunction but the actual FA panel would not reset after receiving an alarm from a smoke head. The system was pre-tested using pull stations and reset fine on Tuesday. Because of this the City did not issue an approval. Phasor, TE and the County contacted Simplex for an emergency call into a technicians to repair or reprogram the main FA panel. Jack talked to Simplex and will be back on site as soon as they arrive today to work on the system to assist in figuring out what is going on and wrong. He believes that he was able to get the technician to understand what was happening and hopes to resolve the issue today. The inspectors agreed to come back this week to approve.

04/26/05 – Phasor bought two strobes locally and will install them today and have everything ready for tomorrow morning. Jack said it was a scramble but he found them and is ready to install. They will be ready for tomorrow’s test. At 2:48 p.m. they reported that everything is set for final FA inspection on Wed at 6:00 a.m.

04/19/05 – Final fire alarm test is scheduled for 04/27/05 at 6:00 a.m. Tom will be on hand from the County for FA issues. TE will attend as Owner’s Rep. Phasor will be EC. Copp stated that all egress issues are resolved and will be working fine for our final test.

04/15/05 – TE contacted Phasor about final completion and inspection by email to make sure everyone is ready for next week.

04/06/05 – TE and Phasor and County are coordinating final inspection details for April 25th. TE waiting on contract interior information from County before confirming

04/05/05 – Project Meeting today. Set new schedule for completion. JB Schmidt scheduled to be complete by April 15. Phasor to be work on 4/15 and 4/18-4/20. Final Inspections to be tentatively scheduled for 04/25/05. TE to contact Phasor for FA inspection coordination with JB. TE to contact Copp about schedule for plumbing space and general building space and to work on resolving software issues. County ES/Facilities to contact Sheriff’s Dept about Panic button for receptionist in ES.

03/25/05 – Reupert delivered some of the final paperwork with no payapp today. TE will contact them about this.

03/15/05 – Portions of the project have been on hold awaiting the replacement of drywall and water sealant. TE received final paperwork and O&M manuals including balance reports from Reupert. The manuals are not bound or copied. TE will copy and make sets for County use and turn them in at the end of the project with final paperwork and payapp from HVAC contractor.

01/31/05 – TE attended last Thursday’s Const Mtg. HVAC is complete. EC is nearly complete. PC is complete with working fixtures. Hot water reached the LAV in under 60 seconds. All fixtures appeared to drain properly. Security is nearly complete but Copp has some final work to do.

01/26/05 – TE faxed one copy and mailed three copies of the Affidavit of Release of Liens to Reupert.

01/24/05 – Jamie of Reupert called TE and indicated that she was preparing final document packet but did not know where to find the Affidavit of Release of Liens forms. TE to mail the Affidavit of Release of Liens to Reupert.

01/18/05 – TTC sent Reupert their punchlist item (balance report) and asked for their O&M’s.

12/27/04 – TTC stopped by the building to coordinate lighting layout with Jack Lamping. Some of the HVAC piping is too close to the ceiling grid and the deep parabolics don’t fit into the grid and below the ductwork and 3-way heating piping and valves. We remedied this situation by moving some lights over a grid space or 2. TTC has a copy of the new locations for as-built purposes. TTC believes the new layout will provide sufficient lighting levels and be a workable layout for the building occupants. The only outstanding issue with the lighting at this point is that the light nearest the column near the restroom can either be swapped out with a shallower fixture like the ones slated for the storage room and the lens be replaced with a paracube or (2) 2×2 fixtures can be used instead of (1) 2×4 fixture. The former would cost the project little or no money, the ladder may cost $200 – $300 out of the remaining allowance. We should have an a final answer later today.

12/20/04 – Ken Reupert out of the office, Jamie will have both of the Affidavit of Original or Subcontractors sent to ThermalTech today or tomorrow (12/21/04).

12/09/04 – Reupert revised Pay Applications 1 & 2 received in the mail. Voice message left for Ken Reupert to disregard earlier message and that the Pay Application will be held for the “Affidavit of Original or Subcontractor” form to be submitted.

12/09/04 – Reupert Pay Applications 1 & 2 Voided due to $600.00 allowance shown on application as a Change Order. Voice message left for Ken Reupert explaining that the Applications were incorrect and will need to be revised.

12/03/04 – TTC talked to Reupert today. All the above ceiling ductwork is complete at this point. The 3-way valves are all piped in. The controls on on schedule at this point. The GC will contact the MC when the diffusers and final connections are ready. The MC has to attach some angles around the fire dampers to meet code and should take of that work next week.

11/22/04 – Reupert called today to discuss the 3-way valves ordered on this project via the submittal change. TE instructed them to pipe the valves in as 3-way valves and use up to $1250 of the allowance for this work and to make the necessary scheduling changes to make this happen. Per our submittals to the MC and CC we changed the 2-way valves to 3-way because this building has constant speed pumps and to prevent dead heading the heating hot water system will require 3-way valves in most installs.

11/18/04 – Reupert called to ask for a size change in the return grill. TE approved a 24 x 12 return opening above the ceiling for this project. TE to verify on site at today’s meeting all their request

10/27/04 – Reupert submitted a $600 allowance request to rework the piping at the bulkhead pursuant to our last construction meeting. TE approved the request from the $2500 mechanical allowance for this project, new balance $1900.

Change order request in approved for security change order and is the amount is not being subtracted from the allowance. TEI issued a revised sketch that corrected the access controlled door locations.

10/21/04 – TE contacted Reupert about missing today’s construction mtg, making the next meeting for sure, submitting their schedule of values, change order pricing for relocating piping and VAV box submittals. Everything is in the works. Reupert is going to send us the schedule, the VAV boxes are already in their shop (we now have to approve them (don’t worry they will be fine)), they will begin working on the change order request.

10/13/04 – AIA Change Order for $1,854.46 mailed to Phasor

10/11/04 – The Plumbing Permit Number is: # 2004P07058.

10/08/04 – TEI to prepare electrical bulletin #1 for 1854.36

10/07/04 – GBBN provided the permit number for the project: The permit number is as follows: #2004P05650

10/05/04 – TEI received devices submittal via email from Phasor.

10/05/04 – DES confirmed that TE sent Lisa the stamped drawings for permit. TE sent them on Thursday 10/07/04.

09/29/04 – Jeanette provided a dimensioned drawing for HamCo plumbing to use for this project – TE reviewed and approved for use, TE to pickup plumbing fixtures from Bo for approval, TE to provide stamped drawings for permit use to Lisa, TE to coordinate revised security (Copp to upgrade entire building including 2 new doors) and TE to write change order for this work to Phasor, Reupert was not at meeting and TTC to confirm that Reupert will be at next meeting, TE requested that GBBN reschedule Oct 20 mtg as it conflicts with CH Archive mtg.

09/20/04 – Ben has asked TTC to coordinate water closet locations with Bo Blank.

09/14/04 – Copp is providing a price to upgrade the whole 250 building, this has to be coordinated through TE and Phasor since our electrical contractor has security money in their bid to do this work.

09/08/04 – Bo advised to remove sanitary so that Reupert can begin construction.

09/08/04 – Pre Construction Mtg completed.

09/03/04 – DES advised that contracts are approved. GBBN will setup pre-construction meeting.

09/28/04 – Lighting submittal approved 9/22/04

10/01/04 – Request for change order pricing from Reupert for Fire Damper

10/02/04 – Reupert gave a verbal price of $375 for the addition of a fire damper

250 WHT – Plumbing Division Upgrade Read More »

250 WHT – Electric Device Study

10/18/06 – Final close-out meeting was held on location. Queen City has completed all contracted work. I have the drawings and will have the information put into electronic format over the next few weeks. I also took the panel index binders. I will have all documents delivered at the same time.

09/19/06 – Construction meeting was held on location. All field work was to be completed by this afternoon. Dick Kuhn of Queen City will be in contact with me when he if finished with his circuit verification. When I have been contacted I will contact all necessary persons to set up the close-out meeting.

08/28/06 – Kick-off meeting held on location.

07/18/06 – Contracts have been submitted.

06/19/06 – Pre-bid meeting was held on location.

250 WHT – Electric Device Study Read More »

250 WHT – Security Camera Upgrade

7/31/08 – Bert reported that the project is finished and final paperwork has been received. Final payment is approved to the contractor. Broken camera has been fixed. Contractor is awaiting final payment.
07/30/08 – Project is complete. County has all final paperwork.
05/16/08 – Bert sent back changer order and payapp #3 signed by County.
05/02/08 – Stapleton has submitted all final paperwork and sent back a signed change order on this project. TEI has reviewed and approved all closeout documents on this project. They are being UPS to Bert Watts for closeout on this project. The change order has to be signed by the owner and copies sent back to TEI and Stapleton for our records.
03/06/08 – Stapleton and Copp have reached substantial completion. The translator has been installed. Remaining items on the job include: our punchlist (early next week), training for the county, programming at the sheriff’s office, Copp is going to replace one camera that is acting up.
02/08/08 – Stapleton sent the change order cost to TEI for the translator and TEI passed it along to Bert Watts for approval on this project. TEI updated the website with current CO and Allowance costs.
01/23/08 – TTC requested a const meeting for this project this Thursday or Friday.
01/22/08 – MAH met with Dick (Stapleton) and Paul (Copp) about the mounting of the exterior cameras. Copp will supply (3) corner mount brackets for $267 allowance. Stapleton will install camera mounts when they arrive (should arrive 1/23). Also discussed was the data port being included on same plate as existing phone jack in lobby, lobby camera location (NE corner and viewing doors), and location of exterior camera at rear entrance door (will be mounted on adjacent wall approximately 24″ above window to avoid washout from wallpack light fixture).
12/14/07 – Stapleton discovered that the holes in the pole bases are only 2-1/2″ and will not accommodate (3) 1″ conduits as the design calls for. Stapleton requests a $500 change order to install junction boxes in the pole bases to solve this problem. TEI agrees with this solution and the change order amount.
12/12/07 – MAH clarified for Stapleton that the control signal for the PTZ cameras was sent over the coax video cable so no additional control wiring is necessary. Also, siamese RG-59 wire with 18AWG power is acceptable for all interior and building mounted cameras. A separate coax and #12AWG power pair is required for the pole mounted cameras that is wet/direct sunlight rated. Copp Systems submittals are approved and should be sent back 12/13/07.
12/04/07 – Const Mtg #2 was held today and TEI distributed meeting minutes. Stapleton will be staring site work this Friday. Ken Edgell will advise the tenants of the 250 WHT building. Stapleton will be boring the light pole bases and conduit routes this weekend. TEI, Ken and Stapleton pick light pole locations in the field for this work.
11/29/07 – The pre construction meeting was held last week. GM typed up the meeting notes. Stapleton called with questions about submittals, dwgs and const mtg time. TEI setup another const mtg for next week with the owner and facilities. We will discuss the RFI’s about the lamp bases and base diameter. Bert sent out the list of approved employees for this project today which included Barnett, Ronald J., Eckart, Carl, Hammitt, Wayne, Leopald, Mike, Leopold, Douglas A., Stevens, Brian K. Terry Cannon emailed Stapleton to ask about Copp system background checks. Mike Huntwork approved all submittals with No Exceptions noted.
10/03/07 – TTC sent the contract for Stapleton to Bert today via City Dash with an allowance of $2500 added to the project. If acceptable, the County can begin the contract process. Stapleton won the bid with a bid of $90,586.00 + $2500 in allowance money. Our electrical plan review was approved on 09/11/2207 with an application # of CIC0703025. The contractor will now have to pay and pick this permit up when the job begins.
09/10/07 – TEI is submitting plans to IBI for plan review and permit # for this job. TEI will provide permit numbers to County for record keeping purposes when we are complete with this process. It will be the contractors responsibility to pick up and pay for the balance of the permit when one is assigned for this project.
08/27/07 – This project has been sent out for bid with hard copies to Mark Donnelly.
08/24/07 – TEI has been instructed to move forward with this project. This project is set to open for bid on 09/26/07. The pre-bid meeting has been set up for 09/11/07.
08/10/07 – A project review meeting was held at the 250 WHT building on Tuesday, August 7, 2007. Items discussed included camera locations and specifications, new light pole locations, access into building, and budget. TEI is awaiting word from the Hamilton County Facilities Department on when this project will go out to bid.
07/30/07 – The drawings and specs are completed. The package is to be sent out today. There will not be front end or ITB# for this project because construction has been postponed until next fiscal year. When TE is given the go ahead from the Hamilton County Facilities Department on this project they will put together the front end of the project manual and issue for bid at that time.
07/09/07 – TE is finalizing the design. Drawings will be turned over to Hamilton County Facilities Department when complete.
06/29/07 – At the monthly Partnering Meeting with Hamilton County it was decided that the money to perform this work would be budgeted for a 2008 project. TE was directed to complete the design and turn over the drawings to the Hamilton County Facilities Department.
06/22/07 – A new cost estimate was presented to Mark Donnelly. TE is awaiting response on whether or not to proceed with the new latest layout and additional cost.
06/15/07 – Project moving along as expected. Changes per meeting with Mark Donnelly are being incorporated and a new cost estimated is being generated.
06/08/07 – New parking lot lighting and camera layouts were presented to Mark Donnelly along with a cost estimate. TE is moving forward with this project. There are a few slight adjustments; number of new poles, location of new poles, and number of cameras. These modifications will be made and presented again to Mark Donnelly.
06/01/07 – TE will present Mark Donnelly with new parking lot lighting and camera layouts early next week. A cost estimate will be included with the new layouts.
05/22/07 – Project review meeting was held today. Various points were discussed as described in the meeting notes. TE is laying out different schemes of possible lighting and camera layouts with the points discussed in the meeting kept in mind.
05/21/07 – Meeting to review current status is schedule for May 22, 2007 with Mark Donnelly.
04/27/07 – Estimates are complete and will be forwarded to Hamilton County Facilities Department today, April 27, 2007.
04/20/07 – Estimates are near completion and should be turned over the Hamilton County Facilities Department by the end of next week, April 27 2007.
04/13/07 – TE is working on the estimates to be turned over to Hamilton County Facilities Department.
04/06/07 – Review meeting was held today, April 6, 2007. TE is to provide pricing on 2 systems and then await owner’s selection.
03/30/07 – Preliminary layouts have been presented to Hamilton County Facilities Department for review. Review meeting will be scheduled for the first week of April 2007.
03/20/07 – TE met with camera vendor. Parking lot lighting and camera layout is currently underway.
03/20/07 – Design is continuing. Parking lot lighting is under design.
03/14/07 – NR created project journal and filled in back data from previous meetings.02/14/07 – Proposed parking lot lighting and camera locations has been completed by TE. This information is awaiting review by Hamilton County Facilities Department.
02/28/07 – Foot candle readings were taken by Phil Lambing in the evening of this date.
02/27/07 – Kick-off meeting held on location by Phil Lambing of ThermalTech. Attendees include Mark Hardin and Bill Scholl of Hamilton County Facilities Department. IT was decided that TE will collect foot candle readings in the parking lot to get a good idea of what will be needed to ensure personnel safety

250 WHT – Security Camera Upgrade Read More »

250 WHT – Monitoring Room Upgrade

Current Status: Construction

03/30/11 – This project is complete. TEI finalized the HVAC permit and paid for it at the City of Cincinnati so EDI can close out this project.

03/02/11 – TTC checked on braided hose install by EDI on humidifier. Brady said they are working on this. TTC review wall mounted installation and there is no good way to clean this install up with a simple product. TTC asked EDI to closeout project and send in final payapp.

12/30/11 – TEI released the punchlist on the project today.

12/15/10 – EDI on board and working on project towards punchlist completion

250 WHT – Monitoring Room Upgrade Read More »

250 WHT – Phone Switch Room

Current Status: Closeout

Contract Date: xx/xx/11

Closeout Status: Requested

06/07/11 – Kick-off Meeting at 250 WHT Building. The existing phone switch room at 237 WHT was also visited.

06/15/11 – SOSS delivered to Bert Watts.

06/23/11 – Signed SOSS received with associated Purchase Order.

06/28/11 – Design has begun. There are concerns about the fire suppression on this project already. Wet sprinkler exist in the storage rooms and IT wants to remove them. TEI says that the city would have to approval such a removal. There are discussions about Alternate cost for a clean agent fire suppression system for this space but TEI is also recommending an alternate to that to provide a pre-action system if we have to keep the wet sprinklers.

07/06/11 – Kick-off Meeting with Mike Barth and Mike Folck of ThermalTech. ThermalTech and GBBN held coordination meeting.

07/11/11 – TTC has suggested asking the city if we can remove the spinklers that existing in the storage rooms now that are limited area sprinklers.

07/21/11 – ThermalTech, HamCo facilities, building personnel, and HamCo IT staff met to review progress drawings. HamCo IT group modified plans to change the location of phone racks, phone switches, voice mail server, and associated equipment. The location of the condensing unit was determined and the routing of the line set was planned thru the existing elevator shaft. Several alternates were discussed including a clean agent fire suppression system and removal of the existing freight elevator.

07/29/11 – GBBN found a transfer grille that ThermalTech will have to address in the clean agent alternate before bidding.

08/05/11 – HamCo facilities and HamCo IT review comments incorporated into design. Drawings and specs issued for bidding including clean agent fire suppression and elevator removal alternates.

08/08 /11 -Bid documents released to Purchasing and ARC Reproductions.

08/18 /11 -Pre-bid meeting held at 250 WHT. Deadline for questions: 08/22/11, deadline for answers: 08/25/11, bid opening date 09/01/11.

08/24/11 – Addenda #1 released by GBBN to Purchasing and ARC Reproductions. Issued to bidders for clarification.

09/01/11 – Bid Opening held. Contractors are selected.

09/02/11 – GBBN authors contract for General Trades Contractor (JB Schmitt Co., Inc.)

09/05/11 – TEI suggests revisions to contracts. Bert Watts approves those revisions to be made. GBBN sends modified contract and signature sheet to Bert Watts.03/27/12 – ThermalTech added new panel PP-1 to the Arc Flash model. An Arc Flash label was added to the panel in the field, and a copy of the updated excel file was emailed to Rodney Lofland and Bert Watts.

10/19/11 – Received Contracts and Purchase Orders from Leo J. Brielmaier Co., J.B.Schmitt Co. and Atkins and Stang Inc.

12/05/11 – Pre-construction meeting held with TEI, GBBN, HamCo, and contractors to review status and coordination. GC and EC expected to mobilize tomorrow (12/6), MC to mobilize when completed with background checks.

12/13/11 – Concrete pad size and location within telephone switch room approved by TEI and GBBN. J.B. Schmitt to proceed with installation.

02/22/12 – Project is substantially complete, waiting on close out documentation. There is a need to have a conduit extended from the existing telephone room in the 237 building to the TB clinic. TE to hold on any work associated with this until further notice from Bert Watts. Upon receipt of all closeout documentation from all vendors, TE will forward to County.

02/23/12 – Bert reported that telecom will be changing the way the fiber is running but County telcomm will coordination this work directly with Neyer and Cinbell

02/28/12 – ThermalTech is in receipt of the closeout documents that you were submitted for this project, along with a receipt for final payment. Per the requirements of the project manual, there are items that must be submitted prior to processing the final payments. Upon receipt of the following items, we can process the closeout documents: Punchlist (completed and signed), Notarized statements of warrantee, AIA Document G706 Contractors Affidavit of payment of debts and claims, AIA Document G706A Contractor’s affidavit of release of leans, separate affidavits and waiver of liens for each subcontractor and material supplier, AIA Document G707-consent of surety to final payment, affidavit of Contractor prevailing wages for all contractors or subcontractors supplying labor to the project.

4/4/12- GBBN As-buiilt drawings were sent to Bert Watts.

05/29/12 – As-builts were sent to Bert Watts.

06/26/12 – Mike Barth of ThermalTech contacted Fred Stang of Adkins and Stang to request all final closeout documentation. Fred indicated that Linda McCormick of A&S on vacation this week, but will follow up ASAP.

07/25/12 – Mike Barth spoke to Linda McCormick of A&S. She indicated that she has the entire close out package ready to submit except the as-built. Linda told me that she would get that to submit as soon as possible, and that they realize that the final pay app is still pending.

8/29/12 – Fred Stang of Adkins and Stang emailed on 8/14/12 indicating that closeout documents would be sent by the end of the week of 8/13/12. To date, still pending.

250 WHT – Phone Switch Room Read More »

250 WHT – Boiler Replacement Project

Current Status: Closeout

Contract Date:

Closeout: Feldkamp has submitted all closeout paperwork. Glenwood has submitted all closeout paperwork.

08/13/10 – We are waiting on an approved SOSS to proceed.

09/24/10 – Project was bid out as scheduled. Bid opening scheduled for Oct 14.

10/18/10 – ThermalTech has recommended Feldkamp and Glenwood. Contracts are waiting on Pre Award responses from Feldkamp. There are questions about the controls contractor.

01/24/11 – Contracts are signed. Tony said he is ready to have the pre const mtg.

02/22/10 – Pre Const mtg complete. Electrical submittals have been sent in and approved. Pre Const Mtg notes sent being completed and sent to Contractors. We are waiting on submittals for the boilers. New project schedule must be approved by Owner.

03/30/11 – TEI has sent submittals back on all the mechanical and all the electrical submittals received. We are still waiting on flue piping submittal and controls submittals. Boiler equipment is about 4 to 6 weeks away from delivery.

04/27/11 – Asbestos abatement going on right now on some equipment. Const set to begin June 1. We are waiting for a schedule from Feldkamp and submittals on controls.

05/03/11 – Tony replied with the following “I would add one more item, that would be background Checks. I have received the (4) Local Checks. The remaining personnel on the list of employees that will be working at this site will need to have a background checks? I have not received any more Local Checks or any BCI Checks.
No work can be started until all the background are complete.

05/03/11 – TEI contacted Feldkamp and asked what is the status of this project? We don’t have project schedule, boiler flue submittals, and control submittals? TTC asked Tony to contact Feldkamp about project status.

05/04/11 – Terry wrote to the Team that Feldkamp had submitted their project schedule and it looks like this: June 1-Project start up, June 1-Demo, June 1-Electrical Demo & Work, June 14-15- Set Boilers, June 16-24-Pipe Boilers, June 16-24-Conrols, June 27-Flue piping, June 29-Inspections, June 30-Factory Startup. Basically the project construction side will take one month. To be safe, I would plan on another month to work out construction and control issues and plan on having something ready on July 31 or so.

05/24/11 – Control submittals returned. Const ready to begin in June but I don’t think contractors will have all background checks complete.

06/22/11 – TTC asked Pat Heeney Feldkamp to provide the pump vendor with pump head or whatever he thinks is best and get them the order.

06/28/11 – Feldkamp has made good progress on the demo since starting. We asked for a change order on the chilled water pumps. They said that they would be back this week to cleanup the boiler room and start to get ready for new equipment.

07/11/11 – ThermalTech checked out boiler progress and change order work on the chilled water pumps for this project. Boilers are demo’ed fine. 2 VFD’s have been installed for the HHW pumps, OA has been rerouted. Feldkamp has fitter change and we are trying to setup a const meeting for the week of July 26.

07/21/11 – ThermalTech was on site to review status. New boilers have been set in place, but no connections have been made. No indication of any contractors on site.

07/29/11 – Const Mtg 4 was held last Tuesday. The schedule was updated to have the work completed by Sept 2, 2011. Feldkamp has a new pipe fitter for this job. We discussed change order opportunities for the chilled water pumps. Vendors are giving us prices. Feldkamp has a $5000 allowance, Glenwood has a $2500 we can use. The exhaust vents will be routed straight up from the area well with rain velocity caps.

08/12/11 – TTC spoke with foreman regarding piping layout, discussion is as follows:

1. The old boilers were individually connected to the make-up water supply with no backflow preventer and we did not catch the fact that the piping only had a regulator inline before the boilers. You will need to provide a Watts 009 type domestic water backflow preventer http://www.watts.com/pages/_products_details.asp?pid=895 to meet OPC section 608.3 to meet Code. Please do the work now and give me a price towards the allowance that I need to use.

2. On the pumps the P&ID line sizes here are the updates. The main line size is shown as 6″ but really most of piping at the pump is 4″. I will update the as-built.

3. On the inlet side of the pump to the suction diffuser that is coming down as 4″ piping and will not require a reduce as we show on the dwg as the suction diffuser can bolt right to the pump inlet at 3”.

4. On the outlet side of the pump the flex connectors came in at 4″ but we don’t have 4″ on the outlet. One pump has 3″ pipe and one pump as 21/2″ pipe. The flex connectors will be size to match the existing piping in the field.

5. The triple duty valves that were existing on the old pumps are not shown to be reinstalled on the new pump. This is correct, we are not requiring the triple duty valves because these pumps are being retrofitted with VFD’s. What we are requiring is what is shown on the PID’s as new butterfly isolation with lockout capability strainer and reducer if needed but the suction diffuser takes care of that. The flex connections are on the outlets and get sized to match.

6. Finally HWP-1 and HWP-2 are the same size pump in the new scheme but one has 3″ outlet piping and one has 2.5″, Thermaltech will update the as-built to reflect this change.

7. Feldkamp showed me how they are going to hook up the MER AHU unit back to the heating supply and that looked like an acceptable plan as well.

The gas piping looks great. The HHW piping at the boiers looks great.

08/22/11 – The Power terminations to the equipment at the 250 boiler job is complete. We still have to perform a factory authorized startup on the variable frequency drives. The control wiring does not have to be complete for us to do the startup but there should be a control person present. We require 1 week notice of when we can perform this startup.

08/25/11 -A&M need access to do controls work. Question into Tony about them starting now with the local backgrounds complete.

08/30/11 – Feldkamp provided a price of $45,000 to replace both CHWP-1 and CWP-1 today via a quote from his vendor. We only $5000 in allowance money so I advised Pat that it would be up to Tony Matre but I did not think he would accept this price for these pumps. I suggest we get quotes from other vendors if needed. Feldkamp says state inspector is complete, flow switches need to be added before he will sign off on install. Controls and startup should be complete by 9/8 or 9/9.

09/14/11 – Modbus is up and running per specs, and A&M has installed code to covert form Centrigrade to Fahrenheit. Boiler and Pump controls programming is complete, A&M will be testing it today. DDC Controls are about 95% complete at this time. Duke is supposed to contact TTC about regulator visit to site. Contractors have punchlist items to complete in 14 days from now.

09/15/11 – Duke is going to meter the incoming gas pressure before and after the meter and report pressure trends to TEI. The building is supplied by what is called “standard” gas service which meant 4-7″ pressure most of the time. It can drop lower in cold weather. When the data is received from Duke a decision will be made about what to do. Duke was also asked to check the regulator inside the building and was told his records indicated there was no regulator at this site-which means the regulator that is high on the wall could be an Owner one and not Duke, which means it could be removed and put boiler regulators back on. This could probably alleviate the pressure problem if the house regulator is what is causing the issue. The only problem is to check the pressure for the water heater that the gas line feeds, or to adjust the house regulator to make sure it gets the least pressure drop through the unit as possible. Once Duke is on site, a final decision can be made. Duke will be out Friday or Monday to install the trending device.

09/22/11 – All closeout paperwork has been received by ThermalTech. TTC processed it and is planning on dropping it off to Tony Matre today at our 2pm LEED meeting with GBBN.

09/23/11 – Close out Documents have been received by both Contractors.

09/30/11 – Tony is paying out Glenwood in full minus allowances but holding Feldkamp closeout for boiler resolution.

10/13/11 – Gas pressure and flow should be fine. The Duke readings were 7.9″ at full flow. Several issues to note on this job are:

1. Our boilers are smaller and therefore there is no real way that Duke can say our gas mains are undersized.

2. There is very little gas piping in this building therefore the overall gas pressure drop is very small even if Duke thinks the 1″ lines to the boilers should be 1,5″.

3. Boiler 1 is running and continues to run just fine.

4. The problem is in the BLR-2 machine itself and we should pursue Turton and tell him the gas pressure read by Duke is 7″ and ask him is there any way to soften the low pressure cut out tendancy.

5. Duke talked about having their remodel team come in-that is the people that do replace meters and regulators. TTC has worked with them before. Someone needs to be at the building with them while the boilers light off and show them what is happening. Also ask them to trend the gas pressure in the main, they have a device that does that.

Step 1- TTC will email Turton.

Step 2- TTC has already called Duke and will check back with them.

Step 3-Keep Boiler 1 in lead.

Step 4- A&M is coming out tomorrow.

10/18/11 – A&M fixed the software gliche on the boiler pumps on Friday October 14th.10/19/11 – The lighting board is not in yet and neither is the flame rod assembly but Ballinger will install when they come in. The gas piping has been changed and Boiler 2 went out overnight. Boiler 1 continues to run flawlessly. The errors are either #107 or #108 normally but we are going to send a hand written error log that Hamco has kept on Boiler 2.

10/19/11 – The lighting board is not in yet and neither is the flame rod assembly but Ballinger will install when they come in. The gas piping has been changed and Boiler 2 went out overnight. Boiler 1 continues to run flawlessly. The errors are either #107 or #108 normally but we are going to send a hand written error log that Hamco has kept on Boiler 2.

11/02/11 – Feldkamp had asked for final payment on this job. TTC e-mailed Pat Heeney to let him know that Hamilton County Facilities would not be willing to pay any more billings until Boiler #2 is fixed and acting properly. Currently it is going out every night, but seems to start back up in the mornings. Ballenger’s tech is out of town until Friday, but there was supposed to be an update on the flame rod replacement 2 weeks ago.

11/04/11 – TTC went to jobsite and witnessed the following: Flame rod sensor was changed out in both boilers. The new sensor is longer and thicker than the old one. BLR-2 started working properly as soon as the flame rod was changed out. The ignition start timing was changed to 2000. The low fire firing rate was changed to 1500 on both boilers.

TTC watched both boilers start up properly and it appeared that BLR-1 was back in LEAD and was getting ready to fire again at a setpoint at 150F.

11/07/11 – On Friday FLR-2 had 3 errors. One was error #108 and two were #109. The changes in the flame rod sensor and ignition timings were evidently not the answer. TTC requested a Tech visit and to call Mike Jackson at Hamilton Co. Facilities, he needs to know about the field visits since it is his building. No money will be released until this matter is resolved. Jim Turton with Ballenger Co. has advised Steve of the continuing problems at this site and will be in touch with Mike Jackson soon.

11/14/11 – Ballenger Company ‘s service department ordered a new boiler module for #2 and will install it as soon as it comes in. This should fix the issues. Ballenger will call the customer and schedule a service trip.

11/30/11 – The Boiler Module #2 was replaced on Monday 11/28/11, the combustion checked, and normal operation observed with no fault trips.

12/06/11 – Boiler #2 was out again. It went out on code 108-Flame Lost in Run. It went out yesterday (12/5) also on the same code.

12/09/11 – Steve Schill (service tech for Ballinger) will be at 250 WHT on 12/12 to run some test sequence operations. He has been in contact with Cleaver Brooks product engineers about the problems at this installation, and we will continue to work on a solution.

12/15/11 – TTC proposed a troubleshooting strategy that would allow tracking the boiler pressure at BLR-2 and BLR-1 and see what the differences are between the boilers and track those readings vs. failures vs incoming gas pressure from Duke. Either TEI does this survey themselves or they will hire a third party. If not problem presents itself TTC recommends the following changes at 250 WHT:

Ask to remove the pressure regulator inside the building and increase the pressure to the gas main to the building beyond the standard house pressure of 7-14″. The factory gas pressure regulators can be reinstalled and allow pressure to add one inline regulator on it too so we can drop its incoming pressure down to 14″. We could turn off permanently the natural gas feeding the labs or install a regulator on that line too but those may be out of service. This may be the best solution moving forward. If all agrees with the strategy, a face to face meeting should occur at 250 between Feldkamp, Ballenger, County and TEI.

12/20/11 – TTC spoke with Dave Messmer at Duke Energy and he says they can increase the gas pressure in the building but they would prefer to deliver 2 psig to the building not 1 psig. TTC asked Jim if the factory regulators from CB handle the 2 psig to 14″ wc turndown and if he sees any issue with it?

Assuming all that works, the County has two options at this point. Put in one 2 psig to 14″ regulator after the Duke regulator and make the whole building house pressure again or we can add regulators on each piece of equipment that doesn’t have them. Jim agrees that bringing 2 psig gas pressure into the building and then reducing it with a main step down regulator would be the “cleanest” approach. Instead of dropping the pressure to 14″ we, he suggest maybe consider a reduction of 9″ to 10″ WC in order to have a little safety factor against operating the boiler gas pressure regulators at what He believes is their maximum pressure limit. Ballenger’s service dept. needs to be notified 10 days before increasing the gas pressure.

12/22/11 – Here are the loads: We have two Cleaver Brooks Clearfire High Efficiency boilers, model number CFC-1000, Input 1000 mbh, Output 920 mbh. Only 1 of these boilers should ever run to handle the building load. The other boiler is 100% backup. Does it matter to Duke what the operation is of the boiler plant or do you size for peak load of all connected equipment? One water heater 250,000 btuh. All of these appliances are within 100 ft of the meter. Please let me know what the next step for increasing the pressure to 2 PSIG as you suggested is and what the schedule of that change might be. I have to have some contractors on site to add some regulators onto our equipment because they can only handle 14 psig incoming gas pressure so I have to coordinate that work too. Finally does Duke have a gas pressure trend log? I need to record the gas pressures before and after these changes.

12/29/11 – I have asked Duke to increase the pressure to the building to 2 psig. We will then have to install a new regulator on your house line that takes it from 2 psig down to 14″ but Jim Turton said he doesn’t want more than 10″wc which I struggle with because after we give him 10″ he will say in the dead of winter the boilers are going out on low gas pressure because Duke demand is so high. Anyways, it will probably be 12″. Their regulators can handle 1 psig (28″sc). I had to give all the loads in the building to Duke so they know what “new” regulator to bring out to the building. I have to confirm with Feldkamp that they will be purchasing and installing a new house regulator using the remaining allowance money. I think this will all take a little bit of time and with the holiday, I don’t think Duke is in a big hurry to get it done this week. What will be interesting to see is what happens when the new pressure to the BLR-2 unit is 10-12″. If it continues to g out an alarm then you will have a real case to make Feldkamp or Ballenger reimburse us all the cost or make it a no charge. Feldkamp has offered to swap the inline gas feeds between the boilers for troubleshooting – is that something you think is worth the effort if we are going with the 2spig to 12 psig regulator?

01/13/12 – TTC talked to Feldkamp and confirmed the new regular type and load. They are calling Duke to coordinate install in a week or two when it gets back up in the 40’s.

01/19/12 – The regulator and materials have been delivered to site and depending on the weather will be installed on Monday the 23 or Tuesday the 24. Start time will be around 9 or 10 to give the building time to warm up.

02/03/12 – Ballinger has been trying to get a factory tech in from Cleaver Brooks to resolve the issue. They hope to have this taken care of soon. Ballinger is copying a division head and V.P. on all correspondences.

02/21/12 – According to Jackson, the BLR-1 at 250 WHT made it through the weekend with no reported anomalies. Both boilers had the grounding point and wiring modified so they are both installed exactly the same way now.

03/16/12 – The County has accepted this project as completed. Terry has requested all closeout documents or an update on the status of the closeout process for a timeline for final payments from Pat at Feldkamp Enterprises.

03/28/12 – Terry C sent Pat at Feldkamp an e-mail saying the last payapp needs to be modified and the change order monies be paid. Terry requested the cost of change order for the extra meter at the building. There is $3,500 remaining allowance monies for this project. The previous change order was not valid so that needs to be torn up and Payapp #6 needs to be changed. Also Terry requested the final markups to create as-built drawings to submit to the County.

04/02/12 – The final invoice sent by Feldkamp is not payable through the County Auditor system, TEI will have to reject the entire pay app. Feldkamp needs to send a revised final payapp #6 that asks for the remaining balance including retainage which is $14,650.00. Send 3 originals to TTC notarized and signed for closeout.

Outstanding items that are required:

-AS-Built Markup – have they been submitted to show field changes?

-Final approved permit document from City

-Final payapp with correct billing amount

-Final certified payroll

-Three O&M manuals for Tony Matre

07/02/12 – TTC asked Pat Heeney for the status of the permit from the City? Are they going to accept our proposition? and that you have 2 weeks to turn in certified payroll to Bert Watts at HamCo before he turns this job into the State Wage and our Division. TTC will follow up with a phone call on status.

07/09/12 – Feldkamp talked with city inspector and looks like they will be ordering double wall vent pipe, not going to accept the way it is unless the manufacturer backs it up in writing which they won’t du to liabilities. Pretty sure there is no allowance monies left. Feldkamp will get measurements and get it on order.

250 WHT – Boiler Replacement Project Read More »

250 WHT – General Health Alternate Study

Project Lead: GBBN

02/08/11 – GBBN met with Bert Watts and the staff from Public Health. The design development design and estimate were modified slightly to combine the Base and Alternate projects together into one project.

12/09/11 – GBBN sent the modified drawings and estimate based on the meeting held on 2/8/11

11/17/10 – Owner review of Design Development drawings and estimates. Owner required a modification of the SOSS to show an Alternate Design for the countertop computer modules.

11/18/10 – GBBN submitted a revised F021 and a new F023 SOSS to Bert Watts.

11/23/10 – GBBN sent final design development sketches and associated Opinions of Probable Costs to the owner.

250 WHT – General Health Alternate Study Read More »

250 WHT General Health Renovations

Project Lead: GBBN

07/28/10 – Attended Kick-off meeting with Bert Watts.

08/06/10 – SOSS sent to Bert Watts for approval.

09/20/10 – Meeting with Tim McCellan of Public Health to redefine the scope and change to two SOSS for alternate design options.

09/22/10 – Two SOSS sent to Bert Watts for approval.

11/17/10 – Owner review of Design Development drawings and estimates. Owner required a modification of the SOSS to show an Alternate Design for the countertop computer modules.

11/18/10 – GBBN submitted a revised F021 and a new F023 SOSS to Bert Watts.

11/23/10 – GBBN sent final design development sketches and associated Opinions of Probable Costs to the owner.

02/08/11 – GBBN met with Bert Watts and the staff from Public Health. The design development design and estimate were modified slightly to combine the Base and Alternate projects together into one project.

02/09/11 – GBBN sent the modified drawings and estimate based on the meeting held on 2/8/11.

250 WHT General Health Renovations Read More »

250 WHT Chilled Water Pump Replacement

Project Lead: ThermalTech

03/14/13 – Background checks for A&M and Atkins & Stang are all approved. Two of three for Triton are approved.
03/18/13 – Triton is sending over project schedule for the job today. They are ready to start next week. The pumps ship on Friday. Brian wants to make sure they can drain down the chilled water and condenser water as needed for this work, TTC told them yes but they still have to coordinate with Jackson and Perkins.
03/25/13 – Triton sent TTC a cost sheet for replacing the existing 6″gate valve with a new Butterfly valve. TTC reviewed all work with Greg and Brian from Triton. They made a small piping change in the condenser water connections which TTC approved on site. The triple duty valve will stay in the system and be rebalanced to match the flow of the new CWP-1 being installed. The gate valve can be replaced for under $400 by Triton. Tony needs to give approval to allocate allowance money for this valve. Triton also noted that the pipe sizes on the Public Works documents are incorrect. The second floor piping is actually 4″ not 3″ and the first floor is actually 3″ not 2.5″. The flow and pressure drops are still fine. Triton is to mark up the As-Built drawings and they will be updated at the end of the job.

03/26/13 – Mike Jackson says all demo’d pumps/motors/rails, etc. needs to go. The only motor to stay will be the new motor (spare) that was purchased last year.

04/17/13 – The installed VFD and disconnect is acceptable for use on this project and meets the safety requirements and lock/tagout protocols of Hamilton County.

04/23/13 – A&M will be on site 4/24 to remove the existing DX-9100 expansion modules that presently control the chiller plant. They will then install a new BacNet controller to control the new chiller plant and tie it into the existing BacNet bus with the new VFD’s and the existing BacNet controller that was installed for the boiler project a couple of years ago. This will allow all of the chiller programming to be in one controller adjacent to the chiller. The intention is to have the chiller plant operational by the end of the day 4/24.

Triton sill try to have the balancer on site 4/24 so A&M can set up the controls with the minimum design flow of 110 GPM through the chiller.

04/24/13 – TTC and MJ review controls and mechanical work for pre punchlist work. Chiller is almost ready to be started.

04/26/13 – AHU-4 is low on flow-probably because of trapped air. CWP-1,2 are labeled backwards from dwgs and the head of the system are lower than designed thus increasing the flow readings on the most of the equipment. This is not the final balance report but is shows that we seem to have enough head and flow in the equipment to meet the design conditions. The final report will be included in the final O&M with the final punchlist for this building. Now waiting on controls update from Roger.

04/26/13 – A&M is still working on final checkout, so they did not have the DP sensors up and functional yet. Jim was going to let TTC know what they were reading so the setpoint could be determined. Without the system control, A&M was not able to place it into minimum flow condition (no control over the valves yet and the pump was in hand). Greg was aware as well, but A&M feels there is air in the lines that feed AHU-4 (east unit on the 2nd floor). It’s flow was much lower than the others regardless of where the pump was run. Greg is going to have maintenance look for air vents. Ultimately A&M still needs to verify AHU-4 flow after venting, verify final DP setting, and check flow through the bypass at AHU-1 with all coils closed. This work won’t take long, but needs to be done to ensure everything is ready before A&M schedules.

05/01/13 – The chiller is running and down to one override for now. TTC visited the site and walked the system with Will and talked to Roger on the phone about the programming. The chiller is up and running and with AHU-1,2,3 in automatic. However we need to keep AHU-4 in 85% open mode to meet the minimum flow of the chiller from field testing. From what TTC saw the dP across the chiller needs to be about 1.8 yesterday to keep it running. The mfg. data says a dP across the evaporator barrel only needs to be 0.9 for 116 gpm. TTC left the AHU-4 at 85% open and the dP at 1.8 when he left. This makes the VFD run about 64% speed which is pretty good at least there will be energy to save. On the flow issue there are a couple of items: The first issue is that for some reason there are multiple circuit setters that are not needed and they are installed in a bad location for our needs. The second issue is that we cannot easily replace the Hoffman valves at AHU-4 to bleed the air out of the system. Triton can replace the existing ones above the reception area for $988. TTC would prefer to have the County replace them instead and save the money for the water heater change order. The equipment is only $138 each. Is this a possibility? Triton to send a cost sheet over for review. There is a county meeting to discuss all options.

05/01/13 – The final report for the controls checkout and verification was completed and as follows:

AHU-4 has a 2 1/2″ circuit setter installed vs the 2″ installed at all other units. As the valves were already fully insulated when we arrived, I only cut access to the balancing ports and the position indicator. After trying to bleed air from the system, manipulating the other AHU control valves, and increasing the pump speed, Jim Biele and I were not able to get the coil to meet design. It was at the time I removed insulation to be sure we didn’t have some unseen problem, and found that the valve was in fact a 2 1/2″ valve. Using the proper performance data, we had adequate flow with the system at the original setpoint of 9 PSID.

The setpoint was determined as follows: pump at design flow, all AHU’s commanded to full cooling, all coils verified to be at design flow. The DP at that time was established as the setpoint. Upon completion of the venting and balancing on Monday, both DP sensors were reading the same value with the system at max flow. DP across the chiller at that time was approx 5.4 psid.

The final step was to verify minimum flow in the system with all valves closed. With AHU-1 in bypass (and the small unit in the basement that also has a 3 way control valve), AHU-2,3,4 closed, and the pump in auto 9 psid, we only measured about 55 gpm through the bypass of AHU-1. Jim increased the pump speed to see what would be required to achieve approx 110 gpm at the AHU and we were up to a DP of approx 25 psi before we met minimum flow (and the pump was at 85% at that point). I don’t see how we’re goint to meet the minimum flow requirement without another 3 way valve.

The bypass is piped such that there is a circuit setter (fully open presently) in the bypass line, and then a common return circuit setter downstream of the 3 way control valve. I had to use that common valve to set the flow through the coil. It is throttled to a setting of 14 (out of 100). Fully open, the coil would have too much flow but we would then have greater flow in bypass mode.

05/16/13 – The new bypass valve has been ordered. It’s a two week lead item. A&M should be installing in June and then TTC will commission it after it’s up and running. The plan is to restrict the bypass on AHU-1 at its circuit setter to a minimum and just use the new bypass as it is all we should need.

05/30/13 – CHW Bypass was approved, Triton waiting on change order approval for water heater. Final change order work should start in 2 weeks.

06/19/13 – ThermalTech meet with the Tony and Mike. They have concerns and all change order work is on hold until the bypass valve issue is resolved and working. ThermalTech contacted the contractors and advised them that more work needed to be done prior to installing the water heater.

06/24/13 – ThermalTech visited the site and collected valve positions, space temps, and differential pressure readings for the bypass work. All space temps appear normal.

08/22/13 – TTC met with Tony and Mike to present two options for modified control. Option 1 is a main 3-way valve and Option 2 is to retrofit the system with 3-way valves. We agreed to do Option #2.

08/23/13 – TTC approved 3-way valve installation with Triton. New valves are on order. TTC working with Triton and A&M for schedule and timing.

09/26/13 – Triton and A&M will install valves this week and commission system for operation to finish this project.

10/21/13 – 3-way valves installed. Water heater replacement alternate next. Then this project will be complete.

10/27/13 – Jackson reports all seems to be working very well.

12/13/13 – Startup domestic water heater. Denny & Triton on site for final startup. TTC provided some final installation instructions.

01/24/14 – Final paperwork being received by Triton for closeout. Signed change order came in for records.

01/30/14 – Need certified payroll and final closeout from all three contractors.

02/21/14 – Triton contact for closeout pay applications. TEI approved second to last payapp.

03/25/14 – Triton and TTC settled on May 1 warranty date. Final closeout paperwork enroute.

04/14/14 – Project complete final PW rates being sent to John Nester.

250 WHT Chilled Water Pump Replacement Read More »

250 Energy Star 2014

Project Lead: TTE

10/09/14 – Terry and Bracken visited the building and took the air, people and light readings for the verification process.

10/23/14 – Final submission paperwork started but not completed yet. TTC is working on final submission for Ralph’s Signature.

11/28/14 – Building was approved for Energy Star with a score of 76 on Application # APP-20141119-0-1640490.

250 Energy Star 2014 Read More »

250 WHT Site Lighting

Project Lead: ThermalTech

02/26/12 – ThermalTech met with Will Perkins, Bert Watts and John Nester to review existing conditions and to define scope. ThermalTech developing SOSS.3/1/13 – SOSS issued to Bert Watts. ThermalTech waiting on approval and on PO.

03/01/13 – SOSS issued to Bert Watts. ThermalTech waiting on approval and on PO.

04/24/13 – SOSS approved and PO issued to ThermalTech. ThermalTech to schedule kick Off meeting with Bert Watts to establish schedule.

06/26/13 – Project bids have been received, and Debra Kuempel is apparent low bid. ThermalTech has called DK for pre-award conference, and will draft contracts as soon as conference is complete.

8/28/13 – DK has signed and returned contracts to Hamilton County. Waiting on NTP to begin work.

09/25/13 – DK has NTP – and will send Mike Barth of TE Submittals for approval. Tom Helmes of DK is matching existing equipment as specified.

10/30/13 – New pole has been received by DK and is scheduled to be installed this week.

01/24/14 – ThermalTech (Mike Barth) and DK met on site for final punchlist backcheck. DK submitted 100% pay application less retainage.

02/25/14 – DK submitted pricing for change order for replacing (6) lamps in parking lot, (1) wall pack lamp on building, and (3) pole light lamps at the coroners office. CO pending approval and signatures.

03/26/14 – DK has approved CO for replacing the lights.

04/24/14 – Change order sent in but not all the work was done so Mike and John need to coordinate the change order work. Ameresco lighting contractor jumped out and replaced lights.

250 WHT Site Lighting Read More »

250 WHT Penthouse Screen Wall Removal

Project Lead: THP

07/01/14 – THP issued review letter of penthouse conditions. County requested SOSS for 2014 structural services.

07/09/14 – THP issued SOSS to remove and repair penthouse structure.

07/17/14 – County approved SOSS.

07/22/14 – THP and County had a design coordination meeting.

07/31/14 – THP issued owner review documents.

08/04/14 – County provided review comments to project manual.

08/20/14 – THP and building tenants had meeting to discuss antennas located on the screen wall.

09/24/14 – THP issued bid document to County for review.

09/25/14 – THP issued bid documents to contractors for pricing.

09/26/14 – Bid Documents Issued.

09/30/14 – ThermalTech and THP met on site to discuss MEP options.

10/13/14 – THP issued addendum #1.

10/14/14 – Addendum No. 1 Issued.

10/21/14 – American Façade, Kramer, and O’Rourke submitted bids. American Façade was the apparent low bidder at $49044.00. THP qualifying bid.

10/28/14 – Bids received by American Façade Restoration, Kramer & Feldman, & O’Rourke. AFR is the apparent low bidder.

11/04/14 – THP reviewed and recommend AFR bid.

11/06/14 – THP issued draft AIA County / AFR contract.

01/07/14 – AIA Contract executed by prosecutor.

01/21/15 – Pre Construction Meeting completed.

01/22/15 – THP issued permit set to AFR and the County. County and THP reviewed and approved AFR bid.

01/28/15 – City of Cincinnati issued a building permit.

01/28/15 – All submittals returned to AFR.

02/03/15 – Preconstruction meeting completed.

02/18/18 – Review meeting for alternate antenna installations.

02/24/15 – THP provide options and pricing for alternate antenna installations. County is reviewing the options.

02/24/15 – All electrical work complete by Phasor Electrical Services with the exception of the reinstallation of the HAMM radio antennas. Antennas will be reinstalled once the screen walls are removed.

02/26/15 – Previous demolition work on hold due to weather. Work planned for 2/28/15, but waiting on final weather report.

03/14/15 – AFR removed the precast panels.

03/15/15 – AFR removed the steel and installed the antenna mast.

03/20/15 – AFR completed remaining work and THP published a punch list.

03/20/15 – City inspector issued a Final Inspection ticket.

04/28/15 – THP received final closeout paperwork form AFR and forwarded AFR closeout paper work to the County.

05/28/15 – THP to finish up CAD drawing and submit to the County.

06/24/15 – THP completed Archibus drawing files and AFR working on closeout project manual.

07/29/15 – Correction from 6/24, THP completed Archibus drawing files and AFR working on closeout project manual.

250 WHT Penthouse Screen Wall Removal Read More »

250 WHT Facade Repair

Project: F39

06/01/12 – THP submitted SOSS.

09/13/12 – County approves SOSS.

10/04/12 – THP County kick-off meeting complete. DD documents due early November and Final bid documents due mid-December with a budget. Bid period mid-February.

10/31/12 – THP working on DD documents.

01/15/13 – THP Issued DD documents for review.

02/08/13 – County returned project manual comments.

02/19/13 – THP and County had a design review meeting. Reviewed construction layout and phasing building needs. County requested additional window information for review.

05/21/13 – THP issued 90% Review documents to the County.

06/27/13 – Project update. Due to weather sensitive work, if project approved work will not occur until next spring. Possible bid project late 2012.

10/31/13 – Project on hold.

01/30/14 – Project on hold.

02/27/14 – Project on hold.

04/24/14 – Project on hold.

04/24/14 – County requested THP review the status of the penthouse precast panels.

05/23/14 – THP reviewed the cooling tower penthouse structure. Based on our observations the deterioration in the steel members has continued to increase. A letter will be issued with the results of the review along with our repair recommendations.

05/29/14 – Overall project on hold.

06/12/14 – THP completed a review of the penthouse cooling tower screen walls. The condition of the walls required stabilization emergency stabilization.

06/13/14 – THP facilitated a quick bid of stabilization of the panels and cooling tower beams. American Restoration was the only bidder able to respond quickly and there bid was within 10% of the estimated work.

06/14/14 – American Façade installed cables and shoring as directed by THP at the screen walls.

06/26/14 – THP anticipates publishing a letter of findings and recommendations by June 27th.

06/26/14 – Overall project on hold.

07/31/14 – Overall project on hold.

08/27/14 – Overall project on hold.

09/25/14 – Overall project on hold.

01/29/15 – Overall project on hold.

02/26/15 – Overall project on hold.

03/11/15 – THP assisted the County with the evaluation of falling concrete from the entry bridges.

03/12/15 – THP issued sketches to stabilize the bridge railings and allow use of the bridges.

03/16/15 – THP published an updated assessment of the entry bridges per the County’s request.

03/26/15 – Overall project on hold.

04/13/15 – County requested an SOSS to repair/replace the bridges. See F66.

04/30/15 – Project been put on hold.

12/09/15 – Projected construction 2017.

250 WHT Facade Repair Read More »

250 WHT Window Replacement

Project Lead: THP

06/01/12 – THP submitted SOSS.

09/13/12 – County approves SOSS.

10/04/12 – THP County kick-off meeting complete. DD documents due early November and Final bid documents due mid-December with a budget. Bid period mid-February.

10/31/12 – THP working on DD documents.

01/15/13 – THP Issued DD documents for review. Documents part of façade repair project as alternate.

09/25/13 – REFER to F39 for project status.

12/09/15 – Project on hold. Projected construction 2017

250 WHT Window Replacement Read More »

250 WHT Door Access Control

Project Lead: GBBN

01/06/16 – GBBN receives email, with scoping sketch attached, about project request. Facilities requests SOSS.

01/11/16 – GBBN issues two SOSS, one for each option, to Facilities Department.

04/18/16 – Facilities sends Estimating Project Requests showing this project as one of the listed projects.

06/30/16 – Submitted as a 2017 Project request.

250 WHT Door Access Control Read More »

250 WHT Bridge Replacement Special Inspection

Project Lead: THP – F79

06/06/16 – As part of the plans review the city required special inspections for both concrete testing and soil investigation.

06/14/16 – THP submitted an SOSS with Terracon completing the special inspection.

06/21/16 – County approved SOSS.

08/25/16 – Refer to F66 for updates.

01/26/17 – City requires extra paperwork from Terracon before they can final the permit on this job.

07/27/17 – City closed out permit for this project. All wrapped up. Ready to Archive.

250 WHT Bridge Replacement Special Inspection Read More »

250 WHT Bridge Replacement

Project Lead: THP – F66

04/13/15 – County requested SOSS to replace the bridges.

04/28/15 – THP issued SOSS. BW says the funding is approved for this project. PO forthcoming.

05/29/15 – County executed the SOSS.

06/17/15 – THP issued review documents to the County.

07/15/15 – THP met with City Fire Department plans examiner to confirm egress requirements.

07/22/15 – THP, Facilities department, and water department met to discuss project impact on users.

07/29/15 – THP, Facilities department, and public health department met to discuss project impact on users.

07/30/15 – THP anticipates issuing bid documents first week of August.

08/14/15 – THP issued bid documents.

08/24/15 – Pre-bid meeting completed.

08/26/15 – Project update: Bids are due 9/8/15.

09/02/15 – Addendum No. 1 Issued, changing the bid due date.

09/16/15 – Addendum No. 2 Issued modifying documents, issuing meeting minutes and answering contractor questions.

09/21/15 – Addendum No. 3 issued answering contractor question.

09/22/15 – Addendum No. 4 issued answering contractor question, issuing a new bid form, and changing the bid due date to 9/25/15.

9/25/15 – One bid submitted above the 10% allowable advertised budget.

10/01/15 – THP published bid finding letter and recommendation. Bid rejected by the County.

10/15/15 – THP published an updated budget based on current market conditions.

12/18/15 – County approved new budget and scope. THP authorized to finalized documents and bid the project.

01/11/16 – THP published updated review drawings and met with County to discuss documents.

01/20/16 – THP issued repair documents for bidding. ITB #008-16.

01/25/16 – THP issued Addendum No. 1, which changed the prebid meeting time to 11 AM.

01/28/16 – Prebid meeting scheduled at 11 AM.

02/12/16 – Bids were received from Smith Construction, Sunesis, Empire, ZSR, Prus, and SSRG. Smith Construction was the apparent low bidder. The submitted bid was within budget.

02/25/16 – THP review the bid with Smith Construction and contacted the submitted references. Based on bid amount, discussion with Smith Construction, and the reference comments; THP recommends Smith Construction.

02/25/16 – THP delivered recommendation letter and draft AIA contract to the County for review.

04/13/16 – County commissioners approved the project. THP notified Smith Construction project is moving forward. Smith Construction planned on starting the work in June.

04/26/16 – County approved the Contract and Issued a PO. THP forwarded both the Contract and PO to Smith Construction.

05/09/16 – THP provide sealed drawings to Smith Construction for permitting.

05/27/16 – Smith Construction working through background checks and fire training.

06/24/16 – Project is currently waiting permit

06/24/16 – Submittals are in.

07/07/16 – Permit approved.

07/20/16 – Preconstruction Meeting Completed.

07/28/16 – Smith Construction finalizing submittals. Start of site work anticipated for August 1st. Next site meeting August 8th.

08/03/16 – Preliminary meeting with building occupants completed to discuss fire watch plan.

08/08/16 – Fire Watch meeting completed between fire department, building department manager, HC Safety, Smith Construction, THP, and County Facilities.

08/15/16 – Construction began for the project. Demolition of Bridge #3 complete and new footing poured.

08/22/16 – Construction progress meeting 02 completed.

08/25/16 – Anticipate pouring bridge #3 foundation walls today.

08/25/16 – Bridge #3 foundation was poured.

09/06/16 – Bridge #3 upper landing and steps poured.

09/12/16 – Bridge #3 lower landing poured.

09/14/16 – Bridge #3 sidewalk adjacent to lower landing poured.

09/15/16 – Bridge #3 concrete test cylinder breaks completed and passed.

09/16/16 – Bridge #3 reopened with temporary rails.

09/19/16 – Demolition of Bridge #1/#2 started.

10/03/16 – Change Order 1 drafted and sent out

10/04/16 – Wall footings poured by Smith without approval of owner’s special inspector

10/06/16 – Change Order 2 for additional sidewalk drafted and sent out

10/11/16 – Terracon approved the excavated bearing condition

10/12/16 – Building struck by Smith dump truck

10/13/16 – Pay App 1 sent to All parties

10/24/16 – Bridge 1 and 2 poured.

11/21/16 – Bridge 1 and 2 structural slab poured.

12/02/16 – Bridge 1 and 2 lower slab on grade poured.

12/08/16 – Bridge 1 and 2 sidewalk slab on grade poured. 12/12/16 – Bridge 1 and 2 opened with temporary rails.

12/19/16 – THP and Smith completed measurements of unit cost allowance repairs.

12/22/16 – Bridge 4 and stairs below were poured.

12/29/16 – Bridge 4 opened with temporary rails.

01/24/17 – Started installation of railings for Bridges 1, 2, and 4.

02/21/17 – Smith still waiting to receive guardrails for Bridge #1 and #2. Tentatively plan to start work on Monday 2/27 and complete on 3/2.

03/23/17 – Project update: Alumina installed all permanent railings. Punch list items planned to be completed this week.

03/24/17 – THP completed site visit and published a punch list as part of the field report.

04/25/17 – Terracon visit the site to complete final special inspection work. Smith Construction not on site, so Terracon left. Terracon visit to be rescheduled.

05/23/17 – THP sent draft final Change Order 03 to Smith Construction.

05/25/17 – All field work complete, including punch list.

07/19/17 – THP sent request to Smith Construction to split payment of CO#3 at the request of the county. Follow-up sent 7/25. No response from Smith yet.

08/25/17 – THP received Smith Construction’s closeout paper work and final pay application.

08/31/17 – THP reviewing closeout paper work and final pay application.

09/05/17- Smith sent final warranty paperwork. THP reviewing.

09/07/17 – THP processed all paper work and sent to County.

250 WHT Bridge Replacement Read More »

250 WHT Recycling Fencing Location

Project Lead: GBBN – F079

03/23/17 – At Partnering Meeting Facilities explains project scope and requests SOSS.

03/24/17 – GBBN corresponds with Bayer Becker requesting proposal for partial survey and staking services.

04/07/17 – Bayer Becker sends proposal to GBBN.

04/10/17 – GBBN authors and delivers SOSS to Facilities.

07/17/17 – Bayer Becker has completed all field work. The next step will be completing the survey drawing and staking the property line for the fence installation. This should be completed by the end of the month.

07/26/17 – Bayer Becker sends GBBN a sign and sealed survey for use by the Owner. Missing monuments and two sets foe nails have been installed on site for use in locating the fencing by Others.

10/23/17 – GBBN receives invoice from Bayer Becker for survey.

250 WHT Recycling Fencing Location Read More »

250 WHT Entry Leak Investigation

Project Lead: THP

05/12/17 – Hamilton County requested SOSS to investigate leaking around the building entries.

05/16/17 – THP visited the site and met with Mr. Perkins to review the leaking conditions to develop a proposal.

05/25/17 – THP developing SOSS.

06/08/17 – THP issued SOSS for review.

06/26/17 – County approved SOSS.

07/27/17 – THP plans to schedule work second week of August.

08/01/17 – THP reviewed the interior conditions of known water leaks and performed water testing on one entry door system and successfully got the entry to leak. Additional testing was performed on the windows.

08/22/17 – THP assessed all public entrances for signs of water infiltration.

09/01/17 – THP issued draft report to County for review

09/06/17 – THP issued final report to County.

250 WHT Entry Leak Investigation Read More »

125 East Court Street Public Defenders Renovation Eighth and Ninth Floors

Project Lead: GBBN

06/18/14 – Kick-off Telephone Meeting with Diana Supe of the Facilities Department to request the SOSS (F105). Clarifications made on scope in follow-up emails and calls from PDO.

06/19/14 – Kick-off Meeting with Ralph Linne and Diana Supe with Terry Cannon of ThermalTech.

06/19/14 – Contract Scope Question document authored by GBBN with input from Interior Project Management and ThermalTech.

06/23/14 – GBBN visits 125 East Court Street with CBRE, PDO and Facilities Department.

06/23/14 – GBBN receives electronic drawings and programming documents from CBRE and distributes to consultants.

06/24/14 – GBBN distributes Meeting Minutes to all attendees.

06/25/14 – IPM and GBBN conduct a field verification site visit to the 125 Court Street Facility. IPM and TEI submit scope hours and descriptions to GBBN for SOSS.

06/26/14 – SOSS hand delivered to Bert Watts at monthly Partnering Meeting.

07/09/14- GBBN makes public records request for existing building Code Information to the City of Cincinnati Planning and Buildings.

07/28/14- Bid Opening for Peripheral Furniture. Office Furniture Source is low responsible bidder. GBBN authors AIA contract for submittal to Prosecuting Attorney’s Office.

08/21/14- GBBN makes revisions to AIA contract and resubmits originals to Public Defender’s Office.

09/08/14- Biweekly construction administration teleconference.

09/09/14- Change Order #001 issued to Office Furniture Source to raise new systems furniture panels for higher countertops at the pass through window.

09/10/14- Biweekly construction administration teleconference.

09/11/14- Panic button logistics and hardware finalized iwth Sheriff’s Department.

09/17/14- PDO requests a change order to install a second door into Storage File Room #803.

09/23/14- Keidle Appliance is awarded the purchase order for the two refrigerators and microwave.

09/24/14- Biweekly construction administration teleconference.

09/26/14 – Spencer says that move in date is set 10/13 for furniture move and appliances will come the week after. Both floors will occupy at the same time. 230 and 800 personnel are both moving over. There may be one group staying behind. SJ needs to see Steve Sears about getting proximity cards programmed. SJ says IPS is the County contractor.

10/01/14- Jack Herbert sends updated staff list for production of signage.

10/08/14- Biweekly construction administration teleconference.

10/17/14- First semi-truck of furniture delivered to building. Cardboard packaging materials removed the following day.

10/22/14- Second semi-truck of furniture delivered to building. Cardboard packaging materials removed the following day.

10/27/14- Appliances delivered for the Eighth and Ninth Floors.

10/28/14- Final signage installed on both floors.

11/3/14- Owner moves into finished spaces.

125 East Court Street Public Defenders Renovation Eighth and Ninth Floors Read More »

230 WHT Asbestos Study

Project Lead: GBBN

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sent list of buildings to be included in Asbestos Abatement Reporting.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/03/12 – Field work completed, draft report completed and ready for initial review.

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

01/26/13 – BRG confirms entry of ACM data into Archibus is completed.

01/28/13 – GBBN conducts spot review and confirms data entry is accurate.

02/28/13 – Pinnacle sends GBBN a proposed completion schedule for remaining work.

03/11/13 – GBBN sent drawings for the field work to Pinnacle upon their request.

03/18/13 – Tony Matre calls GBBN to request a status check on Pinnacle’s delivery schedule.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

05/29/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

06/26/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

07/24/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

08/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

08/27/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

02/24/14- GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/Web Central is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14- GBBN sends another email and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

8/29/14- Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications to finalize the remaining invoices to close out these projects.

230 WHT Asbestos Study Read More »

230 WHT Public Defenders Renovation Study

Project Lead: GBBN

04/02/13 – Kick-off Meeting with Public Defenders and Facilities Department

04/05/13 – Design Team Kick-off Meeting with IPM.

04/08/13 – SOSS submitted to Bert Watts

04/09/13 – Bert Watts calls to request modified SOSS for Schematic Design and Construction Opinion of Probable Costs only.

04/10/13 – GBBN resubmits SOSS (F086) to Bert Watts.

04/22/13 – GBBN receives approved SOSS with Purchase Order.

04/24/13 – GBBN coordinates with PDO for site visit the following day to field verify existing systems furniture.

05/29/13- Revision made to Archibus estimate as a result of additional programming data from Public Defenders Office.

06/06/13- Revised drawings sent to Public Defenders Office based on changes requested by the PDO.

06/13/13- Revision made to Archibus estimate as a result of the drawing change approvals from PDO on the additional programming data from Public Defenders Office.

230 WHT Public Defenders Renovation Study Read More »

230 WHT Public Defenders Relocation to CAB Study

Project Lead: GBBN

06/13/13 – Kick-off Meeting via conference call to the Facilities Department

06/13/13 – Call to Jack Herbert to ask programming questions per Diana Supe’s request.

06/14/13 – Design Team meeting to discuss scope and deliverables.

06/17/13 – Bert Watts escorts Design Team around CAB 9th Floor Computer Room and adjacent spaces.

06/19/13 – GBBN submits list of scope questions to Diana Supe to finalize scope for SOSS (F088) preparation..

06/21/13 -GBBN finalizes Kick-off meeting date with Design Team, County Facilities and Prosecuting Attorney.

06/27/13 – Kick-off meeting date with Design Team, County Facilities and Prosecuting Attorney held in B-90.

230 WHT Public Defenders Relocation to CAB Study Read More »

230 WHT Public Defenders Renovation 2/3 Floor

Project Lead: GBBN

08/14/13 – Kick-off Telephone Meeting with Diana Supe of the Facilities Department to request the SOSS (F092). Clarifications made on scope in follow-up emails.

08/14/13 – SOSS hours solicited from Interior Project Management and ThermalTech. TEI indicated three separate prime contracts required for the bidding process.

08/15/13 – Diana Supe confirms contract authoring will not be required.

08/16/13 – GBBN submits SOSS to Bert Watts for processing.

08/19/13 – GBBN submits SOSS consultant scope and hour break downs to Bert Watts.

08/28/13 – Kick-off meeting with Public Defenders Office and Facilities Department.

02/25/14 – IPM was contacted by the Public Defenders Office to estimate the move costs of only the staff (Juvenile from 230 WHT and Guardian Ad Litem from 800 Broadway) to the 125 Court Street Facility.

02/26/14 – At the Master Plan Meeting this afternoon Ralph Linne indicated this project is still on hold.

06/26/14 – Project still on hold.

08/26/14 – Project CIP set for start in first quarter 2015.

02/20/15 – GBBN forwards updated SOSS to Bert Watts. SOSS renumbered (F001) for new Architectural Partnership.

03/13/15 – GBBN gets confirmation from Ralph Linne project will be approved soon.

03/20/15 – GBBN, TEI, IPM and Facilities meet with Public Defenders staff to kick-off project. Design of upgrades starting immediately.

03/25/15 – GGBN receives call from Jack Herbert establishing programming meeting to review staffing locations and changes to scope for Friday 03/27/15 at 8:30 am.

03/25/15 – Telecom will assist with coordination on I/T but contractors and associated rates are to be used for estimating.

04/14/15 – ThermalTech on site to conduct MEP fieldwork with GBBN working on RCP for updated background drawings.

04/22/15 – 50% Review drawings sent by ThermalTech to GBBN for Thursday Meeting.

04/23/15 – GBBN held 50% review with client. HVAC zoning was approved. Electrical comments including removing an abundance of convenience outlets on the walls. Small modifications are required to the 2nd Floor Receptionist/Admissions area and Third Floor Conference/Storage area

04/28/15 – GBBN meets with client to review and receive approval for modifications required to floor plan

04/29/15 – Design Team to meet to discuss Phasing and Reflected Ceiling Plan coordination between Architecture and MEP discipline scope.

04/30/15 – During PM meeting we discussed how to handle the room number changes at 230. When room numbers change, how do we want to handle this in the renovation? Bert says that once a number is created it can never be removed because records were assigned in the past. Don’t update the exit signs, discussed the relock lighting system and reusing it. State term contract is okay for buying new furniture but 2nd and 3rd floor have different systems. MB asked about putting in receptacles in all 4 walls and BW said that if PDO is okay with not having convenience on every wall of the new offices, Bert said get this in writing. Carpet tile discussion came up, PDO asked for a color scheme that is not in the carpet tile selection, BW asked if we can get Broadloom pattern in carpet tile. PDO would like to match the 125 color and carpet schemes. Fire Protection work would be best to be done after hours. If the system is down for more than 8 hours, Facilities have to notify Risk Management. If night work is done, the contractor has to hire an evening security guard for the work or use the County private security services.

05/13/15 – 90% Final Review Sets delivered to the PDO and reviewed prior to final bidding. Final comments to be ready for final bid documents by 5/18/15.

05/19/15 – Project Issued for Bid. Prebid scheduled for 5/28/15 at 2:30pm at the building.

05/28/15 – Pre-Bid Meeting to be held at 2:30 pm in the Third Floor Media Room.

06/11/15 – Bids accepted at Purchasing Department. Six bids were received.

06/11/15 – GBBN interviews apparent low bidder, Kramer and Feldman Inc. All appearances are that bid is responsive and KFI will hold their bid. GBBN recommends to Hamilton County that KFI bid is to be accepted.

06/12/15 – Hamilton County accepts GBBN recommendation and authorizes GBBN to author contract for KFI, accepting all Alternate Bids but without any additional allowances added to contract.

06/15/15 – GBBN files Building Permit Application with City of Cincinnati.

06/16/15 – Facilities department requests GBBN make requested modifications, from Prosecuting Attorneys office, to KFI contract. GBBN makes modifications and delivers to Facilities.

06/24/15 – Bert sent out signed contract for KFI today. Contract date established at 6/24/2015. The accompanying Purchase Order was also sent.

230 WHT Public Defenders Renovation 2/3 Floor Read More »

230 WHT East 9th Building Facade Assessment

Project Lead: THP
09/23/15 – County requested an SOSS to complete a façade assessment with 10 year master plan.
12/09/15 – Ground and roof survey complete.
01/28/16 – THP working on the report.
02/25/16 – THP has completed a draft and anticipates delivering a final March 9th.
04/14/16 – THP provided a draft report for review and comment.
04/18/16 – County provided review comments to the report.
04/28/16 – THP provided final copy of the report.
05/26/16 – Ready to archive.

230 WHT East 9th Building Facade Assessment Read More »

230 WHT Public Defender Office Renovation Construction Administration

05/22/15 – Bert Watts requested a new SOSS be issued for the Construction Administration portion of this project.
05/26/15 – SOSS submitted in person to Bert Watts.
06/15/15 – GBBN submits the Building and Mechanical Permits to the City of Cincinnati.
07/10/15 – PDO send along a staffing schedule showing phasing and staff involved with each phase move.
07/13/15 – PDO indicates they need the 3rd Floor Media Room until August 5th. GBBN distributes information to team. John Nester and KFI meet with the building manager to discuss demolition debris removal from the building.
07/14/15 – GBBN receives letter from the City of Cincinnati requesting additional information for building permit.
07/16/15 – GBBN sends response letter back to the City of Cincinnati with additional requested information.
07/16/15 – TEI sends VAV submittal back to GBBN with concerns about the manufacturer of the VAV boxes not matching the existing. Heights above the existing ceiling could be an issue.
07/17/15 – GBBN returns approved OKI Wall and Ceiling Submittals. Ceiling tile, to match existing, is a deduct credit to be handled on the first change order.
07/21/15 – GBBN receives carpet samples from KFI.
07/23/15 – GBBN returns approved carpet submittal to KFI. GBBN sends request to KFI for change order request to order Knoll wall cleats for systems furniture that are no longer available on State Contract. KFI pricing is approved for ordering.
07/24/15 – Signage Submittal received by GBBN. GBBN has requested from PDO a complete list of staff names for the sign inserts.
07/25/15 – GBBN received Door Submittals. GBBN requested information from KFI on millwork shelf for Dutch Door gap between leaves.
07/27/15 – Pre-Construction Meeting held at PDO Media Room.
07/28/15 – GBBN receives requested detail on millwork shelf for Dutch Door. Approved submittals are returned to KFI the same day.
07/29/15 – Pre-Construction Meeting Minutes distributed to attendees via email. TTC provided Energy Impact Study to Bert for project. Titus VAV and Air Device submittals received marked up and returned to vendor as FAC.
08/06/15 – GBBN issues Construction Change Directive #1 to KFI for VAV and other submittal changes.
08/07/15 – GBBN is notified the Building Permit is ready for payment and pick-up. GBBN notifies KFI and Owner.
08/11/15 – GBBN returns Casework Submittals to KFI indicated as “Revise and Resubmit”. Addendum changes to millwork scope are missing from submittal.
08/11/15 – GBBN authorizes door hardware vendor to reduce heavy-duty hardware requirements from standard Office doors to match existing conditions in building.
08/12/15 – GBBN responds to RFI for additional Office dimensions.
08/14/15 – TEI issues RFI response to return air source for Office #23, Room #03188.
08/14/15 – Construction Meeting held at 230 WHT, Second Floor.
08/18/15 – TEI issues Change Directive for I/T upgrades to 1 gigabyte system.

08/19/15 – GBBN issues Construction Change Directive #2 to KFI for changes to Office 03153 north wall.

08/20/15 – TEI issues RFI response for 1″ to 3/4″ VAV water supply piping change.

08/21/15 – Construction Meeting held at 230 WHT, Second Floor.

08/24/15 – GBBN visits Hathaway Warehouse to inspect carpet tile delivery. Delivery approved for billing on next Application for Payment.

08/24/15 – TEI returns HVAC Controls Submittals to GBBN. GBBN forwards to KFI the same day.

08/25/15 – TEI received, reviewed and returned Fire Alarm drawings and submittals for the project to GBBN.

08/25/15 – GBBN returned casework resubmittals to KFI marked “Furnish As Corrected”

08/26/15 – Emcor resubmitted HVAC controls submittals updated to TEI marks and TEI re-approved them in an email back to KFI and GBBN.

08/28/15 – Construction Meeting held at 230 WHT, Second Floor.

08/28/15- Wood flush door submittal returned “No Exceptions”.

09/04/15 – Construction Meeting held at 230 WHT, Second Floor.

09/08/15 – GBBN finalized signage details with CPS.

09/09/15 – Mitch Penick distributes list of Second and Third Floor Cable drops to be installed.

09/11/15 – Construction Meeting held at 230 WHT, Second Floor.

09/16/15 – GBBN visits CPS for validation of signage completion for inclusion onto Application for Payment.

09/17/15 – TEI returns Fire Protection Submittals to GBBN. GBBN forwards to KFI.

09/18/15 – Construction Meeting held at 230 WHT, Second Floor. GBBN approves pencil copy of Application for Payment #1.

09/22/15 – GBBN receives Change Directive pricing from KFI on new blinds, wall mount channels and finalized 1 GB I-T system upgrades.

09/25/15 – Construction Meeting held at 230 WHT, Second Floor.

09/29/15 – GBBN issues Change Order #001 to KFI for signatures.

09/30/15 – GBBN makes site visit to TPC for verification of acoustic wallcoverings for billing. GBBN approves Application for Payment #1.

10/02/15 – Construction Meeting held at 230 WHT, Second Floor.

10/05/15 – GBBN receives change order request from KFI for Receptionist glass type change.

10/09/15 – GBBN attends Construction Meeting. GBBN approves Application for Payment #2.

10/16/15 – Construction Meeting held at 230 WHT, Second Floor.

10/13/15 – KFI sends pricing document for ASI-1.

10/21/15 – GBBN receives call from PDO about making proposed changes for Drug Felony Court staff on Second Floor Lobby.

10/22/15 – TEI sends electrical and mechanical proposed changes to Drug Felong Court Offices to GBBN.

10/23/15 – Construction Meeting held at 230 WHT, Second Floor.

10/26/15 – Facilities responds to KFI that only the second floor restroom ceilings need to be painted.

10/27/15 – GBBN delivers and submits the Engineering Change for the Drug Felony Court Offices to the City of Cincinnati. The processing fee of $46 was paid.

10/28/15 – GBBN issues Change Directive #3 to KFI for the Felony Drug Court Office Changes.

10/28/15 – John inquired about thermostat style. Emcor has been contacted.

10/30/15 – GBBN issues Change Directive #3 to KFI.

11/06/15 – Design Team attends construction meeting. Walk-through performed on Third Floor before meeting.

11/09/15 – GBBN approves Application for Payment #3 and delivers to Bert Watts.

11/12/15 – GBBN submits Engineering Change to City of Cincinnati Buildings and Inspections.

11/13/15 – Design Team attends construction meeting. Walk-through performed on Third floor.

11/18/15 – GBBN issues Change Directive #4 to KFI.

11/20/15 – Design Team attends construction meeting. Walk-through performed on Second Floor.

11/27/15 – Design Team attends construction meeting. Walk-through performed on Second and Third Floors.

12/04/15 – Design Team attends construction meeting. Walk-through performed on second floor. Owner requested more office furniture changes. GBBN approves Application for Payment #4 and delivers final copies to Owner. Keying meeting held with Acme Lock.

12/08/15 – Project is progressing very nicely. ThermalTech collected pricing on changing out the VAV box valves from Triton and sent to Spencer and County. No call from the fire protection vendor about replacing the existing fittings – I am not sure this was done.

12/21/15 – GBBN receives extension of SOSS for additional construction administration.

01/05/16 – GBBN authors and delivers Construction Change Directive #5 to KFI.

01/06/16 – IPM forwards change order pricing from Planes Commercial Services for Owner requested changes for furniture relocation changes.

01/08/16 – Design Team attends construction meeting. Walk-through performed on second floor.

01/10/16 – KFI meets with Building Department Inspector to discuss and attain approval for request to move Second Floor, West Office walls one foot to the east. Inspector approves change request but insists on Engineering Change be submitted to City.

01/11/16 – The owner approves request to move Second Floor, West Office walls one foot to the east.

01/11/16 – TEI and GBBN resolve issue with Triton over incorrect VAV intake air duct sizes. Inspector noticed a 8″ verses 10″ duct installation on the second floor. Triton to replace incorrect 8″ ducts with the correct 10″ sizes.

01/12/16 – GBBN issues Change Order #002 to KFI. GBBN approves, signs and delivers Application for Payment #5.

01/15/16 – Design Team attends construction meeting. Walk-through performed on Second and Third Floors.

01/17/16 – GBBN issues Change Directive #006 to KFI.

01/18/16 – Change Order work for rusted sprinkler lines was not performed due to failure of materials to be delivered onsite.

01/21/16 – IPM issues change order request for changing of Resource Room work surfaces per owner’s request.

01/22/16 – GBBN issues request to Contemporary Plastics, Inc for additional signage along with clarified artwork file and suggested layout drawing at 3rd Floor Receptionist area.

01/22/16 – GBBN attends weekly construction meeting. Approves Application for Payment #6.

01/24/16 – KFI forwards to GBBN the pricing documents for additional owner requested furniture relocation changes.

01/25/16 – ThermalTech discusses MEP issued with Emcor and Triton about balancing and controls. Triton is checking on leaks in third floor and cold calls for us and will open all balance vales. TTC inquired about other changes to existing systems.

01/26/16 – GBBN applies for Engineering Change #2 with the City of Cincinnati Building Department. PDO request made to County Sheriff’s Department for additional panic buttons. Trilogy lock has been programmed by the County Trades Department and security closure problem is solved.

01/28/16 – GBBN paid for and picked up the approval for Engineering Change #2. Final set of approved documents delivered to KFI at weekly meeting on Friday.

02/16/16 – GBBN authors and distributes Construction Change Directive #7.

02/18/16 – GBBN authorizes Contemporary Plastics to execute large additional sign for 2nd Floor Receptionist. Resends digital files.

02/18/16 – TEI issues Electrical Punch List to GBBN.

02/19/16 – GBBN directs contractor to ignore CCD#7 due to additional owner directed changes. GBBN to revise and resend.

02/19/16 – PDO sends directive for relocation of proposed millwork at Admissions scanner location.

02/19/16 – Facilities approves authorization for contractor to make revisions to Admissions Counters and L-shape scanner counter at Receptionist.

02/22/16 – Owner sends Excel File for names to be printed on sign inserts.

02/23/16 – TEI completes electrical punchlist visit and sends the report to GBBN. Per previous conversations, GBBN to collect all of the punch lists from all trades and the owner, and issue at once.

02/23/16 – Owner sends revisions to GBBN on sign insert name list.

02/24/16 – Owner directs contractor to clean existing wallcovering at Media Room in lieu of replacement.

03/03/16 – Facilities sends PDO Punch List to GBBN for inclusion into overall punch list.

03/07/16 – TEI sends itemized change orders from HVAC contractor to GBBN and Facilities.

03/09/16 – GBBN releases copy of Change Order #3 for comments. County and ThermalTech provide comments.

03/09/16 – KFI sends updated Cincy Electric Change Order #3 pricing to GBBN.

03/10/16 – KFI responds with correction recommendations to GBBN Change Order #3 comments.

03/11/16 – County Facilities requested new SOSS to capture As-Built Documents and IFM Data input for record drawings.

03/15/16 – GBBN contacts KFI about painting chipping issue on second floor.

03/21/16 – Facilities agrees to have another change order, #4, to capture any additional items including the additional signage.

03/21/16 – Planes responds to request for modesty panel installation dates to be on site.

03/22/16 – TTC released Mechanical Punchlist Rev 2 to contractors.

03/23/16 – GBBN meets with Contemporary plastics for Large 2nd Floor Reception sign installation. 2nd Floor Signs are to be installed and the inserts, for both floors, are given to PDO for installation. 26 additional signs are requested by PDO via change order.

03/28/16 – TTC discusses status of Mechanical Punchlist Rev 2 with Doug Emery of Triton who reports that the balancer and recommissioning agent were never given authorization to perform the Alternate work. This has been rectified and they will be on site to do this work soon. TTC instructed the contractor to coordinate this work with Ernie Hedricks and make sure he was present for all of this work.

04/11/16 – GBBN forwards full punchlist to KFI.

04/12/16 – GBBN adds the repair and repainting of the northwest stair (material routing) to the punchlist for KFI.

04/14/16 – GBBN authors the preliminary Change Order #3 reflecting pricing that is still missing. KFI requests meeting of all interested parties to discuss change orders.

04/18/16 – Hamilton County indicates they need not be present in the meeting to discuss the change orders.

04/21/16 – Hamilton County sends list to Planes for items, currently stored off-site, to be returned to the building.

04/22/16 – Planes responds to request with proposed schedule for item return.

04/26/16 – KFI indicates all subcontractors have been contacted by KFI for submittal of all remaining change order items and pricing.

04/26/16 – KFI requests on site meeting with GBBN to discuss locations of acoustic wallcovering in the second floor Admissions area. Meeting scheduled for 04/27/16.

04/27/16 – TEI discusses with HamCo Data/Comm department (Mitch) the punchlist items that Tele/Comm has for the project and issues punchlist to GBBN.

04/27/16 – GBBN forwards Tele/Com Punchlist to KFI.

05/23/16 – GBBN requests final back-up from KFI for Change Order #3 and status of Punch List completion.

05/25/16 – KFI sends final back-up for final change order paperwork. KFI indicates punch list work should be completed by end of this week.

06/03/16 – GBBN authors, and mails, Change Order #003 to KFI.

06/14/16 – The final executed Change Order #003 copy is received by GBBN.

06/27/16 – GBBN receives the final copies of Application for Payment #8 from KFI.

06/30/16- GBBN approves Application for Payment #8 and delivers to Facilities Department.

12/29/16 – Project archived by TTC.

230 WHT Public Defender Office Renovation Construction Administration Read More »

230 WHT – Public Defender Office Renovation Project Closeout and As-Built

Project Lead: GBBN

02/29/16 – GBBN submits SOSS to Facilities for approval.

04/08/16 – GBBN sends as-built drawings to Facilities for review.

04/12/16 – Facilities sends approved SOSS to GBBN.

04/15/16 – Facilities indicates the as-builts need to be slightly revised for website access and manipulation. More information to follow.

04/26/16 – KFI requests meeting to discuss locations of acoustical wallcovering to be installed in Second Floor Admissions Suite.

05/13/16 – Planes reports that final modesty panels have been installed, related to their scope of work.

05/18/16 – Bert Watts forwards email with additional directives and answers to GBBN questions related to as-built and IFM input.

05/25/16 – ThermalTech done with mechanical and electrical as-builts. We are moving on to fire protection and plumbing. Ryan working directly with TJ on electronic cad files.

05/23/16 – GBBN requests final back-up from KFI for Change Order #3 and status of Punch List completion.

05/25/16 – KFI sends final back-up for final change order paperwork. KFI indicates punch list work should be completed by end of this week.

06/03/16 – Facilities Department requests scheduling dates and times for final punch list work.

06/24/16 – KFI reports the final Triton change order work will be scheduled for 7/9 and 7/16.

06/22/16 – GBBN completes As-built electronic drawings and uploading to the County IFM/WebCentral database.

06/26/16 – TEI requests Triton coordinate with KFI for warranty’s start dates related to change order work completion.

06/27/16 – GBBN sends copies of all final Punch Lists, from all disciplines and PDO, to Facilities for their records.

07/06/16 – KFI confirms stairwell change order work to be completed by the end of the week.

07/11/16 – TEI informs the team that the change order work scheduled over the weekend was not completed due to existing restrictions.

07/13/16 – John Nester confirms Triton shipment of Terminator Strainers by the end of the day.

07/18/16 – ThermalTech sent revised As-Built CAFM drawings to TJ at GBBN for reprocessing.

07/21/16 – TEI indicates Triton has confirmed the change order scope with their intentions.

07/25/16 – John Nester confirms Triton did not arrive on site for Mechanical Change Order work. Also work to repair material delivery damage in the northwest stairwell was not completed as originally scheduled.

07/26/16 – John Nester communicated the new dates for Triton to perform the change order work will be 8/2/16, 8/4/16 and 8/6/16.

07/27/16 – ThermalTech has Triton has O&M’s under review and has requested new equipment cuts.

08/08/16 – Triton reported today that all the change order work on the valves and unions is complete. They will be back to finish up the diffusers and thermostat after they coordinate with Josh.

08/22/16 – TTC stopped by and performed another back punchlist on the Terminator valves which were found to be complete and spot checked. A couple of other items were emailed to the contractors for changes and the t-stat and Admissions office diffusers were not done. ThermalTech sent email to project team outlining the findings.

08/23/16 – KFI was contacted to confirm that all suspended acoustic tile was used in the construction project. TEI reported a rear hallway has a section of existing suspended acoustic tile sagging and required corrective work. Facilities reported back that Trades has been issued a work order to repair the ceilings due to a potential safety issue.

08/25/16 – Bert asked for us to push for all closeout documents for this job. TTC emailed Triton for new warranty letter for new parts, the rest of the Triton O&M look good.

09/07/16 – GBBN receives pencil copy of Application for Payment #9 from KFI. Facilities approves payment with amount of retainage remaining on application.

09/09/16 – GBBN Signs and Delivers Application for Payment #9 to Facilities.

09/16/16 – GBBN receives executed copy of Application for Payment #9 from Facilities.

09/28/16 – ThermalTech is waiting on O&M’s Cincinnati Electrical Services. Bert request all final bills from all partners and contractors by end of October.

10/18/16 – KFI delivers record set of drawings from City of Cincinnati and three sets of O&M binders to GBBN. GBBN’s In4 Group meets with Facilities to discuss as-built drawing uploading logistics.

10/21/16 – KFI delivers via mail the Close out AIA documents to and red line as-built drawings to GBBN.

10/24/16 – GBBN delivers As-Built Drawings, Record Drawings, AIA Close out Documents and Application for Payment #10 (Final) to Facilities.

10/24/16 – GBBN delivers electronic updated MEP xref as-built drawings to Facilities.

10/27/16 – TTC will hand deliver some additional warranty paperwork from Triton to John Nester for Terminator Valves.

03/21/17 – GBBN confirmed to Facilities all three SOSS projects related to this project have been 100% completed, invoiced and paid.

230 WHT – Public Defender Office Renovation Project Closeout and As-Built Read More »

GENERAL – THP – Engineer’s Galbraith – Garage Lintel Repair

Project Lead: THP
01/27/17 – Hamilton County requested SOSS.
03/02/17 – THP provided Hamilton County with a SOSS.
04/27/17 – Project status THP had two phone conversations with Engineers department over scope and services of SOSS provided by THP. Engineering department plans to recommend the SOSS as is.
05/22/17 – SOSS received for repair
06/14/17 – THP met with County on site to review engineer’s garage lintels project.
06/28/17 – THP anticipates sending out 50% owner review drawings for engineer’s garage.
07/26/17 – Met with Mark M. onsite to review Service Garage 95% owner documents. Set to put documents out next week.
07/27/17 – Met with Mark and gave them review documents last week.
08/02/17 – THP issued bid documents to American Façade Restoration, SSRG, and ZSR. THP invited Lithko, but they declined due to current work load.
08/09/17 – THP issued addendum no. 1.
08/16/17 – THP received bids from Contractors.
08/18/17 – Reviewed bids with County.
08/25/17 – THP issued updated bid documents with to American Façade Restoration, SSRG, and ZSR. Project scope updated to incorporate isolated masonry repairs into 2018 work to provide overall savings.
08/31/17 – Bids dues September 9th
09/07/17 – Contract sent to County for approval.
10/20/17 – County and AFR executed the contract.
10/30/17 – Preconstruction meeting scheduled.11/13/17 – THP visited the site to review buried steel conditions that did not match the original drawings.
11/17/17 – THP issued updated sketches for pricing to modify steel repairs that matched field conditions.
11/20/17 – THP and County agreed verbally to AFR change order pricing. THP issued a change order for the field modifications.
11/28/17 – AFR completed work and cleaning site.
11/29/17 – AFR, Hamilton County, and Hamilton County plan to walk the site to create a final punch list.
02/22/18 – If project is paid out and closed, this can be archived. THP to check.

GENERAL – THP – Engineer’s Galbraith – Garage Lintel Repair Read More »

THP – Facility Building – Envelope Planning Development

01/26/17 – Hamilton County requested SOSS.
03/23/17 – THP developing SOSS.
02/22/18 – Facilities requested overall portfolio assessment report for all the work they have been collected. Historical review of when surveys were completed.
04/04/18 – THP sent SOSS for review.
06/21/18 – SOSS approved.
10/01/19 – THP sent draft format for review.
10/17/19 – HC approved format.
08/27/20 – THP sent report this morning.

THP – Facility Building – Envelope Planning Development Read More »

General Services – THP

09/17/13 – County requested SOSS for 2014 structural services.
09/26/13 – THP issued SOSS.
09/26/13 – Hamilton issued executed SOSS.
01/30/14 – THP waiting for active water infiltration in the Coroner Building to evaluate scope of work. Work will probably occur in the spring.
02/27/14 – Coroner Building work on hold.
06/13/15 – THP met with County to provide review of existing plaza sealant joints and recommendations for future repairs.
08/26/15 – County requested THP review Sprint / Clearwater Tower to be installed on the CAB building.
09/24/15 – THP completed initial review of Sprint Tower, then project placed on hold. County requested typical load capacity of the roof. THP to review with the County.
12/03/15 – County requested SOSS for 2015 structural services.
12/09/15 – THP issued SOSS.
12/10/15 – County approved SOSS.
11/17/16 – Hamilton County requested SOSS for 2017.
01/09/17 – THP provided SOSS.
04/27/17 – THP analysis the computer flooring in 800 Broadway for testing equipment. Based on unit information and response from flooring manufacturer; the unit can be located in the room. THP noted the pallet jack may have trouble with the ramp and could damage the floor.

General Services – THP Read More »

GBBN – 2018 Space Allocation – Drawing Updates

11/10/16 – GBBN is contacted by Facilities to arrange a meeting to discuss a new SOSS and project.
11/13/16 – GBBN authors SOSS and delivers to Facilities.

03/22/18 – Facilities initiates GBBN to begin using this approved SOSS for field verification at 230 WHT Law Center.

04/02/18 – GBBN confirms Facilities contact for initiating the field verification at 230 Law Center.

04/20/18 – 800 Broadway First Floor corrected drawing files were updated and uploaded to the website.

06/25/18 – GBBN files to be updated are attached to email to Facilities for the CAB 10th Floor West Suite. GBBN makes repost and sends CAFM drawings to Facilities.

07/18/18 – GBBN visits 230 WHT Law Center to begin filed verification.

07/19/18 – GBBN revisits 230 WHT Law Center to finish field verification of locked spaces and rooms not accessible the day before.

08/02/18 – Facilities indicates the preferred final order of last two buildings to be field verified and uploaded. The Courthouse is to follow the 230 Law Center.

08/27/18 – John Gilbert, Building Manager, confirms all of the GBBN Departmental Allocations are correct.

08/28/18 – GBBN uploads updated drawings to website.

09/25/18 – GBBN and Facilities communicate about field verification scope for the Justice Center. GBBN will field verify the Justice Center immediately following the Courthouse.

09/5/18 – GBBN emails Building Manager to request escort in building to begin field verification tours of the Courthouse.

09/25/18 – Facilities and GBBN exchange information to document the scope of field verification at the Justice Center Buildings.

10/18/18 – GBBN sends updated Courthouse Departmental drawings to Owner for review.

10/22/18 – Facilities and GBBN discuss scope involving AED and First Aid Kit documentation and review by Owner.

11/28/18 – GBBN to meet with Building Manager today to begin field verification efforts.
12/11/19 – Courthouse 6th floor numbering/room name conflicts are resolved.
12/18/19 – Parking lot updates to theBasement and exterior parking areas are completed.
01/11/19 – GBBN sends Departmental updated drawings to Facilites. Facilities confirms override completed.
01/14/19 – GBBN sends electronic deparmental and architectural drawing updates to Facilities for overriding of existing files.
01/15/19 – Courthouse updated plans in pdf are transmitted from GBBN to Facilities.
01/31/19 – Facilities requests additional outbuildings to be field verified. Building Manager contact information is shared.
07/05/19 – GBBN electronically transfers Updated Field Verified drawings to Facilities for 230 WHT, 800 Broadway, Courthouse and the Justice Center.
08/06/19 – GBBN meets Mike Jackson to field verify 250 WWHT, 264 WHT and 2611 Highland. GBBN confirms with othe Partners that no existing electronic drawing files exist for 2611 Highlands Ave.

08/15/19 – GBBN informs Facilities that Courthouse Room #205 Architectural updates/As-Builts have been completed. MEP updates need to be completed at this time. Facilities suggests waiting until the CAB, 9th Floor Computer Room scope of work has been completed with the Server Room project.
09/24/19 – GBBN only has 2020 Auburn to field verify and document any updates. Contact with Bill Scholl has not be initiated as of yet.
11/21/19 – GBBN meets with Bill Scholl, Building Manager at 2020 Auburn, to walk the building and perform field verification.
12/20/19 – GBBN sends revised Evacuation plans for 2020 Auburn to Facilities.
12/23/19 – Facilities indicates GBBN should renew County access badge to staff working on this project since existing badge is expired.
01/30/20 – Facilities confirms receipt of 2020 Auburn Wayfinding Sign transmission. Pushing to WebCentral to occur in near future.
03/26/20 – GBBN is working with ThermalTech to derive and estimating method for editing the website for As-Builts during an ongoing project.

GBBN – 2018 Space Allocation – Drawing Updates Read More »

GBBN – 2018 Project Request Estimating Binder Assembly

05/29/17 – Hamilton County requested SOSS.
06/01/17 – GBBN contacts ARC to confirm rough printing cost reimbursable costs.
06/05/17 – GBBN authors and provides Hamilton County with a SOSS.
07/11/17 – GBBN is notified by Facilities that printing of the binders will be delayed. GBBN notifies ARC of the same information.
09/22/17 – GBBN is contacted by ARC Reprographics regarding the timetable for this project scope. GBBN to inquire during Partnering Meeting as to the timetable and report back to ARC.
1/22/18 – Facilities sends all Front End Summary Sheets to GBBN for inclusion into the binders.
1/29/18 – Pick-up of binders, CD and other materials by ARC for Binder Assembly.
02/23/18 – ARC delivers entire package of binders to GBBN. GBBN delivers to Facilities the same day.
3/15/18- Facilities issues solution for Reimbursable Expense distribution.

GBBN – 2018 Project Request Estimating Binder Assembly Read More »

GENERAL – GBBN – 2018 Project Request Estimating

Project Lead: GBBN
05/24/17 – Original Project Request Estimate list is issues to Partners at Partnering meeting.
05/29/17 – Hamilton County requested SOSS.
06/01/17 – GBBN has in-house meeting to discuss LEED EB+OM Estimates.
06/02/17 – GBBN forwards LEED EB+OM suggestions to other partners.
06/05/17 – GBBN meets with Planning and Development Staff to discuss Burlington Road Expansion Request.
06/05/17 – GBBN authors and provides Hamilton County with a SOSS.
06/07/17 – Facilities forwards a vendor quote for use in Project Request Estimate #1891.
06/09/17 – Facilities contacts GBBN to add another estimate to the list (#1944).
06/12/17 – GBBN calls THP to discuss combined estimates and dates for background presentations. Facilities instructs GBBN and IPM to discuss and clarify all scopes of work that are separate from the Project Request Estimate included in this list.
06/13/17 – GBBN and TEI have meeting at GBBN to discuss combined project estimates. Facilities confirms which elevators are included in the Project Request Estimate #1932.
06/13/17 – Facilities contacts GBBN to add another estimate to the list (#1945).
06/15/17 – TEI sends GBBN a rough sketch and area identification plan for the JCC Security Booth Project Request Estimate.
06/16/17 – GBBN and TEI meet at the JCC Lobby to discuss Security Booth Project Request Estimate.
06/19/17 – GBBN sends TEI Floor Plan drawing for review.
06/21/17 – GBBN and TEI meet for Design Charrette on Communications Center Expansion Project Request Estimate #1897.
06/23/17 – GBBN/In4 and Facilities have multiple discussions on the continuing problem of uploading digital photograph files into the Archibus CAFM Software.
06/26/17 – GBBN/THP/TEI agree with Facilities on approach for the LEED EB+OM Base and LEED estimate logistics.
06/27/17 – GBBN, IPM and Facilities walk the Courthouse Floors visiting all restrooms. Decision is made on which restrooms are to be included in estimating.
06/28/17 – GBBN sends drawing of applicable Courthouse Restrooms to TEI for their use in estimating.
07/10/17 – Facilities confirms the operator costs are to be included in the Project Request Estimate #1879.
07/11/17 – GBBN is notified by Facilities that printing of the binders will be delayed. GBBN notifies ARC of the same information.
07/14/17 – Facilities requests Estimate #1903 be revised to include four (4) sets of double doors and two (2) single stair doors.

04/02/18 – Test Edit

GENERAL – GBBN – 2018 Project Request Estimating Read More »

GBBN – Campus Buildings – NFPA 80 Fire Doors

01/27/17 – Hamilton County requested SOSS.
03/02/17 – THP provided Hamilton County with a SOSS.
04/03/17 – GBBN meets with Facilities to review existing building drawing and specification documents.
04/20/17 – SOSS approved and delivered along with Purchase Orders.
09/13/17 – GBBN begins on this project and drawing research commences.
03/09/18 – Facilities transmits additional documents for the fire door ratings, including original construction documents, submittals and Door Schedules.
03/11/18 – GBBN sends first building inventory compilation to Facilities for review. Facilities recommends door totals along the bottom of the inventory for simplicity.
03/18/18 – GBBN completes 5 of 6 building Inventories. Justice Center is to be completed once Facilities locates original construction documents.

04/11/18 – Facilities confirms all sources for original construction drawing Door Schedule or Life Safety Drawing have completed without success in finding any. GBBN is instructed to complete the Justice Center listing using their best professional judgment on fire door locations.

07/11/18 – Facilities confirms only swinging doors are to be included in listings. Also confirms the Alternate Bids from original construction that were accepted.

07/13/18 – All six (6) final reports for existing fire rated doors is sent to Facilities.

 

07/16/18 – Facilities confirms the scope of work has been completed.

 

GBBN – Campus Buildings – NFPA 80 Fire Doors Read More »

GBBN – Space Allocation – Drawing Updates

12/12/16 – GBBN is contacted by Facilities to arrange a meeting to discuss a new SOSS and project.
12/13/16 – GBBN authors SOSS and delivers to Facilities.
12/20/16 – GBBN receives approved SOSS.
01/26/17 – Bert says they will have to go into each building and look for building changes and update these onto the CAFM Archibus changes.
03/21/17 – GBBN and In4 meet with Facilities to discuss next step and phase of this project related to the County Administration Building.
03/31/17 – GBBN meets with John Gilbert to begin Field Verification of CAB all floors.
04/10/17 – GBBN transmits updated drawings to Facilities for purpose of mark-ups of Departmental Allocations.
06/15/17 – GBBN meets with Building Management to walk entire building and perform field verification at 800 Broadway.
08/18/17 – GBBN re-ran hatch pattern software on each CAB Floor Plan from CAFM. Adjusted plans were sent to Facilities.
08/23/17 – GBBN forwards to Risk Management Safety Department the GBBN modified Alms & Doepke Life Safety Plans for internal review.
08/24/17 – Risk Management Safety Department approves GBBN modified Alms & Doepke Life Safety Plans.
08/25/17 – CAB Chargeable Area issues discussed with GBBN/In4. Review of the CAB Plans were run and a discussion about Pro-Rated Areas and Space Managers commenced.
08/28/17 – GBBN / In4 responded about Chargeable Areas with updated Pro-Rated documents for Facilities’ Review.
09/15/17 – Tim Schuh, of Facilities, reports back that “Update Area Totals” are only run when the drawings are updated.

02/16/18 – Facilities sends email requesting 800 Broadway Life Safety and Departmental Allocation drawings be printed in pdf and sent to Facilities. Also A&D Departmental Allocations Drawings.

02/20/18 – GBBN sends all requested pdf files to Facilities.

02/21/18 – Facilities requests additional Chargeable Area revisions to the 800 Broadway Sub-Basement, 1st, 2nd, 4th, 6th, 17th and 18th Floor Space Allocation Plans.

02/21/18 – Facilities requests all of the County Administration Space Plans be revisited for consistency in Chargeable Area verses Room Area Breakdowns.

02/22/18- GBBN sends 800 Broadway 17/18th Floor plan updates to Facilities.

03/21/128 – GBBN completes updates to all 800 Broadway on IFM.

03/22/18 – GBBN uploads 17/18th Floor updates to IFM with modifications to updated Departmental Allocations.

GBBN – Space Allocation – Drawing Updates Read More »

GBBN – Family Restrooms – Prototype and Estimate

Partner Lead: GBBN
10/11/16 – GBBN is contacted by Facilities to arrange a meeting to discuss a new SOSS and project.
10/13/16 – IPM and GBBN and ThermalTech hold meeting with Facilities to discuss new SOSS. New project is to design a prototype single-sex/Family restroom to be added new or a renovation of an existing restroom for use by the public. Intent is to determine any existing code requirements affecting this need and locations for them.
10/18/16 – ThermalTech sends proposed labor hours for MEP to GBBN.
01/26/17 – Study can be started with the goal of creating a unit box cost for creating these in a typical office space in any building. Specifics of putting these in each building can be done later. GBBN to determine how many are required in each building and where they may go (e.g. only in public JC bldg and maybe every other floor in 800, TBD by Architect).
01/30/17 – GBBN reports findings from the Department of Justice Technical Assistance Services. Comments related to requirements for gender neutral, civil rights, plumbing and local verses Federal Laws.
08/29/17 – GBBN completes two possible layouts and forwards to TEI for review. TEI provided review comments to GBBN and plumbing fixtures to use, Amer Std is the BOD for this project. GBBN will expand plan to section and keep working on this project.
11/30/17 – GBBN will send final layout to TEI and TEI will price up the cost to build this “inside the project scope area”. Ancillary areas not included in this estimate.

02/12/18 – GBBN completes drawing updates and entry in Archibus Project Request Estimate #1950.

GBBN – Family Restrooms – Prototype and Estimate Read More »

GBBN – Master Plan Services – Existing and Future Buildings

10/12/15 – Facilities notifies GBBN the UC Reading Road Campus option will not be pursued any further. GBBN requested to submit a new SOSS for Master Plan Services for Existing and Future Buildings”.
10/12/15 – GBBN authors and delivers SOSS to Facilities.
12/08/15 – GBBN receives call from Diana Supe about preliminary approval of SOSS.

08/17/18 – Facilities requests three (3) copies of the Master Plan Phase II printed and delivered to Facilities.

08/21/18 – Copies ordered from Phippps. Facilities confirms printing can be billed to General Services.

09/25/18 – Invoice for printing received by GBBN.

GBBN – Master Plan Services – Existing and Future Buildings Read More »

GBBN – LEED Specifications

01/28/10 – Bert Watts at monthly meeting discussed need for SOSS to be submitted.
03/08/10 – GBBN began editing LEED EB+OM checklist based on 2009 LEED EB+OM manual.
03/11/10 – Energy and Atmosphere webinar held in GBBN’s Office.
03/25/10 – Material Resources Webinar held in GBBN’s Office.
03/26/10 – GBBN internal LEED EB+OM discussions. Tony Yunker to be LEED EB+OM specialist LEED AP.
03/30/10 – GBBN internal LEED EB+OM discussions on costs implications to project and design costs.
04/28/10 – SOSS to be presented to Bert Watts at monthly partnership meeting.
05/12/10 – Signed and Approved SOSS returned.
06/01/10 – Meeting with Phil Babinec, specification writer, to kick-of project.
07/27/10 – Phil Babinec is authoring first protocol and procedural document for review.
08/05/11 – Set of standard specification Table of Contents generated.
02/28/14 – Meeting with specification writer and Professional Services Group about scheduling for completion of this scope of work.
03/03/14 – Internal meeting to reacquaint specification writer on project scope and deliverables.
09/26/14 – Phil is working on these to LEED Version 4. Bert agreed.
12/07/15 – GBBN re-engages the specification authoring. A table of contents and specification master is completed.
12/23/16 – GBBN has in-house staff meeting to discuss agenda for Owner Re-kick-off Meeting.
01/06/17 – GBBN holds follow up in-house meeting to discuss and review items collected as exhibits to share with Owner in next meeting.

GBBN – LEED Specifications Read More »

GBBN – General Services

01/09/15 – GBBN attends interview with Selection Committee at County Administration Building, Room #605
01/30/14 – GBBN attends monthly Partnering Meeting.
01/29/15 – GBBN is notified of their successful renewal of the Architectural Partnership.
02/20/15 – GBBN sends Exhibit B to Facilities Department for use in authoring new contract.
02/24/15 – GBBN sends Exhibit A to Facilities Department for use in authoring new contract.
03/13/15 – Final Approved Contracts received from Hamilton County. Contract initialized with Public Defender’s Office 2/3 Floor Renovation Project. No General Services SOSS requested.
05/12/15 – General Services SOSS requested by Bert Watts.
05/26/15 – SOSS hand delivered to Bert Watts.
06/25/15 – GBBN attends monthly Partnering Meeting.
07/30/14 – GBBN attends monthly Partnering Meeting.
08/27/15 – GBBN attends monthly Partnering Meeting.
09/24/15 – GBBN attends monthly Partnering Meeting. Delivered new SOSS for extension.
10/29/15 – GBBN attends monthly Partnering Meeting.
11/03/15 – GBBN delivers SOSS #F010 for 2016 General Services to Facilities.
12/07/15 – Facilities transmits approved SOSS to GBBN.
12/09/15 – GBBN attends monthly Partnering Meeting.
01/28/16 – GBBN attends monthly Partnering Meeting.
02/19/16 – GBBN and Facilities agree to terms for Construction Administration Submittal Review scope for CAB Lobby Building Security to be billed to General Services.
02/25/16 – GBBN attends monthly Partnering Meeting.
03/23/16 – Facilities inquires about potential services for the IFM/WebCentral Space Plan updates for the 800 Broadway northwest corner. GBBN sends an estimate of hours required for the services.
03/31/16 – GBBN attends monthly Partnering Meeting.
04/18/16 – GBBN reviews and approves CAB Lobby Security Millwork Submittals.
04/26/16 – GBBN performs Hamilton County Internal Contract Updates.
04/28/16 – GBBN attends monthly Partnering Meeting.
05/26/16 – GBBN attends monthly Partnering Meeting.
06/28/16 – GBBN completes website updates.
06/29/16 – GBBN attends monthly Partnering Meeting.
07/27/16 – GBBN completes website updates.
07/28/16 – GBBN attends monthly Partnering Meeting.
08/24/16 – GBBN approved for CAB Monitor Relocation services via the General Services.
08/25/16 – GBBN attends monthly Partnering Meeting.
09/29/16 – GBBN attends monthly Partnering Meeting. GBBN asked to inquire about renewel of 800 Broadway LEED EB+OM Certification verses new LEED version.
10/04/16 – GBBN responds to Facilities about the Recertification requirements for 800 Broadway after research by GBBN’s LEED specialist.
10/27/16 – GBBN attends monthly Partnering Meeting.
12/05/16 – GBBN submits SOSS for 2017 General Services.
01/07/17 – GBBN received approved SOSS.
01/17/17 – THP sends BOCC Title Sheet updates to GBBN.
01/26/17 – GBBN attends monthly Partnering Meeting.
01/30/17 – Facilites sends updated Purchase Orders for LEED Specifications and ADA Assessment (CAB) due to erroneous closing of both SOSS.
02/02/17 – Facilities sends Small Business updates to GBBN
02/16/17 – Facilities sends Green Seal Paint Information to GBBN.
02/17/17 – Facilities sends OSHA Fact Sheet to GBBN
02/23/17 – GBBN attends monthly Partnering Meeting.
03/23/17 – GBBN attends monthly Partnering Meeting.
04/24/17 – GBBN discussed with Facilities, generating renderings of 800 Broadway, for the suggested security camera installations on this project. The intent is to interface with the City of Cincinnati Historic Preservation Department for approval.
04/04/17 – GBBN participates in “History In Your Own Backyard” filming for the Alms and Doepke Building.
04/27/17 – GBBN attends monthly Partnering Meeting.
05/16/17 – GBBN emails City of Cincinnati Historic Conservator about impending Security Camera placement on front facade of building.
05/18/17 – GBBN calls City of Cincinnati Historic Conservator about impending Security Camera placement on front facade of building. A voice mail is left.
05/19/17 – City of Cincinnati Historic Conservator emails GBBN to indicated this building is not “locally registered, but is Federally Registered”. This results on no requirement for evaluation by the City of Cincinnati, only Federally but only if Federal Funding is used for the project. GBBN reports findings to Facilities.
05/25/17 – GBBN attends monthly Partnering Meeting.
06/08/17 – GBBN attends meeting at Courthouse, Room #115 to discuss potential Reconfiguration of southern space in office. Facilities determines this can be handled through State Term contracting in lieu of a new SOSS.
06/29/17 – GBBN attends monthly Partnering Meeting.
07/18/17 – GBBN attends City of Cincinnati Buildings and Inspections seminar on Accessibility. Discussed changes with Facilities as an update to the Accessibilities Assessments.
07/27/17 – GBBN attends monthly Partnering Meeting and completes Website Updates.
08/31/17 – GBBN attends monthly Partnering Meeting and completes Website Updates.
09/25/17 – GBBN attends monthly Partnering Meeting and completes Website Updates.
10/26/17 – GBBN attends monthly Partnering Meeting and completes Website Updates.
11/30/17 – GBBN attends monthly Partnering Meeting and completes Website Updates.
01/25/18- – GBBN attends monthly Partnering Meeting and completes Website Updates. After Partnering Meeting a separate meeting for the new Website Software was held.
02/21/18 – GBBN updates Website using new software.
02/22/18 – GBBN attends monthly Partnering Meeting.
03/22/18 – Facilities authorizes GBBN to author a Gantt Chart for Administration showing the entire anticipated project Schedule for the HCJC Recovery Unit Build-Out.
03/23/18 – GBBN sends Gantt Chart to Administration for review.
03/26/18- GBBN attends Justice Center Space Augmentation Project Meeting.
03/29/18 – GBBN attends monthly Partnering Meeting and completes Website Updates. After Partnering Meeting a separate meeting for the new Website Software was held.
04/23/18 – Facilities determined Justice Center State Grant Budget and Schedule Analysis would be separate SOSS and not part of General Services.
05/31/18 – GBBN attends monthly Partnering Meeting.
06/28/18 – GBBN attends monthly Partnering Meeting.
07/26/18 – GBBN attends monthly Partnering Meeting and completes website updates.
08/29/18 – GBBN completes updates to Website.
08/30/18 – GBBN attends monthly Partnering Meeting.
08/17/18 – Facilities requests three (3) copies of the Master Plan Phase II printed and delivered to Facilities.
08/21/18 – Copies ordered from Phippps. Facilities confirms printing can be billed to General Services.
09/25/18 – Invoice for printing received by GBBN.
09/27/18 – GBBN attends monthly Partnering Meeting.
10/25/18 – GBBN attends monthly Partnering Meeting.
11/29/18 – GBBN attends monthly Partnering Meeting.
01/03/19 – Facilites confirms CH Room #205 Permit Reimbursable Expense may be billed to this General Services SOSS.
01/31/19 – GBBN attends monthly Partnering Meeting.
02/28/19 – Monthly Partnering Meeting moved to tomorrow due to conflicts.
03/01/19 – GBBN attends monthly Partnering Meeting.
03/28/19 – GBBN attends monthly Partnering Meeting.
04/25/19 – GBBN attends monthly Partnering Meeting.
05/30/19 – GBBN attends monthly Partnering Meeting.
06/27/19 – GBBN attends monthly Partnering Meeting.
07/22/19 – Facilities agrees to invoice #F072 CAB 10th Floor Conference Room Community Developmenmt project, with unapproved SOSS. to General Services.
07/25/19 – GBBN attends monthly Partnering Meeting.
08/29/19 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
09/26/19 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
10/31/19 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
12/12/19 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
01/30/20 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
01/31/20 – Facilities confirms GBBN can discontinue attending any future Partnering Meetings after the March meeting.
02/27/20 – GBBN completes website updates and GBBN attends monthly Partnering Meeting.
03/26/20 – GBBN completes website updates. The regular Partnering Meeting is cancelled due to COVID-19 and State of Ohio shutdown.

GBBN – General Services Read More »

Comm Center – Emergency Power Study

Partner Lead: TEI
02/25/17 – TEI receives call from AKM that the power system at the Comm Center is having glitches – where the building has lost power and emergency generators have not started twice since last summer. TEI, AKM, Mike Jackson, Duke, and the generator reps and maintenance contract companies are all meeting on site on 02/24/17 to analyze the cause and develop corrective actions.
05/25/17 – Estimate is on 2018 project list for entire power assessment for this site.
02/22/18 – Ready to archive.

Comm Center – Emergency Power Study Read More »

BOE – Training Center Renovation Build-Out

11/10/17 – Facilities requests SOSS be prepared by GBBN.11/14/17 – GBBN authors and delivers SOSS to Facilities.
11/13/17 – TEI submits MEP scope of services to GBBN.
11/14/17 – GBBN authors and delivers SOSS to Facilities.
11/15/17 – BOCC approves BOE Training Center Build-Out project to proceed.
11/29/17 – GBBN and TEI attend Client project kickoff meeting on 11/29/17. Discuss schedule, budget, and design parameters. Additional Field Verification done and photographs taken.
11/30/17 – Next review meeting for IT is 12/13. The SD presentation meeting is scheduled for 12/20. TEI does not need a site plan, roof plan or underslab drawing for this work. GBBN will send us updated plans next week. GBBN can also send section and wall cuts soon.
01/25/18 – Review sets given to BOE for review by BOE and Bldg Owner. We are waiting on comments back and then we will bid this project out. GBBN will update specs and bid dates
02/09/18- Oswald supplies carpet and toilet accessory selections from recent renovation for use in replicating the same in the new build out.
02/16/18 – BOE requests small vision lights be added to Training Room doors for visibility into rooms from Lobby.
02/20/18 – ThermalTech to complete bid sets to send to GBBN for 02/26/18 issuance.
02/20/18 – GBBN distributes ITB information. ITB#021-18 selected by Purchasing. Existing Prevailing Wage Rates will be used due to no new substantive changes made recently. BOE approves 3/7/18 at 10:00 am as Pre-Bid Meeting date.
03/07/18 – Pre-Bid Meeting held at 4700 Smith Road. Meeting Agendas prepared by GBBN are issued and Minutes Recorded along with a Sign-In-Sheet filled out.
03/13/18 – Addenda #1 with Pre-bid Meeting Minutes was issued.
03/15/18 – Addenda #2 issues by ARC and Purchasing.
03/22/18 – Bid opening extended to 3/28/18. Addendums 1-4 released and update the budget and scope to take mechanical deduct alternate for a different control packages.
03/26/18 – GBBN meets Dorn Fire Protection to tour building and contract site.
03/27/18- City of Norwood Building Department was contacted for information on Permitting requirements and logistics.
03/28/18- TEI contacts Hamilton County Plumbing Department about submissions for Permitting.
03/29/18- Bid Opening to be held at 11:00 AM at CAB, Room #507. Apparent low bidder is John P. Tumlin and Sons, LTD.
04/04/18 – GBBN holds Bid Interview with Douglas Tumlin. Meeting Minutes and recommendations send to Facilities. Facilities issues decision to proceed with the contract authoring to John P. Tumlin and Sons, Ltd.
04/05/18 – Facilities reviews and approves final AIA Contract copies to be printed and delivered to Facilities.
04/12/18 – Facilities informs GBBN that the contracts have been approved.
04/18/18 – GBBN submits permit applications for Building and Mechanical Permits to the City of Norwood.
05/01/18 – Plumbing and Fire Protection stamped and signed drawings sent to GC for permitting.
05/08/18 – GBBN/TEI send Plumbing CAD drawings to contractor.
05/08/18 – GBBN forwards tax exempt form to Contractor via Facilities.
05/09/18 – GBBN forwards CAD reflected ceiling plan to Electrical Contractor.
05/10/18 – GBBN forwards Oswald Keying and Wood Door finish information to Contractor.
05/10/18 – TEI forwards Plans Examination language to GBBN for Revision letter.
05/10/18 – Door Hardware Submittal returned from GBBN to GC.
05/11/18 – TEI forwards MEP Revision Draiwngs to GBBN.
05/11/18 – GBBN sends Construction Change Directive (CCD) #1 to GC.
05/11/18 – GBBN coordinated revised door swings, locations and hardware with Facilities, BOE and Door Hardware Consultant. Plan Revision letter finalized.
05/17/18 – City of Norwood notifies GBBN that Building and Mechanical Permit are approved. Owner and GC are notified.
05/22/18 – Certified Letter from Becker Electrical forwarded from Purchasing to Facilities and GBBN. GBBN forwards Plan Revision Letter and documents to General Contractor. GBBN completes and forwards revised Door Submittal to GC. TEI sends approved Light Fixture Submittals to GBBN, then forwarded to GC.
05/23/18 – Pre-Construction Meeting is held at BOE Offices. City of Norwood informs GBBN that specification books were not included in permit approval package picked up by GC. Tumlin notified. HVAC and Plumbing Fixture Submittals returned by TEI and forwarded to GC. TEI informs resubmittal will follow for Pressfit.
05/24/18 – Electrical Stamped and Signed Drawings given to Electrical Contractor for IBI Permit. First of Tumlin Background Checks have cleared the Local stage.
05/29/18 – ThermalTech attended pre-const meeting with project team and has completed submittal review for the plumbing and HVAC for this project. TTC will try to complete the Fire protection review by 5/31. Plumbing press-fit fittings were approved for use on this project.05/30/18 – GBBN distributes Pre-Construction Meeting Minutes to all attendees. Plumbing Re-submittal approved by TEI and distributed by GBBN to GC. TEI reviews Fire Protection Submittals and indicates “Revise and Resubmit”. GBBN forwards to GC.
05/31/18 – Fire submittal was asked for revise and resubmit and returned to the contractor. Electrical still needs to see conduit and feeders and lights. Flooring samples are approved.
06/06/18 – Construction Meeting #1 is held at BOE. Site investigation and photos are taken. Wood Door stain approval is hand delivered.
06/13/18 – Construction Meeting #2 is held at BOE. Site investigation and photos are taken.
06/20/18 – Construction Meeting #3 is held at BOE. Site investigation and photos are taken. It was determined the plumbing for the restrooms are were switched. Plumbing inspection was held
06/27/18 – Construction Meeting #4 is held at BOE. Site investigation and photos are taken. Change Order #1 originals, signed by the Architect, are delivered to JPT for signatures.
07/11/18- GBBN issues Construction Change Directive #2.
07/20/18- Signed copy of Application for Payment #2 is received by GBBN from Facilities.
07/24/18 – GBBN resends permission letter from BOE to Tumlin, copied to LaForce and Kleine and sons, concerning the lock core bit number/key for new core keying.
07/25/18 – Construction Meeting #5 is held at BOE. Site observation and photos are taken. Punchlist date to coincide with Construction Meeting #7 on 8/8/18. TTE followed up on some plumbing, fire and hvac items with the contractors. GBBN also completed Architectural/GC Punch List.
08/01/18 – Construction Meeting is held.
08/08/18 – GBBN and TEI conduct Punch List inspection. Construction Meeting is held afterwards.
08/15/18 – GBBN receives Application for Payment #3 (after requested revisions from Pencil Copy Review).
08/16/18 – GBBN resends all door keying information from bidding to Tumlin to be forwarded to LaForce once again.
08/17/18 – GBBN forwards approved Application for Payment #3 to Facilities.
08/24/18 – Build-Out review meeting with BOE personnel. TTE completed back punchlist of MFEP items and submitted back to GBBN for distribution for the project. GBBN submits all Punch Lists and Back Punch Lists to Facilities for all disciplines.
08/25/18 – GBBN receives from Tumlin the completed and signed Punch Lists including the completion of the Fire Protection Record.
08/28/18 – GBBN receives via email Change Order Request #3 from Tumlin.
08/29/18 – Pursuant to the Counties directive the Construction Change Order Request from Tumlin is rejected.
09/07/18 – GBBN approves pencil copy of Application for Payment #4.
09/11/18 – GBBN signs and delivers Application for Payment #4 to Facilities.
09/17/18 – GBBN receives Warranty and Close out Manuals from Mayers Electric via transmittal from Tumlin.
09/27/18 – GBBN turned over electrical closeout documents to TTE for review and approve. BOE confirmed the access controls are done, cleaning is scheduled, supplies are ordered, training is scheduled for next week. HVAC training still needed.
10/02/18 – GBBN receives Mayers Electric Signed Completed Punch list.
10/08/18 – GBBN signs and delivers Final Application for Payment #5 to Facilities for Processing.
10/23/18 – TEI reviews electrical close out documents and delivers to HCFD for archiving. ThermalTech sent all plumbing field work to Bert for clogged drain issue.

1/21/19 – GBBN recieves closeout documents from Tumlin. MEP portion distributed to TEI for review. Closeout AIA documents sent to Facilities.

1/18/19 – TEI acknowledges approval for MEP closeout documents. Still awaiting as-built drawing from MEP Subcontractors.
02/26/19 – GBBN recieves inquiry from Tumlin concering closeout of Application for Payment #5.
02/27/19 – GBBN meets with Facilities to review all closeout documents in possession of both GBBN and Facilities. A final list of the missing items is inventoried and reported back to Tumlin.

03/26/19 – Final fire alarm inspection scheduled to be performed at 1:30 on 03/28/19. Project closeout will be completed after the final inspection.

BOE – Training Center Renovation Build-Out Read More »

CAB – Conference Room #607A/B – Two Office Renovation

Partner Lead: GBBN
09/06/17 – Facilities contacts GBBN and requests that a new SOSS be authored for this first phase of the overall project. Facilities confirms the west wall of the existing Conference Room is to be converted to a glass storefront similar to the GBBN Standards Build-out proposal.
09/07/17 – GBBN issues SOSS to Facilities.

CAB – Conference Room #607A/B – Two Office Renovation Read More »

CAB – Sheriff Re-Entry Renovation Study

06/05/17 – Facilities contacts GBBN about new project and scheduling for Kick-off Meeting.
06/06/17 – GBBN sends Facilities and TEI quick floor plan of the scope discussed in the meeting.
06/08/17 – GBBN quick floor plan of the scope discussed in the meeting to IPM for further investigation. IPM agreed little other options are possible due to the tight spatial constraints. Any other options would not affect estimating.
06/26/17 – GBBN meets with Re-Entry Staff to discuss 2018 Project Request Estimates #1877/8 and possible differences from Estimate #1941.
06/27/17 – GBBN , Facilities meets with Re-Entry Staff to show Four Options for the Renovation. Option #3, without Interview Rooms was selected. Estimate #1877 for the 2018 Estimates was eliminated. Option #4 presented in the meeting will be used for the Estimating Purposes.
07/14/17 – Facilities reports back to GBBN indicating which final version of plan is to be finalized in the Archibus Project Request Estimate. TEI confirms the final layout will not dictate any MEP cost revisions to the estimate. The estimate has been finalized.
02/22/18 – Project ready to archive.

CAB – Sheriff Re-Entry Renovation Study Read More »

CAB – Conference Room #607A/B Office Renovations/CAB 6th Floor West Office Renovations/Standards

Partner Lead: GBBN
02/16/17 – Facilities contacts GBBN about new project and scheduling for Kick-off Meeting.
02/21/17 – GBBN meets Facilities and Traci Paquette at the CAB to hold Kick-off Meeting.
02/22/17 – GBBN contacts TEI to discuss scope of project and to discuss questions for Facilities concerning the CAFM/As-Built requirements. GBBN sends question to Facilities for answers. Facilities sends answers to GBBN.
04/26/17 – GBBN meets with Jeff Aluotto and Facilities to discuss expanded scope of work, for more of the same office suite. New finish palates, layouts and associated renderings will be generated. Various options for new office suite layouts and material selections for most of the west half of sixth floor.
06/09/17 – GBBN meets with Administration to present conceptual ideas for proceeding on the CAB 6th Floor West Office Suite.
07/20/17 – GBBN meets internally to discuss the latest developments on the project. GBBN later sends scope questions related to next steps and future regular status update meetings. Facilities responds to GBBN’s questions about next steps with the project and next SOSS. Preliminary contact with made with Theresa before Jeff Aluotto’s pending vacation. Facilities will report back with more input from Theresa concerning the scope required for the next SOSS.
07/26/17 – GBBN finalizes details with RCF concerning Mock-Ups and systems furniture. carpet and glass wall installation capabilities by RCF. GBBN forwards electronic drawing files to RCP for use in organizing mock-ups.
08/03/17 – Facilities confirms Trades can install Electrical Whips for new systems furniture.
08/08/31 – GBBN receives communications from River City Furniture Representative for State Term Contracting.
08/10/17 – GBBN authors SOSS, specifically for this modified scope of work, and delivers to Facilities.
08/25/17 – GBBN receives call from Facilities confirming project is on hold. Facilities requests construction estimate for scope of work be completed before GBBN terminates work.
08/31/17 – GBBN receives clarifications on scope of estimating from Facilities.

10/23/18 – Jeff Aluotto makes request through Steve Kenat that all latest Design information from this project be forwarded to his attention.

CAB – Conference Room #607A/B Office Renovations/CAB 6th Floor West Office Renovations/Standards Read More »

CAB – Chiller and Cooling Tower Replacement

11/17/16 – THP – Hamilton County requested SOSS from THP and TEI about this same time.
01/25/17 – ThermalTech receives signed SOSS and PO for this project.
02/02/17 – Getting data back from Trane, Carrier and York. No one can do Centrifugal at 208V for this job except Carrier but they have to remote mount the starters and controllers somewhere else. Trane.
02/16/17 – TEI, facilities and building manager meet to kick off project.
02/22/17 – ThermalTech working on LCC and marginal rates from Duke. Amy, Annie and Terry working on LCC worksheets. TTC got new Duke Rate sheet from Michelle
02/23/17 – The County provide direction today to size the new chillers for the addition of 9th and 10th floor in the future. check piping sizes and pumps and cooling tower for the future load as well. TTE to take this into account for new design.
03/09/17 – TTE sent new email to County with recommended Chiller sizes. We are awaiting a new submittal from Trane to confirm physical sizes of new chiller shells. TTE awaiting County’s best guess of combined chiller load during summer. Emcor says they do not have this information on file.
03/15/17 – Based on conversation with HamCo and ThermalTech load calcs we are gong to proceed with a 350 ton chiller as the base chiller for this project. This gives us enough future machine to handle the addition of the 9th and 10th floors if and when those spaces are renovated.
03/21/17 – LCC equation complete. TTC writing bid specs for vendors.
04/26/16 – First set of quotes have arrived at ThermalTech. We are beginning the LCC process.
05/24/17 – Met with County presented LCC results for this project. Narrowed selection down to two chillers to be used in bid. ThermalTech conducted more fieldwork for the replacement project.
06/12/17 – THP – Provided a proposal for structural engineering design services to Thermal Tech.
06/26/17 – We are down to two chillers one for the base bid with standard refrigerant and one with future refrigerant. We will design around these two machines for the bid. We have finally reached three workable designs on the cooling towers, one from Marley, one from BAC and one from Evapco. The Marley solution consists of four cooling towers, Evapco and BAC consists of 2 towers. We are trying for a July bid opening for this project or maybe early August.
06/28/17 – County okay with bidding out two chiller options and three cooling tower options, ThermalTech to bid out in July and start construction ASAP knowing that CT may be done in 2018.
07/12/17 – THP notified via email proposal is acceptable.
07/24/17 – Chilled Water pumps are scheduled to arrive next week. TEI to work with DK to get installed in a fashion that works for this job. Change Order submittal must be discussed. Three cooling tower options have been design, one base bid, two alternates. After field work from last week, even these designs are very tight. TEI to meet with THP and discuss. A new review set is ready for County review.
07/27/17 – Penthouse roof under warranty with Tremco and its the white aggregate. THP will start design on the dock and roof next week.
08/15/17 – THP provided review letter for proposed new cooling tower loading.
08/18/17 – THP provided review drawings for structural and waterproofing repairs at the loading dock.
08/30/17 – Project is out for bid. Prebid scheduled for 1:30pm on 9/14/17. THP issued structural and waterproofing loading dock repair documents.
09/18/17 – THP issued addendum 01 questions responses to TEI.
09/25/17 – Addendums 1,2,3 have been issued on this project. We have extended the Bid Opening to Oct 4, 2017.
10/24/17 – Bid were opened and both bids (Peck and DK) were over budget. A post bid analysis was completed by ThermalTech and delivered to Facilities on 10/24 for their use. Several items were identified as being out of scope, under estimated, or omitted from the original scope. The analysis found that the project probably is about $380,000 to $420,000 above the original scope estimate.
11/28/17 – ThermalTech collected new bids on alternate equipment in an effort to get this project in under the original budget. We have received pricing from Trane, JCI and McQuay. We are working on an LCC cost to go along with this equipment to see hat impact the different equipment types have on the project.
11/30/17 – Final prices due by 12/1 at 2pm to Bert. TTC and Barth to take care of.
01/25/18 – ThermalTech to rebid the chillers out as air cooled chillers for LCC then bid this out as a new project.
02/21/18 – ThermalTech preparing new bid for LCC Air Cooled Chillers. We should have this out for bid in a week. TEI has fully developed the PID for the new air cooled chiller scenario and reviewed internally to make sure it works being a departure from the existing system and it will work. Some piping modifications will take place, a bypass will be moved and the chilled water return on the air handlers on the first floor must be reconnected in a different place. TEI also laid out new chillers on the roof structure and they are too big to fit into the old penthouse area so we developed two alternate scenarios where they can sit on the roof between the existing DX rooftop units. TEI contacted THP for SOSS to redesign the system for the new locations. TEI will submit revised plans and cost to Facilities within a week.

CAB – Chiller and Cooling Tower Replacement Read More »

CAB – Lobby Finishes

Partner Lead: GBBN
10/10/16 – Facilities emails GBBN about conversations with Paula Drake with the Auditor Office. She would like to discuss after our next 3rd Floor Meeting.
10/21/15 – IPM and GBBN are approached by Facilities Department to propose additional upgrades to the interior Lobby finishes in addition to the Security Office upgrade.
12/18/15 – IPM and GBBN submit proposed refinishing concept including lighting upgrades and Opinion of Probable Costs to Facilities Department.
10/13/16 – GBBN is approached again by the County to propose changes to the directory and accent wall in the Lobby by Jeff Aluotto. GBBN discovers the new Directory supplied on the recent project is not the one specified and therefore installed in the incorrect location.
10/17/16 – GBBN and Facilities are approached by Paula Drake, Auditor Office, after a meeting on the 3rd Floor Project, to discuss Lobby finishes and Paula’s ideas on how to proceed.
10/17/16 – GBBN authors SOSS for two options and associated Opinions of Probable Costs on the Lobby Finishes. Projected completion date is 10/21/16.
10/21/16 – GBBN requests additional time from Facilities to complete the task.
02/23/17 – No new information, probably of year if this project goes forward.
03/21/17 – Facilities discusses owner requested small changes to most recent Lobby Renovation presentation package. A mark-up of the presentation is given to GBBN and the changes were discussed
04/25/17 – GBBN has completed mark-ups and waiting to complete renderings of front Elevation and Blade Signage recommendations to present to Owner. GBBN will adjust the budget for this job.
08/31/17 – GBBN can finish up report, project will be on hold after that.
09/07/17 – GBBN receives final estimating input from The RCF Group related to the Storefront costing and detailing.
09/08/17 – GBBN submittals final Opinion of Probable Costs to Facilities for the GBBN Build-Out Scheme.

10/23/18 – Jeff Aluotto makes request through Steve Kenat that all latest Design information from this project be forwarded to his attention.

CAB – Lobby Finishes Read More »

CAB – Auditor’s 3rd Floor Renovation

07/25/16 – Facilities contacts GBBN and IPM about Kick-off meeting on this project.
08/17/16 – Kick-off meeting established for 08/24/16.
08/24/16 – Kick-off Meeting held at CAB Third Floor. Walk through of space held after meeting conclusion. Facilities forwards two carpet replacement options for separate but simultaneous carpet replacement project. GBBN contacts TEI for MEP scope input and options for the SOSS authoring.
08/24/16 – GBBN forwards documents to ThermalTech for investigation into the MEP scope and SOSS involvement.
08/25/16 – IPM to perform field verification of existing system.
08/29/16 – IPM performs additional field verification of the east side of the Third Floor.
08/30/16 – GBBN receives three re-carpeting Options for the various areas of the Third Floor from Facilities.
08/31/16 – GBBN authors and delivers the SOSS to Facilities.
09/01/16 – IPM transmits first preliminary layout of the Auditor’s Office Renovation per the owner’s directives. Auditor responds the layout still needs more work.
09/06/16 – IPM transmits second preliminary layout of the Auditor’s Office Renovation per the owner’s directives. Auditor responds the layout still needs more work.
09/07/16 – IPM transmits third preliminary layout of the Auditor’s Office Renovation per the owner’s directives. Auditor responds the layout still needs more work.
09/13/16 – IPM transmits fourth preliminary layout of the Auditor’s Office Renovation per the owner’s directives. Auditor responds the layout still needs more work.
09/21/16 – Auditor’s Office meeting with IPM, GBBN and Facilities held to discuss final approved layout and logistics for implementing project with various vendors.
10/12/16 – GBBN and Facilities hold discussions on renumbering and renaming the various spaces affected by this renovation.
10/14/16 – GBBN completes construction documents and forwards to ThermalTech to begin MEP design.
10/10/16 – Facilities emails GBBN about conversations with Paula Drake with the Auditor Office. She would like to move forward with the project without the expedited walk-through process. The new proposed gypsum board partitions will not be added until next year. Spectra Flooring is directed to remove the 5th floor VCT flooring from their quote.
10/24/16 – IPM and GBBN are contacted that recent retirements in the Auditor Office will require additional changes to the layout. IPM contacts Auditor for meeting to discuss.
10/25/16 – IPM completes latest revisions to the preliminary layout and obtains approval from Auditor. GBBN updates ThermalTech with new drawing and we will work with Architect to get EC dwg prepared. HVAC dwg will be given to GBBN for inclusion on their dwgs if possible.
12/21/16 – ThermalTech releases permitting drawings for this renovation.
12/29/16 – Renovations are submitted for permitting and work is underway.
01/25/17 – Permit was received today for this project.
01/26/17 – Paula Drake emails to indicate consolation of more tax maps were accomplished and therefore one short map cabinets could be dismantled.
01/27/17 – Planes Moving indicates Spectra and Planes will mobilize on Saturday for installation of carpet and furniture moving.
01/28/17 – IPM reports the moving and carpet installers arrived late. Carpet installers indicated they were not aware demolition of existing carpeting was involved.
01/29/17 – IPM indicated carpet was installed but base was not completed.
02/16/17 – Facilities calls GBBN to inform that Paula Drake has requested several Owner Changes. These changes are extensive enough to require an Engineering Change to the City of Cincinnati. GBBN to inquire with IPM and TEI for estimated fees for making the drawing and as-built changes, including reimbursable expenses for Engineering Change.
03/15/17 – GBBN coordinates scope of services for Engineering Changes with ThermalTech and IPM. This includes application and plan review fees for IBI and City of Cincinnati Buildings and Inspections. The SOSS is authored and submitted to Facilities.
05/25/17 – Project on hold pending new direction.
07/31/17 – City of Cincinnati Building Inspector called GBBN to discuss status of Permit Inspections. GBBN indicated Owner has stopped work based on potential changes that would require Additional Services for an Engineering Change. Inspector indicated he would indicate work was on hold.
10/18/17 – Interior Project Management indicates Auditor has requested some additional work to be performed on next phase.
02/22/18 – Project ready to archive. City has approved permit and CO. Extend permit within 10 days prior to expiration.

CAB – Auditor’s 3rd Floor Renovation Read More »

CAB – ADA Assessment

Partner Lead: GBBN
12/16/15 – Facilities report to GBBN that Preliminary Cost Estimate portion of reports have incorrect references to County Administration Building. Facilities inquires about status of CAB ADA Assessments. GBBN reports the SOSS was never approved to commence beginning of project.
12/17/15 – Facilities transmits copy, of originally approved SOSS to GBBN to commence beginning of project.
04/18/16 – Facilities sends Estimating Project Requests showing the cost estimating portion of these Assessments as listed projects.
06/28/16 – Opinions of Probable Costs for the implementation of the ADA Assessment findings were entered into Archibus as a Project Request Estimate.
03/23/17 – GBBN and Facilities agree to have Assessments completed at the same time as the Annual Project Request Estimating.
07/24/17 – GBBN printed all Archibus Project Request Estimates from 2016 (#801, 802, #627 and #804) and 2018 (#1862, #1851 and #1831) for inclusion into final reports.
10/25/17 – GBBN has all final Project Request Estimates printed and ready for insertion into final reports.

CAB – ADA Assessment Read More »

A&D – Life Safety Drawing Updates

Partner Lead: GBBN
03/01/17 – GBBN – Hamilton County requested SOSS and indicates a separate F-Number be used.
04/11/17 – Facilities responds to GBBN scope questions.
04/13/17 – GBBN issues SOSS to Facilities.
06/29/17 – Meeting was held to review updates of Life Safety Drawings and explain concepts and fundamentals used in color selection and hatching determination. The color of orange and blue were chosen due to each being located across the color wheel from each other for greater contrast.
07/11/17 – Facilities confirms the plan views in the CAFM drawings are to be rotated “accordance with their position so left and right are always true to the egress path.
08/23/17 – GBBN forwards to Risk Management Safety Department the GBBN modified Alms & Doepke Life Safety Plans for internal review.
08/24/17 – Risk Management Safety Department approves GBBN modified Alms & Doepke Life Safety Plans.
11/30/17 – Drawings have been received from GBBN. Facilities coordinating with existing frames and carpenters’ will mount on the wall and rotate as necessary.

A&D – Life Safety Drawing Updates Read More »

A&D – Painting and System Furniture Replacement Renovation- Phase 1/ Phase 2

09/02/16 – Letter from Mr. Michael Patton of JFS giving update
06/07/17 – BOCC votes to approve the project for JFS.
06/21/17 – BOCC votes to approve the Meeting Minutes of the 06/07/17 Board Meeting.
06/23/17 – Facilities suggests Design Team begin thinking about an SOSS or SOSS’s for this project.
06/24/17 – GBBN contacts IPM and TEI to discuss ideas for numbers and durations of SOSS. Potential Agenda document circulated by GBBN.
05/26/16 – Facilities sends back Agenda review comments to GBBN. Facilities requests possible dates for Kick-off Meeting from Design Team.
07/24/17 – GBBN, IPM and TEI attended a kick-off and status meeting with Facilities and JFS. A SOSS was requested from the Design Team for the Phase I, Schematic Design and Programming Phase of this project.
07/31/17 – GBBN and TEI send to Facilities an inquiry about Systems Furniture Wire configurations. Facilities responds indicating the 3 circuit configuration is acceptable.
08/04/17 – Facilities responds to GBBN’s questions about scope and renderings for the SOSS.
08/08/17 – GBBN receives SOSS data and input from IPM and TEI for the Phase I Schematic Design and Programming Phase.
08/10/17 – GBBN authors and delivers the SOSS to Facilities.
09/14/17 – GBBN and IPM have meeting with JFS to re-engage on discussions related to logistics and scheduling on project.
09/15/17 – GBBN issues Meeting Minutes to Design Team and owner for review.
10/25/17 – Meeting with JFS for Children’s Services A&D Interiors Programming Meeting to include discussions with the Executive team followed by discussions with the division which is located on 4th floor, 5th floor, and some of 6th floor.
11/28/17 – IPM updates Facilities on status of project and Design Team meetings with JFS.
01/25/18 – 2nd Floor, from 3rd Floor completed. More Offices/Conference Rooms have been requested on these floors as well as the 5th/6th. This extra scope of adding more privacy offices, stacked by floors, will be investigated. THP will be needed as a consultant to investigate File Storage Capacity. ADA consultant will be required for ADA Comprehensive Audit Reviews. Cost estimating will be required after IPM completes Design Layouts for each floor to determine of costs for high cubes or hard-wall offices to ceiling are more effective. The SD SOSS will be reviewed to determine if additional scope can be absorbed or not. All programming documents will be distributed to All Groups for review by May of 2018.
02/22/18 – 2,4,5 finished, 3 is drafted, others are being updated, project going well.
04/09/18 – IPM requests additional fees to continue programming due to JFS increased scope creep. IPM sends proposal to GBBN for SOSS preparation.
04/11/18 – IPM issues project update for JFS meetings and decisions rendered.
04/16/18 – Meeting with Design Team and Facilities to discuss project status and schedule for the remainder of the project. IPM distributes the latest floor plan layouts to each party.
04/18/18 – GBBN/THP/IPM discuss file groupings and storage relative to a Load Study to be performed by THP.
04/26/18 – Meeting update stated that final drawings are in approval stage by JFS. Once the executive group signs off on these drawings the plans will be ready for the partners. They are trying to gain efficiencies in people relocation and keeping storage with each group. Use LEED approach for this project, make it green as possible and we will probably go after LEED-CI. Provide SD documents and two estimates, one for LEED and one for standard.
05/16/18 – Facilities circulates the final schematic Phase 1 drawings, created by IPM, as approved by the JFS Executive Committee.
05/17/18 – TEI sends SOSS input to GBBN for the Phase 2 portion of the project.
05/23/18 – Facilities indicates LEED may be a component of this project. GBBN discuss internally what the scope of work will be for Certifying this project. This information is shared with the design team.
05/24/18 – GBBN, IPM, TEI and Facilities meets to discuss the remainder of the project. GBBN presents the finalized Preliminary Design and Construction Schedule for the project.
05/29/18 – IPM sends to GBBN the SOSS input for the “Mock-Up Only” SOSS.
05/30/18 – IPM sends to GBBN the SOSS input for the remainder of the Phase 2 (through CD’s) project.
5/30/18 – Facilities confirms JFS has requested the Approved Standard Cubicle “B”, also referred to as the “Field Office Cube Configuration”, be the typical workstation to be used for the Mock-Ups.

A&D – Painting and System Furniture Replacement Renovation- Phase 1/ Phase 2 Read More »

A&D – Rekeying Project

08/22/16 – Bert Watts requested GBBN contact Tony Matre to discuss a potential re-keying project for this facility.
08/24/16 – A voice mail was left with Tony to make initial contact.
08/30/16 – A kick-off meeting was held with JFS, Facilities, GBBN and Assa Abloy to discuss keying options and electronic security locking devices. A site walk through was held to allow Assa Abloy to view existing door hardware types.
08/30/16 – GBBN authors and delivers SOSS to Facilities for the project.
09/06/16 – Facilities requests another copy of the SOSS Coversheet with updated SOSS number.
09/22/16 – Facilities requests literature to document various Keying Master/Grand Master options, Pros and Cons along with an estimate for the rekeying, without any door maintenance, based on the 307 existing doors listed on the spreadsheet by the Building Manager earlier and sent to GBBN. Assa Abloy estimated 30% of the existing doors were panic hardware for this exercise.
09/23/16 – Assa Abloy sends Opinion of Probable Cost estimate for re-keying and the schematic documents relaying the Master Keying options to GBBN. GBBN forwards the information to Facilities via email.
10/12/16 – GBBN authors revised SOSS and delivers to Facilities.
11/28/16 – RFP received from four vendors. Bid Tabulation compiled by GBBN and sent to Tony Matre.
12/01/16 – GBBN instructs Acme they have been selected as the Low Responsible Bidder. GBBN authors AIA contract and delivers to Tony Matre.
12/5/16 – GBBN contacts Acme concerning bidding questions to complete bid recommendations to Owner.
01/10/17 – GBBN confirmed fee is exhausted and henceforth GBBN has completed all obligations. Assa Abloy contacted by GBBN about representing the Owner at the Keying Meeting.
01/26/17- Keying meeting held at A&D with Acme Lock and Assa Abloy. Drawings from bid set are to be used for the proper door numbering to be used on the documentation. Existing malfunctioning card reader in basement stair will be repaired by Maintenance and not part of this project. All drawings and specification section sent to Tony Matre for future use.
03/10/17 – Inquiries were received by GBBN relative to recent meetings and keying schedules between JFS and Assa Abloy. Steve Sears reports to GBBN that Acme Lock still has not received all their Background Checks to begin working onsite. He mentioned JFS is still conduction internal discussions related to input needed by Acme for the keying hierarchy requirements. /Steve felt the process was still moving forward. GBBN reported this information to Assa Abloy.
09/14/17 – GBBN holds impromptu meeting with Assistant Building Manager. The Keying Project is scheduled to soon begin fabrication once final submittals are approved.
11/18/17 – Last we’ve heard they are working on the cores or shipping them. Keep on project list for coordination for A&D Furniture job.
02/22/18 – Project complete, need to decide what to do with old keys. 15 minute changeover to new keying system. Project ready to archive.

A&D – Rekeying Project Read More »

A&D – Wireless Network Project

03/29/16 – Bert Watts requested a SOSS for a wireless network study for all floors of the building (Sub-basement through 7th floor). ThermalTech issues SOSS. Project pending approved SOSS and PO.
04/27/16 – TEI receives approved SOSS and PO. TEI, Bert Watts, John Nester, Claude Toulsen and Mark Miller have kickoff meeting to discuss existing conditions and JFS desired WiFi parameters. JFS investigating with the state network possibility to add to state network hardware.
05/25/16 – TEI conducts walk through of the building with Claude Toulsen. Identified locations of existing WAP’s, Identified proposed locations for new WAP’s, discussed state requirements and standards, and Claude T to forward to TEI state requirements and recommendations.
06/27/16 – ThermalTech working with Claude Toulsen to identify the state requirements for the system components. The State standards and the county standards do not match. Although JFS is not mandated to utilize the state standard equipment, CT would like to know the implications of using that equipment (cost, etc). ThermalTech to provide costing data for both the state and the county standard systems and make recommendations accordingly.
07/27/16 – TEI meeting with Claude Toulsen on 7/27/16 for progress meeting. The state equipment supplier (Aruba) has been non-responsive for weeks when I have made attempts to contact them for technical support. TEI to discuss this with CT and we are recommending that JFS utilize the Fortinet (county standard equipment) versus the Aruba.
08/23/16 – TEI to submit to Claude Toulsen and Bert Watts final draft of report for final comments and distribution by 8/31/16.
09/28/16 – TEI received final comments from Bert Watts, pending comments from Claude Toulsen for final distribution.
10/25/16 – TEI received final comments from Claude Toulsen – will conclude study portion of project.
01/25/17 – TEI submits SOSS for implementation of report recommendations. Project Pending approval of SOSS and PO.
02/22/17 – TEI receives approved SOSS and PO for the project. Project kick off meeting scheduled with Facilities and JFS on 2/23/17 at 2:00 PM.
03/22/17 – TEI performs field work and finds existing spare breakers in panels on each floor to provide power to the network switches and the WAPs that are a part of the project. Working on Construction cost estimates to have ready for discussion at 04/06 design meeting.
04/26/17 – ThermalTech has meeting with JFS staff and Facilities. TEI completing Bid Docs for Final design review meeting by end of April. TEI to request meeting first week of May to provide final review and establish bid parameters.
05/22/17 – ThermalTech and facilities meets with JFS staff. TE and Facilities presents the HamCo telecom group policies to JFS staff. JFS staff to meet independently and return to TE and facilities with direction that they wish to pursue. TE waiting on final design criteria from JFS IT staff.
06/27/17 – ThermalTech to coordinate with Purchasing, JFS and facilities for dates to put in the ITB. ITB to be issued ASAP. Hold until funding is in place.
07/25/17 – Project on HOLD until funding is in place.
08/28/17 – Project on HOLD until funding is in place.
08/31/17 – Redo entire business model so telephone support will be more prevalent. Wi-Fi not required. BW will set something up in the future.
09/26/17 – project to be completed in conjunction with the furniture/painting project.
05/30/18 – project to be completed in conjunction with the furniture/painting project.
11/28/18 – project to be completed in conjunction with the furniture/painting project.
01/29/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
03/26/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
04/24/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
05/29/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
06/26/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
07/24/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
08/27/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
09/25/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
10/30/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
10/31/19 – Move project to Archive, its in the A&D Interior finishes projects.

A&D – Wireless Network Project Read More »

A&D – ADA Assessment

Partner Lead: GBBN
06/16/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings.
06/17/11 – SOSS submitted in person to Bert Watts
09/16/11 – Signed SOSS received from Bert Watts.
08/24/13 – GBBN completes estimating on impacts of ADA Assessment Studies.
02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.
10/13/15 – Bert Watts requests that all Assessments be completed by the first of the upcoming year
12/03/15 – Assessments completed, printed and three sets delivered to Bert Watts.
12/15/15 – Facilities report to GBBN that Preliminary Cost Estimate portion of reports have incorrect references to County Administration Building.
01/08/16 – GBBN picks up reports from Facilities for making corrections.
04/18/16 – Facilities sends Estimating Project Requests showing the cost estimating portion of these Assessments as listed projects
06/28/16 – Opinions of Probable Costs for the implementation of the entered into Archibus as a Project Request Estimate.
03/23/17 – GBBN and Facilities agree to have Assessments completed at the same time as the Annual Project Request Estimating.
07/24/17 – GBBN printed all Archibus Project Request Estimates from 2016 (#801, 802, #627 and #804) and 2018 (#1862, #1851 and #1831) for inclusion into final reports.
10/25/17 – GBBN has final Project Request Estimates completed for insertion into final reports.
10/28/20 – Waiting on hard copies.

A&D – ADA Assessment Read More »

2020 – Fire Alarm System Replacement Study

07/25/17 – Facilities department receives indication that the existing Fire Alarm system is beyond usable life and that parts are no longer available for the existing system. Requested an SOSS from TEI to provide an assessment of existing conditions and make recommendations. TEI issues SOSS for project to provide assessment of the fire alarm system and provide recommendations. TEI receives approved SOSS and PO.
08/28/17 – Report in progress. TE receives information from Siemens on existing system obsolescence dates and also conducts meeting and building walk through with John Nester and Bill Scholl.
09/26/17 – ThermalTech is completing to study. Will submit draft of Study to Facilities department by 10/06/17 for review and comment.
10/25/17 – ThermalTech submits final copies of report to Bert Watts for distribution.

01/22/18 – Next steps pending review of study.
02/20/18 – Next Steps pending review of study.

03/27/18 – Next Steps pending review of study…

04/25/18 – Next steps pending review of study.

2020 – Fire Alarm System Replacement Study Read More »

2020 – Fire Alarm Surge Protection

10/25/16 – TEI issues SOSS for project to provide surge protection for the fire alarm system. Project pending approved SOSS and PO.
01/25/17 – Project pending approval of SOSS and PO.
02/22/17 – Project pending approval of SOSS and PO.
03/22/17 – Project pending approval of SOSS and PO.
04/26/17 – Project pending approval of SOSS and PO.
05/22/17 – Project pending approval of SOSS and PO.
06/27/17 – TEI receives signed SOSS and PO. Drawings issued to Bill Scholl and Tony Matre for review and comments. Package to be issued (small projects bid) upon receipt of comments.
07/25/17 – Pending review comments from Bill Scholl and Tony Matre.
08/28/17 – AKM asks TEI if this can wait and be installed as part of the fire alarm system replacement project. TEI spoke with Bill S and Bill is concerned with all of the electrical storms that happen at the facility that there would be a surge that could be catastrophic to the existing system if the protection was not put in place now. TEI and AKM have a discussion, and AKM said to get pricing on drawings that were developed and he will evaluate pricing and issue contract for work if he has $$ in his budget at towards the end of the year.
09/26/17 – Project released for bids from Cincy Electrical, DK and Phasor. Bids due back the ThermalTech by 9/29/17 and noon.
10/25/17 – AKM tells TEI that he is going to have DK install the system for their bid of $1,591 for the surge protection. Install to proceed upon approval of submittals.
11/29/17 – DK receives PO for the work and is instructed to schedule work with Building Manager.
01/22/18 – DK has completed construction. ThermalTech requested closeout document from contractor.
02/20/18 – Closeout pending receipt of closeout documents from DK.
03/27/18 – Closeout pending receipt of closeout documents from DK.
4/25/18 – Closeout pending receipt of closeout documents from DK.

2020 – Fire Alarm Surge Protection Read More »

230 – ADA Assessment

06/16/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings.
06/17/11 – SOSS submitted in person to Bert Watts.
09/16/11 – Signed SOSS received from Bert Watts.
10/27/12 – Preliminary Report completed and sent to Bert Watts for review. Estimating portion of study yet to be completed.
08/24/13 – Estimating completed on the impacts of the ADA Assessments.
02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.
10/13/15 – Bert Watts requests that all Assessments be completed by the first of the upcoming year.
12/03/15 – Assessments completed, printed and three sets delivered to Bert Watts.
12/15/15 – Facilities report to GBBN that Preliminary Cost Estimate portion of reports have incorrect references to County Administration Building.
01/08/16 – GBBN picks up reports from Facilities for making corrections.
04/18/16 – Facilities sends Estimating Project Requests showing the cost estimating portion of these Assessments as listed projects.
06/28/16 – Opinions of Probable Costs for the implementation of the ADA Assessment findings were entered into Archibus as a Project Request Estimate.
03/23/17 – GBBN and Facilities agree to have Assessments completed at the same time as the Annual Estimating Project Requests.
07/24/17 – GBBN printed all Archibus Project Request Estimates from 2016 (#801, 802, #627 and #804) and 2018 (#1862, #1851 and #1831) for inclusion into final reports.
10/25/17 – Project Request Estimates are printed and ready for insertion into final reports.

230 – ADA Assessment Read More »

250 – General Health Door Renovation

Project Lead: GBBN
07/28/17 – Hamilton County requested SOSS to investigate adding a new door and new Office Wall.
07/31/17 – GBBN visited the site and met with General Health to discuss scope of work. A hand drawn sketch was presented to GBBN. GBBN photographed and field verified the site. GBBN and TEI verified the proposed scope of work would require permitting.
08/03/17 – GBBN authored and issued SOSS for review.
08/21/17 – County requested a revised SOSS, based on a reduced scope to be compliant with no permitting required. A simple opening through the existing gypsum board partition is requested. TEI confirmed no added load to electrical service means no IBI permit required.
08/23/17 – Facilities clarifies the final scope of the project to GBBN and TEI.
08/25/17 – GBBN authors and delivers revised SOSS to Facilities.
09/18/17 – GBBN clarifies scope with Facilities to use hollow metal door frame in new opening for durability. Double studs and header will be used in expanded opening rough framing for frame installation and anchorage.
09/22/17 – GBBN confirms to Facilities the drawings are completed to the point of final field verification and owner review of drawings.
10/02/17 – Facilities requests final drawings from GBBN for issuance to Trades. GBBN sends drawings with inquiry about final Owner review meeting.

250 – General Health Door Renovation Read More »

800 – 2015 Roof Repair – Cleaning

Project Lead: THP
04/13/15 – County requested SOSS.
04/28/15 – THP issued SOSS.
07/31/15 – County issued approved SOSS.
08/26/15 – Project update: THP anticipates issuing 90% Owner review drawings by 8/31.
09/21/15 – THP issued DD documents.
09/22/15 – County provided comments to DD documents.
11/04/15 – Prebid meeting occurred.
11/13/15 – Addendum No. 1 issued.
11/14/15 – County – three bids from Midwest Maintenance, SSRG and ZSR.
11/30/24 – THP issued a letter recommending ZSR, based on the low bid and follow up conversation.
11/20/15 – THP issued draft AIA contract.
12/08/15 – County provided edits to contract for THP to update.
01/28/16 – Project summary. ZSR – final AIA contract, signed it and sent to the County for execution. ZSR submitted tentative submittals.
01/27/16 – County commissioners approved ZSR contract.
02/10/16 – THP returned submittals.
02/25/16 – ZSR finalizing construction schedule. THP trying to work with SHPO to coordinate anticipated work.
04/28/16 – Project update: ZSR plans to start work later part of May.
05/05/16 – THP makes contact with SHPO. They direct THP to regional manager. THP emails John Sandor of “Technical Preservation Services” for project review.
05/10/16 – Preconstruction Meeting Held On-Site
05/16/16 – Project began with erection of scaffolding and sidewalk protection
05/23/16 – THP makes site visit to review scope with superintendent
05/24/16 – Weekly meeting Held On Site
05/24/16 – THP receives contact back from John Sandor. THP to issue email to John S. summarizing conversation. John S. will issue a letter on the project with his official recommendations.
05/25/16 – Scaffolding complete
05/31/16 – ZSR to start construction.
06/21/16 – Construction progress meeting
06/28/16 – Limestone demolition is almost complete.
06/29/16 – Revised limestone anchorage detail issued by THP for pricing.
07/05/16 – Met project team for progress meeting and to document progress.
07/08/16 – THP developed AIA change orders 1 & 2 and forwarded to ZSR.
07/08/16 – THP issued 7/7 progress meeting notes and field report.
07/12/16 – Developed kerf edge repair detail and forwarded to ZSR.
07/12/16 – ZSR not on site, waiting for materials to arrive.
07/19/16 – Met project team for progress meeting and to document progress.
07/27/16 – Bert confirmed ZSR has – payment for app. #1.
07/26/16 – THP issued 7/19 meeting notes and field report.
07/27/16 – Met ZSR at site to review progress, and stone profile/alignment issues.
07/28/16 – Demolition of stone panels at the bottom is complete. Stone ordered with 8 week delivery anticipated. Crews removing the metal caps.
07/28/16 – THP visited site and met with Darnell to review and document water infiltration.
07/29/16 – THP issued field report 07 from 7/27 & 28 site visits.
08/02/16 – Met project team for progress meeting and to document progress.
08/03/16 – THP researched specified patch and consolidation treatment materials.
08/08/16 – THP issued 8/2 meeting notes and field report.
08/08/16 – THP researched specified water repellent.
08/10/16 – THP emailed ZSR following up on outstanding items from field report 08.
08/11/16 – THP visited site to document progress, and issued field report 09.
08/16/16 – THP emailed ZSR dimensioned sketch of typical stone panel showing fabrication details to facilitate installation.
08/17/16 – THP visited site and met with Darnell to review and document water infiltration.
08/18/16 – THP issued field report 10 from 8/17 site visit.
08/23/16 – THP visited site to observe and document roof progress.
08/25/16 – THP issued field report 11 from 8/23 site visit.
08/26/16 – THP inspected stone patches at East roof face while rappelling to assess tower facades.
08/30/16 – Progress meeting and THP site visit to document progress.
09/06/16 – THP issued 8/30 meeting minutes and field report 12.
09/09/16 – THP made two visits to site to document progress and review stone profile with ZSR, and issued field report 13.
09/13/16 – Progress meeting and THP site visit to document progress. THP coordinated revised installation detail for stones due to field conditions.
09/14/16 – THP issued 9/13 meeting minutes and field report 13.
09/27/16 – Progress meeting and THP site visit to document progress, and issued meeting minutes and field report 13.
10/03/16 – THP finalized approval of ZSR’s Applications for Payment 2, 3, and 4.
10/06/16 – THP – and reviewed Stone Center shop drawings.
10/07/16 – THP met with ZSR to review Stone Center shop drawing to identify what changes needed to be made.
10/11/16 – Progress meeting, and THP site visit to observe and document progress.
10/13/16 – THP – and reviewed revised Stone Center shop drawing, and returned to ZSR to be revised and resubmitted.
10/18/16 – THP issued 10/11 meeting minutes and field report 16.
10/20/16 – THP – and reviewed revised Stone Center shop drawing, and returned to ZSR to be revised and resubmitted.
10/21/16 – THP – and reviewed final Stone Center shop drawing, and returned to ZSR with exceptions noted.
10/25/16 – THP – and reviewed ZSR’s Application for Payment #5, and forwarded to Hamilton County.
10/26/16 – THP site visit to observe and document progress.
11/01/16 – THP issued field report 17.
11/01/16 – Progress meeting, and THP site visit to observe and document progress.
11/01/16 – THP issued 11/1 meeting minutes and field report 18.
11/02/16 – THP finalized approval of ZSR’s Applications for Payment 2-5 and delivered to Hamilton County.
11/15/16 – Progress meeting, and THP site visit to observe and document progress.
11/17/16 – THP issued 11/15 meeting notes and field report 19.
11/18/16 – THP site visit to observe preformed sealant strip mockups, and issued field report 20.
11/29/16 – Progress meeting, and THP site visit to observe and document progress.
11/30/16 – THP issued 11/29 meeting minutes and field report 21
12/03/16 – 12/04/16 – ZSR installed new limestone roofing.
12/06/16 – THP reviewed ZSR’s proposals for change orders 3 & 4 and replied with revisions required per contract.
12/09/16 – THP issued field reports 21 & 22, and delivered Application for Payment 6 and Change Orders 3 & 4 to Hamilton County.
12/27/16 – Progress meeting, and THP site visit to observe and document progress. THP issued 12/27 meeting notes and field report 24.
12/28/16 – THP provided ZSR information about stone cleaning products to be used for developing test areas.
01/04/17 – ZSR finished installation of snow guards.
01/16/17 – American Scaffolding began removing scaffolding.
01/23/17 – ZSR site visit to document removal of scaffolding and progress of preformed sealant strip installation.
01/23/17 – ZSR site visit to document removal of scaffolding and progress of preformed sealant strip installation, and issued field report 25.
02/22/17 – Project on hold due to weather conditions.
03/01/17 – THP visited site to document leaks at 17th and 18th floor mechanical spaces.
03/02/17 – THP issued field report #26 with plan diagrams identifying leak locations.
04/11/17 – THP visited the site during a rain event to document wall and roof leaks. Findings and recommendations emailed to County.
04/17/17 – THP and ZSR discussed plan to test leak areas and testing of stone cleaning.
05/12/17 – THP visited site to observe and document progress of work and test sample cleaning areas.
05/12/17 – THP issued field report #27.
05/17/17 – THP met ZSR and Prosoco product rep at site to discuss options for additional stone cleaning products.
05/19/17 – THP emailed additional stone cleaning products to ZSR for test sampling.
05/25/17 – ZSR completed premold and sealant installation. Material ordered for cleaning samples. Cleaning probably occur next week (weather permitting).
06/08/17 – THP visited site to coordinate with ZSR application of limestone cleaning product for testing, and document progress of roof repairs.
06/08/17 – THP issued field report #28 documenting cleaning test areas, methods, and products.
06/09/17 – THP issued field report #29 documenting progress and identifying additional work items.
06/13/17 – THP visited site to sound stone patches and document results of stone cleaning tests.
06/27/17 – Meeting at site with Hamilton County, ZSR, and THP to review results of stone cleaning tests. THP recommended two samples for additional testing and pricing.
07/27/17 – County approved tentative design and construction budget for cleaning change order work. ZSR and THP exploring staining patches vs. cleaning more effective option.
08/31/17 – As part of the cleaning repair project, ZSR complete the general construction cleaning. Refer to F98.

 

800 – 2015 Roof Repair – Cleaning Read More »

800 – Juvenile Court and Domestic Court Relocation Study

06/06/17 – GBBN contacted by Facilities about authoring SOSS.
06/07/17 – Hamilton County Facilities requests some modifications to the SOSS including using #F052.
06/08/17 – Revised SOSS submitted to Facilities.
06/27/17 – Facilities sends approved SOSS to GBBN.
06/28/17 – Facilities and GBBN begin discussions for a Kick-off Meeting date.
08/02/17 – Meeting with Facilities and GBBN to discuss scope and approach for moving ahead with project.
08/05/17 – GBBN holds internal review meeting before meeting for presentation to Owner.
08/17/17 – Meetings at 800 Broadway with both Juvenile Court and Domestic Relations Court. Tour of Domestic Court Offices was conducted after meeting. Domestic Relations presented Programming List for GBBN’s use.
08/25/17 – GBBN internally produces meeting minutes and circulates for review.
09/22/17 – GBBN holds internal review meeting before meeting for presentation to Owner.
10/10/17 – Final presentation review set distributed in office for associated personnel to review and comment.
10/18/17 – GBBN communicates with Facilities and Administration related to timing for meeting for final presentation. A final Onwer review draft is sent to the Owner. Ralph Linne responded with corrected financial information.
10/20/17 – Corrected draft with updated financial information is sent by GBBN to all parties involved.

800 – Juvenile Court and Domestic Court Relocation Study Read More »

800 – EMU Relocation Study

Project Lead: GBBN
03/28/17 – GBBN contacted by Facilities about setting up Kick-off Meeting with Sheriff Department.
03/31/17 – Hamilton County Facilities and GBBN meet with Sheriff to discuss project goals. Letter from Sheriff requesting project presented to GBBN. Facilities requested SOSS from GBBN.
03/10/17 – Met with Hamilton County to review scope and field conditions.
03/23/17 – THP provided Hamilton County with a SOSS.
04/05/17 – GBBN visits site for field verification of measurements and to take photographs.
04/06/17 – GBBN corresponds with Facilities for final questions related to scope of work. GBBN authors SOSS and delivers to Facilities.
04/14/17 – SOSS approved.
05/04/17 – GBBN revisits site for additional field verification, measurements and to take more detailed photographs.
05/05/17 – GBBN interviews ThermalTech for costing details on Electrical and Mechanical issues.
05/11/17 – GBBN sends six (6) optional designs to Facilities for review.
05/12/17 – Facilities selects two final options for estimating. One with the existing demising wall to remain and one without the existing wall present.
05/22/17 – GBBN completes preliminary Opinions of Probable Costs for each of the two final options.
05/23/17 – Facilities indicates only one option, with the existing demising wall removed, is required for estimating.
06/14/17 – GBBN, Facilities and EMU meeting to discuss the version of the schematic design selected and estimated. Minor modifications were requested for the final option.
07/18/17 – Facilities indicated this project has been terminated. The move may result in relocating to the Third Floor Mezzanine instead.
07/24/17 – TEI discussed project with County and GBBN and is doing an energy study for the 24/7 part at the very least. The Energy Impact Study has been submitted for this project.
12/19/17 – TTC adds a comment.

800 – EMU Relocation Study Read More »

800 – 2015 Roof Repair

Project Lead: THP
04/13/15 – County requested SOSS.
04/28/15 – THP issued SOSS.
07/31/15 – County issued approved SOSS.
08/26/15 – Project update: THP anticipates issuing 90% Owner review drawings by 8/31.
09/21/15 – THP issued DD documents.
09/22/15 – County provided comments to DD documents.
11/04/15 – Prebid meeting occurred.
11/13/15 – Addendum No. 1 issued.
11/14/15 – County – three bids from Midwest Maintenance, SSRG and ZSR.
11/30/24 – THP issued a letter recommending ZSR, based on the low bid and follow up conversation.
11/20/15 – THP issued draft AIA contract.
12/08/15 – County provided edits to contract for THP to update.
01/28/16 – Project summary. ZSR – final AIA contract, signed it and sent to the County for execution. ZSR submitted tentative submittals.
01/27/16 – County commissioners approved ZSR contract.
02/10/16 – THP returned submittals.
02/25/16 – ZSR finalizing construction schedule. THP trying to work with SHPO to coordinate anticipated work.
04/28/16 – Project update: ZSR plans to start work later part of May.
05/05/16 – THP makes contact with SHPO. They direct THP to regional manager. THP emails John Sandor of “Technical Preservation Services” for project review.
05/10/16 – Preconstruction Meeting Held On-Site
05/16/16 – Project began with erection of scaffolding and sidewalk protection
05/23/16 – THP makes site visit to review scope with superintendent
05/24/16 – Weekly meeting Held On Site
05/24/16 – THP receives contact back from John Sandor. THP to issue email to John S. summarizing conversation. John S. will issue a letter on the project with his official recommendations.
05/25/16 – Scaffolding complete
05/31/16 – ZSR to start construction.
06/21/16 – Construction progress meeting
06/28/16 – Limestone demolition is almost complete.
06/29/16 – Revised limestone anchorage detail issued by THP for pricing.
07/05/16 – Met project team for progress meeting and to document progress.
07/08/16 – THP developed AIA change orders 1 & 2 and forwarded to ZSR.
07/08/16 – THP issued 7/7 progress meeting notes and field report.
07/12/16 – Developed kerf edge repair detail and forwarded to ZSR.
07/12/16 – ZSR not on site, waiting for materials to arrive.
07/19/16 – Met project team for progress meeting and to document progress.
07/27/16 – Bert confirmed ZSR has – payment for app. #1.
07/26/16 – THP issued 7/19 meeting notes and field report.
07/27/16 – Met ZSR at site to review progress, and stone profile/alignment issues.
07/28/16 – Demolition of stone panels at the bottom is complete. Stone ordered with 8 week delivery anticipated. Crews removing the metal caps.
07/28/16 – THP visited site and met with Darnell to review and document water infiltration.
07/29/16 – THP issued field report 07 from 7/27 & 28 site visits.
08/02/16 – Met project team for progress meeting and to document progress.
08/03/16 – THP researched specified patch and consolidation treatment materials.
08/08/16 – THP issued 8/2 meeting notes and field report.
08/08/16 – THP researched specified water repellent.
08/10/16 – THP emailed ZSR following up on outstanding items from field report 08.
08/11/16 – THP visited site to document progress, and issued field report 09.
08/16/16 – THP emailed ZSR dimensioned sketch of typical stone panel showing fabrication details to facilitate installation.
08/17/16 – THP visited site and met with Darnell to review and document water infiltration.
08/18/16 – THP issued field report 10 from 8/17 site visit.
08/23/16 – THP visited site to observe and document roof progress.
08/25/16 – THP issued field report 11 from 8/23 site visit.
08/26/16 – THP inspected stone patches at East roof face while rappelling to assess tower facades.
08/30/16 – Progress meeting and THP site visit to document progress.
09/06/16 – THP issued 8/30 meeting minutes and field report 12.
09/09/16 – THP made two visits to site to document progress and review stone profile with ZSR, and issued field report 13.
09/13/16 – Progress meeting and THP site visit to document progress. THP coordinated revised installation detail for stones due to field conditions.
09/14/16 – THP issued 9/13 meeting minutes and field report 13.
09/27/16 – Progress meeting and THP site visit to document progress, and issued meeting minutes and field report 13.
10/03/16 – THP finalized approval of ZSR’s Applications for Payment 2, 3, and 4.
10/06/16 – THP – and reviewed Stone Center shop drawings.
10/07/16 – THP met with ZSR to review Stone Center shop drawing to identify what changes needed to be made.
10/11/16 – Progress meeting, and THP site visit to observe and document progress.
10/13/16 – THP – and reviewed revised Stone Center shop drawing, and returned to ZSR to be revised and resubmitted.
10/18/16 – THP issued 10/11 meeting minutes and field report 16.
10/20/16 – THP – and reviewed revised Stone Center shop drawing, and returned to ZSR to be revised and resubmitted.
10/21/16 – THP – and reviewed final Stone Center shop drawing, and returned to ZSR with exceptions noted.
10/25/16 – THP – and reviewed ZSR’s Application for Payment #5, and forwarded to Hamilton County.
10/26/16 – THP site visit to observe and document progress.
11/01/16 – THP issued field report 17.
11/01/16 – Progress meeting, and THP site visit to observe and document progress.
11/01/16 – THP issued 11/1 meeting minutes and field report 18.
11/02/16 – THP finalized approval of ZSR’s Applications for Payment 2-5 and delivered to Hamilton County.
11/15/16 – Progress meeting, and THP site visit to observe and document progress.
11/17/16 – THP issued 11/15 meeting notes and field report 19.
11/18/16 – THP site visit to observe preformed sealant strip mockups, and issued field report 20.
11/29/16 – Progress meeting, and THP site visit to observe and document progress.
11/30/16 – THP issued 11/29 meeting minutes and field report 21
12/03/16 – 12/04/16 – ZSR installed new limestone roofing.
12/06/16 – THP reviewed ZSR’s proposals for change orders 3 & 4 and replied with revisions required per contract.
12/09/16 – THP issued field reports 21 & 22, and delivered Application for Payment 6 and Change Orders 3 & 4 to Hamilton County.
12/27/16 – Progress meeting, and THP site visit to observe and document progress. THP issued 12/27 meeting notes and field report 24.
12/28/16 – THP provided ZSR information about stone cleaning products to be used for developing test areas.
01/04/17 – ZSR finished installation of snow guards.
01/16/17 – American Scaffolding began removing scaffolding.
01/23/17 – ZSR site visit to document removal of scaffolding and progress of preformed sealant strip installation.
01/23/17 – ZSR site visit to document removal of scaffolding and progress of preformed sealant strip installation, and issued field report 25.
02/22/17 – Project on hold due to weather conditions.
03/01/17 – THP visited site to document leaks at 17th and 18th floor mechanical spaces.
03/02/17 – THP issued field report #26 with plan diagrams identifying leak locations.
04/11/17 – THP visited the site during a rain event to document wall and roof leaks. Findings and recommendations emailed to County.
04/17/17 – THP and ZSR discussed plan to test leak areas and testing of stone cleaning.
05/12/17 – THP visited site to observe and document progress of work and test sample cleaning areas.
05/12/17 – THP issued field report #27.
05/17/17 – THP met ZSR and Prosoco product rep at site to discuss options for additional stone cleaning products.
05/19/17 – THP emailed additional stone cleaning products to ZSR for test sampling.
05/25/17 – ZSR completed premold and sealant installation. Material ordered for cleaning samples. Cleaning probably occur next week (weather permitting).
06/08/17 – THP visited site to coordinate with ZSR application of limestone cleaning product for testing, and document progress of roof repairs.
06/08/17 – THP issued field report #28 documenting cleaning test areas, methods, and products.
06/09/17 – THP issued field report #29 documenting progress and identifying additional work items.
06/13/17 – THP visited site to sound stone patches and document results of stone cleaning tests.
06/27/17 – Meeting at site with Hamilton County, ZSR, and THP to review results of stone cleaning tests. THP recommended two samples for additional testing and pricing.
07/27/17 – County approved tentative design and construction budget for cleaning change order work. ZSR and THP exploring staining patches vs. cleaning more effective option.
08/31/17 – As part of the cleaning repair project, ZSR complete the general construction cleaning. Refer to F98.

800 – 2015 Roof Repair Read More »

800 – ADA Assessment

06/16/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings.
06/17/11 – SOSS submitted in person to Bert Watts.
09/16/11 – Signed SOSS – from Bert Watts.
02/27/12 – GBBN inquired with David Holland of Otis Elevator about ADA compliance options and pricing guidelines.
09/13/12 – Report completed and sent to Bert Watts for review. Estimating portion of study yet to be completed.
08/24/13 – Estimating completed on the impacts of the ADA Assessments.
02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.
10/13/15 – Bert Watts requests that all Assessments be completed by the first of the upcoming year.
12/03/15 – Assessments completed, printed and three sets delivered to Bert Watts.
12/15/15 – Facilities report to GBBN that Preliminary Cost Estimate portion of reports have incorrect references to County Administration Building.
01/08/16 – GBBN picks up reports from Facilities for making corrections.
04/18/16 – Facilities sends Estimating Project Requests showing the cost estimating portion of these Assessments as listed projects.
06/28/16 – Opinions of Probable Costs for the implementation of the ADA Assessment findings were entered into Archibus as a Project Request Estimate.
03/23/17 – GBBN and Facilities agree to have Assessments completed at the same time as the Annual Estimating Project Requests.
07/24/17 – GBBN printed all Archibus Project Request Estimates from 2016 (#801, 802, #627 and #804) and 2018 (#1862, #1851 and #1831) for inclusion into final reports.
10/25/17 – GBBN has final Project Request Estimates completed for insertion into final reports.

800 – ADA Assessment Read More »

250 WHT – ADA Assessment

06/06/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings.
06/08/11 – SOSS submitted in person to Bert Watts.
06/14/11 – Signed SOSS received by GBBN.
07/21/11 – Review meeting with I/T, Bert Watts and ThermalTech to review drawings and design.
07/28/11 – GBBN visited site and took photographs above existing ceilings and confirmed dimensions. Final design coordinated with ThermalTech.
09/16/11 – Signed SOSS received from Bert Watts.
02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.
10/13/15 – Bert Watts requests that all Assessments be completed by the first of the upcoming year.
12/03/15 – Assessments completed, printed and three sets delivered to Bert Watts.
12/15/15 – Facilities report to GBBN that Preliminary Cost Estimate portion of reports have incorrect references to County Administration Building.
01/08/16 – GBBN picks up reports from Facilities for making corrections.
04/18/16 – Facilities sends Estimating Project Requests showing the cost estimating portion of these Assessments as listed projects.
06/28/16 – Opinions of Probable Costs for the implementation of the ADA Assessment findings were entered into Archibus as a Project Request Estimate.
03/23/17 – GBBN and Facilities agree to have Assessments completed at the same time as the Annual Estimating Project Requests.
07/24/17 – GBBN printed all Archibus Project Request Estimates from 2016 (#801, 802, #627 and #804) and 2018 (#1862, #1851 and #1831) for inclusion into final reports.
10/25/17 – Project Request Estimates are printed and ready for insertion into final reports.
10/28/20 – Waiting on hard copy binders prior to archiving this project.

250 WHT – ADA Assessment Read More »

Scroll to Top