Hamilton County Facilities

Archived Projects

Archived Projects

2013 GENERAL SERVICES THP

12/24/13 – SOSS Requested

01/03/13 – SOSS Submitted to County.

01/07/13 – SOSS Executed.

03/20/13 – THP met with County to review beam condition in the basement of the Administration building. Based on the initial visit an additional assessment needs to occur to determine the effect of the active deterioration on the beam. The assessment will determine the need to stabilize or repair the beam.

06/04/13 – Coroner building is reporting long term leaks in the basement under the entry slab. Bert requested THP contact Mike Jackson and determine the possible leak/scope.

06/14/13 – Coroner building – THP reviewed entry after short term heavy rain. Evidence of long term water infiltration was evident, but entry did not leak. Reported findings to County with to recommendations: water test or wait for soaking rain to determine water leak. County directed THP to wait for a soaking rain; then publish a letter of findings.
10/31/13 – THP waiting for active water infiltration in the Coroner Building to evaluate scope of work.

01/30/14 – THP plans to archive project.

2013 GENERAL SERVICES THP Read More »

2013 GENERAL SERVICES GBBN

01/16/13 – SOSS submitted.

01/23/13 – Signed SOSS returned by Bert Watts to GBBN.

12/24/12 – THP – GBBN issues permit drawings; THP documents included.

01/23/13 – GBBN confirms to Millay & Company there is to be no Mechanical Permit initiated by the Owner due to no work required unless required by the Building Department.

01/31/13 – Attended HCFD Partnership monthly partner meeting. GBBN delivers signed General Services Contract to Bert Watts.

02/28/13 – Attended HCFD Partnership monthly partner meeting. GBBN delivers CD to THP and IPM for 2013 Estimating binder.

04/25/13 – GBBN attends monthly HCFD monthly partner meeting.

05/30/13 – GBBN attends monthly Partnering Meeting.

05/30/13 – We discussed the SBE packet for new bids. If we are 0% we do not have to include the actual packet in the bid specification to save paper.

05/30/13- County requests GBBN submit payment on Alms and Doepke Building Pinnacle Engineering Invoice on the General Services SOSS,

06/26/13 – GBBN performs Website updates.

06/27/13 – GBBN attends monthly Partnering Meeting.

07/25/13 – Monthly Partnering Meeting is suspended.

08/29/13 – GBBN attends monthly Partnering Meeting.

2013 GENERAL SERVICES GBBN Read More »

2013 GENERAL SERVICES THERMALTECH

Contact: Terry Cannon

Status: Active

Status:

11/19/12 – SOSS submitted.

11/29/12 – SOSS Approved.

12/12/12 – TTC updated front end documents to remove Terrorist documents.

02/01/13 – TTC updated front end bid documents to remove change President to Chris Monzel.

02/12/13 – TTC & SJ updated front end documents to add the non English speaking language to the Supplemental Conditions.

02/15/13 – TTC updated font end documents to remove the SBE paperwork and language.

03/14/13 – 800 Broadway Vacuum Pumps – TTC recommends doing the following after tracking down some factory information and meeting with Process Construction: 1. Temperatures coming back in the condensate piping are high indication leak-by at the traps: Recommendation-do a full trap survey and repair dysfunctional traps. 2. Temperature in “hurling” chamber start low when system is off and then rise to 190F. The aquastat on the hurling chamber is set at 190F so this tank will quench and drain continuously when the temperature is above 190F. We changed the MUW to this unit from softener water to standard city water because it is typically drained upon use. There is no need to use soft water for this mark up. This work was already completed today when I was there. 3. The condensate pumps are on a mechanical alternator and take turns pumping condensate in the lower chamber to the DA tank for boiler feed water make-up. 4. The vacuum pumps however are lead/backup. VP-1 is always the first pump on when the system vacuum gets close to 0″HG. It provides up to 4″ HG of vacuum, if this pump cannot provide vacuum, it automatically turns on the second pump and both VP-1, VP-2 run together to provide 4″HG. The vacuum limits are between 4″ to 8″HG. 5. Please leave all four HOA switches in the Auto position at all times. 6. With this knowledge, I believe I can report the Vacuum Pump Package on the left in the boiler room is working properly. 7. The vacuum package on the right appears to have a pump seal leaking and should be repaired prior to putting back into service. 8. Please repair the building steam traps to reduce the inlet temperatures from the traps to approximately 180F. Process stated that the vacuum system must be used when the building has low loads but you may find that under high loads (32F or lower) the steam system has enough pressure to push the condensate through the system and you can turn them off the vacuum pumps-that is for your users to decide if that can be done without leaving so much condensate in the building systems.

03/26/13 – Updated Website. Sent out some new formatting rules for users.

2013 GENERAL SERVICES THERMALTECH Read More »

ROYAL GLEN PUMPING STATION Pump Station

Lead Partner: ThermalTech

Current Status: Construction

Status:

10/05/12 – IBI approved 98% inspection today. MB at TEI called Steve Twehues of Duke and requested power get restored ASAP. Steve to contact IBI, get release letter, and schedule restoration of power with Steve Wessels (likely early next week). Project can then be closed out.
10/31/12 – IBI released approval. Duke energy powered the pump up, but there is no meter at this time. Duke energy is insisting that the exiting PT’s are relocated up approximately 2-3 feet on pole, they feel that this is a safety issue once the platforms are installed, they will be too close to be within reach. TTE and trades argued that this area is only accessed by “qualified personnel”, and Duke CPC agreed, but metering division is requiring that they are moved, stating that kids are thrift and can climb fences and that this is a safety issue.

08/28/13 – TE met with Steve Wessels and FD Lawrence. FDL pulled report on soft start, and determined that the soft start was starting/stopping every time that the pump ran. TE sent wiring diagram to Steve Wessels to wire a stop float and a start float.

01/24/14 – Back punchlist complete. This project is complete.

ROYAL GLEN PUMPING STATION Pump Station Read More »

2014 COST ESTIMATES

Partner: All Partners

Status: SOSS

Status:

04/25/13 – Bert reported that we are still probably doing estimates for next year but it may be later this year than most. They will handle resubmitted projects and the partners will get the new projects.

05/30/13 – BW reported that they are getting close to releasing the list to the partners but RWL has to review several items. This list may be bigger than usual if we get to do the entire list this year. This may include some work on the 20 year project.

07/08/13 – GBBN receives the “Capital Roof Plan” showing the historical replacement data and estimated pricing of the six downtown campus buildings from Tremco Roofing.

07/11/13 – GBBN submits SOSS to County for approval.

07/30/13 – GBBN receives approved SOSS from County.

07/23/13 – GBBN meets with Darnell Edwards to review elevator replacement estimating scope.

07/25/13 – GBBN meets with Joe Merkt to visit the Justice Center Roof for the roofing replacement estimate.

07/26/13 – GBBN meets with Mike Florimonte to visit the CAB and 230 WHT Law Center Roofs for the roof replacement estimates.

08/08/13 – GBBN meets with Aluminum Resources to discuss the Window Replacement estimates for the six downtown campus buildings.

08/09/13 – City of Cincinnati Elevator Inspection Department responds with Elevator Code Requirements applicable to the 800 Broadway Elevator Equipment Replacement.

08/10/13 – Kone Elevators responds with Estimating data to GBBN for the 800 Broadway Elevator Equipment Replacement. Existing equipment is Montgomery-Kone.

08/13/13 – GBBN meets with Maria Karvelas to discuss the 230 WHT Pre-Trial Estimating Scope.

08/15/13 – GBBN sends preliminary plans to Maria Karvelas for review.

08/16/13 – Maria Karvelas indicates preliminary drawings for the Pre-Trial estimate meet the requirements.

08/21/13 – GBBN receives pricing back from Seeger Glass for the replacement of the Justice Center High Security Windows.

08/26/13 – GBBN completes all estimating into Archibus.

08/28/13 – TEI reviewed combined estimates and made minor changes.

09/03/13 – GBBN contacts ARC to notify of impending printing requirements within the next two to three weeks.

07/08/13 – County provided list of project estimates for 2014.

07/17/13 – THP submitted SOSS for review.

08/08/13 – County approved SOSS.

08/27/13 – THP completed structural estimates and entry into Archibus.

2014 COST ESTIMATES Read More »

BOARD OF ELECTIONS ADA Ramp Entrance

Lead Partner: GBBN

Current Status: Construction

Status:

12/07/12 – THP 824 ADA upgrade project requested from the County. THP to provide structural services for entry ramp. Building Owner forwards existing PDF files of building floor plans.

12/08/12 – GBBN- issued SOSS to Hamilton County.

12/10/12 – GBBN, THP and TEI kick-off meeting and building tour.

12/12/12 – Existing hard copies of original building drawings received from Owner. ARC creates electronic copies for GBBN who distributes to TEI and THP.

12/13/12 – GBBN receives signed SOSS from Hamilton County.

12/14/12 – THP – THP issued SOSS to Hamilton County.

12/17/12 – GBBN meets with Building Owner and Contractor to discuss scope and walk existing building.

12/18/12 – THP – County executed THP SOSS. Building Contractor sends Otis Elevator ADA upgrade estimate to GBBN.

12/18/12 – GBBN sends ADA handicap access ramp layout to TEI and THP. CUH added by TEI and steel structure added by THP.

12/19/12 – Meeting with BOE staff that changes scope of work to include Lobby lift not ramp, no 2nd or 3rd floor restroom renovations and modified 3rd Floor renovations. Drawings generated by GBBN and circulated to BOE/ Facilities and Building Owner/Contactor.

12/19/12 – THP entry scope modified to allow for lift in lobby vs. constructing a room with a ramp adjacent to the entry.

12/20/12 – Ralph Linne notifies GBBN to proceed with generation of construction documents based on Building Owner original scope drawings.

12/21/12 – Small changes request to new scope drawings on the3rf Floor Office Area. Changes made by GBBN and sent to BOE. BOE signed off on new scope drawings.

12/28/12 – Final pricing and scope drawings sent to Millay & Company by GBBN.

01/02/13 – GBBN forwards new card reader lockset to BOE for approval.

01/04/13 – Ralph Linne notifies GBBN to proceed with amended scope from original SOSS per BOE Staff requests. GBBN sends approval to commence to TEI/THP. GBBN calls City Transportation and Planning to ask about handicap parking space in front of building. Left voice mail. No return call ever received.

01/07/13 – GBBN and TEI perform reflected ceiling field verification.

01/08/13 – GBBN meets with Midwest Accessibility Products to discuss details on lift installation and code approval.

01/12/13 – Ralph Linne confirms Prevailing Wage Rates required in specifications for contractor work on this project.

01/14/13 – Millay & Company confirms storefront replacement to be from existing horizontal door header and down. Existing transoms to remain.

01/15/13 – TEI sends stamped and sealed drawings to GBBN for permitting.

01/16/13 – THP sends stamped and sealed drawings to GBBN for permitting.

01/16/13 – GBBN notifies Millay& Company that stamped drawings, electronic CD and permit application available for pick-up at GBBN offices. Millay & Company requests electronic drawing files sent for review. GBBN complies.

01/21/13 – Millay & Company pick-up drawings from GBBN offices.

02/20/13 – Milay & Company sends a copy of the City of Cincinnati Permit Center building application response letter to GBBN. Most issues deal with existing building conditions.

02/22/13 – GBBN contacts Norwood Hardware about response letter issue on access control

02/25/13 – TEI reports findings concerning existing outside air repairs by building owner and test results from TEI research on existing units.

03/13/13 – Millay & Company receives letter from The City of Cincinnati Permit Center. Two items require further information for building permit approval.

03/14/13 – GBBN issues directive to BOE and Building Owner about front door over-swinging existing steps as code violation that must be addressed.

03/25/13 – GBBN receives return call from Plans Examiner with additional information concerning front door potential solution.

03/26/13 – The Building Owner and BOE agree upon GBBN Scheme B solution for addressing front entrance existing code violation solution.

04/12/13 – GBBN submits City of Cincinnati Permit Center requested Response letter and drawing corrections.

04/19/13 – City of Cincinnati Plans Examiner requests Mechanical Permit drawing for submission for earlier Mechanical Permit.

04/23/13 – TEI delivers stamped and signed Mechanical Drawing to GBBN for submittal to the City Permit Center.

08/22/13 – GBBN and THP attend meeting with Millay and Company to discuss structural coordination of steel support steel under the existing Lobby for lift elevator installation.

BOARD OF ELECTIONS ADA Ramp Entrance Read More »

2015 20-YEAR PROJECT ESTIMATES THERMALTECH

Lead Partner: TTE

Current Status: SOSS

Status:

09/17/14 – SOSS submitted.

09/26/14 – Prep work started for these estimates. Waiting on Administrator approvals.

10/29/14 – THP completed initial field work and estimates. THP entering data into Archibus.

12/12/14 – BW called with an SOSS update. This project is approved for work at a new SOSS. TTC marked approved and gave Becky the PO for future billing. Coroners office 20 Year cost to be added to scope.

01/19/15 – All 20 year estimates are complete. TTE coordinate with THP and GBBN for roof estimate at Coroners Office to complete the entire list.

01/21/15 – GBBN reported that Coroner’s Roof Estimate was complete.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

2015 20-YEAR PROJECT ESTIMATES THERMALTECH Read More »

2015 PROJECT ESTIMATES THP

Lead Partner: GBBN

Current Status: SOSS Approved

Status:

07/22/14 – THP issued SOSS.

08/04/14 – County requested SOSS for 20 year project estimates.

08/05/14 – GBBN issued initial SOSS for County review.

08/21/14- GBBN submits revised SOSS with 20-Year projects removed from the Annual Estimating

08/22/14 – County approved Revised SOSS.

09/03/14 – County approved SOSS.

09/23/14 – THP published Archibus estimates.

10/29/14 – THP completed initial field work and estimates. THP entering data into Archibus.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

2015 PROJECT ESTIMATES THP Read More »

2015 PROJECT ESTIMATES THERMALTECH

Lead Partner: TEI

Current Status: SOSS Approved

Status:

09/26/14 – Many estimates completed. Fieldwork underway. Project due 10/5/14.

10/05/14 – Most projects complete. Some stragglers and large projects remain to be estimated.

10/23/14 – ThermalTech down to Courthouse Server project remaining to be estimated. TTC to finish this week.

12/13/14 – TTC to review final project status and coordinate with GBBN. I believe all projects are complete and estimates are in.

01/19/15 – 2 leftover projects were completed by ThermalTech in Jan 2015. All projects are now truly complete.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

2015 PROJECT ESTIMATES THERMALTECH Read More »

2015 PROJECT ESTIMATES GBBN (20-Year and 2015)

Lead Partner: GBBN

Current Status: SOSS- F107

Status:

0717/14 – Bert Watts sends email to partner with initial listing of projects.

07/18/14 – GBBN inquires about 20/30 year projects, cost of living increases and approaches for delivery of these estimates. Bert Watts responds to GBBN.

07/21/14 – Bert Watts responds to questions via email and deliverable date.

07/22/14 – THP initials email and spreadsheet for discussion on lead partner roles in shared project estimates. GBBN responds back to THP.

07/29/14 – GBBN informs ARC Reprographics of probable schedule for deliverables of printing and binder assembly.

10/07/14- GBBN visits Burlington Garage and completes roof replacement estimate.

10/09/14- GBBN completes all 20-year Capital Improvement Estimates.

10/17/14- GBBN coordinates with Bert Watts on scope for the Technology Estimates at the Courthouse and Justice Center.

10/23/14- GBBN completes all 2015 Project Estimates including LEED Silver Estimates.

02/25/15 – GBBN finishes creating all pdf files for printing. ARC Reprographics contacted for pick-up.

03/22/15 – GBBN picks up empty binders from Facilities department for pickup by ARC Reprographics.

03/24/15 – ARC Reprographics picks up empty binders from GBBN for assembling final volumes of Project Request Estimating Volume Sets.

2015 PROJECT ESTIMATES GBBN (20-Year and 2015) Read More »

ADA Building Assessments

Partner: GBBN

Status: Active

Status:

05/04/11 – Bert Watts notified GBBN of prospective project via email.

05/19/11 – GBBN attended the SWOBOA seminar in new ADA requirements.

06/16/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings. See the SOSS’s F045 through F052 below.

02/12/12 – Otis Elevator declines to assist GBBN in Elevator Assessment due to liability reasons. Suggests local consultant for assistance.

08/21/12 – GBBN completes last ADA Assessment Report for the Courthouse.

08/28/12 – GBBN begins estimating portion of Assessment Reports.

08/24/13 – GBBN completes estimating impacts of ADA Assessment findings on each building.

02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.

ADA Building Assessments Read More »

BURLINGTON RD GARAGE Damaged Wall Panel Replacement

Lead Partner: GBBN

Current Status: Close-out

Status:
10/14/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building fabrication. Voice Mail is left.

10/18/14 – Project manual cover from original building construction sent to Metallic Building Company

02/24/15 – County requested a full letter report and authorized additional field work.

10/24/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building fabrication. Voice Mail is left.

11/18/14 – GBBN contacts Metallic Building Company about information on original pre-engineered building color samples

11/25/14 – County Engineers reported existing overhead door stuck and has been closed temporarily not to be used until repairs completed.

12/15/14 – Metallic Building Company delivers quote for replacement part list to GBBN.

12/26/14 – GBBN authors and delivers SOSS to Bert Watts.

02/25/15 – Bert Watts emails approved SOSS and Purchase Order to commence work.

03/13/15 – GBBN attends Owner Review Meeting to review bid package documents.

03/13/15 – GBBN issues informational requests to five (5) selected bidders for project.

03/17/15 – GBBN sends invitations to Bid to all five (5) selected bidders. Electronic copies of documents included in email.

03/24/15 – GBBN holds Pre-Bid Meeting at Offices of County Engineers’ Burlington Road Garage. Hard copies of bid drawings and specifications handed out to potential bidders and owner.

03/25/15 – John Nester forwards scope quote from Overhead Door Company for overhead door repairs.

04/02/15 – Bids received and bid tabulation compiled for Facilities Department. GBBN commences interviews with those bidders submitting bids.

04/03/15 – GBBN forwards Recommendation Letter to Facilities for lowest and responsible bidder.

04/03/15 – Hamilton County approves recommendation and instructs GBBN to author contract to Century Construction Inc.

04/03/15 – GBBN hand delivers hard copies of AIA contract to Facilities Department.

04/07/15 – Century Construction delivers signed copy of Safety Receipt Form to Facilities Department.

04/10/15 – GBBN receives color samples chips from Century requiring approval.

04/13/15 – GBBN visits building and approves color samples from manufacturer and sends approved submittals to Century.

04/21/15 – GBBN receives Schedule of Values from Century, via Facilities Department.

04/29/15 – Pre-Construction Meeting held at site. Signed and executed contract hand delivered to Century from the Facilities Department. This date established as the contract commencement date.

05/15/15 – Century reports all construction work is completed. Facilities performs site inspection and punch list. One item, caulking bead at overhead door jamb is required.

05/19/15 – Facilities performs site inspection back punch list. The one item, caulking bead, has been installed as requested.

05/20/15 – GBBN signs first/final Application for Payment.

05/26/15 – GBBN sends email to Century requesting all close-out documents be processed and executed.

06/03/15 – Change Order #1 for additional signage scope, authored by GBBN and sent to Century for signatures.

06/15/15 – GBBN receives close out documents from Century Construction.

06/16/15 – GBBN receives executed Change Order #1.

06/16/15 – GBBN receives Application for Payment #0002 from Century but without Change Order #1 included. Century to revise and sent to GBBN once project change order work is completed.

07/20/15 – GBBN receives Application for Payment #0002 with Chan ge Order #1 included. GBBN signs and delivers to Facilities Department.

07/20/15 – Century Construction announces the change order signage has been installed on the building facade. John Nester confirms the work has been completed to the User Group’s satisfaction.

BURLINGTON RD GARAGE Damaged Wall Panel Replacement Read More »

2015 Electric Deregulation Bid

12/11/14 – Bert requested new SOSS this week for several end of year projects including A&D General Service, BW General Service, and 2015 Dereg Services.

03/31/15 – TTC requested updated account numbers for the Elec Dereg project from all clients for the 2015 bid.

04/01/15 – Greg Gelhausen replied to my account number request and wants to add one account to the bid. TTE said no problem.

04/14/15 – ITB 010-15 has been assigned to this project.

04/15/15 – TTE requested billing data from Duke on all accounts included in this bid.

04/20/15 – David Hisser returned all billing data to TTE for Calendar Year 2014.

05/25/15 – First Draft should be ready this week for Ralph and Tony to review and approve.

06/24/15 – Project is out for bid. Addendum 1 has been sent out. Addendum 2 is being prepared. We have 4 bidders registered.

07/16/15 – Dynegy contract approved for all four departments. Service starts in Jan 2016.

08/26/15 – Dynegy offered all Hamilton County employees a Preferred Discount plan on home electricity through 2015 or 2017.

2015 Electric Deregulation Bid Read More »

2016 Project Request Estimating ALL

05/16/15 – County requested SOSS from Partners.

05/18/15 – Bert Watts forwards email with “List of Projects by Partner” to all partners.

05/26/15 – GBBN hand delivers SOSS to Bert Watts.

05/29/15 – THP anticipates issuing SOSS.

06/02/15 – THP issued SOSS

06/05/15 – County executed SOSS for THP

06/24/15 – ThermalTech is complete with all but 3 estimates which are to be worked on tomorrow. Bert added #1824 for 800 Broadway Emergency Generator to TEI scope today. THP completed estimates and data entry into Archibus.

06/25/15 – GBBN completed with all but four estimates. ADA/Title II/III Projects Request Estimates are ongoing. Bert said that all projects must be done by 6/25 so he can make the early July deadline for the County.

07/20/15 – Facilities Department sends binder summary documents to GBBN for printing. GBBN informs ARC of the impending printing schedule.

08/26/15 – A call to ARC Reprographics confirmed the binder printing and assembly is nearly complete. ARC expects to deliver the binders to GBBN on Monday August 31st right on schedule.

08/31/15 – ARC Reprographics delivers all binders and existing documents to GBBN Offices.

09/01/15 – GBBN delivers Hamilton County copies of binders to Facilities Department.

2016 Project Request Estimating ALL Read More »

Fire Alarm & Sprinkler Testing

Partner: ThermalTech

Status: Active

Status:

06/24/15 – Project is out for bid. Addendum 1 has been sent out. Addendum 2 is being prepared. We have 4 bidders registered.

07/29/15 – Two day prebids complete. Add01 is issued. Add02 will be issued tomorrow. Bid opening on schedule for August 27.

08/27/15 – Bid opening scheduled for today. 2 Addendums issued total on this project.

09/23/15 – Tony selected SA Comunale form base bid initial term as the recommended bidder for this project. ThermalTech to author the contract for Facilities.

10/28/15 – Contracts approved. Project can be archived.

Fire Alarm & Sprinkler Testing Read More »

2017 Project Cost Estimates

All Partners

Status:

04/18/15 – Bert sent out estimate list for SOSS pricing. Facilities sends list of Project Request Estimating “Project by Partner” list to GBBN.

04/22/16 – Facilities sends email clarifying number of “standard” binders and “summary” binders along with CD’s to be delivered. Also clarification to other estimates are provided.

04/25/16 – IPM sends proposal for hours to be incurred for interiors scope of estimating.

04/25/16 – Facilities requests two separate SOSS, one for the estimating and one for the binder assembly and reimbursable expenses.

04/26/16 – GBBN hand delivers both SOSS to Facilities.

04/26/16 – Facilities requests that GBBN/IPM contact Facilities first for initial estimate contact on each Project Request and for any RFI.

05/25/16 – TEI proceeding nicely on cost estimates. We are hoping to be complete by 5/27/16 with all engineering estimates.

06/01/16 – TEI complete with 2017 estimates. We updated a few and added one after discussing with Bert Watts.

06/10/16 – GBBN completes all estimates.

06/20/16 – Facilities approves GBBN to begin estimate printing for final binder assembly.

06/28/16 – GBBN completes electronic project request estimate printing and notifies ARC for pick-up of all materials for binder assembly.

2017 Project Cost Estimates Read More »

2017 PROJECT REQUEST ESTIMATING PROJECT Estimating and Binder Assembly

Lead Partner: THP

Current Status: SOSS

Status:

04/18/16 – County requested GBBN complete project estimates for new 2017 work.

04/28/16 – GBBN provided an SOSS for review.

05/17/16 – County approved SOSS.

05/25/16 – GBBN reports to Facilities that it has completed estimates and entered them into Archibus for all assigned projects.

06/01/16 – Project estimates completed printing to pdf. Progress reported to Facilities.

06/14/16 – Facilities sends completed Binder Summary sheets to GBBN.

06/20/16 – GBBN completes packaging of al materials for ARC pick-up. ARC instructed to send deliveryman. Facilities confirms final numbers of binders and CD to be processed.

06/22//16 – ARC makes pick-up of all materials.

07/05/16 – ARC requests one pdf file be reprocessed and emailed. GBBN processes and emails back.

07/27/16 – GBBN sends request for status to ARC concerning printing and binder assembly.

07/28/16 – ARC responds the binders should be delivered between August 1 and the 4th.

08/01/16 – ARC delivers the binders and materials to GBBN. GBBN delivers one set of each binder to Facilities for review. Modified end binders required but approval given to GBBN to deliver all remaining binders.

08/02/16 – All final assembled binders and CD’s delivered to Facilities. CD delivered to IPM and TEI.

08/25/16 – GBBN delivers CD to THP at Partnering Meeting.

09/23/16 – GBBN receives final ARC invoice for printing services.

2017 PROJECT REQUEST ESTIMATING PROJECT Estimating and Binder Assembly Read More »

2017 STRUCTURAL PROJECTS Estimates

Lead Partner: THP

Current Status: SOSS

Status:

04/14/16 – County requested THP complete an investigation of slab settlement and cracking observed in the building.

04/18/16 – County requested THP complete project estimates for new 2017 work.

04/27/16 – THP provided an SOSS for review.

05/17/16 – County approved SOSS.

05/25/16 – THP has completed estimates and entered them into Archibus for all assigned projects except 17-FAC-2020-1847 and 17-FAC-5035-1848. Also confirmed Archibus entries for 17-REC-0138-1633 (entered by GBBN, LEED estimate currently $0.00 – not entered) and 17-FAC-1021-1845 (entered by THP and Thermal Tech).

05/27/16 – THP’s goal for having remaining two projects estimated and entered.

06/01/16 – Project estimates complete.

2017 STRUCTURAL PROJECTS Estimates Read More »

Emer Generator PM Bid

02/24/16 – Tony called and said that this project and PO are approved. Bid in March, Award in April, current contract runs out in May.

03/30/16 – Barth has made progress on the specifications they are about 90% complete. We are ready to get dates and an ITB and for Owner review.

04/26/16 – Project manual is ready. Date of Issuance will be 4/28/16. Bid Opening 5/26/16.

04/27/16 – Bid package sent to purchasing on 04/26/16. Pending bidding process.

05/25/16 – Bids open tomorrow. Two Addendums on project so far. All seems to be going well.

06/17/16 – Bids opened and there were anomalies. Tony to get information to ThermalTech as to which bidder each of the user groups has selected (Facilities, Cell Towers, Engineers).

06/27/16 – TTC to write a contract for Cummins for the Facility project. OK to share this contract with other departments if they need this. I told Tony this would be done last week, I will try to finish today.

07/18/16 – Tony is discussing with Kerry and is trying to stick with Cummins for the this contract. Kerry questioned the Alternate no bids by Cummins as legitimated on this job.

07/22/16 – Kerry and JoAnn and Tony are discussing rebidding this project due to Cummins not submitted Alternate bids for years 4 & 5.

07/25/16 – Talked to Tony and Gina today about the Alternate items in the Egen bid and we are going to rebid this project and we have change front ends to the standard county non-prevailing wage front end document and change Alternates to Optional Years. New ITB is 059-16.

07/28/16 – Talked to Tony and we are going to rebid all departments. I discussed a small SOSS to just pay for the the hours of this bid. We have a new ITB but no bid schedule yet.

08/03/16 – Tony said he approved my SOSS-A for rebidding this work. TTC to proceed.

08/25/16 – Egen PM Rebid sent out for bidding.

09/02/16 – No substantial questions on rebid yet. Bid opening scheduled for 9/8/16.

09/08/16 – Bid opening is today. Results to follow.

09/23/16 – IC won the second bid but didn’t include any battery replacement in year three. After several emails and reviews with Purchasing and the Prosecutors department, they are going to let their bid stand if they provide the battery replacements in year three.

10/25/16 – Post bid and Pre-Award meeting was held last Friday. Everything seems to be in order and TEI will write the contract for IAC today.

11/10/16 – All three revised contracts sent to Tony today for use on the Rebid work. IAC is the new vendor.

Emer Generator PM Bid Read More »

ELECTRICAL SWITCHGEAR PM SPECS

Lead Partner: TEI

Current Status: Approved

Status:

07/22/15 – TEI develop preventative maintenance specifications for Electrical switchgear in the following buildings. Alms and Doepke, Courthouse, 800 Broadway, 230 East Ninth Street, 250 William Howard Taft, and the County Administration Buildings.

10/28/15 – TEI working on specifications and coordinating with John Nester. TEI developed a scope matrix to review with John Nester, and also has written PM procedures. John Nester to confirm with HamCo PM procedures that the specs and the procedures are all encompassing.

12/07/15 – TEI sends John Nester preliminary specifications, questionnaire, and scope matrix for review and discussion.

04/27/16 – ThermalTech and John Nester meet to review specs. Information required from each building on “Mission Critical” equipment in building that can not see an outage. John Nester and Mike Barth are scheduled to attend next Building Managers Meeting on May 4th to facilitate the acquisition of information. Upon receipt of data from all buildings, specifications will be completed.

05/25/16 – Data from building managers due to John Nester at the June 1 building Managers meeting. Upon receipt of the data from all of the buildings, specifications can proceed.

06/27/16 – Data from building managers not all submitted to John Nester to date. ThermalTech provided JN a list of building that data still missing for. JN following up with Bldg Mgrs.

07/27/16 – ThermalTech met with John Nester just before MB Vacation. JN and MB concluded that specific data from building managers will not be obtained, and that the specifications need to be written in such a manner that we will give the overall concepts at each building, and we will size the emergency egens accordingly, but then state that building specifics will be worked out on a building by building basis.

10/27/16 – Comments back from John Gilbert this week, now ThermalTech can assist in getting the quotes together for the switchgear cleaning in the upcoming year. John Nester will lead this for HamCo.

01/27/17 – Specs are complete, project is ready to archive. Project can be be at any time, no dates were specific in the bid documents.

ELECTRICAL SWITCHGEAR PM SPECS Read More »

Burlington Garage Storage Shed Expansion

Lead Partner: GBBN

Current Status: SOSS

Status:

08/17/16 – Facilities confirms GBBN has no As-Built scope for this project on the SOSS.

08/18/16 – GBBN discusses <30% existing structure addition requirement for full existing building structural analysis. GBBN reports findings to Facilities. 08/22/16 - GBBN gets SOSS scope from TEI for Electrical scope of work. Hard copies delivered in the mail. 08/23/16 - GBBN consults with THP to discuss structural SOSS and permitting requirements for the project. 08/24/16 - GBBN forwards contact information from original contractor of Pole Barn Shed for investigation into alternative delivery method.

Burlington Garage Storage Shed Expansion Read More »

GALBRAITH SERVICE GARAGE LINTEL INVESTIGATION

Lead Partner: THP

Current Status: SOSS

Status:

03/16/16 – County requested THP investigate a deteriorating lintel at the service garage.

03/18/16 – THP visited the site to review field conditions.

03/31/16 – THP provided an SOSS for review.

07/08/16 – County approved SOSS.

07/28/16 – THP to schedule field work and complete field work in August.

08/22/16 – Field Assessment trip completed.

09/28/16 – THP anticipates final report being released 10/15/16.

GALBRAITH SERVICE GARAGE LINTEL INVESTIGATION Read More »

Energy Star Validations

09/02/16 – Buildings should be ready for certification after August bills are entered in late September. ThermalTech to draft SOSS for each building for approval.

10/14/16 – All fieldwork is complete for the certifications.

10/18/16 – TTC has reviewed all the SEP and found most to be compliant. The Courthouse requires some changes prior to submitting to the EPA. TTC contacted Tony Matre to discuss and make changes.

10/19/16 – TTC to meet Dave Johnson on site to reocver steam usage data for Courthouse Energy Star.

10/21/16 – These buildings have, 230,250,800,Admin, A&D have been uploaded to Energy Star. The Courthouse is not ready for SEP yet until we work out some occupancy issues that TEI is flagging as potential issues.

10/25/16 – TTC created a new SEP for the Courthouse with the updated numbers agreed upon between Tony and Terry. TEI will take to Ralph for signing on Thursday and hopefully upload to Estar on Friday.

11/10/16 – All six buildings have been submitted. Five buildings have been approved. We are waiting on the Courthouse approval at this time.

Energy Star Validations Read More »

BOARD OF ELECTIONS – RELOCATION SERVICES ESTIMATING

Lead Partner: GBBN

Current Status: Active- Project Closeout

01/22/16 – County requested availability for kick-off meeting with Board of Elections.

01/27/16 – Meeting date established for Kick-off Meeting at 824 Broadway Building. Kick-off meeting held at BOE Offices.

01/28/16 – IPM and GBBN visit existing Warehouse for site investigation and photographing of existing conditions.

02/04/16 – GBBN receives approved SOSS from Facilities.

02/09/16 – Facilities directs GBBN/IPM to use estimate number 1835 in Archibus for the estimating efforts.

02/10/16 – GBBN/IPM receives first space planning design from Owner’s Reality Agent.

02/23/16 – IPM visits proposed building site with BOE for the site investigation for the purpose of estimating the move services.

02/24/16 – GBBN and Facilities agree on concept for estimating electrical disconnect services to be placed into the estimate.

02/24/16 – IPM begins estimating input for the move services.

03/02/16 – IPM/GBBN confirm with Facilities that the Move Services will require a public bid if over $49,000.

03/03/16 – TEI communicates information about the Data Room/Network relocation component of the relocation services. Facilities responds to inquiry about inert gas/fire suppression systems.

03/07/16 – Facilities responds to additional requests for information about phone switch and data/I-T questions.

03/10/16 – TEI provides Network/Data/I-T relocation estimating data and cost figures.

03/11/16 – GBBN and IPM finalize estimating in Archibus with the exception of phone/I-T relocation pending input from BOE.

03/23/16 – GBBN/Facilities/HamCo Telecommunications/BOE meet to discuss I-T/Network/Phone relocation component of move services estimating. Telecom to provide estimate to BOE for running new data wiring at new facility. BOE to inquire with CBTS and Building Owner related to Inert Gas Extinguishing and Phone provisions in lease and services agreements for Telecommunications.

04/19/16 – BOE instructs Facilities that revisions to new facility space planning are not completed, by other Architectural firm, so data outlet location drawing have not been completed, for sending to Hamilton County Telecommunications Department for completion of their Opinion of Probable Costs for the data/telecommunications component, for insertion into GBBN overall Opinion of Probable Cost.

05/19/16 – GBBN attends Kick-off Meeting with RFP Team.

05/20/16 – Facilities requests SOSS from GBBN for the Moving Services Scope of Work.

05/24/16 – IPM meets with Sally Krisel to discuss scope and overall project delivery dates.

05/26/16 – GBBN submits SOSS to Facilities at monthly Partnering Meeting.

06/02/16 – GBBN and IPM attend BOE RFP Construction update meeting.

06/07/16 – GBBN and IPM attend BOE Design Services Kick-off Meeting.

06/08/16 – IPM completes BOE on site existing furniture/equipment field verification.

06/16/16 – GBBN and IPM attend BOE RFP Construction update meeting. IPM releases final furniture and equipment layouts to BOE for final approval.

06/30/16 – GBBN and IPM attend BOE RFP Construction update meeting.

07/14/16 – GBBN and IPM attend BOE RFP Construction update meeting.

07/21/16 – GBBN and IPM meet with BOE to review Moving Services Bid Package with BOE Directors.

07/28/16 – Next scheduled BOE RFP Construction update meeting with Developer, Building Team, BOE and Facilities.

08/15/16 – BOE Move Services ITB #061-16 Issuance of Bidding Documents.

08/23/16 – BOE Move Services ITB #061-16 Pre-Bid Meeting held. 824 Broadway was toured first, followed by 3600 Red Bank Road Warehouse and concluded at the 4700 Smith Road Facility.

08/30/16 – Final Day for Bidding Questions. GBBN receives one set of questions from Purchasing Department for Addenda.

09/01/16 – GBBN issues Addenda #1 to Purchasing and ARC.

09/08/16 – GBBN attends bid Opening for BOE. Two bids received and Purchasing releases copies of both bids to GBBN.

09/15/16 – GBBN and IPM meet with Planes Moving and Storage Inc to discuss bid, scope and validity of bid documents. Planes agrees to honor bid and agrees in principal to enter into contract with Hamilton County for this project.

09/19/16 – GBBN authors a Meeting Minute summary for Facilities with GBBN and IPM recommending Planes be awarded the contract.

09/26/16 – GBBN and Facilities discuss status of Meeting Minutes, recommendation and contract authoring. Subject of accepting Alternate Bid to be determined with conversations with the Board of Elections.

10/03/16 – GBBN authors AIA contract for Planes Moving and Storage. Delivers to Facilities.

10/05/16 – GBBN and IPM tour construction site to field verify critical furniture installation dimensions. Critical dimensions are found to be acceptable.

10/15/16 – Wessells Moving and Storage emails GBBN about the return of their Certified Check. GBBN emails Facilities about it immediately.

10/17/16 – Wessells calls GBBN to personally inquire about the return of the Certified Check. GBBN calls Facilities to inquire but no answers are available. GBBN calls Purchasing to obtain more information and obtains answer. GBBN calls Wessells back to inform them the bid recommendation has not been officially accepted by the County therefore check can not be returned until that time by Purchasing.

01/17/17 – IPM reports roof leak in new Warehouse area will delay move of elections equipment to new facility. Building Owner to have roof repaired.

02/22/17 – IPM reports to GBBN that move is progressing very well and move should be completed soon. BOE is very happy with progress by Planes Moving.

03/16/17 – GBBN authors and delivers Additional Services SOSS for IPM services due to delays related to roof leaks and delayed move-in of the Warehouse Elections Equipment.

03/17/17 – Planes issues request for additional services to be allocated from the Allowance built-in to the contract. GBBN requests that Planes re-issue request with additional cost break down including material and labor.

03/22/17 – Planes revised request received. Facilities approves request and authorizes GBBN to author Change Order #1 reflecting revised request.

03/23/17 – GBBN issues Change Order #1, with Architects signature, to Planes via mail.

03/27/17 – GBBN authors and mails Change Order #1 Revisions as requested by BOE.

04/20/17 – GBBN informs Planes that AIA Documents are required to submit any Application for Payments to the County per the Project Manual.

04/26/17 – GBBN coordinates completion of AIA Documents with Planes.

BOARD OF ELECTIONS – RELOCATION SERVICES ESTIMATING Read More »

Board of Elections- Training Center Renovation Study

Partner Lead: GBBN

Current Status: SOSS submitted

08/08/17 – Hamilton County requested Kick-off Meeting at BOE SOSS.

08/22/17 – GBBN and TEI meet with Facilities and BOE to discuss project, measure, photograph and field verify the existing space. Hamilton County requested SOSS.

08/25/17 – GBBN authors and provides Hamilton County with a SOSS.

08/26/17 – GBBN contacts Architect from RFP project to inquire about MEP drawing files from RFP Project. Architect responds sending along contact information for CM. CM is contacted and and sends files to GBBN.

08/26/17 – GBBN receives field verification dimensions from TEI for existing sanitary drain cleanout locations.

09/12/17 – Facilities communicates Project Request Estimate number to GBBN.

09/13/17 – GBBN communicates with Property Manager and CM related to RTU and Plumbing information.

09/14/17 – GBBN researches codes and Plumbing Fixture Unit requirements.

09/15/17 – GBBN finalizes the concept floor plan and circulates to Design Team. TEI finalizes HVAC concept approach with Facilities.

09/19/17 – Property Manager forwards information on Mechanical and Plumbing Contractors that worked on last renovation.

09/20/17 – TEI confirms contact with Mechanical Contractor.

09/22/17 – GBBN finishes Architectural and General Construction input into Archibus Project Request Estimate.

09/25/17 – TEI confirms contact with Plumbing Contractor and confirms concrete was placed in abandoned underground plumbing lines. Estimates are complete by ThermalTech for this project.

10/06/17 – BOE confirms to GBBN that tables used for trainees may be only 3 feet wide.

10/09/17 – BOE requests changes to the table and Training Room configurations. The Lobby is decreased in size and extra space dedicated to both Training Rooms.

10/10/17 – GBBN sends updated drawing to BOE for review.

10/11/17 – BOE confirms to GBBN which modified option has been selected for use. Decision on how to eventually pursue real project, if approved, is still pending discussions with Building Owner.

11/29/17 – GBBN and TEI attend Client project kickoff meeting on 11/29/17. Discuss schedule, budget, and design parameters.

Board of Elections- Training Center Renovation Study Read More »

PBS – Sound System Repair Project

03/21/06 – TEI asked for an engineering change order which covers extra time spent by ThermalTech during the construction phase and occupancy permit time on this project. Joe said he signed it and went on to his boss Eric Stuckey. This project is officially complete.

02/13/06 – TTC finally approved the closeout documents, final pay applications # 6 & 7 and as-built drawings for this project. The only thing left is TE request for additional payment.

12/02/05 – TE requested a revised final payapp reflecting $6200 change order that was approved for the north end zone speakers. All final paperwork and as-builts have been received from Durrell in hard copy and CD. TTC made a copy of this information and is sending all originals to Joe Feldkamp for his use included 3 binders of O&M’s required by spec. TE will have have a hard copy of the 1/2 sized dwgs, just the CD.

11/30/05 – Chris Schaeffer called to inform Terry that the County reached settlement with Ed Simon and his lawyer’s and that a court appearance would not be needed.

11/28/05 – Upon final check the sound system is working, the new speakers are installed and working and the final paperwork has all arrived including the as-builts for this building. TTC has to write an engineering change order for ThermalTech’s Extra Time and WJHW Extra Time on this project and submit it for payment for the year 2005.

11/14/05 – Durrell and TJ’s total change order totaled $6200 ($5600 + $600). Joe Feldkamp approved. TTC confirmed with both contractors. Chris Horrell and Scott have scheduled Durrell’s visit for this Wed 1/16/05. Work to be completed by Thursday. TE shall send out the hard copy paperwork to all vendors.

11/10/05 – TTC was contacted by Chris Schaeffer about a possible court appearance in December over the bidding of this project. TTC discussed County bidding procedures and current ORC requirements for bidding and how the Sound Engineer, Audio Contractor and Electrical Contractor was selected for this project.

09/12/05 – Pay Application #4 is being resent to TE. TTC will approve and send to County for payment. TJ delivered payapp to TE today.

09/08/05 – TTC emailed contractors about closeout for project and punchlist. Sound was excellent last Friday when TTC went to the Colts-Bengals preseason game. TTC sat in section 315 and was impressed with quality of sound and clearness of PA announcer.

08/09/05 – Durrell reported that, Tom and I went over these items and will have most knocked out this week prior to this weekends game. What will be left will have to do with getting QSC down to make the cosmetic changes to the amplifier control system to make it that much more user friendly and correctly control the amplifiers that are being displayed.

08/08/05 – TTC coordinated the final change order amounts with TJ Williams and will modify the change orders for final signing today. Both change orders are complete. TTC will deliver them by hand to PBS tomorrow and try to get Bill Meyer to stop down and sign them. Punchlist was compiled and emailed out to contractors (hyperlink below).

08/01/05 – WJHW and Durrell completed the punchlisting work. Ron Baker is going to send the punchlist to TTC for distribution. TTC talked to Scott Simpson about items that he needed added from his end and left a message for Joe about his items. The consensus appears to be that everything is very nearly complete and everyone is very happy. Hopefully this will lead to a quick closure and a working sound system ready for the season in a very short time period.

07/19/05 – We have reached resolution on the PBS Sound Change Orders. Amy will approve change order #1 8855.00 for the countertops and change order #2: 2,060.74 for restocking fees from TJ. TE will write the new change orders for these amounts and send them to TJ for signatures and then onto JF for signatures by the County. WJHW and Durrell have scheduled the Engineering Commissioning for this project on 07/27 thru 07/29. TTC will be out of town on Wednesday but will assist on Thurs/Fri as needed. Punchlist should be fine as Durrell and Scott Simpson have been working hand in hand during the project. TE and WJHW will supervise and TE will try to set up and Const Mtg on Friday for a final update on progress before we start the as-built drawings for this job. Durrell reported by email on 07/18/05:

Last week Durrell got all the speakers working (with only two exceptions) and wired to the correct amplifiers. The West amp room is complete, all racks laced and cleaned, all amplifiers working. The East we ran out of time Friday, but we have all amplifiers working with the correct speakers, we need to spend one day lacing up and minor cleaning.

We found one 2″ driver not working on the East side that will have to be accessed and one crossover on a full range speaker on top of the north end zone – each will require one day’s work.

The west club area is finished and working and the east is about two hours away (got held up due to a wedding party).

The control room is up and working. We had a MediaMatrix card fail (used backup for tuning) and Scott Simpson has to provide us with info where to mount the two computer screens and the Volume meter, both minor installs. The console and all the other equipment is in a functioning correctly including the software upgrades. We want to rebuild the control block that exist for the control screens for QSControl – some coordination will need to exist between Scott Simpson, Tom Moores and we would like Ron Baker’s input – when the commissioning is done.

Durrell will schedule two days prior to WJHW’s coming to PBS for their commissioning to be sure all of these minor items are finished. We are waiting on Ron Baker for that date (date has been set see above)

07/08/05 – Eric Stuckey, Joe Feldkamp, Diana Craynon and Bill Meyer called today to inform me that the change order has be stopped and no work will be done on it and it is most likely canceled until later. We informed TJ Williams and TTC is supposed to cancel Monday’s field trip to work on it.

07/05/05 – TTC emailed Eric Stuckey the final Change Order #01 cost including the cabling and the countertop for approval. PDF. TTC met Chris Schaeffer, Scott Simpson, Steve Durr, Sam Kinman and Ed Simon and his associates downtown today to supervise a field visit and walk through with the County for the County lawsuit.

06/27/05 – TTC sent out CD’s to HamCo for law suit.

06/23/05 – TJ Williams sent the revised ACO out today. PDF. Terry and Joe asked for TJ to redo the change order to reelect the credit that the County will be receiving in place of the speaker parts that won’t be installed. TTC and JF will then talked to Amy about writing a change order to finish the project off with the cabling upgrade. The Const Mtg verified that many, many of the issues with the speakers were resolved by fixing wiring and termination points. ThermalTech believes that by knowing this it is a fair inference that the 3000 foot cable splices are probably not infallible.

06/22/05 – Const Mtg #02 was held. Durrell reported that all base work is complete except for software upgrade on MM. Durrell offered to do all the CO work except for the cabling for the $50,000 allowance. TTC agreed that this work be a fair barter. We decided to accept the countertop change order from jb schmitt. We will pursue a change order to get the cabling issue taken care of this year and Joe and TTC will talk to Amy about it after TJ provides an update T&M price NTE for the work.

06/16/05 – TTC visited the site earlier in the week with JB Schmitt and they turned in a quote today for the new countertop work at PBS. TTC forwarded the quote to the team for a decision. Countertop = $5695.00 and New Window = $3160.00.

06/06/05 – Durrell sent an email request Topper be added to all correspondences on this project. TE forward to Joe Feldkamp for approval. PDF.

05/31/05 – TE tried to reach WJHW for a conference call to discuss moving forward with additional bidding on Change Orders for this project. CO# 2 and CO# 4 are significant and may have to be bid out separately. TJ Williams called today to see about CO approvals. TTC sent the Allowance email to Bill Meyer. TTC should have sent last week when it was approved but somehow that didn’t happen. TE and WJHW still need to talk to Joe about Club Level work and scope.

05/24/05 – TE issued a recommendation letter to PBS about Change Orders for this project. TE spoke to Durrell and told them they must proceed with scheduling on the assumption that the Change Orders # 2 and # 4 are not approved. The County will issue a formal approval as soon as it can. This may lead to scheduling conflicts later near substantial completion but bidding and change order policies must be adhered to for this project. PDF

05/17/05 – Consultants and JF are in consultation about approving change order request. TE has requested direction from their sub WJHW on what is essential and what is not. First TJ payapp is approved and sent to JF.

05/11/05 – TJ submitted 5 change orders today to the project. PDF TE setup a construction meeting for Thursday at 1:30 p.m. to discuss project progress. TJ contracts are signed and in security for contractor to pick up.

04/27/05 – Contract has been approved by the Commissioners. TTC advised the contractors that the contract and PO would soon be in their hands. TE and WJHW will have subs complete by the end of the week.

04/26/05 – WJHW has submittals for AV work on the job. TE has reviewed the submittals fro EC compliance and found no errors so we will approve them with “No Exceptions Noted” to that end, we have told TJ the same. TJ inquired about contract approval and TE told them Wed at Board meeting, we should know. Please advise us when you hear information about Contract.

04/22/05 – TE received submittals for TJ yesterday. TE is checking for EC items. TE shipped one to WJHW for AV items. TE has delivered all dwgs and specs to TJ for permit application. JF reported that contract is in front of board for approval on 04/27/05. Everyone is still working at their own risk to date. Durrell has sound system working in bowl for weekend draft picks. County Prosecutor asked for some video footage of splice problems in the amp rooms. PBS reported that some have been fixed but other still remain to be documented and that Durrell may know best which ones to document. JF and TTC communicated about this pre-work in email PDF.

04/19/05 – TE sent out an email stating the Durrell may be doing some additional work in the Club levels that is above the scope of work outlined in the contract. Monies for this work shall be determined later.

04/18/05 – TJ sent their employee list into the County for this project. PDF. JF reported that contracts have been submitted and the project is up for Board approval on 04/27/05.

04/12/05 – TE had TJ resign new contracts forms and delivered to Kerry Dowling for approval. Kerry said that she would sign these on 04/11/05 and TE would have City Dash pick up the newly signed contracts and have them delivered back to Joe Feldkamp for submission to the County Commissioners for approval. TE sent 3 sets of dwgs to Dallas for WJHW to sign for TJ to turn into IBI for permit sets. TE and JF told TJ at the pre construct mtg on 04/11/05 that all work done by Durrell and TJ before receiving the contract and the PO is “at your own risk” type work.

02/23/05 – TE delivered contact to Joe Feldkamp. TTC and JF discussed contractor over phone and coordinated paperwork due to prosecutor. JF will submit contract for prosecutor review. TE will hold on notification to contractors until all paperwork is finalized. TTC would like to see 2 week turnaround in contract to keep scheduled intact.

02/22/05 – TE has received all required bid paperwork and finalized the Contract. Contract, Drawings, Spec Books and Drawings will be sent to Joe Feldkamp today.

02/16/05 – County and PBS indicated to proceed with Base Bid and Alternate 2 for this project.

02/16/05 – TTC and WJHW discussed the Alternates from the bids and are basically recommending that the County accept Alternate # 2 at this time and wait on Alternate # 1 because of the unknown variables included with updating the system. TE recommends fixing all the existing problems first before adding a new layer of master control that my contribute new and undiscovered problem of us to troubleshoot in the field plus upgrading to the BIAMP system will add additional dollars to the existing SOSS as this is a scope change for engineering (WJHW is working on an adder price). We will write the contract with Alternate #2 for the time being.

02/08/05 – Bids opened. TJ Williams appears to be the low bidder. TE has contacted contractor for additional paperwork and will begin contract work immediately. County needs to provide a signed bid evaluation form with Alternate recommendations for contract.

01/25/05 – Addendum 3 distributed. Durrell asked a new question for Addendum 4. The bid was extended to February 3, 2005.

01/21/05 – TE coordinated with WJHW and County to extend bid date one week and to send out Addendum 03 on Monday with updated information for bidding and alternate. Purchasing Department instructed TE to contact ICB Audio via email about non-inclusion into the accepted bidder’s list for this project.

01/20/05 – TE distributed Addendum 01 on 01/11/05 and Addendum 02 on 01/20/05. Addendum 03 should come out on 01/21/05. TE has written a rejection letter and given it to Purchasing to give to ICB as they do not meet the Professional Stadium Experience Requirement on this project. The SoundCom qualifications have been sent to WJHW for review and we are currently waiting on SoundCom to confirm a couple of questions about which office will serve this project but they most likely will be approved for bidding as they do meet the quals. TTC asked if the bid should be extended since SoundCom is being added. TE is awaiting the County’s decision. The second prebid was attended by about 8 contractors. Muzak declined to bid and left the prebid after we stated that OEM equipment must be used for repair.

01/19/05 – Prebid is finished. Addendum # 01 wads distributed. Addendum # 02 is going out tonight. Addendum # 03 is scheduled out tomorrow. ICB will not be an approved vendor. TE has to provide a letter to Purchasing for the use, modify and send.

01/14/05 – Joe Feldkamp called to inform TE that because the prosecutor wants a firm number for cost to provide as-built drawings that we can change the bid for to add an alternate to have the AV contractor provide a complete set of as-builts encompassing the entire scope of work at the stadium. TE shall modify the bid form accordingly.

12/24/24 – TE invited Audio Specialist Contractors. Project Manual is on the street, on schedule. Prebid set for January 5th. WJHW will be in town for the prebid. Everything appears to be set for bidding att his time.

11/04/04 – TE found and sent the AV drawings to WJHW today. Final design is still scheduled for final delivery on 12/08/04.

10/25/04 – WJHW sent an informal report from the field trip last week. PDF

10/19/04 – TE, WJHW, PBS and HamCo had a meeting and set the following schedule for this project (see below)

10/19/04 – TE and WJHW met onsite with the owners and ironed out the scope of the project, schedule of the project and the expectations of the project. WJHW will begin design and target first week of December for final engineering documents. TE will release minutes in a follow up email. Contract will be bid to a local EC with a Audio Specialist assigned as a sub.

10/15/04 – TE will meet WJHW onsite on Tuesday for kickoff meeting. WJHW will be onsite late Monday afternoon. They have coordinated their time with Scott Simpson.

ThermalTech solicited consultant bids and wants to team with WHJW from Texas for this project.

Conference call on August 17 between Eric Brown, Bob Bedinghaus, Joe Feldkamp and Terry Cannon with WHJW was held to discuss itemized consultant cost and scope of consultant work on this project.

TE is awaiting a signed SOSS from the County.

The County is awaiting a one page report from WHJW outlining the added benefits of using WHJW on top of the Durrell report.

Project scheduled to be signed in August 04, Designed in Sept – Oct 04, Bid Nov 04, Awarded in Dec 04, Construction Jan 05.

PBS – Sound System Repair Project Read More »

PBS – Occupancy Redistribution Project

03/20/06 – Joe approved TEI’s cost on the ECO for Sound project. This project is officially complete and ready to be archived.

11/30/05 – After speaking with City Permit office they confirmed that TE did pay for these permits. TTC called Randy this morning and told him that these permits were paid for on 10/18/05. TTC is awaiting a call back to clear this up.

11/25/05 – Randy Campion called to inform TE that there is a remaining balance on these permits. TTC called the city to see what that cost was because TE has already paid for the new permits with a check. Once this is cleared up Randy will send new Certificates of Occupancy.

10/18/05 – All revisions have been accepted and approved by the City. New permits costs = $354.00. New occupancies have been set to 1021 (East Club) and 986 (West Club). According to Randy Campion once the permit is paid for, which TTC did today, the permit will close and information will be sent to Fire Dept. They will issue a new occupancy for private club events. to PBS.

09/28/05 – The City received all the information from Cole & Russell but need it properly inserted into the permit dwg sets. TTC will stop at the permit office and manually do this on Friday or earlier if possible.

09/20/05 – After the City sent the letter emailed by TTC to PBS yesterday requesting additional egress information, TTC talked to Cole & Russell about this information. C&R believes that they already have all that information collected from the sliding door project and will call Carl Graeber and discuss directly with him. They can get all that information to the City on Friday or early next week. TTC will check back with city and C&R about progress at that time. We believe the city will accept this and process the permit app immediately thereafter for final inspection.

09/08/05 – TTC contacted city. Permit should be reviewed by 09/13/05. TTC will check back at that time.

08/25/05 – The permit is still being reviewed by the City. TTC will continue to check on status.

0815/05 – TTC met Randy Campion at the PBS site on Monday, Randy approved the 821 and 851 increased occupant load and will sign the CO paperwork and send it to PBS. After the meeting, PBS said that the 30% OA was not a problem so that they want even higher occupant loads. TTC turned in another set of prints with the higher numbers of 986 and 1021. The city made us turn in for all new permits: 2005P06669 and 2005P06670.

07/18/05 – City called with Approved Permit numbers today. Permit was split up into 2 permits 2005P05544 AND 2005PO5589 ($284). TTC will pick-up permit on Tuesday morning. Inspector, Randy Campion has to come to the site to approve and give us a new CO for the space. This will be coordinate with HamCo & PBS in the next couple of weeks.

06/30/05 – TTC got GD to sign occupancy permit drawings in regards to HVAC OA requirements. TTC submitted for permit. Permit # 2005P05544. TTC informed all parties that permit can be checked at www.cincinnati-oh-gov at anytime. Amit was also promoted to Project Manager, so we are unclear if he will review this permit.

06/16/05 – Eric called today and TTC reported that Amit had returned one of his phone calls stating that he was seriously behind in permit reviews. With that knowledge, TTC stated that we should just go ahead and subject a revised CO application and talk to him them as opposed to conferencing in with him early.

06/06/05 – TTC sent an email outlining TE’s field findings to Joe, Sam and Eric. TE need direction from PBS to proceed on next level or work.

06/03/05 – Sam Boehringer of TE collected field data to update actual occupancies of the space.

05/25/05 – Eric Brown setup a meeting with the CFD department about occupancy requirements of the club level space.

PBS – Occupancy Redistribution Project Read More »

PBS – Deep Well Pump Replacement

03/23/06 – TTC spoke to John Wagner of Moody’s today and here is where the problem is: the actual repairs cost $15,573 not $6573, the 6573 +the 9000 already paid = the total cost of repairs on this job. This means that they are still giving you back $4427 on the job. John outlined this in a letter in September which I am having faxed to me. With this information, I will redo the paperwork and send it up to John for use on completing this project. I have to write a new change order, allowance usage and final pay application to make all the numbers work out right.

03/20/06 – TEI received final paperwork on this project today from Moody’s. This will be forwarded to Joe for payment on this project. TEI to begin phase II service contract immediately.

02/16/06 – Moody contacted TEI to request AIA forms. TTC sent them out in US mail for their use. They should complete these, notarize them and get them back for closeout.

02/06/06 – After an inquiry by Sam Kinman, TTC found the payapps sent to ThermalTech for approval. They were approved by Sam on 11/21/05. The problem is that they are not on AIA invoices which means there is no where for TTC approve. Assuming they are approved by TTC on these forms, the Contractor still has not turned in standard county documents for project closeout. TTC will forward a copy to Moody’s and ask for return of these documents. TTC completed a full packet of information required and mailed to Moody’s today via US Mail. TTC will follow up with a phone call today as well.

11/30/05 – Sam Kinman reported today in an email back to TTC that the deep well pump replacement job is complete. Since TE wasn’t used very much during construction, TTC assumes the punchlist is fine and no additional work needs to be done. TTC will archive the project from the database and closeout the project number. TE has never received a payment to approve, nor the final County paperwork to approve for that payment, nor manage any of the allowance monies. All this will need to be done before the project is closed out in the County’s books.

08/08/05 – TTC contacted the County about status of the Deep Well Pump Contracts. The previous entry does not state that the contracts were sent to PBS.

07/18/05 – Bid were opened. Moody was apparent low bidder at about $29,400. $20,000 in Alternates can be taken (ALT #1 and ALT #3). TE has contract written for $49,400 and will give 4 original copies to PBS for approval with Board. Bid PDF

07/05/05 – TTC worked on July 4 to get Addendum 2 complete and sent it out for distribution. PDF

06/27/05 – TE worked on Add01 and it will go out to the Contractors on 06/28/05. PDF

06/13/05 – TE sent out Project Manual for bidding. PDF

06/06/05 – Comments received from Sam and John Wagner of Moody in Dayton. TTC will update Project Manual and prepare for bidding ASAP. PBS talked about including a 3-year service contract on top of the bid. TE has done these in the past and can add this scope to the project if so directed by the County for bidding. This would be an engineering scope change to this project but it makes very good sense to include it now (12 hours x $80 = $960) and that includes the contract modifications for the Alternate bid to take optional years.

06/01/05 – Comment received from Joe and Eric. Nothing from Sam yet.

05/30/05 – TTC sent a project manual out for review over the weekend to PBS and County. Once comments are received, TE will distribute to public for bidding. All dates must still be coordinated with HamCo Purchasing.

05/26/05 – TTC contacted Moody’s for some specific questions about parts replacement. The Project Manual is built for front end. TTC needs to add dwgs and mechanical section. Bid Form needs to be modified for this job.

05/17/05 – The team had serious discussions about project schedule today. PBS re-iterated their concern about flooding. TE provided a timetable for construction that appeared not to be acceptable to PBS. TE had discussions with JF about project and will try to speed up project manual creation significantly to lessen risk. It is TE’s belief that County Purchasing has already decreed that this project does not meet Emergency Status.

PBS – Deep Well Pump Replacement Read More »

PBS – Pro Shop Metering Project

03/29/06 – TTC reviewed the billed KW and KWH to the PBS Pro Shop and the numbers looked good. The pro shop is using less than 1% of the total power consumed at the building.

KW KWH
February

50.91 21,863
January

34.91 28,950
December

79.91 25,448
November

59.28 16,077
October

72.30 14,661
September

63.67 16,528
August

53.30 4,166
02/01/06 – TTC check on the meters and to review monthly billings at the site. The meters appear to be reading in the Megawatts which seems really high at first glance. TTC to reconcile with actual building data.

11/16/05 – TA visited the site today. Reviewed punchlist and determined that Bond Electric has not completed the issues described on the punchlist. TE called Bond to tell that them that can’t get paid until these items and the final paperwork is complete.

11/15/05 – As-Built drawings for this job were turned over to Wayne Trent of HamCo Facilities today.

06/17/05 – Const Mtg was held at PBS. Sam did not attend. Equipment is not on site yet but Bond is ready to get to work as soon as it arrives.

02/28/05 – Purchasing called to inform TE that Bond does NOT have a performance bond or check submitted for this project. We should not let them begin work without this paperwork in place. TA to confer with Jack Boland today and emphasize the need for this check immediately.

02/10/05 – Contracts and Bid Results are in County’s hands. TE awaiting further direction on this project.

11/17/04 – Bid Results

10/12/04 – Project is out for bidding.

Addendum#1 distributed.

Addendum#2 distributed.

Addendum#3 distributed

PBS – Pro Shop Metering Project Read More »

PBS – Deep Well Pump Service Contract

02/02/07 – After many contract revisions, phone calls and problems, the Prosecutor finally allowed preventative only maintenance contract that Kerry wrote and gave back to everyone to use. Other repairs and emergency repairs must be bid our as prevailing wages. TEI does not and will not every agree with this approach. We took prices for many other services to save the County money but those were not accepted as part of this job by Hamco Prosecutors office.

01/10/07 – TTC got Kerry’s new email address and forwarded the revised contract to her for any final changes that she would like to make. Kerry confirmed that the packet was received at her office.

01/08/07 – TTC hand delivered the final contract with Kerry’s marks to security for Jenny and Joe to pick up and resubmit to the Prosecutor’s Office.

12/26/06 – TTC will finalize the deep well pump contract this week.

03/29/06 – TEI has not heard from Daktronics with a registered service repair list yet so I called and got Greg’s email and sent him the request again.

03/21/06 – TEI finished the SOSS and will drop it off at the HamCo Facility Department on Wednesday for this project.

PBS – Deep Well Pump Service Contract Read More »

PBS – Energy Study

03/20/07 – Project ready to archive.

11/30/05 – TTC and GD have to meet internally to review the 10/11/05 findings and energy usage. GD believes there can be savings found in schedules and space control but we will need “buy in” from facility department to implement. TTC has to setup meeting with GD to review other items but County end of year crunch on projects has dampened progress. All work will be done by end of year.

10/11/05 – TTC and GD met on site and reviewed the whole facility with Sam, Joe, Eric and the financial manager.

05/10/05 – Kickoff meeting for project with JF, TTC.

PBS – Energy Study Read More »

PBS – Video Wall Replacement Project

12/19/07 – Nor Comm has provided the AIA closeout paperwork, warranty letter and payapps. TTC signed and City Dashed it to Joe Feldkamp. This project is complete.

09/03/07 – TTC has received and approved the O&M’s. TTC is hand delivering the box of O&M’s and final payapp to PBS tomorrow at 9am at the Deep Well Pump prebid.

08/28/07 – TTC contacted Nor-Com again about final payment via email with a Read Receipt.

08/20/07 – Nor-Com contacted Joe today about final payment. TTC emailed Joe back station what happened to Payapp #2 as listed below. To date, we have not received any additional paperwork.

07/02/07 – TTC has contacted Howard Milkis and Nor-Com several times for closeout on this project. No response to TEI. TTC will try to contact the office directly today and find out how we are going to close out this project.

05/14/07 – PBS did not use TEI service much at all on site during this project. TEI has been in contact with Joe and Scott numerous times during construction as things were going well. TEI contacted owner today for punchlist and closeout items for Nor Comm. As far as TEI knows, this project is complete.

03/30/07 – TE received submittals for review and promised to work on them this week. Nor-Com has a schedule forthcoming.

03/16/07 – Scott and Joe held a kickoff meeting. TTC to follow up and publish some const mtg notes this week. A second Const Mtg is to be scheduled. PBS would like TV in before draft day.

02/13/07 – All contracts and information is in the Prosecutors office for review. Comments have been added and the contract should be approved very soon. TEI provided a copy of the bid results to Kerry Dowling per her request last week. Joe Feldkamp is following up with the Prosecutor Office.

01/30/07 – TEI finished the revised contract and returned it to PBS for use on this project. Now TEI is waiting for approval and signatures to move into a pre construction meeting.

01/10/07 – TTC hand delivered the contract based on the Base Bid cost to Joe for submission to the Prosecutor’s office. TTC included a $2500 allowance in the project after the bids were opened.

12/26/06 – TTC will finalize the deep well pump contract this week.

PBS – Video Wall Replacement Project Read More »

PBS Video Switcher

10/26/09 – Final paperwork is received. TTC approved and mailed to Joe.

09/22/09 – Project is complete. We have approved payapp #2. Once all the closeout paperwork has been received and training is complete. We can close out this project.

08/25/09 – One payapp has been approved. Punchlist has started. Training continues.

07/29/09 – Project has been bid and awarded to Rosco. Work is proceeding and Chris Williams will be able to check in on progress on August 4th when he visits Cincinnati for the Brewers game.

06/23/09 – This project is in contract approval stage at HamCo.

PBS Video Switcher Read More »

PBS Z-Ramp Replacement

09/14/09 – Additional documentation has been sent to Kerry for contract approval.

08/25/09 – Joe needs additional bid information for the project. United needs to provide final bid paperwork to Joe.

0729/09 – Project has been bid. Prices were tabulated and sent to bidders. Final contract was $16,300 and included $500 in allowance monies. TEI has written the contract and given to the County for signing.

06/23/09 – This project is out for small project bidding.

PBS Z-Ramp Replacement Read More »

JC – Administration Space Reconfiguration Study

10/19/17 – GBBN contacted by Administration to conduct a Study.
10/20/17 – GBBN responds related to information already known and to inquire more about scope.
10/24/17 – GBBN sends preliminary schematic design sketches on applicable spaces within JCC that may be considered in the Study.
09/25/17 – Facilities visits site and confirms back to GBBN and Administration which areas, proposed by GBBN, are valid and which are not. Discussions with ThermalTech, concerning capacity and operations of existing mechanical system, are related to Administration. Facilities echoes TEI concerns about increasing occupant load inside existing buildings.
10/25/17 – GBBN sends final inmate occupant counts, for the dormitory style option, related to schematic designs, to Administration. GBBN instructed to await approval from the Administrator about proceeding into Phase II (detailed Opinion of Probable Cost).
10/31/17 – GBBN attends walk-through meeting with Sheriff’s Committee. Existing spaces in JCC Third Floor and Courthouse JAX spaces on 6th floor are reviewed and photographed.
11/10/17 – GBBN attends meeting with Public Defender Office to discuss status and deliverables.
11/13/17 – GBBN and Facilities meet to discuss all various projects and status.
11/20/17 – GBBN meets with Administration to discuss strategy for grant application submission.
11/21/17 – GBBN meets with Sheriff’s Committee to discuss applications for Administration Space Layouts and possible intended uses.
11/21/17 – GBBN submits completed design sketches, Inmate Counts (Dorm and Closed Cell) for all potential spaces and input from Sheriff’s Committee meeting to Administration.
02/22/18 – Drawings sent to County and forwarded to State for review.

03/26/18 – GBBN attends HCJC Space Augmentation Project Meeting.

JC – Administration Space Reconfiguration Study Read More »

JC – Security Camera System Replacement

06/27/17 – ThermalTech sends SOSS to facilities for approval.
07/25/17 – Project pending approval of SOSS and PO.
08/28/17 – Project pending approval of SOSS and PO.
09/26/17 – Project approved at the 09/13/17 BOCC meeting. Upon receipt of the approved SOSS and PO, ThermalTech will schedule project kick off meeting.
10/25/17 – Project kick off meeting scheduled for 11/09/17 with facilities and Kevin Horn.
11/29/17 – TEI began the field investigation audit for the existing system on 11/28/17. Field investigation to be complete prior to Christmas break, and then work directly into the SD phase of the work.
01/22/18 – TEI has completed the SD and is well in the DD phase of the project. After the pre-construction meeting for the Kiosk and Matrix project – TEI to request a 60%review meeting with facilities and HCSO.
02/20/18 – TEI has design progress meeting with the HCFD and HCSO – and scheduled a follow up walk through of the building to confirm final camera placements on 03/01/18. ThermalTech planning to issue final review set of drawings to HCFD by mid march for review. Anticipate issuing for bidding approx early April upon reciept of review comments. ThermalTech sends PDF of documents to HCSO after review meeting to send to State of Ohio for approvals.
03/27/18 – TEI walked the building to confirm the camera locations, and also discussed items of the system with Sheriff’s Office IT Dept.
04/25/18 – TEI scheduled a 100% final review meeting with HCFD and HCSO for 10:00 AM on 05/08/18.
06/27/18 – Project issued for bidding on 06/25/18. Prebid conference scheduled for 07/12/18. Bid opening scheduled for 07/26/18.
07/25/18 – Project is currently bidding. Bid opening date extended 1 week and new bid opening will be 08/02/18.
08/29/18 – Project bids received, and were over the published budget. ThermalTech. Facilities and HCSO meet on 08/28/18 to discuss scope and/or budget modifications. ThermalTech schedules meeting on 09/11 with HCSO to review the proposed revised scope (=replacement of all existing analog cameras in building, maintain existing IP cameras in building, and add POD cameras only as base bid). HCSO tasked with creating a priority for all requested additional cameras on the project. Anticipate issue for re-bid 1st week of October 2018.
09/26/18 – TEI, HCFD and HCSO scheduled to meet to review revised package and also discuss dates for the re-bid on Friday 09/28/18. Issuance for rebid pending meeting results.
10/23/18 – Project is out for bidding. Prebid meeting scheduled for 10/30/18 at 10:00 AM. Bids will be received at purchasing on 11/15/18.
11/28/18 – Project bids received. TEI authors contract and sends to BW to get to prosecutor for approval. Upon receipt of contract and PO. project will begin construction. HCSO contacts TEI and requests information for State submission.
01/29/19 – Project approved by the BOCC. PO and signed contract approved, and JN sent the pre-construction submittal checklist to DK for initiate the pre-construction submittals. a pre-construction meeting will be scheduled and conducted in the next few weeks.
02/26/19 – TEI hosts construction kick-off meeting at the JC. DK slated to mobilize immediately, however there will be 2-3 weeks of programming that will be performed off site.
03/26/19 – Construction is progressing. All racks for switches are installed in the LCs. There is a concern about tall individuals hitting their heads on the racks, and DK to install padding and yellow tape. Fiber system being installed and progressing. New NVRs installed in server room and burning in. Camera’s will be switched out starting in the next several weeks. Programming continues to progress “behind the scenes”.
03/28/19 – Make sure we hold off on doing new work in these spaces until we get approval from ODRC and Facilities gives us the green light that all approvals are in place; very important.
04/24/19 – ODRC indicates the HCSO (verbally) that the project is approved. HCFD states get it in writing. HCSO stated that they are meeting on Capacity project on Monday, and will ask for the signed letter in person on 4/29 if not received prior to the meeting. DK continues to work on the project, infrastructure in the basement and first floors of both buildings. Once that is complete, they will be working up through the north tower first and then the south tower. Anticipate that Stanley will be on site about the time that the first tower is completed to make the switch over. DK is in constant contact with Stanley with this project.
05/29/19 – HCSO receives letter from ODRC with project approval. JN from HCFD states that DK can proceed with the alternate work (in the Pods). TEI authors CO for the inclusion of a doorbell in room 110 per the HCFD request.
06/26/19 – Camera system installation moving now, working on 3rd floor of north tower this week. anticipate that the north tower will be complete (other than housing units) by middle of July, and the south tower by the middle of August. Housing units will be completed in September for both buildings. HCSO wanted to confirm that project will be complete prior to October 2019, as that is when the ODRC will be on site for annual inspections. DK indicated that would not be an issue. The HCSO is very happy with the resolution and quality of video data that they are getting on the new cameras. The main comment at the const meeting was that there is a Night and Day difference in quality.
07/24/19 – North tower complete on Valerus system (except elevators and PODs), South tower Basement, 1 and 2 complete (By the end of this week). Stanley integration will be on site the week of 07/29/19 to upload and reprogram the PLC system so that all of the touch screens in the LCs and the Central Control booths are programmed for the new system and the work arounds that have been in place during the migration can be removed. There was an issue where the video matrix units both lost power (power blip) and determined that these are not on building UPS power. ThermalTech and Keith Otis met on 07/24/19 to evaluate solution.
08/27/19 – North tower 100% complete. South tower upper 3 floors remaining. Then elevator cameras and project ready for punchlist. TEI and HCSO scheduled to perform punchlist on 09/05 and 09/06.
09/25/19 – ThermalTech conducts punch list for both towers. Final meeting scheduled for 10/29/19 – all punch listed items should be completed by final meeting.
10/30/19 – TEI and HCSO meet for final construction meeting. There were a few punch list items that are still incomplete. TEI will email the team with the final comments. DK to submit all closeout documents per the project manual and then the projects will be closed out.
12/11/19 – Upon receipt of the closeout documentation and as-built documents, the project can be closed out.
01/28/20 – TEI and facilities request schedule of closeout documentation from DK. In progress.
02/26/20 – DK submits final signed off punchlist. DK states that as-built and close out documents will be delivered to TEI for review/approval on 02/26/20,
03/26/20 – DK delivers As builts and O&M manuals to TEI for review. TEI in process of reviewing.
06/23/20 – TEI finalizing CAD process for the As-Built drawings to submit to County.
07/29/20 – TEI to have N4 convert as-builts for the IFM system, and project complete.
08/21/20 – Project closeout pending pay application corrections from DK.
08/27/20 – BW said ready to archive.

JC – Security Camera System Replacement Read More »

JC – Matrix Security Replacement

03/25/15 – County requested a “high level” opinion of probable cost for the Matrix system replacement at the JC. TEI submitted to BW a very high level Opinion of probable cost. BW asked for an SOSS for TEI to establish a JC specific opinion of probable cost, with the JC specific ancillary systems to confirm that all of the ancillary systems would be compatible with the new Matrix head end. TEI waiting for PO and signed SOSS.
04/29/15 – TEI receives signed SOSS and PO from HCFD. TEI emails Rocky Mullins to schedule site visit – and will make site visit pending scheduling of visit to develop complete understanding of existing system and all ancillary systems connected to the matrix.
05/26/15 – TEI met with Mark and ICS at justice center to review the existing conditions and what is connected to the existing Matrix and how the connections are made. TEI is drafting report for Facilities Department including revised cost estimate.
06/24/15 – TEI submitted the final report to HamCo. Upon review of the report, HamCo requested an SOSS for the installation of the recommended upgrades. TEI submitted SOSS to HamCo and is awaiting approval and Purchase order.
07/22/15 – SOSS and PO pending approval.
01/26/16 – TEI receives calls from Sheriffs office that the matrix is failing. TEI directs sheriffs office to contact BW for status of funding.
04/27/16 – Project on hold pending funding.
05/25/16 – SOSS re-issued – pending approval and PO (new TEI contract term).
06/27/16 – SOSS and PO pending approval. (Note – funding approved at 06/15/16 BOCC Meeting).
07/27/16 – SOSS and PO pending approval.
08/23/16 – TEI receives signed SOSS and PO (PO#568305). TEI, Sheriff’s office, and BW conducted a kick-off meeting at the JC. TEI to begin field work at completion of 2020 Matrix project.
09/28/16 – TEI had discussions with ICS re cards in existing matrix that are out and “not replaceable”. ICS located used cards and were installing them to get the blind LC’s back in working order. Fieldwork to be scheduled with Rocky Mullens/Mark Sengawald in the next week or so.
10/25/16 – TEI conducts field work and documentation of existing conditions. A design meeting is necessary to discuss features of existing system versus what is available with current technology; project is progressing.
01/25/17 – TEI completes design after Sheriff’s office assigns Kyran Weithofer as the Sheriff’s PM for the project. 100% design review meeting conducted on 01/25/17, project to be sent to purchasing on 01/31/17 for ITB.
02/25/17 – Project is out to bid, with bids due back to purchasing on 03/02/17. TEI conducts pre-bid meeting on site and has issued Addendum #1 and Addendum #2.
03/22/17 – Project received 2 bids. Based on budget, HamCo wants to reject both bids and send out for re-bid with added scope. This is to be approved at 3/22/17 BOCC meeting.
04/26/17 – Facilities instructs ThermalTech to hold on re-bid, asked for SOSS to solicit maint agreement. TEI provides SOSS – pending approval and PO. Then Facilities to have ThermalTech re-package Matrix and issue the maintenance agreement spec at the same time.
05/22/17 – Project on hold pending approval and PO for Maintenance Agreement.
06/27/17 – PO for maintenance agreement has been received, and ThermalTech to develop specs for Maintenance agreement and repackage the matrix project for simultaneous issuances (tentatively end of July)
07/25/17 – Matrix Project and Maintenance Agreement Projects are complete and are to be issued for bids on 08/01/17 (ITB – 039-17 Maint Agreement, ITB 040-17 for Matrix).
08/28/17 – Bids opened on 08/23/17 – within budget. TEI is working to validate bids and then will author contracts for both projects.
09/26/17 – TE authors contract for DK to install work for the project. Upon notification that contracts are complete, TE will schedule pre-construction meeting to kickoff construction phase of the project.
10/25/17 – Facilities indicated that contracts have been approved and are waiting on hard copies and PO to come back from purchasing to schedule pre-construction meeting. Anticipate this meeting to occur in the first couple of weeks of November.
11/29/17 – DK receives PO and signed contract on project. Since DK was awarded this project and the Kiosk infrastructure project – and the work for these areas are in same spaces throughout the building, DK to work on both projects concurrently. Pre-construction meeting to be scheduled as soon as the contract for the kiosk project is available.
01/22/18 – A pre-construction meeting was scheduled with the team and DK for 01/30/18. This project to run concurrently with the JC Commissary Kiosk Project.
02/20/18 – DK mobilized and has started construction on project. Weekly const meetings to occur every Tuesday at 9:00 AM throughout duration of project. ThermalTech has reviewed and approved all submittals, materials are on order and scheduled to arrive in next 2 weeks.
03/27/18 – Construction of this project and the Video Visitation Infrastructure Project is ongoing. Matrix equipment is on site and cameras are being programmed at DK office and brought to site.
04/25/18 – Construction underway on project. Equipment to be installed in rack to start the “burn in” process this week.
05/30/18 – All equipment is installed in racks and burn in procedure underway. DK waiting on Stanley to provide schedule of when the changeover to occur (when Stanley on site). Anticipate by end of first week of June all work to be installed and running on new system.
06/27/18 – Stanley scheduled to be on site on 06/28/18 at 11:00 AM. TEI, DK, HCSO and HCFD to meet with Stanley to discuss implementation plan.
07/25/18 – Stanley on site for PLC programming during mid-July. DK working to make all new cameras work in matrix – existing cameras were transferred first. Construction progress meeting and pending issues discussion scheduled after partner meeting at 1:00 PM at the Justice Center with Facilities, TE, DK and HCSO.
08/29/18 – DK indicates that the project is complete. ThermalTech, Facilities and HCSO conducts punchlist walk through and ThermalTech issues project punchlist. DK working on punchlist items.
09/26/18 – DK indicated that they have to bring Stanley back to site for re-programming to get the project completed according to the bid documents. completion of punchlist pending Stanley availability.
10/23/18 – ThermalTech and HCFD receives email from Lt. Weithofer that nearly all of the punch list items are complete. JN requests a date from DK when the final items will be 100% complete.
11/28/18 – Project closeout pending DK finalization of pending punch list items.
01/29/19 – Project closeout pending the complete submission of close out documents from DK.
02/26/19 – TEI finally received final close out documents from DK. TEI to process and deliver to HamCo.
03/26/19 – TEI delivers closeout documents to facilities department. Okay to archive.

JC – Matrix Security Replacement Read More »

JC – Commissary Kiosk Electric

06/24/15 – TEI received signed SOSS and Purchase Order for project. Mike Barth to establish Kick off meeting with Hamilton County to start project.
07/22/15 – Design kickoff meeting scheduled for 07/23/15 at 9:00 AM at the Justice Center with HCFD and Kevin Horn of the HCSD. Design schedule get developed at 07/23/15 meeting.
08/25/15 – Design Team met on 7/23 to discuss proposed locations. HCSD (Kevin Horn) investigating cost associated with obtaining pedestal mount units so that in the larger Pods, the kiosks can be located adjacent to the columns (much better view from LC). ThermalTech waiting on final design direction from HCSD.
09/23/15 – Design is on-going. TEI met with county electricians to determine location to feed power to panels that will serve electric to the Kiosks. TEI will need to meter the power risers for a period of 30 days per NEC to determine if there is capacity on the existing power risers that are in the building. Upon the completion of the metering process, pending certification of the presumed capacity, the project design can be completed and the drawings issued for bidding purposes.
09/24/15 – Bert said to hold this on public bidding until the funding methodology is in place.
10/28/15 – Electrical capacity on feeders being metered for 30 days per the requirements of the NEC. 30 days compiling data will be complete on 10/30/15 – and ThermalTech will meet with meter installer to remove the meters on Friday 10/30/15. Final Design Meeting scheduled for 11/10/15 to discuss final design review and get bid package ready to send out.
12/07/15 – TEI issued complete document set to Bert Watts for review. Bert has reviewed, and indicated to the Commissary staff that the funds must be allocated by purchasing prior to issuance for bidding. Ready to issue for bid pending funding allocation.
12/08/15 – Project on hold until Kevin advises on funding.
01/26/16 – Project on hold until Kevin advises on funding.
02/23/16 – Project on hold until Kevin advises on funding.
03/29/16 – Project on hold until Kevin advises on funding.
04/27/16 – Project on hold until Kevin advises on funding.
05/25/16 – Project on hold until Kevin advises on funding.
06/27/16 – Project on hold until Kevin advises on funding.
07/27/16 – Project on hold until Kevin advises on funding.
08/23/16 – Project on hold until Kevin advises on funding.
09/28/16 – TEI and John Nester met with Sheriffs office (Kevin) and discussed a project for inmate video visitation, and the kiosk functions in this project could possibly be included in the Video Visitation equipment as well. Possibly looking to combine both projects into a single project.
10/25/16 – TEI issues SOSS to Facilities for study to work on kiosk/video visitation as a single project, pending approval.
01/25/17 – SOSS for study approved. TEI progressing with study – reviewed the capabilities of the Video Visitation systems, and communicating with Kevin Horn for capabilities of the original Kiosk systems to include in report.
02/22/17 – TEI finishing up the study and will issue to facilities for review by 03/01/17. Upon receipt of comments from facilities, will issue final report.
03/22/17 – TEI delivers report to BW – who presents to Sheriff’s personnel. Scope has increased and TEI to re-visit report and address additional scope items from Sheriff’s office.
04/26/17 – Work in progress. New review set anticipated to be to facilities by mid May. Facilities stated that this may get bumped if the SOSS for the matrix maint agreement is approved (that project and the matrix re-bid is higher priority).
05/22/17 – ThermalTech has revised the study to include the items from the initial feedback. TE and facilities requests a meeting with Sheriff’s office first week of June. Meeting pending feedback from Sheriffs office.
06/27/17 – ThermalTech receives signed SOSS and PO to develop the Video Visitation ITB specifications. ThermalTech developing the ITB and is estimating 4 weeks to have a review copy to sheriffs office and to facilities.
07/25/17 – TEI meets with Sheriff’s Office and Facilities. ITB pending funding being put into place. TEI will have all drawings and project manual ready for issuance by August 15. Once funding is in place – ITB # will be requested and project issued for bidding.
08/28/17 – TEI has bid package complete and ready for issuance for bids pending an ITB number and legal wrap dates, and will contact purchasing for the finalization of these pending items once facilities confirms that all funding is in place for the work.
09/26/17 – TEI has bid package complete and ready for issuance for bids pending an ITB number and legal wrap dates, and will contact purchasing for the finalization of these pending items once facilities confirms that all funding is in place for the work. TEI email PDF copies to JN to forward to Kevin Horn at Sheriff’s office.
10/25/17 – Project has been issued for bidding. Pre-bid meeting scheduled for October 27 at 10:00 at the project site. Bids due to purchasing on November 9 at 11:00 AM. ITB # 050-17
11/29/17 – Bids received and opened on 11/09/17. DK was lowest qualified bid, and contracts have been drafted and sent to prosecutors office for approval. Upon receipt of approved contracts and PO – pre-construction meeting will be scheduled with DK.
01/22/18 – BOCC approved DK contract on 01/17/18, and a pre-construction meeting was scheduled with the team and DK for 01/30/18. This project to run concurrently with the JC Matrix project.
02/20/18 – DK has mobilized to site and project is under construction. Construction progress meetings occur simultaneously with the Matrix project. The 2″ conduits above the mezzanines have proven problematic, and DK to utilize square wireway mounted directly to deck. All cables in LC to utilize 4″ conduit into the top of the data rack.
03/27/18 – Construction is ongoing. 5th floor north tower complete. 4th floor, north tower complete by 03/29 EOD. DK stated that they are on schedule for timely completion of project.
04/25/18 – Construction is on going. North tower complete except for medical area. South tower 2nd and most of 3rd floors complete bu the end of the week.
05/30/18 – Construction is on going, near complete. Punchlist is scheduled for June 5, 2018 at 10:00 AM. Facilities, HCSO and TEI to complete punchlist.
06/27/18 – Construction complete. ThermalTech and HCSO conduct punchlist field visit, and ThermalTech delivers punchlist to team. DK to clarify quote for fiber switches.
07/25/18 – TE issues punchlist. There is a meeting after the July partner meeting at 1:00 PM to discuss a few remaining items on the punchlist, then a back check of the punchlist to be scheduled.
08/29/18 – ThermalTech, facilities and HCSO conduct punchlist back-check. There were a few open items remaining on the punchlist. DK to address and submit signed -off puchlist with closeout documents for the project.
09/26/18 – Close out of project pending the submission of close out documents from DK.
10/23/18 – Close out of project pending the submission of close out documents from DK.
11/28/18 – Close out of project pending the submission of close out documents from DK.
01/29/19 – Close out of project pending the submission of close out documents from DK.
02/26/19 – TEI finally receives the final closout documents from DK. TEI processing an will deliver to HamCo.
03/26/19 – TEI delivers close out documents to facilities department. Facilities requests updated pricing from DK for installation of phone upgrades to be completed as a potential CO to the project.
04/24/19 – HCFD requests possible CO pricing from DK for adding kiosks in the Reading Road and the Woodburn Avenue facilities, and the telephone pricing for all of the buildings. Pending funding availability.
05/29/19 – TEI authors CO for DK to route cables to kiosk locations, terminate cabling with RJ45 data crimp ends, and provide the holes as necessary per the request of the HCFD.
06/26/19 – CO pending the acceptance of the contract between Inmate phone system vendor and Hamilton County.
07/24/19 – CO pending the acceptance of the contract between Inmate phone system vendor and Hamilton County.
08/27/19 – CO pending the acceptance of the contract between Inmate phone system vendor and Hamilton County.
09/25/19 – CO pending the acceptance of the contract between Inmate phone system vendor and Hamilton County.
10/30/19 – Project pending execution of the contract between Inmate phone system vendor and Hamilton County.
12/11/19 – Project pending execution of the contract between Inmate phone system vendor and Hamilton County.
01/28/20 – Project pending execution of the contract between Inmate phone system vendor and Hamilton County.
02/26/20 – Project pending execution of the contract between Inmate phone system vendor and Hamilton County.
10/28/20 – Project ready to Archive.

JC – Commissary Kiosk Electric Read More »

JC – AHU Access Platform (N&S Gyms)

Partner Lead: THP

11/17/16 – Hamilton County requested SOSS.

01/09/17 – THP provided SOSS.

01/20/17 – Hamilton County approved SOSS.

02/22/17 – JC Platforms THP to meet with building operators in the afternoon for first design meeting.

03/10/17 – THP provided review drawings to the County.

04/19/17 – THP, Facilities staff, and Sheriff staff met to discuss final bid documents and construction/security requirements.

04/27/17 – Bid documents schedule to be published week of May 1st.

05/02/17 – Bid documents published.

05/08/17 – Prebid meeting occurred.

05/19/17 – No bid questions received for JC platforms.

05/22/17 – Addendum 01 for JC platforms (pre-bid mtg minutes only) issued.

05/25/17 – Bid opening schedule for June 1.

06/01/17 – JC bid opening. SSRG is low bidder at $66,170.00.

06/06/17 – THP recommends SSRG to county for JC platform job.

06/26/17 – JC Platforms waiting on SSRG to send in revised forms for contract completion with the county.

07/25/17 – J Nester requests additional contract information from SSRG. SSRG Answered yesterday. Waiting for county to finalize contract.

08/25/17 – SSRG to provide schedule. SSRG plans to visit the site to verify dimensions and complete beam scanning. The project team plans to have the pre-construction meeting with building personnel at time of visit.

09/21/17 – Pre-Construction Meeting onsite.

09/22/17 – Stamped set sent to SSRG for permit.

09/25/17 – Special inspections report sent to SSRG for permitting.

09/28/17 – Terracon scheduled (by SSRG) to scan beams for tendons.

09/26/17 – Steel shop drawings submitted. THP in coordination with fabricator.

10/18/17 – Permit drawing changes sent to HGC. Waiting on news of permit status

10/19/17 – Second round of steel shop drawings submitted and comments returned.

10/20/17 – THP Discussed shop drawings with HGC. Attempted to reach Neiheisel on behalf of HGC. No answer.

11/22/17 – HGC completed installation of frames and demobilized. THP visit the site and published field report.

11/29/17 – THP plans to review final installation with HGC.

JC – AHU Access Platform (N&S Gyms) Read More »

JC – 3rd Floor Handwashing Sink

12/29/16 – TTC sent options into County on this sink, location and plumbing. We are awaiting additional direction from owner.
01/26/17 – Bert said that estimate was sent to Kevin Horn for approval on this job to become a project. This could get started next month.
03/09/17 – No updates, on hold for now.
04//26/16 – No updates to project.
06/19/17 – SOSS approved and TEI to meeting with County on kicking off this project.
07/24/17- Drawings are issued for Review tomorrow. TEI requested Permit cost form QCM.
08/30/17 – QCM has submitted permit drawings for the sink. We are awaiting the permit # to share with the County.
09/25/17 – ThermalTech has picked up permit drawings and permit and sent to John Nester for owner use. A hard copy set of dwgs was delivered to the owner last week with equipment selections. TEI stands ready to assist as needed during construction.
10/24/17 – Permit is issued and work should be underway. TEI stated that HCDF can purchase an equal sink from a local vendor for this work and that should be fine.
11/28/17 – County has started the project. DK has been contacted for coredrilling.
11/30/17 – Work has begun on this work and the pilot holes have been drilled.
02/22/18 – Project complete and ready to archive.

JC – 3rd Floor Handwashing Sink Read More »

JC – 3rd Floor Recovery Unit Study

07/25/17 – GBBN meets with Facilities, and the Sheriff’s Department, to discuss scope and walk through spaces to be considered for this project. The 3rd Floor North, 3rd Floor South and the Courthouse 7th Floor East are to be considered as potential locations for the Recovery Unit in the Study.
08/11/17 – THP issued SOSS for structural and building envelope support services for review of new windows in recovery unit study.
08/12/17 – GBBN authors and delivers SOSS to Facilities.
08/28/17 – Approved SOSS delivered to GBBN.
09/22/17 – GBBN and Facilities meet with Sheriff’s Department to discuss Study in greater detail. GBBN issues Meeting Meetings and sends to Facilities. Facilities confirms accuracy of Meeting Minutes and approves them for circulation to TEI. THP contacts GBBN to confirm THP was original structural engineer for the JCC project and has original drawing set.
09/25/17 – GBBN send meeting notes and follow up plumbing and HVAC design inquiries to ThermalTech.
09/25/17 – THP communicates knowledge of existing building structure and floor slab construction to GBBN. GBBN circulates structural and proposed restroom block concept design to TEI.
09/25/17 – GBBN sent and email to THP concerning JCC structural conditions and possible modifications requested by the County. THP responded the same day.

10/19/17 – GBBN finishes Architectural estimating input into Archibus Project Request module.

10/26/17 – GBBN and Facilities to meet with Sheriff’s Committee to review plan layout options.

10/31/17 – GBBN attends walk-through meeting with Sheriff’s Committee. Existing spaces in JCC Third Floor and Courthouse JAX spaces on 6th floor are reviewed and photographed.

11/10/17 – Archibus Project Requests input is completed by TEI and GBBN for both options.

JC – 3rd Floor Recovery Unit Study Read More »

CH – 7th Floor Core and Shell Study

07/17/17 – Kick off Meeting with GBBN and Facilities to walk the space and adjacent areas.
07/19/17 – Facilities confirms extending an elevator to this level would be required as part of the scope.
07/27/17 – Scope of work for this is to just do the study and construction estimate. Include utilities, elevator, windows, core and shell upgrades. Can an elevator be installed that just goes between 6 and 7 – is that cheaper. SOSS requested in less than two weeks, provide scope, cost, investigation, code review and and quick SD type design.
08/08/17 – GBBN meets with Tim Davis of Aluminum Resources to discuss window replacements and possible criminal justice type window replacements.
08/11/17 – THP issued SOSS for structural support services for renovation study.
08/12/17 – GBBN authors and delivers SOSS to Facilities.
06/27/19 – Ok to archive.

CH – 7th Floor Core and Shell Study Read More »

CH – Server Room Consolidation

06/25/17 – Hamilton County requested SOSS for a consolidated server room on the second floor of the Courthouse.
06/30/17 – THP – TEI notified THP will be needed for a new Courthouse server room.
07/27/17 – Team going to meet and discuss revised scope in the next couple of weeks for brainstorming kickoff meeting.
08/31/17 – Partners meeting to kickoff scope and design meeting for this project at Courthouse.
08/31/17 – THP – Hamilton County defined server room requirements for SOSS.
09/14/17 – THP met with Terracon to assist with SOSS.
09/18/17 – GBBN begins field verification and Project Request Estimate research.
09/20/17 – GBBN researches Abatement Report from Pinnacle Engineering related to this project and distributes information to Design Team.
09/20/17 – THP published proposal to TEI and provided Terracon proposal.
09/22/17 – GBBN completes base electronic drawing file composition to verify scope and extent of work.
09/22/17 – THP published updated proposal to TEI.
09/25/17 – ThermalTech mailed a full copy of the revised SOSS for Schematic and Budget estimates to Facilities this week.
10/24/17 – SOSS still in approval stages. Team regular discusses status of project and we are working on verifying existing background data for this space. ThermalTech has briefly discussed the QC process internally and have assigned two owners and department heads to review the project given its high visibility.
11/28/17 – We held our first SD design meeting today with the client. New worksheet and equipment request need to be sent out for work and the preliminary project schedule created with the partners for this project. GBBN sent out proposed office layout for 263. If asked we are hoping to use only two parking spots only.
01/20/18 – Terracon and ThermalTech were on site for the first round of soil boring test and underground detective. Underground locations went fine and were marked by the company. A follow up report and drawing is forthcoming. Data found matched up with the drawing provided by the owner. However existing condensing units were too close to one of the AC units so it was relocated. The drill team had concerns about snow hanging off ledge above and with the weather so the drilling was postponed to February 24.
02/22/18 – ThermalTech release the first meeting notes from the design meeting along with progress to date on the schedule. Terracon will be back on Saturday to drill the soil bore test pit. We are also are going to need two test pits to determine the construction and shape of the footers around the courtyard for the design of the future platform. Terry scheduled to meet Kirby after partner meeting on Thursday.
02/24/18 – THP: Terracon rescheduled for test boring. Only 1 boring will be done due to small site and existing equipment. (2) Boring were not required, but cost was minimal for backup boring. Terracon to schedule (2) test pits to gather soil conditions information.
02/26/18 – Underground utility report release to the project team by Terracon. TEI forward to owner.-
03/06/18 – Test bore results are release to the project team. TEI sent to owner and THP.
03/16/18 – Revised SOSS for additional services for GBBN and Terracon sent to County for approval.
03/24/18 – TEI to meet with GBBN on new room configuration next week.
03/28/18 – THP: County has approved Terracon to do test pits. THP on hold waiting on soil/existing condition information to design foundation and platform. Column location will be determined partially by foundation system.
03/29/18 – THP waiting on the test pits to start design. Team discussed location of Egen on this project and TEI to adjust the schedule for new design issues.
04/21/18 – TEI, THP and Terracon on site for two test pits. Pits were dug and completed on Saturday. Updates and photos sent to County on Monday. GBBN updated the site plan with the footers found on site. ThermalTech started working on new site plans and will have a conference call setup for the partners to discuss or findings and platform designs.
04/23/18 – THP – Terracon completed test pits in the Courtyard. Footing depths of the west and south walls were discovered to be at different levels. TEI started working on new site plans.
04/25/18 – Archibus number was enabled for editing again by the partner team. ThermalTech sent existing cost and sketches to everyone prior to editing.
04/26/18 – Bert said to get the worksheet for loads updated first and then TEI to select a week to meet with CAGIS and update new inventories. TEI needs to show some hard copy progress for Bert to review. THP, GBBN, and TEI to work with Terracon for platform design.
05/17/18 – TEI contacts CMSnet to discuss data rack sizes and loading.
05/18/18 – TEI and THP discuss and share design concepts on the platform for this project. TTC and SJ send column locations to Ken for discussion. I believe we are leaning towards spread footers on this project.
05/25/18 – TTC creates Option #2 layout for incorporating the JC data center servers into the Courthouse and stumbles on what may be a better location for the CH Data Room with or without the additional servers. TEI discussed benefits with GBBN on new location.
05/29/18 – Relocating the JC Sheriff data center to the CH was explored by TEI and an email summary sent to BW for use on the JC Recovery Four Pod scenario. TEI completes estimate for relocation and sends to Facilities at $184,000 to relocate 7 racks to CH Server Room build-out. CRAC units change in size to 50 tons each and require four condensing units instead of two, UPS, generator and the platform all must get larger.
06/25/18 – TEI has developed two platform designs for 30T and 40T condensing units. We have laid out all the servers in the new racks giving at least one rack to each department, this will need to be coordinated with departments. We have contacted CMS to see the server rooms with the technicians and confirm the CMSnet racks on Wednesday at 9am. Terracon final soils report is forthcoming.
06/29/18 – THP – Terracon published soils report.
07/26/18 – THP and ThermalTech working through design development issues of platforms. In the past month TTE has collected server information from CMSnet and contacted all other departments for final server loads. A preliminary layout was completed after the CMSnet survey and found that 21 Racks are sufficient for the new design. Facilities has reached out to other County departments for additional tenants that may want to be move over prior to the final cooling and electric load worksheets are complete. Sizing for the cooling units leaning towards 30 ton units. Fuel oil routing SD drawing, Admin 9th Floor and Roof SD drawings being drafted by TTE for Archibus update. We will update the original #1827 project number. TTE meeting with JII fire today for an updated vendor quote on the Fire Suppression work on Admin 9th floor at 11:30am. A lot of work going into wrapping up the SD design and cost estimate phase currently.
08/03/18 – GBBN confirms CAB-9th Floor Computer Room Abatement (ACM) scope with Pinnacle Engineering.
08/07/15 – Facilities answers final SD questions on scope to design team.
08/09/18 – Design Team wraps up Schematic Design Phase with updates to Archibus Project Request Estimate.
8/15/18 – Facilities confirms the displacement of the four workstations and blade walls in the east CMS area off the entry. GBBN makes the corrections to base drawings and distributes to TEI.
08/23/18 – Bert met with CMSnet and Department Heads at monthly meeting and reviewed the SD plan with the latest information.
08/29/18 – Met with CMSnet twice this month and updated drawings and final calculations. Only a couple of department still remain for verification. We will attend next PM meeting with CMSnet for presentation.
09/20/18 – The basic revised estimating is complete minus coordination on some of the final bidding number and cost for new scope items. Comments from CMS and Owner welcomed for final adjustments. One thing TTC noticed was that the design fees on the new estimate can be reduced to TEI. ThermalTech request additional funds to completed next phases of project including Construction Design Documents and Bidding. TEI collecting SOSS’s for next phase from partners for submission.
10/15/18 – ThermalTech has submitted the Construction Design and Bidding SOSS for all partners for the next phase of this project.
10/22/18 – Bert sent an updated Probate court inventory worksheet for ThermalTech to use. TTC to incorporate next week.
11/28/18 – TEI, THP and GBBN met at GBBN offices and reviewed the SD phase scope, cost estimate and schedule. We finalized the scope and schedule between the partners, assigned drawing responsibilities, and requested a setup meeting with Bert to discuss details on the structure. We will put some preliminary dwgs together and meet on Dec 11 at 9am.
12/20/18 – TEI, THP and GBBN hold design team meeting to discuss scheduling and deliverables.
12/28/18 – TEI and GBBN perform above ceiling MEP field verification. Photos taken.
01/10/19 – GBBN sent updated floor plan for the server room and Room 263 today for ThermalTech to use in design. ThermalTech is marking up new plans for design with latest changes.
1/11/19- GBBN meets with door hardware consultant to discuss door hardware and specifications for this project.
01/22/19 – TEI has setup all new drawings for hvac, elec, plumbing and fire to the new floor plans and started designing in earnest to the new designs. THP turned in four drawings for the new drawing package and will try to have draft dwgs ready later next week. GBBN has the floor plan complete and is updating the Life Safety drawing for our use on this project. TTC contacted the city about the use of water in this space and requested a face to face meeting. We will advise what we find.
01/31/19 – TEI to setup fiber meeting with telecom, cms, and facilities for new fiber connection with CBS.
02/25/19 – GBBN visits Rooom #263 with Facilities to review and measure ceilign and bulkhead heights. Existing ceiling and new SAT ceilings scope coordinated iwth TEI and Facilities.
02/28/19 – TEI/THP and GBBN to meet for coordination review of each firm’s drawings. Electronic drawing files sent to TEI in advance.
02/28/19 – Bert and Terry met with CMSnet and Dept Heads and presented a 75% complete working set of review drawings for the group. We discussed scheduled and Const on the project and they city specifically inquired about the crossover fiber between the Admin and CH to which TEI answered that we will be working on putting in a parallel redundant fiber to make sure that connections stays live.
03/07/19 – Design Meeting held. TEI produces Agenda and proposed Project Schedule.
03/15/19 – GBBN sends drawing updates to TEI for Owner Review.
03/22/19 – TEI sends list of changes required to documents and requests input on Construction Sequencing.
03/27/19 – TEI and Bert met with the Steering Committee to review the current drawings, scope, phasing, cost, and schedule for the project. Drawing were issued for review along with the schedule. We are shooting for bidding in end of April.
03/29/19 – TEI sends email with additional requested changes to design and documents. Construction material delivery logistics are discussed.
04/01/19 – TEI sends requiest for Server Room duct opening patching scope.
04/09/19 – TEI sends documentation discussing pros and cons of changing sizes of the Liebert Units to be used on the project.
04/15/19 – GBBN recieves Door Hardware Consultant Hardware Set documentation from vendor.
04/17/19 – Meeting with Telecomm, TEI send meeting notes out for review.
04/23/19 – TEI indicates all three existing window openings, in the Server Room permiter, are to be infilled iwth new louvers for consistency. Future Liebert Unit replacement will not be done through the existing window openings. GBBN revised background drawings accordningly and relocates new double door relative to resized Liebert Units and locations.
04/25/19 – Four Liebert configuration has been incorporated into the floor plans, the doors have been shifted to accommodate the additional CRAC unit, THP provided revised platform drawings with new ladder layout and hinged cover information (TEI reviewing now), THP finalizing load study with four units (TEI provided new weights with only refrigerant). We need to set final scheduled for review drawings and bidding with the County.
05/27/19 – Telcomm meetings have been held, we are working on final details for the project design. final answers and comments due back from County on June 10 with the intent of bidding this project late June or early July.
06/27/19 – Final design is almost complete. We are planning on issuing final design review drawings end of day on 6/28. TTC revised the schedule to distribute at the Steering Committee meeting on 6/27 with new completion date of April 2021. Cost estimate is partially updated with the hopes of completing updating by end of day Friday. Project should be bid in July and August 2019.
07/25/19 – Final design is complete. ThermalTech dropping off a revised set of final review documents today at the Partner meeting including all specifications for the project. Pricing effort, review and update underway to find a cost that matches the scope and is within budget. We are trying to bid this project as soon as possible.
08/15/19 – GBBN sends SOSS data, for Construction Administration services, to TEI for inclusion into the SOSS, to be submitted to Facilities.
08/16/19 – GBBN receives email from TEI concerning new listing of Alternate Bids for documentation on Construction Documents. GBBN updates CD’s to reflect CAB 9th Floor Computer Room scope of work, to now be listed as Alternate Bid G-1.
08/28/19 – The budget and dates have been finalized with Facilities and Purchasing. We will have this project ready for bidding by 9/4 with the revised budget. The Admin building has been moved to an Alternate and TEI renumbered the Alternates and combined a few of them to make the project easier to understand and bid for the vendors. Final drawings and specifications are being reviewed and prepared for the Issued for Bid data listed above. All partners have agreed to the date of Issuance for this project.
09/20/19 – The prebid meeting was held and well attended by GC, MC, EC and FPC alike. TTE will prepare Addendum #1 and issue from the prebid meeting discussions.
09/25/19 – Addendum 1 Issued.
10/03/19 – Addendum 2 Issued.
10/17/19 – Addendum 3 Issued.
10/23/19 – Addendum 4 Issued.
10/24/19 – GBBN creates Addenda #5 revised scale drawing for issuance.
10/25/19 – Addendum 5 Issued.
10/28/19 – Addendum 6 Issued.
10/30/19 – County Issues Addendum 7 and extends the Bid Opening to November 12, 2019. ThermalTech working on additional items for concrete, hot aisle design, plumbing drain pan submitted by contractors.
12/11/19 – The bids have been opened last month and we received three qualified bids. ThermalTech has met with the apparent low bidder, Graybach, and found them to be responsive to the bid. The recommendation for approval was emailed to Bert and the County has started preparing the contracts and moving forward with the project. TTC and BW have a meeting scheduled with the Steering Committee later today for an update.
12/12/19 – Prosecutor has approved the contract for this job and it has been sent to Graybach for approval.
01/24/20 – Graybach contract has been approved by the BOCC, PO was received by Facilities. BW emailed TTC to release the bidders on the submittal process. Paperwork is forthcoming.
01/27/20 – ThermalTech contacted Graybach with approval information and asked them to start the submittals, Schedule of Values and Project Schedule for this job. We would also like to setup the Pre-Const meeting with the Contractors. TTC Create Project Team distribution group and additional people have been invited to Procore site for management of this job.
02/18/20 – GBBN returns approved submittals for Doors, Frames and Door Hardware.
02/20/20 – TTC and BW met with CMSNet project managers and provided a project updated stating that construction should begin in late March or early April on this project.
02/24/20 – Three submittals have been sent to the design so far. 1) Structural was rejected due to a Missouri not Ohio stamp, 2) Doors and Hardware was reviewed by GBBN, TTC to forward back to Graybach, and 3) HVAC submittals #1, TTE reviewed and will send back to Graybach on 2/22 of their use. Geiler used Liebert for this project which is the basis of design.
03/04/20 – TEI distributes update on Project Progress status.
03/11/20 – GBBN receives a copy of the Plan Review Response letter with indications of scope for each design team.
03/24/20 – Submittals and Permitting are working their way through the process. The County shared some data about access to the site and the building for the contractor that may impeded access to the building for the original start time. Graybach asked about background check progress which was provided yesterday to Graybach. We are working on new details for the Kohler generator submitted by DK and this week we have confirmed the generator is smaller, the same weight and almost the same size belly tank. We have a meeting tomorrow with Graybach and DK to discuss final details before we review the submittal again.
04/30/20 – Background checks not complete yet, County checking on LEADS checks during Covid. ThermalTech received Hot Aisle Containment, Lighting and Generator this month. We are waiting on resubmittals for the structural steel and gratings for the clarifications we provided last month to the vnedors for updating the submittals. We are waiting on the final schedule and Schedule of VAlues for this job for approvals. Graybach submitted a not cost not time extension change order noting the delays at the beginning of this work so far due to Covid.
05/25/20 – ThermalTech and GBBN finalizing permit response drawings and remarks for 5/29/20. Graybach working on project schedule based on background check protocols. County working on LEAD background check procedures. Hot aisle containment submittal retuned Furnish As Corrected, Lighting submittal returned Revise & Resubmit, Structural submittals are waiting on resubmittal, and Generator re-submittal returned as Approved as Noted.
06/17/20 – The Permit Response letter and drawings has been submitted to the city for consideration and approval. This was a large package that required a 100% digital submission for the city this year.
06/24/20 – Lighting submittals were updated twice and returned to DK in their final approved form on 6/19. Structural submittals are awaiting stamp updates before THP takes another crack at that and TEI owes JCI a return on the Clean Agent Fire Suppression submittal. The SOV has been sent to the County for approval. Background checks were revisited and potentially could be 8 weeks out for approvals. Graybach is working on the revised schedule for an Aug 1, 2020 start date.
07/23/20 – Clean Agent submittals have been reviewed and returned to JCI. We also inquired about the wet sprinkler system submittals which were not included. JCI said they have to get another guy in the company to finish them but they are underway. TTE checked on coordination drawings status and permit status from the Partners.
07/29/20 – GBBN and THP have resubmitted permit responses to ThermalTech today. TTE will get the new upload link for the city and complete the resubmission process. Graybach wondering about background check status and updates.
08/19/20 – City contacted TTC with news the permit is approved and some special instructions on the door hardware set control that has to be installed. TTC followed up with Barth and Johnson on that requirement and I think what we have will be fine. Rycca and Bert shared additional background checks information with Graybach and inquired about getting the safety plan in place too.
08/20/20 – Permit is Approved (1000 MAIN – 2020P01574). There is a balance left on the permit that we forwarded to Graybach so they have the information to get the permit in place when the project restarts. We checked on the status of the SOV, Project Schedule, Wet Sprinkler submittal Drawings, Coordination Drawings, and first Payapp with Graybach.
08/26/20 – Graybach asked for SOV comments for this project. After checking old emails it was found that Graybach requested that TEI collect all the SOV comments and submit them in one block. TTE to follow up on today. County provided SOV updates immediately. TTC will get them out to Graybach today.
09/18/20 – This month the FPC came down for fieldwork in the space. New Clean Agent drawings were resubmitted for approval and FPC RFI was sent in on atrium ceiling access.
10/28/20 – This month the LEADS checks go one step closer to being ready. Rycca reached out and started coordinating background checks with Graybach. The wet fire sprinkler submittals arrived for review yesterday. TTC updates Spencer and Ken on CH Server Room progress.
12/10/20 – TTC reached out to Graybach at the end of November to follow up on Structural submittals for this project as we have not heard anything new. DK has UPS equipment in town for this job. TEI instructed them to work billing through Graybach if funds are needed to be paid. Graybach working on background checks and a revised project schedule for Jan 2021 start times. County says a large number of LEAD checks are approved, we must be started by Feb 1, 2021.
12/30/20 – TTC reached out to Graybach for updated schedule, final submittals and Pre Const #2 schedule.
12/31/20 – Archive the Design and Bidding, move January 2021 to Courthouse Server Room Construction.

CH – Server Room Consolidation Read More »

COURTHOUSE Roof Y and Z Leak Investigation

Partner Lead: THP


05/05/17 – Hamilton County requested SOSS to investigate roof leaks on the Y and Z roofs along the west elevation.

05/25/17 – THP developing SOSS.

06/08/17 – THP issued SOSS for review.

06/26/17 – County approved SOSS.

07/27/17 – THP plans to schedule work second week of August.

08/25/17 – THP visited site to do visual survey of roofs Y & Z, and interior of 6t and 7th floor spaces below roofs.

08/25/17 – THP visited site to do visual survey of roofs Y & Z, and interior of 6th and 7th floor spaces below roofs.

09/28/17 – Based on weather forecast, THP planning on conducting thermal scans October 3rd.

10/03/17 – THP documented roofs Y & Z using infrared camera.

10/06/17 – THP met Underground Detective to inspect all drains at roofs Y & Z.

10/25/17 – Roof cuts scheduled, weather permitting.

10/26/17 – THP visited site to perform investigative roof cuts.

11/28/17 – THP finalized draft of report summarizing findings and recommendations.

COURTHOUSE Roof Y and Z Leak Investigation Read More »

CH – Law Library Renovation

05/15/17 – Hamilton County Facilities informs GBBN of pending approval for project. Facilities requests SOSS.
05/16/17 – GBBN contacts consultants about project and clarifies scope of work included.
05/19/17 – GBBN contacts former Law Librarian to discuss intents in 2016 verses any changes due to change in Librarian.
05/22/17 – GBBN performs site visitation and discussions with Lauren Morrison, new Librarian.
05/24/17 – GBBN and TEI visit site, Facilities to discuss existing drawings, and the Mechanical Space to the north of the existing Stack Area.
06/28/17 – GBBN, IPM, TEI and Facilities hold kick-off Meeting with Law Librarian for Kick-off Meeting.
07/05/17 – GBBN holds in-house discussion to finalize scope and design issues such as Alternate Bids.
07/19/17 – ThermalTech discussed scope change on project with GBBN. More work and revised SOSS required.
08/07/17 – Meeting with Facilities and Law Librarian to discuss additional scope. GBBN asked to author additional SOSS with separate F-number.
08/14/17 – GBBN authors SOSS, for extended scope, and delivers to Facilities.
08/21/17 – GBBN met with Paul Hauser, Facilities Trades to discuss plaster repair scope and material recommendations.
08/29/17 – GBBN sends background drawings and Title Block to TEI.
08/30/17 – GBBN and TEI met regarding MEP coordination issues. Money approved for this project yesterday.
08/31/17 – Discussed scope on project. BW said to include two RR for upgrade (could be alternate), access ramp, move computer door, update break room, expand conference room, update browsing area, investigate covered windows (check on this ), potentially add speaker and microphone if room is enlarged, up to TEI to choose VAV height for this unit.
09/12/17 – GBBN receives approved SOSS for extended scope of services.
09/15/17 – GBBN has internal meeting to discuss full scope now that second SOSS for extended services has been approved.
09/21/17 – GBBN forwards lighting cutsheets and specifications for proposed lighting fixture selections to TEI.
09/25/17 – ThermalTech HVAC schedule for internal review tomorrow on this project. The basic load calcs are complete. TTC to follow up on plumbing and fire protection design.
10/17/17 – GBBN and Facilities meet with Law Librarian for Design Progress Meeting. Final Sketch-Up model forwarded to Librarian for her use in presenting to the Board, and ThermalTech for use in coordination. New window units for the State of Ohio Room will be designated as an Alternate Bid.
10/27/17 – Law Librarian forwarded information concerning the microfiche cabinet size and numbers.
11/09/17 – GBBN internal coordination meeting. Microfiche locations coordinated and power/data routing proposed to TEI.
11/10/17 – GBBN and TEI meet with Leesman Lighting to discuss light fixture selections and specifications.
11/16/17 – Law Library Design Review Meeting at Courthouse. Microfiche layouts coordinated.
11/30/17 – Final Review set due Dec 14 with Owner and Tenant.
03/14/18 – Prebid meeting held for this project at the Courthouse. It was well attended.
03/24/18 – Addendums 1-3 issued for this project. TEI relocated the Ohio Room diffusers for a cleaner install and verified the two ladder locations will work for this job.
03/28/18 – Bid Opening held at CAB, Room #507.  Bids received were in excess of the 10% above Published Estimate and therefore rejected as mandated by Ohio Revised Code.  Facilities to consider next step for reissuing for bidding.

04/25/18 – ThermalTech has started modifying the existing drawings for the new value engineered bid documents.

CH – Law Library Renovation Read More »

CH – Fire Alarm System Upgrade

06/27/17 – Hamilton County requested SOSS for a complete new fire alarm system in the entire building.
07/25/17 – TEI authors SOSS and submits to HamCo for approval. Project pending SOSS approval and PO.
08/28/17 – Project pending SOSS approval and PO. BOCC will vote on this 9/13
09/26/17 – BOCC approves project at 09/13/17 meeting. TE authors memo to BW addressing the accessibility to the building for the existing system audit. Kickoff and field work to be scheduled upon receipt of signed SOSS and PO.
10/25/17 – TEI conducts kickoff meeting with facilities. TEI has been working on the initial field verification of all of the existing fire alarm system devices. Estimating that the field documentation will be complete approximately the end of the first week of November. TEI holds meeting with Fire Marshall to discuss building issues (construction techniques, historical significance, evacuation protocol, etc.) and distributes the meeting minutes to the team.
11/29/17 – TEI concludes field investigation/Audit of existing system. TEI Working on SD package of new design of system and will distribute SD plans to facilities upon completion for review.
01/22/18 – TEI has 90% design review meeting with HamCo (facilities, Building ops and bldg mgr). Final project schedules discussed.
02/20/18 – ThermalTech delivers 100% review drawing and project manual to Bert Watts for review. ThermalTech evaluating the cost estimate for the project and upon receipt of review comments from Bert Watts – project will be issued for bids.
03/27/18 – ThermalTech to deliver to Purchasing by 03/30/18 project ITB information to be available for bidding to the contractors on 4/3/18. Bids due 5/10/18. Prebid Meeting on 4/19/18.
04/25/18 – Prebid meeting occurred on 4/19. Addendum #1 has been issued with meeting minutes and questions submitted. Bid opening scheduled for 05/10.
05/30/18 – Bids opened and were on budget and award-able. DK apparent low bid. TEI authors contracts and sends to BW for review and approval. TEI sends BW final contracts to forward to prosecutors office for approval.
06/27/18 – Project kickoff pending receipt of contacts and BOCC approval.
07/25/18 – Project kickoff pending receipt of contacts and BOCC approval.
08/29/18 – BOCC approves DK contract – and HamCo Facilities delivers approved contract to DK. DK is developing submittal drawing currently, and will we will be scheduling a pre-construction meeting in the upcoming weeks once submittal drawing have been reviewed and approved.
09/26/18 – Construction kick-off pending receipt of fire alarm submittals.
10/23/18 – Pre-construction meeting was held on 10/19/18. DK mobilization date for project was 10/22/18. JCI/Simplex finalizing submittals – picking up ThermalTech review comments.
11/28/18 – DK has mobilized on the project and began construction. One booster panel was relocated to the lower level from first floor area A. Working on completing the backbone in the building prior to getting into court spaces. Also working on removing the fire fighter phones from the existing spaces for the general contractor to keep busy. DK to provide a 2-week look ahead of when they will be getting to court spaces.
01/29/19 – DK continuing the progress, nearing completion of the installation of devices in the basement and sub-basement floors of the CH. DK anticipates 2-3 weeks and the basement will be completed. Waiting on submittals for the BDA.
02/26/19 – Work continues in process. New system Backbone is installed throughout the building. Sub Basement, Basement, 7th floor work complete. Working on the 6th floor now and will be complete on 6 in the next week or two. Moving to the 5th floor next. DK submits RFI for the BDA replacement – TEI to get Daryl Meadows interpretation on BDA upon his return to the office after 2/27/19.
03/26/19 – Work continues on project. There have been construction issues that are being worked out with the contractor. DK to provide pricing for code changed requirements for the BDA (Code changed between issuance for bids and issuance for permits) and the BDA now requires battery backup. DK also to provide pricing for devices found above the holding cells on 6th floor.
04/24/19 – Work is continuing on project. Areas complete are sub-basement, basement, seven, six and most of five. DK working on 4th floor currently. DK is starting to become concerned with schedule, since it took the FA sub-contractor over 4 months to turn in the project submittals. DK scheduling inspections of the 5th, 6th and 7th floors (tentatively May 8 after 4:30 PM). These floors are now on the Simplex system in the building. Elevators will be last things converted (all floors) since they are on all floors and circuits are run vertically in building.
05/29/19 – The building department and the fire department have inspected the SD, and the speaker strobes on 5, 6, and 7. They were pleased and instructed to keep proceeding with the plans that were submitted, as the system was designed. Work continues and DK is working on the 3rd floor and 2nd floor at this time.
06/26/19 – The work continues to proceed on the project. Anticipate that the 2nd floor will be complete and turned over by July 1. DK anticipating contacting the building department as requesting the next inspection for floors 1, 2, 3 and 4 during the week of July 15th. BDA submittal received by TEI and returned to DK to complete the submittal. TEI waiting on re-submission.
07/24/19 – Inspections conducted on 07/18/19 for floors 1, 2, 3 and 4. The Inspections were successful and the SD and AV devices were approved and accepted. DK finalizing work on first floor and working in the basement. DK receives PO from Triton to include the devices in the Law Library so the entire building is included under the one warranty on the project. DK waiting on JCI/Simplex for shop drawings for the Law Library and then that work will be completed asap.
08/27/19 – All devices for the law library are roughed in. Triton to communicate with DK when to device out (post painting). Basemen devices complete for the most part. Corners, elevators and air handlers are now being worked on.
09/25/19 – Basement and Law Library Inspection occurred on 09/25/19. ThermalTech completes punchlist #1 and issues to all parties. East elevator lobbys (all floors) still incomplete. There are several areas where the work is incomplete, and TEI will be returning for a punch list follow up visit.
10/30/19 – construction meeting was held on 09/24/19. There are elevator issues that were communicated to HCFD that must be addressed prior to final elevator inspection (the elevators are not functioning properly and will not recall – will not pass inspections). Additionally, there is coordination with the energy management system (for the AHU’s) for a pre-test and final test, such that they are all left running for both the pretest and the final test (since the testing occurs off hours). The door release is pending a project by Risk Management that is replacing the access control system. TEI to schedule final punchlist. Other than a few items, and the final inspections, the project is substantially complete.
12/11/19 – Project is nearly complete. There are operational issues with 3 of the elevators, a few AHUs, and a couple tamper flows that must be repaired before DK can call for the final inspection with the building department and fire department. A list of items was sent to design team and HCFD is working on the repairs and will notify when the work is complete. Final inspections will then be scheduled.
12/12/19 – County updated us on current operation and issues for the project closeout including fire pump controller, elevator interface and AHU interface in this building.
01/28/20 – HamCo, TEI and DK meet on 01/28/20 to discuss outstanding repairs and schedule for repairs and project completion (final inspection).
02/26/20 – Upon notification from HCFD that all elevator, tamper switch, and AHU repairs are completed, DK will schedule final inspection with City and FD.
03/26/20 – On 03/25/20 – DK and TEI receive notification that all of the repairs are complete, TEI asks DK to schedule pre-testing and completion of project, and then final inspection.
06/23/20 – DK scheduled final inspection. The day prior to the final inspection, DK conducted a pre-test, and several item repairs were still incomplete. Final inspection still pending repairs. City of Cincinnati want to close out the permit, needs final to happen.
07/29/20 – TEI, DK and JCI Simplex conduct final testing with the building department and the fire department. Everything passes inspection. JCI Simplex had submitted the engineering change for the active shooter message to the building department. Upon approval of the engineering change – building inspector needs to come back 1 final time for a brief demonstration that it works as indicated, and the project will have final approval.
08/21/20 – Project final inspections complete and approved. Project closeout pending change order message and connection to the BMS. DK has been emailed multiple times for schedule to complete these tasks, TEI has not received responses to the email inquiries.
09/23/20 – TEI meets with Honeywell, DK, JCI/Simplex and HCFD and Tim Schuh to get all data for the implementation of the safe-link card (tie the FA system into the BAS system). TEI sent floor plans to Honeywell and all parties confirmed that they have everything that they need to complete the implementation of the system.
12/09/20 – DK scheduled to be on site on 12/09/20 to provide building personnel with required training on the system. Honeywell and JCI Simplex scheduled to be on site on 12/10/20 to make final connections of the safelink card, at which point all on site work to be complete. Upon receipt, review and approval of close out documents, this project will then be complete.
01/28/21 – Working on closeout on final project. MCB to review final integration.

02/23/21 – TEI working with Matt Butz to obtain all final lien wavers, PW docs etc, to finalize closeout documentation.

03/24/21 – All final documents sent to HCFD. Project complete.

CH – Fire Alarm System Upgrade Read More »

CH – AHU-51, 53, 54 Replacement

01/25/17 – TEI submits SOSS for project. Project pending SOSS approval and PO.
11/17/16 – Hamilton County requested SOSS.
02/16/17 – TEI, Facilities and Building Manager meet on site to kick off project.
02/22/17 – Trane has provided first cut sheet on modular unit for this job, we are trying to fit it into different locations, we are going with a 20 ton unit.
03/01/07 – ThermalTech sent preliminary equipment locations to the County and requested fieldwork to follow up on schematic design. We could potentially have a design meeting at this point and solidify where the unit will be installed.
03/09/17 – ThermalTech updated the floor plans after another field trip down to the site and proposed a final location of one 20-ton unit on the 6th floor with locations for new ductwork and a new wall to enclose the new unit. The county to follow up with Sheriff about using this space for a new unit. TTE moving forward with schedules and Trace runs.
03/15/17 – Revised cost estimates sent to Bert. We are still overbudget but not as badly after electrical modified their cost. We are waiting on revised data from GBBN and THP prior to making additional changes to the estimate. We can make the 6th floor unit work but now its a capital investment issue. Load calcs are complete and we can serve these spaces with a 20 ton, 10,000 cfm unit and we believe we can fit all the adjoining ductwork together to make that happen, the unit would go on the 6th floor.
03/17/17 – TEI contacts GBBN and THP, requesting Architectural and Structural respectively, assistance on this project and included the 5th and 6th floor proposed work drawings for reference.
03/20/17 -50% design dwgs were sent for review to Bert, Tony and Andy. The construction estimate is a little higher than the 192,000 originally budgeted. We are currently trying to finalize the general and structural numbers.
03/20/17 – GBBN sends estimating input to ThermalTech on Architectural implications of the project.
03/21/17 – Spoke to John Milar at THP and we will meet on Thursday to review the AHU locations for the Alternate bids.
03/23/17 – THP – Project explored different approaches not to provide platforms. Meeting now planned to evaluated platforms on 3/23/17.
04/26/16 – Jail Holding unit was added to the design and added as an Alternate to the job. New review drawings were sent to County on 4/25. Additional budgeting was requested for additional design and change orders by owner.
04/27/17 – THP reviewed field conditions and analysis original drawings. Proposed unit and location do not require modification to the structural frame.
05/12/17 – Project is 90% designed but in holding pattern awaiting bid results from the JC Platforms.
06/26/17 – Received revised budgets from Trane on this project and worked on relief air scenario a little bit more. Bid opening could be in July for this project.
06/28/17 – Render the Jury Room for Judge Shannon to see the new ductwork and VAV box.
07/20/17 – GBBN and TEI meet with Facilities for a Field Verification session on site.
07/24/17 – Design team met on site with GBBN to start wall and ceiling work. Some abatement is required at windows we are using for this project. Wall layout confirmed. ThermalTech updated HVAC drawings and they are ready for review. It was decided the Jury room would have an L Soffit instead of a new ceiling, TEI to work with GBBN on this and add access panels for VAV box maintenance.
07/24/17 – GBBN meets with Pinnacle Engineering and Facilities to examine the extent of abatement required around the existing windows and wall peeling paint. Facilities confirms abatement will be included in the Bid Package for this project. Abatement required is the removal of the interior window glazing putty (with window removal), scraping of the peeling and loose lead paint and removal of all pigeon droppings on the sills and wall surfaces. This will be the same for all four (4) windows in this area affected by the scope of work.
07/27/17 – Controls price came in yesterday for $20,000 to upgrade the system for the new layout. This includes removing three units and extending new controls to the new unit named AHU-53N. ThermalTech proposed new smaller soffit and VAV in mezzanine, county okay with this approach.
08/21/17 – Meeting with TEI and GBBN to view area and existing windows to the south of the visitation booths.
08/30/17 – TEI will get ITB and estimate complete this week, project to be Issued for Bid on 9/7/17.
08/31/17 – BW stated that he thinks the drawings are good to go. TTC stated he needed to update the HVAC details for access through the visitation booth add notes for painting the louvers to match the outside of the building color on that row.
09/19/17 – The prebid meeting was conducted today with good turnout by many contractors, some mechanical and some general contractors attended.
09/25/17 – Addendums 1 & 2 have been issued for this project. The bid opening is scheduled for Oct 12 for this project.
10/24/17 – Addendums 3,4,5 have been issued and the Bid Opening extended to Nov 2 for budget issues and equipment clarifications.
11/14/17 – TEI and GBBN attend Post Bid Meeting with Apparent Low Bidder at TEI’s Offices.
11/28/17 – GBBN and ThermalTech have update the drawings to Permit status and removed all the work not being installed and updated the floor plans to make the fifth floor room the new Mechanical Room. Some work remains and some coordination still remains but we believe it will definitely work it is just small spaces and not a lot of free room around the equipment.
02/08/18 – Const Mtg held. Submittals are coming in and being returned to contractor. ThermalTech met Triton on site for fieldwork.
02/19/18 – All HVAC submittals returned. Permit cost worked out with Triton, they can follow up with the City for costs.
02/20/18 – Door, Frame and Door Hardware submittals stamped “Approved as Noted” and returned to ThermalTech.
03/12/18 – Pre-construction meeting held with Triton for this project. Project schedule, SOV, and additional submittals required from Triton. Permit not ready yet, Triton to work out final cost with city, ThermalTech has worked out all the details with the city plans examiner. Triton to distribute meeting notes and revised schedule.
03/21/18 – VAV submittal returned for Tuttle and Bailey with revised btus per TEI markups. Fire Protection & Controls submittals still need review by TEI.
03/24/18 – HVAC Permit is Issued per EZ-trak. Electrical permit is reviewed and on hold for pickup by EC. Next Meeting is Monday. Triton reported today that the room is not clear for construction yet.
04/23/18 – Const Mtg #4 – Triton is on site working on demo and new work. AH-53 has been removed from KP area. New ductwork is being installed. Existing pipe has been turned off and some of the existing piping has been capped off. A leak in Cooper area may be related to our work and shutting down our heating hot water to AH-53. Work is on schedule.
04/09/18 – Const Mtg #3 held and meeting notes distributed. We worked on some of the supply duct routes and return paths.
04/23/18 – Const Mtg #4 held and meeting notes distributed. Reroute return duct KP area, submit CO for sprinkler piping change, finalize HHW and CHW lines to and from units and some of the piping in Shanahan area will be below the duct.
05/07/18 – Const Mtg #5 held and meeting notes distributed. Honeywell on site and starting to work, interior lighting in AHU discussed, const mtgs changed to weekly for final run, Triton to cover all vents in Shanahan’s area and clean debris up daily in work area.
05/14/18 – Const Mtg #6 held and meeting notes distributed. Triton asked to submit change orders for extra work on this project so far. Shanahan soffit will be converted to rigid board ductwork and pants fitting to be fixed before insulation.
05/21/18 – Const MTg #7 held and meeting notes distributed. We are wrapping up Shanahan courtrooms and moving over to Cooper area. Honeywell controls are in place and starting to control the unit. IBI inspection schedule for next week KP ceiling should be going back up, change orders approved, painting has started and we are moving into the final phase of the project.
06/26/18 – Final inspection was approved last Monday. Mechanical and Electrical punchlist have been distributed. Request for Change Order Work #2 has been designed by TEI and sent to Triton for pricing. We have a rough idea of contingency monies left on this project and will try to fashion the changes with that remaining funding.
07/16/18 – Met AAB on site for testing of the airflow through the AHU. We tested the unit at various speeds and took videos on the inner workings of the unit and discovered at 45hz water migrates from the drain pan to the fan section under the drain pan divider. We will contact the manufacturer to rectify this issue.
07/25/18 – Final punchlist was back checked this month. The water leaked returned to which TTE and Triton have been working to resolve with JCI almost daily – there is a lot of behind the scenes work and communications Facilities not included on discussing issues and remedies for this problem. As of yesterday, Triton has increased the depth of the trap, resealed the interior of the unit, and tested interior drainage. JCI tested the levelness of the unit and found it to be installed properly, water was poured into the drain pan and found to drain back and down to the outlet of the unit and at 40hz all seemed to be well.
07/26/18 – The unit was set up to 45Hz and allowed to run overnight at the higher speed. If the unit is still dry we will release it to automatic operation.
08/28/18 – TTC went on site with Triton to work out the reheat coil fitting above the mezzanine in Shanahan’s area. It’s a very tight fit and the two other VAV boxes have to have their supply ducts move so the new zoning works. Other than that one coil, everything else was fitting well. TTE approved controls submittals last week and confirmed with Randy Waddell yesterday for final order.
08/29/18 – Triton reported things are going well but contacted Honeywell to see when they will be on site adding controls and piping to the system.
09/24/18 – ThermalTech met with Triton last week to hash our some piping changes that were not making sense in the field and Triton is making those changes this week, followed by insulator and controls contractor wrapping up. All work to be done by Thursday September 27. Triton still working at night. TEI still looking for hot water reheat lockout temperatures from Honeywell.
10/23/18 – All change order work is complete and the system is programmed into the controls. Space temperatures look good today and the heating appears to be on. All spaces are 72 and above. TEI will start the closeout process on the project.
11/29/18 – Triton dropped off the OM’s yesterday to ThermalTech and TTC hand delivered them to the County including final payapps and closeout paperwork at the Partner Meeting. This project can be archived.
01/22/19 – Project running good. TEI collected all sensors from the space except for the one in the Sheriff surveillance space. Hopefully Barth will recover that for me.
01/23/19 – Project Ready to Archive.

CH – AHU-51, 53, 54 Replacement Read More »

COURTHOUSE Roof 10 Repair

Partner Lead: THP

06/11/15 – County requested SOSS.

06/13/15 – THP and County visited the roof.

06/25/24 – THP anticipates issuing the SOSS.

07/17/15 – County Facilities, THP, TTE and Chambers Control met to discuss phasing the project and completing the work.

07/30/15 – Due to the different scope of work, THP split Court House roof project into Roof 10 (repair/replacement) and Roof T (warranty extension) for tracking purposes.

08/01/15 – THP anticipates issuing an SOSS to the County.

08/03/15 – THP issued SOSS to County.

08/07/15 – County approved SOSS.

08/26/15 – Project update: THP developing design documents.

09/24/15 – Project update: THP developing design documents.

10/29/15 – THP completed roof scan, roof cuts and field measurement. Design development documents anticipated to be released 11/2/15.

12/09/15 – THP working on bid documents with update roof configuration from field findings.

01/28/16 – THP working on bid documents

02/25/16 – THP confirmed plumbing routing and delivered update plumbing drawings for review by the County.

03/21/16 – Prebid meeting conducted.

03/28/16 – Addendum no.1 issued.

03/31/16 – Last day for contractors to submit questions.

04/04/16 – Last addendum will be issued.

04/12/16 – Two bids were submitted with both Contractors within the project budget. Imbus Roofing was the apparent low bidder.

04/13/16 – THP completed a cursory reviewed of Imbus’ bid and recommend the County accept all alternates.

04/14/16 – THP issued draft AIA contract for County review.

05/20/16 – County issued PO and Contract to Imbus Roofing.

05/26/16 – Imbus working through background checks and project planning.

07/22/16 – THP contacted Imbus regarding submittals. Ed with Imbus stated he would gather submittals and send to THP.

08/05/16 – Preconstruction meeting completed.

08/25/16 – Imbus in the process of mobilizing.

09/28/16 – Imbus has roof 10 completely removed and the temporary roof installed. Have had some leakage issues, but otherwise turning water. THP provided pipe post support detail to Imbus for pricing. Imbus initially submitted $524 per pipe and revised to $400 per pipe installed. County authorized to proceed with fabrication and installation. Imbus started tear-off and temporary roof installation last night on roof 6. American Façade plans to begin sealant work on cornice adjacent to roof 10 and along north and south walls of law library tomorrow. Imbus and THP meeting tomorrow to review pipe penetration near RTU in southwest corner of roof 10.

01/26/17 – Project update: Roof 10 – complete , Roof 6 – complete except downspout installation, Roof 5 – last phase of layup this week. Flashings, cap flashings, and terminations still to do. Stainless steel trough at Roof 10, painting roof hatch at Roof 5, and HVAC duct replacement at Roof 5 still left as well. Change order for securing electric lines on outside of parapet at Roof 5 being developed. This work is outside our scope, but Imbus subcontractor has provided cost for work. Imbus plans to turn parking in courtyard back to county this week. Hoist and scaffolding was to come down over the weekend. Bert asked THP to look at stained glass windows and protection from winter ice or snow.

02/22/17 – Roof 5, 6, and 10 generally installed. Imbus working on final detailing and flashing conditions

03/23/17 – Project update: Roof membrane installation complete. Imbus has several items to finish prior to reaching substantial completion.

03/23/17 Roof 6 and 10 need punch list developed.

03/23/17 Roof 5 has the following efforts to complete: Reconnect HVAC units, including running new conduit/power on parapet wall. Duct work (elbows) need replaced. Terminations and flashings need to be complete below the duct work. New posts need to be cleaned and painted. New posts need sealant to prevent water from being harbored on top of the cap plate. Prepare and paint the roof hatch. Repair junction boxes. Complete the termination of roof membrane at stained glass window. Repair the CMU block at steel stair landing tie-in at wall. Finish target at roof drain on north side of Roof 5. Fix the walk mats that are not lying flat. Change order work – replace displaced electrical conduits. Finish counterflashing installation.

04/27/17 – Imbus finalizing punch list. Work anticipated to be finished week of May 1st.

05/18/17 – THP issued final punch list.

05/25/17 – Imbus working on punch list.

07/26/17 – THP to complete review of final punch list.

08/28/17 – Final punch list repairs were reported to be completed Friday 8/25. THP to complete final review 8/31.

09/27/17 – THP to complete final review of final punch list.

10/20/17 – THP publish updated punch list.

10/24/17 – Imbus and County walked the roof to review the punch list.

11/30/17- Imbus completed all punch list items. County is waiting on final prevailing wage from contractor.

COURTHOUSE Roof 10 Repair Read More »

CH – ADA Assessment

06/16/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings
06/17/11 – SOSS submitted in person to Bert Watts.
09/16/11 – Signed SOSS received from Bert Watts.
03/16/12 – GBBN scheduled to meet with Building Manager to begin Field Verification.
08/21/12 – GBBN completes ADA Survey Report. GBBN begins estimating component of the Report.
02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.
10/13/15 – Bert Watts requests that all Assessments be completed by the first of the upcoming year.
11/03/15 – GBBN completes Assessment, prints final copies and delivers to Facilities.
12/15/15 – Facilities report to GBBN that Preliminary Cost Estimate portion of reports have incorrect references to County Administration Building.
01/08/16 – GBBN picks up reports from Facilities for making corrections.
04/18/16 – Facilities sends Estimating Project Requests showing the cost estimating portion of these Assessments as listed projects.
06/28/16 – Opinions of Probable Costs for the implementation of the ADA Assessment findings were entered into Archibus as a Project Request Estimate.
03/23/17 – GBBN and Facilities agree to have Assessments completed at the same time as the Annual Project Request Estimating.
07/24/17 – GBBN printed all Archibus Project Request Estimates from 2016 (#801, 802, #627 and #804) and 2018 (#1862, #1851 and #1831) for inclusion into final reports.
10/25/17 – Final Project Request Estimates have been printed and ready for insertion into final reports.

CH – ADA Assessment Read More »

ROUND BOTTOM GARAGE Asbestos Study

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sends list of buildings to be included in Asbestos Abatement Reporting.

02/14/12 – Pinnacle Engineering requested drawing files for the purpose of documenting findings.

02/15/12 – GBBN sent drawing files to Pinnacle Engineering in PDF form.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/03/12 – Field work completed, draft report completed and ready for initial review.

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

01/26/13 – BRG confirms entry of ACM data into Archibus is completed.

01/28/13 – GBBN conducts spot review and confirms data entry is accurate.

02/28/13 – Pinnacle sends GBBN a proposed completion schedule for remaining work.

03/18/13 – Tony Matre calls GBBN to request a status check on Pinnacle’s delivery schedule.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

02/24/14 – GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/Web Central is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14- GBBN sends another email and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

08/29/14- Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre to finalize invoicing for these projects.

ROUND BOTTOM GARAGE Asbestos Study Read More »

RECORD CENTER Asbestos Study

03/30/12 – Meeting with Tim Schuh of Facilities Department to discuss Archibus Input Strategy

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/04/12 – GBBN receives drawing files from C-R Architecture upon request for use by Pinnacle.

05/07/12 – GBBN transmits drawing files to Pinnacle for use in field documentation.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

12/22/12 – GBBN sends request to Pinnacle Engineering for remaining ACM translation data for continued Archibus data entry.

02/26/13 – GBBN inquires with Pinnacle for status of remaining documents to be sent to GBBN.

02/27/13 – Pinnacle reports back that progress has been made and further timetable for receipt will be coming 2/28/13

02/28/13 – Pinnacle sends GBBN a proposed completion schedule for remaining work.

03/18/13 – Tony Matre calls GBBN to request a status check on Pinnacle’s delivery schedule.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

0611/13 – GBBN receives floor plan updates in electronic form. GBBN updates CAFM drawings for the 1916 for future reference.

02/24/14 – GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/WebCentral is ongoing. GBBN was granted access to the database to complete the drawing downloads. No existing drawing of 1916 Central Parkway exists in Archibus. GBBN to visit site and do field ottom: 2px”>

02/20/15 – GBBN in communications with Tony Matre to finalize invoicing for these projects.

RECORD CENTER Asbestos Study Read More »

GALBRAITH RD GARAGE Asbestos Study

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sends list of buildings to be included in Asbestos Abatement Reporting.

03/30/12 – Pinnacle Engineering requested drawing files for the purpose of documenting findings.

03/31/12 – GBBN sent drawing files to Pinnacle Engineering in pdf form.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/03/12 – Field work completed, draft report completed and ready for initial review.

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

01/26/13 – BRG confirms entry of ACM data into Archibus is completed.

01/28/13 – GBBN conducts spot review and confirms data entry is accurate.

02/28/13 – Pinnacle sends GBBN a proposed completion schedule for remaining work.

03/18/13 – Tony Matre calls GBBN to request a status check on Pinnacle’s delivery schedule.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

06/10/13 – Pinnacle Engineering response with email indicating CAB report will arrive 06/11/13 and CAB on 06/14/13.

06/14/13 – Galbraith Road Garage Report arrives from Pinnacle. CAB report is not included.

02/24/14 – GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/WebCentral is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14 – GBBN sends another emial and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

08/29/14 – Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre to finalize invoicing for these projects.

GALBRAITH RD GARAGE Asbestos Study Read More »

RIPPLE RD GARAGE Asbestos Study

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sends list of buildings to be included in Asbestos Abatement Reporting.

02/23/12 – Pinnacle Engineering requested drawing files for the purpose of documenting findings.

02/24/12 – GBBN sent drawing files to Pinnacle Engineering in pdf form.

02/24/12 – Pinnacle began field investigation at the site.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/03/12 – Field work completed, draft report completed and ready for initial review.

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

01/26/13 – BRG confirms entry of ACM data into Archibus is completed.

01/28/13 – GBBN conducts spot review and confirms data entry is accurate.

02/28/13 – Pinnacle sends GBBN a proposed completion schedule for remaining work.

03/18/13 – Tony Matre calls GBBN to request a status check on Pinnacle’s delivery schedule.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

06/09/13 – GBBN inquires with Pinnacle Engineering about delays in deliverables.

02/24/14- GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/WebCentral is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14 – GBBN sends another emial and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

08/29/14 – Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre to finalize invoicing for these projects.

RIPPLE RD GARAGE Asbestos Study Read More »

1916 CENTRAL PARKWAY Asbestos Study

07/01/14 – GBBN sends another emial and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

08/29/14 – Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre to finalize invoicing for these projects.

1916 CENTRAL PARKWAY Asbestos Study Read More »

2014 GENERAL SERVICES GBBN

09/17/13 – Bert Watts requests Partners to submit SOSS for 2014 General Services.

09/18/13 – SOSS submitted to Bert Watts.

01/30/14 – GBBN attends monthly Partnering Meeting.

02/27/14 – GBBN attends monthly Partnering Meeting.

02/24/14 – Bert Watts indicates the JCC Mural project services will be billed to the General Services.

02/25/14 – GBBN and TEI meet with Bert Watts to discuss moving the Recorder’s File Storage to the CAB 10th Floor CLEAR area. Bert requests the services for the Schematic Design and Opinion of Probable Costs be billed to the General Services.

03/18/14 – GBBN delivers estimating binders to Facilities after review finds all printing and assembly of binders to be in order.

04/24/14 – GBBN attends monthly Partnering Meeting.

03/27/14 – GBBN gets new Partner ID Badge at Sheriff’s Office in Courthouse to replace lost badge.

04/24/14 – GBBN attends monthly Partnering Meeting.

05/29/14 – GBBN attends monthly Partnering Meeting.

06/23/14 – GBBN completes the CAB 8th Floor As-Built drawing layering standard review and reconciliation.

06/26/14 – GBBN attends monthly Partnering Meeting.

07/28/14- Facilites sends Master Service Agreement Admendment to GBBN for signatures.

07/28/14- Facilities sends three building (230 WHT Law Center/CAB Basement/A&D) existing As-Built drawings to GBBN for layering verification review.

07/31/14- GBBN attends monthly Partnering Meeting and delivers signed Master Service Agreement Admendment to Facilities.

09/02/14- Bert Watts contacts GBBN about a project to renovate an existing space in 800 Broadway, 6th Floor.

09/05/14- Sketch sent from Bert Watts about pop-up project at 800 Broadway.

09/15/14- GBBN attends kick-off meeting with Bert Watts, JFS and Juvenile Court.

09/16/14- ThermalTech sends the MEP Estimating Documents to GBBN. GBBN sends combined project Estimate to Bert Watts for review.

09/30/14- GBBN receives email invitation to visit Patrol Headquarters to investigate addition for a Kennel and to investigate an operable partition renovation to the Comm. Center.

10/16/14- GBBN receives email with Operable Partition quote, developed by OKI (7/7/14), from Bert Watts via John Nester.

10/07/14- GBBN receives email from Bert Watts about estimate project requests created in Archibus for estimating.

10/09/14- GBBN sends first iteration of Patrol Headquarters Kennel addition floor plan to Facilities and TEI for review.

10/15/14- GBBN completes estimate for Patrol Headquarters Kennel addition.

10/16/14- GBBN receives comments and suggested floor plan revisions for the Patrol Headquarters Kennel estimate.

10/17/14- GBBN contacts Metallic Building Systems about Burlington Garage siding repairs by email off the link from the website.

10/20/14- GBBN sends updated Patrol Headquarters Kennel floor plan to TEI and Facilities for review and estimating.

10/20/14- GBBN sends deflection criteria information to THP to review for roof joist loading. Structural drawings received from TEI are forwarded to THP for investigation.

10/24/14- GBBN contacts Metallic Building Systems about Burlington Garage siding repairs by telephone. Voice mail was left.

10/27/14- GBBN receives call from Valcom Enterprises related to inquiry about floor mounted operable partition system. Telephone memo forwarded from GBBN to Facilities and THP.

10/29/14- Bert Watts forwards final design criteria on Comm. Center operable partition for estimating (three separate estimating options) purposes. GBBN calls Valcom Enterprises for quotation on actual floor mounted operable partition.

10/30/14 – GBBN attends monthly partnering meeting. Next Meeting scheduled for January 2015 if GBBN awarded contract extension.

2014 GENERAL SERVICES GBBN Read More »

800 Broadway Polygonal Pavilion Roof Repair

October 26, 2011 Update THP develops test repair options and met with SSRG to review for pricing. THP to submit separation SOSS for contractor work.

Past Comments

Due to findings, weather sensitive repairs, and schedule; THP proposed completing a safety survey and trial repairs. County requested a letter report summarizing needed work to be possibly incorporated into a larger 2012 project. A SOSS for the letter reported was requested.

September 23, 2011 THP met with County to review conditions of roof.

Early September THP completed field review and design analysis.

August 3, 2011 SOSS approved.

July 18, 2011 THP Submitted SOSS for review.

800 Broadway Polygonal Pavilion Roof Repair Read More »

2011 General Structural Services

Hourly budget funds exhausted for F24A. THP directed to submit for additional $5,000 as F24B.

Past Comments

July 26, 2011 County approved SOSS F24A.

July 18, 2011 THP submitted SOSS F24A for additional funds.

Hourly budget funds exhausted; Bert Watts requested a SOSS for the second half of the year.

Bert Watts requested THP provide a SOSS for the study and repair of the 800 Broadway limestone panels.

THP reviewed reported cracking of Hillcrest Oak Cottage and provided a summary letter on May 5, 2011. Bert Watts requested an SOSS to complete a study of the cracking issues.

THP completed initial review of 800 Broadway limestone condition and provided summary email for review.

THP reviewing 800 Broadway LEED EB proposal structure.

May 5, 2011 SOSS approved.

April 28, THP provided SOSS.

April 24, 2011 SOSS requested SOSS.

2011 General Structural Services Read More »

Parkhaus Garage Repairs THP Prime

October 26, 2011 Update – Contractor noted they are waiting on Joint and several warranty from the manufacturer, which is anticipated later this week.

Past Comments

All pay requests minus retainage approved; waiting on warranty and closeout paperwork.

August 31, 2011 Substantial letter completion letter issued; along with final deduct change order due to liquidated damages.

All work complete as of early August.

July 22, 2011 RAM issued via email that the new hand rail embed should be fabricated and on site at the end of the week of July 25.

July 12, 2011 THP issued new hand rail embed replacement details to RAM. RAM submitted details for embeds to be fabricated.

July 7, 2011 THP approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 4, in the amount of $20,617.20.

July 6, 2011 THP noted, RAM damaged some existing handrail embeds when removing existing handrail. THP to review conditions and issued repair details.

July 5, 2011 RAM re-mobilized on site to begin replacement of the handrails at the NW stair and liquidated damages begin.

June 9, 2011 THP approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 3, in the amount of $29,794.20.

May 26, 2011 THP approved, with exceptions noted, the steel hand rail shop drawings for NW stair tower.

May 23, 2011 RAM demobilized from the project site so Hamilton County has full use of the garage facility. RAM will re-mobilize on site once the steel handrail shop drawings and fabrication are complete. Per liquidated damages letter RAM is scheduled to return for installation of the steel hand rail on July 5, 2011.

May 25, 2011 steel hand rail shop drawings for NW stair tower received.

May 23, 2011 substantial completion date but RAM has not satisfied the substantial completion date requirements. No steel hand rail shop drawings submitted for NW stair tower. Liquidated damages letter pertaining to steel hand rail to be issued by THP per Bert Watts (Hamilton County) direction and approval. Steel hand rail shop drawings and fabrication were never weather dependent work items.

May 23, 2011 THP issued Field Report No 05 for Phase 2 (final) membrane strip installation.

Weekend of May 20, 2011, RAM completed vault slab placement over anodes, and remaining Phase 2 membrane strip installations. Inclement weather postponed this phase of membrane installation till this date.

May 17, 2011 Anode testing report by Bushman and Associated issued.

May 13, 2011 THP issued Field Report No 04 for completion of Phase 1 membrane strip installation. THP also approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 2 in the amount of $54,344.40.

May 10, 2011 Membrane manufacturer (Neogard) letter pertaining to exposed membrane aggregate being compromised was issued.

May 6, 2011 THP issued Field Report No 03 for Phase 1 membrane installation. Inclement weather prevented completion of all of Phase 1 membrane strip installation areas.

May 6, 2011 Final T&M tickets submitted by RAM for anode relocation.

April 29, 2011 Change Order No 01 work items approved by all parties for a deduct to the projects Cash Allowance in the amount of $8,735.00. Total project budget remains unchanged.

April 26, 2011 THP issued Change Order No 01 to reflect Bulletin No 01 pricing so RAM may begin the additional work. This Change Order added two weeks to the substantial completion date. New substantial completion date is May 23, 2011.

April 25, 2011 Hamilton County accepted Bulletin No 01 pricing which was within the projects original Cash Allowance.

April 25, 2011 RAM submitted Bulletin No 01 pricing.

April 21, 2011 RAM began membrane work on Levels 2 through 5.

Week of April 18, 2011 Anode placement began in the vaults.

April 15, 2011 THP issued Bulletin No 01 to RAM for pricing for additional concrete and waterproofing repairs.

April 13, 2011 Progress Meeting.

April 8, 2011, THP issued Field Report No 02.

April 7, 2011 RAM completed construction joint sealant replacement on Levels 2 through 5.

As of March 24, 2011 RAM has not submitted steel shop drawings for hand rail.

March 18, 2011 THP approved RAM’s Pay Application No 1, in the amount of $40,194.80, and forwarded to Hamilton County.

March 3, 2011, THP issued Field Report No 01.

Anode installation scheduled to begin week of April 4.

Weather conditions for this weekend appear favorable, so RAM may perform sealant replacement April 1 weekend.

January 6, 2011 preconstruction meeting completed. Work to scheduled to begin February 7 to allow for weather.

THP has all submittals except cathodic protections.

Contract approved.

County commissioners reviewing contract.

Contract signed by Ram reported to be returned to County.

September 27, 2010 THP sent updated contract for County review.

September 9, 2010 THP sent draft contract for County review.

Bids received and Ram Construction apparent low bidder.

Bids due August 18, 2010.

Pre-bid meeting scheduled for August 4, 2010 at 10:00 a.m.

Project out to bid on July 23, 2010.

Project Documents sent to County for review on July 19, 2010.

THP and Jim Bushman accessed vaults to confirm conditions for implementing corrosion protection system on June 23, 2010.

THP is coordinating work with corrosion consultant.

Parkhaus SOSS approved May 14, 2010.

SOSS submitted 3/3/10.

THP anticipates SOSS delivery by 3/5/2010. (2/24/10

Kickoff meeting complete.

THP needs to schedule a kickoff meeting.

THP working with subcontractor to develop proposal.

Parkhaus Garage Repairs THP Prime Read More »

1021 Patrol Headquarters Waterproofing Repairs THP Prime

October 19, 2011 THP, SSRG and County met to review the leak to determine if work is warranty or a new item. Due to lack of water/leak; the team decided to wait until rain/leak event and review the condition at that time.

New leak reported in same switch gear room in late September during a heavy rain.

Past Comments

September 15, 2011 County finalizing process of SSRG final pay application.

September 14, 2011 SSRG sent prevailing wage information to County.

September 11, 2011 THP forwarded final pay application and close-out manual to the County.

SSRG completed punch list items early August and THP verified items were complete.

July 13, 2011 THP published punch list to SSRG. Steven noted the work will be completed and THP is holding onto the final pay application (retainage) until the work is complete.

THP is waiting on warranties to process final pay application.

THP plans to punch on June 30, 2011.

Change Order No. 1 work (Window repairs) complete as of Friday, 5/20.

Change Order No. 2 sign by HGC, awaiting County approval.

THP forwarded Change Order No. 2 for the urethane injection of the electrical and sprinkler rooms to HGC for signature on 5/16.

During heavy rains of late April, leaking at the switch gear room and sprinkler room (new leak) occurred. THP recommended injection of crack from interior of both room. April 25, 2011 THP and HGC met to discuss the condition and request pricing.

During restoration repair, additional window sill and steel structure repairs associated concrete sill were identified. THP requested cost from HGC to complete the repairs. Change Order #1 approved by the County.

Subsurface waterproof and exterior injection work complete by HGC.

January 27, 2011 Work on hold until weather is within allowable specifications (early spring). The County requested all submittals and background checks be completed this February.

March 30, 2011 THP sent HGC the change Order form for the repair work associated with the window deterioration.

March 28, 2011 THP received approval from the County to proceed with a change order for HGC to repair the deteriorated window.

March 25, THP received final pricing from HGC regarding the work to repair the deteriorated window.

March 25, 2011 HGC finished the drain tile and landscaping work which completed all base bid work.

March 23, 2011 THP requested pricing from HGC for associated window deterioration.

March 23, 2011, HGC completed injection repairs and installation of the drain tile / back fill.

January 27, 2011 Work on hold until weather is within allowable specifications (early spring). The County requested all submittals and background checks be completed this February.

THP is waiting on submittals and contractor background check.

County conducted preconstruction meeting on 12/29.

Project needs to schedule a preconstruction meeting.

The requested project schedule and submittals from Structural System.

Contract approved.

October 29, 2010 the County provided updates to the proposed Contract. THP updated and returned the contract.

October 8, 2010 THP sent draft contract to County for review.

September 30, 2010. Bids were within budget and THP recommended Structural Systems (HGC).

Bids are due September 30, 2010.

September 21, 2010 Addendum #1 was issued, which was the meeting minutes from the prebid meeting.

September 17, 2010 bid documents were sent to HGC, ZSR, Lithko Restoration, and Langenheim & Thomson Company.

September 16, 2010 THP provided bid documents to the County.

September 9, 2010 County provide comments to review documents.

September 3, 2010 THP provided review documents to the County for review. Project estimate is below County threshold for publically bid project, so project bid is by invitation.

County requested construction budget and THP reviewing.

THP provided owner review documents on August 23, 2010.

County approved drainage system.

County reviewing THP proposed approaches of a new slab or drainage system (THP on hold).

THP and County had kick of meeting on June 21, 2010 to complete repairs recommended in report

THP issued letter report on June 18, 2010.

THP arranging with contract excavation of wall area.

Excavation needed for investigation is planned for mid-March, due to adjacent utility lines and required handwork.(2/24/10)

SOSS approved 2/3/2010.

THP submitted SOSS 2/1/2010.

THP needs to submit SOSS and complete survey.

Kick off meeting completed with Bert Watts and John Millar.

1021 Patrol Headquarters Waterproofing Repairs THP Prime Read More »

Memorial Hall 2010 Facade Assessment

Can project be closed out?

March 8, 2011 report entered into Archibus.

March 4, 2011 report sent to County.

THP working on report.

January 3, 2011 THP & Lithko completed a water test of the south wall parapet.

January 2, 2011 Lithko restoration a safety survey to remove all loose stone material. THP completed façade lift inspection during safety survey.

THP working on project.

January 3, 2011 THP & Lithko completed a water test of the south wall parapet.

January 2, 2011 Lithko restoration a safety survey to remove all loose stone material. THP completed facade lift inspection during safety survey.

December 10, 2010 THP completed initial visual survey. Survey revealed loose sandstone and THP recommended completing a knock down survey by a contractor. Due to weather conditions repairs should occur in the spring. THP getting pricing from the contractor.

November 15, 2010 SOSS approved.

October 26, 2010 THP submitted SOSS for review.

October 26, 2010 THP and County completed kick off meeting.

October 19, 2010 County requested SOSS from THP.

August County and THP discussed preliminary Memorial Hall assessment numbers.

Memorial Hall 2010 Facade Assessment Read More »

CAB 10th Floor Community Development Expansion

2/9/10-Meeting with Bert Watts at Community Development

2/18/10- Issued SOSS to Bert Watts.

2/19/10-Bert questioned GBBN verses TEI scope and permitting costs.

2/22/10-Terry Cannon of TEI issued email with scope, SOSS and permitting resolutions.

3/6/10- Received signed SOSS.

3/8/10- Met with Mike Florimonte to field measure adjacent storage space. Receive directive to eliminate one workstation for a total of 3. The fourth area to become storage.

3/15/10-Received Purchase Order (538771) from Bert Watts.

3/17/10-Susan Walsh approved rotated third workstation.

3/31/10-Final Design Development drawings submitted to Bert Watts for Susan Walsh’s review.

4/6/10- Building Permit Application, Drawings, Electronic Submittal and Check delivered to Cincinnati Buildings and Inspections.

4/21/10- Approved Building Permit paid for and picked-up from Cincinnati Buildings and Inspections.

4/22/10- Approved Permit and Drawings Delivered to Bert Watts.

5/18/10- Inspector Larry Keifer has requested an additional sprinkler head be added in the expansion space.

6/24/10- Sprinkler permit has been filed and still pending.

7/29/10- Bert Watts declared this project closed and ready for Archives.

CAB 10th Floor Community Development Expansion Read More »

Sheriff HQ – Electrical Device Identification and Arc Flash Study

05/30/08 – Ginter sent the panelboard schedule in excel format. TEI forwarded to County and sent allowance usage certificate to Ginter for signing. Ginter has to provide an approved IBI permit at conclusion of this project.

04/09/08 – All Work is complete. TEI will finish and stamp the permit drawing for Ginter. Ginter will get IBI for making the conference room on emergency panel for colonel. This will use the last of the allowance money and closeout the project.

01/07/08 – Ginter has completed punchlist items. MAH will conduct back check when meeting on extra work takes place. The Colonel would like to have some receptacles on emergency power in the conference room so they can use as a command center. The work will be discussed with final approval from Tony Matre.

12/14/07 – Change order was requested for Ginter to access the $2000 allowance. TEI has requested additional itemized backup and an explanation of the additional devices from Ginter. Jim Ginter sent the additional items to TEI and MH is reviewing for approval today. MH created the punchlist for the project and is distributing the punchlist to the contractor today as well.

12/11/07 – Construction meeting was conducted and punchlist was created moving toward a final closeout. Punchlist items will take a few weeks because of the lead time in ordering engraved labels. Aside from some misunderstanding in the labeling requirements the work appears very thorough. Ginter turned over mark-ups. Ginter to submit pay apps and TEI to write a deduct change order for unused allowance.

11/30/07 – As promised Ginter reported today that this project is complete. TTC responded back to their email that we would use the const mtg for our punchlist and to advise about allowance usage on this project so TEI could write a deduct change order for closeout. TTC also sent all the closeout documents to Ginter for use on this job.

11/28/07 – Ginter provided an update today stating the the ID project was going well. TEI will setup a const mtg the week of 12/10.

11/09/07 – TTC distributed Pre Const Mtg minutes from last week. Ginter is on the job and ready to complete by the end of this year.

08/31/07 – TTC received word from HCFD that the insurance issue has been resolved. TEI awaiting word from HCFD so that this project can move into the Construction Phase.

08/15/07 – NR wrote: “Any idea about when this project is going to be ready for construction?” Bert( HCFD) responded: “I am still working out Insurance issues with Michael Ginter, he is working on getting me the correct Certificate of Insurance. Jim and I are working on getting the LEADS background checks completed.” TEI awaiting word from Hamilton County Facilities Department to move into construction phase.

08/10/07 – TEI awaiting word that the contract has been signed by Ginter Electric so that this project can move into the construction phase.

07/30/07 – NR received word from Bert Watts at the Hamilton County Facilities Department that the contract was sent to Ginter Electric last week for their signature. TE is awaiting word that the contract has been signed so that this project can move forward with the construction phase.

06/29/07 – TE awaiting word that the contract has been signed to that this project can move into the construction phase.

06/22/07 – Contract has been awarded to Ginter Electric. The contract has been sent to Mark Donnelly; TE is awaiting signed contract to proceed with pre-construction meeting.

06/15/07 – Hamilton County Facilities is reviewing the bid tabulation. TE is awaiting word about which contractor has been awarded the contract so that we can move forward with this project.

06/08/07 – This project opened for bid yesterday. TE is awaiting the bid tabulation from the Hamilton County Purchasing Department.

06/01/07 – This project is set for bid opening on June 7, 2007.

05/25/07 – The pre-bid meeting was held on site today. Those in attendance included Kevin and Steve Kallmeyer of Kallmeyer Electric, Jim Ginter of Ginter Electric, Nick Richmond of ThermalTech Engineering, and Walt Hendrick/ Mike Jackson/ Ken Caruso of Hamilton County. A site tour was given as well as a specification and drawing review. This project is expected to go to bid on June 7th of 2007.

05/21/07 – Project went out for bid on May 18, 2007. Pre-bid meeting has been scheduled for Friday, May 25 at 10:00am. Meeting place is the lobby of the Patrol Headquarters. NR contacted Captain Mark Hendrick to discuss working hours. It was decided that normal working hours would best suit this project because of limited access to certain areas of the facility. NR sent an email to Mark Donnelly informing him of this.

04/27/04 – Drawings for the Device Identification portion of this project are complete and will be present for Hamilton County review in the meeting today, April 27 of 2007. The Arc Flash Labels are at the printer and should be completed within the next 2 weeks.

04/20/07 – Arc Flash Labels are being dropped off to the printer next week. The Device Identification portion of this project is complete and the drawings will be complete next week.

04/13/07 – Single Line Diagrams have been established and Arc Flash Study has begun. TE found discrepancies with the As-Built drawings and what was found in the field so they are making another field visit today, April 13, 2007. This visit is meant to trace the source of the panels in the barns and out-buildings. There is an automatic transfer switch in the Property Room that needs to be traced also. Dan Myer of TE will also be on site to meet with a county employee to locate above ceiling equipment.

04/06/07 – Kick-off meeting was held. Project is moving along as expected.

03/30/07 – Kick-off meeting is scheduled for next Thursday, April 5th of 2007.

03/23/07 – Project progressing as expected. Kick-off meeting tentatively scheduled for the first week in April. TE to set up meeting with Hamilton County Facilities.

03/20/07 – Fieldwork is progressing and is about 80% complete.

03/14-07 – NR created project journal and filled in back data from previous meetings. Project awaiting signed SOSS to be returned to TE. 90% of field work has been completed for the Device Identification portion of this project. Field notes not inputted electronically per awaiting signed SOSS.

Sheriff HQ – Electrical Device Identification and Arc Flash Study Read More »

SHERIFF PATROL HQ Street Widening

09/29/10 – Project closed and archived.

08/16/10 – We talked to Debra Kuempel today. O&M’s were submitted and I believe sent to the County last November. We have been holding for the final change order. Kevin and Donna at DK agreed the Change Order Credit was going to be $5761 for this job. Laurie is typing, we will delivery for signature to DK today and then they can get their closeout docs in order and we can close this job.

08/13/10 – Payapps updated for both contractors. As Built dwgs completed by TEI. QCM needs to sign the change order and send to Bert.

07/28/10 – Check on DK change order work and approve as-builts for project completion.

05/26/10 – DK is installing the fiberglass pan in June. We are awaiting QCM closeout docs.

05/15/10 – TTC is working on closeout documents for QCM. We have the final payapp but I don’t know if we have the O&M manuals so I contacted QCM again to check the status.

04/26/10 – Project is complete save the fiberglass pan issue.

03/23/10 – DK got an okay to provide pricing for a new fiberglass drip pan for the panel as we wait for THP to work on better site drainage.

02/22/10 – TTC signed additional payapps for QCM and DK for payment on this job. We are ready to close it out. There is an issue about a ground fault alarm and wiring on the fire pit. DK said they may just replace the wire and be done with it.

12/31/09 – Debra Kuempel did the overnight work on the conduit sealant upgrade and I believe we are down to final closeout. We have a warranty issued with the pit having a grounding issue at the fire alarm panel. DK has sent a technician to repair.

10/20/09 – TTC sent out punchlist today to contractors with instructions to closeout project. We are accepting CO#09 for blacktop from QCM. We have to work out the $10,000 allowance with Debra Kuempel and the $7500 with QCM for this project to write the final Change Orders. The email included instructions to closeout and finalize change orders and allowances.

09/22/09 – The project is nearly complete. TEI will be performing the punchlist in the next few weeks. DK is going to be on site on Thursday to finish up their work. Queen City Mechanical submitted change orders for processing today. We received a new COR #8 for piping. TEi asked for more info on this change order. We should be able to close out in a month.

08/26/09 – Final tie-ins for both fire protection and fire alarm are being made. By the end of this week, everything should be 99% complete and ready for punchlist.

07/27/09 – Bert and Terry talked last week about having TEI modifying our permit to list the Fire Pit as existing equipment. TTC called but the Inspectors office was closed. I will try back again later. The County has asked for the CWW to submit their drawings and apply for a permit for the work separately.

06/23/09 – All the permit issues have been resolved. TTC contact QCM mechanical by email and phone to get an update on status of fire main trench. No update but TTC will check on 06/24 when he visits the site for the FA project. DK has not been back to the site since the new power was brought back online. We believe they will return when they work on the trench with QCM.

05/22/09 – DK has finished the transformer relocation. The building is back up on Duke power from the new transformer. The cables are being collected for pickup. Prus provided the new fire main and fire pit for us. QCM will be out 05/26/09 to begin trenching the parking lot for the remaining work on fire alarm and fire sprinkler work.

04/03/09 – TTC sent an email update to the team for the pit, given it is located in the parking lot. Tony is going to look at the final location. Bert and Tony to advise. Luckily, we talked about this happening in the pre construction meeting.

02/19/09 – GCWW has brokered a deal to have Ray Prus provide the water tap to the R/W for QCM from the new water main. Ford Development will build the pit from that location. We have asked for a credit from QCM for the smaller scope.

02/0509 – QCM informed us that a new water main is being installed in Hamilton Ave. I advised QCM to investigate using that main instead of the one we originally projected for use.

02/02/09 – TTC modified the project schedule and sent out for approval to all the vendors. Jackson questioned the actual shutdown and switchover date but TTC told him that was not set in stone yet. The City has approved the water permit. We are waiting on ODOT approval of the plans before digging.

01/05/09 – Payapp #3 came in for DK and ThermalTech approved and sent to Bert. This payapp went to Bert first which may delay this payment.

10/16/08 – ThermalTech sent profile drawing to QCM for submission to state. TEI sent new permit drawings to Debra Kuempel for permit application. DK is getting price from Duke for work on this project per the scope of work on the specs as TEI wrote.

08/29/08 – Contracts approved. Pre Const Set for next Thursday.

08/22/08 – No update from County. TEI inquired about proceeding. Tony answered that contracts will be in front of the Board next Wed. 08/27.

08/08/08 – Tony reported the Prosecutor has contracts for approval. They are pushing hard.

07/31/08 – County reported that all contracts are at Prosecutor’s Office awaiting approval.

07/30/08 – TEI has delivered all contracts to Contractors for signing. TEI sent stamped permit drawings to Queen City Mechanicals for CWW permit application. QCM stated that CWW will want permit tap fee as soon as permit is awarded. This process may be the longest lead item of the whole job.

07/18/08 – Pre Award Meeting complete. All contractors recommended for project. Debra and Queen City Mechanical both stated they understood the project, the schedule and agreed their price was valid for this scope.

SHERIFF PATROL HQ Street Widening Read More »

SHERIFF PATROL HQ Signage Upgrade

01/24/11 – TTC asked for a written letter from KFI to proceed with closeout as the punchlist is not fully complete as the scratches on the sign have to be touched up.

10/28/10 – We have visited the site several times as the foundation has been poured, electrical has been run and masonry work is ready to begin.

09/29/10 – Holding for State to complete road work.

08/13/10 – Payment 1 has been sent.

07/28/10 – TEI to approve payapp and send to Bert. It looks good, have to visit the site to see the sign.

04/26/10 – We are on hold until June.

03/23/10 – It has been reported that the sign is complete.

02/24/10 – John Brockman called with a question about backlighting the can. TEI will return the call.

02/05/10 – TTC visited Ernst signs and worked out final details on the sign building scheduled for April. TTC updated all parties.

12/31/09 – TTC submitted a permit answer to HamCo building inspections. The next step is theirs. We may have to resubmit to start the project again.

09/22/09 – The new street is very close to the sign. The County is working with ODOT to finalize the sign work. Our contractors are preparing a new shop drawing to the County permit office with the galvanized steel frame.

07/29/09 – No updates because Street Widening is still on hold.

06/23/09 – KF has not returned our call or emails about sign permit approval. At this time it is being held for review by Marty in HamCo Bldg Dept awaiting our clarification on how the sign post will be embedded into the sign base and what material it will be. We may need a meeting or conference call with KF and Brockman signs.

05/22/09 – Zoning has approved our sign permit. The bldg department is questioning the supports for the sign. Tom Speer is checking his design for us.

03/02/09 – Pre-Construction meeting held. KFI will order materials and store sign at HQ to allow invoicing. On hold until street widening is complete.

SHERIFF PATROL HQ Signage Upgrade Read More »

SHERIFF TARGET RANGE Match House Investigation

01/29/15 – County requested THP review the Match House walls.

02/23/15 – THP sent email with general recommendations and an opinion of probable cost.

02/24/15 – County requested a full letter report and authorized additional field work.

03/26/15 – THP anticipates publishing the final letter report.

03/26/15 – THP published final letter report.

SHERIFF TARGET RANGE Match House Investigation Read More »

PBS – Sound System Repair Project

03/21/06 – TEI asked for an engineering change order which covers extra time spent by ThermalTech during the construction phase and occupancy permit time on this project. Joe said he signed it and went on to his boss Eric Stuckey. This project is officially complete.

02/13/06 – TTC finally approved the closeout documents, final pay applications # 6 & 7 and as-built drawings for this project. The only thing left is TE request for additional payment.

12/02/05 – TE requested a revised final payapp reflecting $6200 change order that was approved for the north end zone speakers. All final paperwork and as-builts have been received from Durrell in hard copy and CD. TTC made a copy of this information and is sending all originals to Joe Feldkamp for his use included 3 binders of O&M’s required by spec. TE will have have a hard copy of the 1/2 sized dwgs, just the CD.

11/30/05 – Chris Schaeffer called to inform Terry that the County reached settlement with Ed Simon and his lawyer’s and that a court appearance would not be needed.

11/28/05 – Upon final check the sound system is working, the new speakers are installed and working and the final paperwork has all arrived including the as-builts for this building. TTC has to write an engineering change order for ThermalTech’s Extra Time and WJHW Extra Time on this project and submit it for payment for the year 2005.

11/14/05 – Durrell and TJ’s total change order totaled $6200 ($5600 + $600). Joe Feldkamp approved. TTC confirmed with both contractors. Chris Horrell and Scott have scheduled Durrell’s visit for this Wed 1/16/05. Work to be completed by Thursday. TE shall send out the hard copy paperwork to all vendors.

11/10/05 – TTC was contacted by Chris Schaeffer about a possible court appearance in December over the bidding of this project. TTC discussed County bidding procedures and current ORC requirements for bidding and how the Sound Engineer, Audio Contractor and Electrical Contractor was selected for this project.

09/12/05 – Pay Application #4 is being resent to TE. TTC will approve and send to County for payment. TJ delivered payapp to TE today.

09/08/05 – TTC emailed contractors about closeout for project and punchlist. Sound was excellent last Friday when TTC went to the Colts-Bengals preseason game. TTC sat in section 315 and was impressed with quality of sound and clearness of PA announcer.

08/09/05 – Durrell reported that, Tom and I went over these items and will have most knocked out this week prior to this weekends game. What will be left will have to do with getting QSC down to make the cosmetic changes to the amplifier control system to make it that much more user friendly and correctly control the amplifiers that are being displayed.

08/08/05 – TTC coordinated the final change order amounts with TJ Williams and will modify the change orders for final signing today. Both change orders are complete. TTC will deliver them by hand to PBS tomorrow and try to get Bill Meyer to stop down and sign them. Punchlist was compiled and emailed out to contractors (hyperlink below).

08/01/05 – WJHW and Durrell completed the punchlisting work. Ron Baker is going to send the punchlist to TTC for distribution. TTC talked to Scott Simpson about items that he needed added from his end and left a message for Joe about his items. The consensus appears to be that everything is very nearly complete and everyone is very happy. Hopefully this will lead to a quick closure and a working sound system ready for the season in a very short time period.

07/19/05 – We have reached resolution on the PBS Sound Change Orders. Amy will approve change order #1 8855.00 for the countertops and change order #2: 2,060.74 for restocking fees from TJ. TE will write the new change orders for these amounts and send them to TJ for signatures and then onto JF for signatures by the County. WJHW and Durrell have scheduled the Engineering Commissioning for this project on 07/27 thru 07/29. TTC will be out of town on Wednesday but will assist on Thurs/Fri as needed. Punchlist should be fine as Durrell and Scott Simpson have been working hand in hand during the project. TE and WJHW will supervise and TE will try to set up and Const Mtg on Friday for a final update on progress before we start the as-built drawings for this job. Durrell reported by email on 07/18/05:

Last week Durrell got all the speakers working (with only two exceptions) and wired to the correct amplifiers. The West amp room is complete, all racks laced and cleaned, all amplifiers working. The East we ran out of time Friday, but we have all amplifiers working with the correct speakers, we need to spend one day lacing up and minor cleaning.

We found one 2″ driver not working on the East side that will have to be accessed and one crossover on a full range speaker on top of the north end zone – each will require one day’s work.

The west club area is finished and working and the east is about two hours away (got held up due to a wedding party).

The control room is up and working. We had a MediaMatrix card fail (used backup for tuning) and Scott Simpson has to provide us with info where to mount the two computer screens and the Volume meter, both minor installs. The console and all the other equipment is in a functioning correctly including the software upgrades. We want to rebuild the control block that exist for the control screens for QSControl – some coordination will need to exist between Scott Simpson, Tom Moores and we would like Ron Baker’s input – when the commissioning is done.

Durrell will schedule two days prior to WJHW’s coming to PBS for their commissioning to be sure all of these minor items are finished. We are waiting on Ron Baker for that date (date has been set see above)

07/08/05 – Eric Stuckey, Joe Feldkamp, Diana Craynon and Bill Meyer called today to inform me that the change order has be stopped and no work will be done on it and it is most likely canceled until later. We informed TJ Williams and TTC is supposed to cancel Monday’s field trip to work on it.

07/05/05 – TTC emailed Eric Stuckey the final Change Order #01 cost including the cabling and the countertop for approval. PDF. TTC met Chris Schaeffer, Scott Simpson, Steve Durr, Sam Kinman and Ed Simon and his associates downtown today to supervise a field visit and walk through with the County for the County lawsuit.

06/27/05 – TTC sent out CD’s to HamCo for law suit.

06/23/05 – TJ Williams sent the revised ACO out today. PDF. Terry and Joe asked for TJ to redo the change order to reelect the credit that the County will be receiving in place of the speaker parts that won’t be installed. TTC and JF will then talked to Amy about writing a change order to finish the project off with the cabling upgrade. The Const Mtg verified that many, many of the issues with the speakers were resolved by fixing wiring and termination points. ThermalTech believes that by knowing this it is a fair inference that the 3000 foot cable splices are probably not infallible.

06/22/05 – Const Mtg #02 was held. Durrell reported that all base work is complete except for software upgrade on MM. Durrell offered to do all the CO work except for the cabling for the $50,000 allowance. TTC agreed that this work be a fair barter. We decided to accept the countertop change order from jb schmitt. We will pursue a change order to get the cabling issue taken care of this year and Joe and TTC will talk to Amy about it after TJ provides an update T&M price NTE for the work.

06/16/05 – TTC visited the site earlier in the week with JB Schmitt and they turned in a quote today for the new countertop work at PBS. TTC forwarded the quote to the team for a decision. Countertop = $5695.00 and New Window = $3160.00.

06/06/05 – Durrell sent an email request Topper be added to all correspondences on this project. TE forward to Joe Feldkamp for approval. PDF.

05/31/05 – TE tried to reach WJHW for a conference call to discuss moving forward with additional bidding on Change Orders for this project. CO# 2 and CO# 4 are significant and may have to be bid out separately. TJ Williams called today to see about CO approvals. TTC sent the Allowance email to Bill Meyer. TTC should have sent last week when it was approved but somehow that didn’t happen. TE and WJHW still need to talk to Joe about Club Level work and scope.

05/24/05 – TE issued a recommendation letter to PBS about Change Orders for this project. TE spoke to Durrell and told them they must proceed with scheduling on the assumption that the Change Orders # 2 and # 4 are not approved. The County will issue a formal approval as soon as it can. This may lead to scheduling conflicts later near substantial completion but bidding and change order policies must be adhered to for this project. PDF

05/17/05 – Consultants and JF are in consultation about approving change order request. TE has requested direction from their sub WJHW on what is essential and what is not. First TJ payapp is approved and sent to JF.

05/11/05 – TJ submitted 5 change orders today to the project. PDF TE setup a construction meeting for Thursday at 1:30 p.m. to discuss project progress. TJ contracts are signed and in security for contractor to pick up.

04/27/05 – Contract has been approved by the Commissioners. TTC advised the contractors that the contract and PO would soon be in their hands. TE and WJHW will have subs complete by the end of the week.

04/26/05 – WJHW has submittals for AV work on the job. TE has reviewed the submittals fro EC compliance and found no errors so we will approve them with “No Exceptions Noted” to that end, we have told TJ the same. TJ inquired about contract approval and TE told them Wed at Board meeting, we should know. Please advise us when you hear information about Contract.

04/22/05 – TE received submittals for TJ yesterday. TE is checking for EC items. TE shipped one to WJHW for AV items. TE has delivered all dwgs and specs to TJ for permit application. JF reported that contract is in front of board for approval on 04/27/05. Everyone is still working at their own risk to date. Durrell has sound system working in bowl for weekend draft picks. County Prosecutor asked for some video footage of splice problems in the amp rooms. PBS reported that some have been fixed but other still remain to be documented and that Durrell may know best which ones to document. JF and TTC communicated about this pre-work in email PDF.

04/19/05 – TE sent out an email stating the Durrell may be doing some additional work in the Club levels that is above the scope of work outlined in the contract. Monies for this work shall be determined later.

04/18/05 – TJ sent their employee list into the County for this project. PDF. JF reported that contracts have been submitted and the project is up for Board approval on 04/27/05.

04/12/05 – TE had TJ resign new contracts forms and delivered to Kerry Dowling for approval. Kerry said that she would sign these on 04/11/05 and TE would have City Dash pick up the newly signed contracts and have them delivered back to Joe Feldkamp for submission to the County Commissioners for approval. TE sent 3 sets of dwgs to Dallas for WJHW to sign for TJ to turn into IBI for permit sets. TE and JF told TJ at the pre construct mtg on 04/11/05 that all work done by Durrell and TJ before receiving the contract and the PO is “at your own risk” type work.

02/23/05 – TE delivered contact to Joe Feldkamp. TTC and JF discussed contractor over phone and coordinated paperwork due to prosecutor. JF will submit contract for prosecutor review. TE will hold on notification to contractors until all paperwork is finalized. TTC would like to see 2 week turnaround in contract to keep scheduled intact.

02/22/05 – TE has received all required bid paperwork and finalized the Contract. Contract, Drawings, Spec Books and Drawings will be sent to Joe Feldkamp today.

02/16/05 – County and PBS indicated to proceed with Base Bid and Alternate 2 for this project.

02/16/05 – TTC and WJHW discussed the Alternates from the bids and are basically recommending that the County accept Alternate # 2 at this time and wait on Alternate # 1 because of the unknown variables included with updating the system. TE recommends fixing all the existing problems first before adding a new layer of master control that my contribute new and undiscovered problem of us to troubleshoot in the field plus upgrading to the BIAMP system will add additional dollars to the existing SOSS as this is a scope change for engineering (WJHW is working on an adder price). We will write the contract with Alternate #2 for the time being.

02/08/05 – Bids opened. TJ Williams appears to be the low bidder. TE has contacted contractor for additional paperwork and will begin contract work immediately. County needs to provide a signed bid evaluation form with Alternate recommendations for contract.

01/25/05 – Addendum 3 distributed. Durrell asked a new question for Addendum 4. The bid was extended to February 3, 2005.

01/21/05 – TE coordinated with WJHW and County to extend bid date one week and to send out Addendum 03 on Monday with updated information for bidding and alternate. Purchasing Department instructed TE to contact ICB Audio via email about non-inclusion into the accepted bidder’s list for this project.

01/20/05 – TE distributed Addendum 01 on 01/11/05 and Addendum 02 on 01/20/05. Addendum 03 should come out on 01/21/05. TE has written a rejection letter and given it to Purchasing to give to ICB as they do not meet the Professional Stadium Experience Requirement on this project. The SoundCom qualifications have been sent to WJHW for review and we are currently waiting on SoundCom to confirm a couple of questions about which office will serve this project but they most likely will be approved for bidding as they do meet the quals. TTC asked if the bid should be extended since SoundCom is being added. TE is awaiting the County’s decision. The second prebid was attended by about 8 contractors. Muzak declined to bid and left the prebid after we stated that OEM equipment must be used for repair.

01/19/05 – Prebid is finished. Addendum # 01 wads distributed. Addendum # 02 is going out tonight. Addendum # 03 is scheduled out tomorrow. ICB will not be an approved vendor. TE has to provide a letter to Purchasing for the use, modify and send.

01/14/05 – Joe Feldkamp called to inform TE that because the prosecutor wants a firm number for cost to provide as-built drawings that we can change the bid for to add an alternate to have the AV contractor provide a complete set of as-builts encompassing the entire scope of work at the stadium. TE shall modify the bid form accordingly.

12/24/24 – TE invited Audio Specialist Contractors. Project Manual is on the street, on schedule. Prebid set for January 5th. WJHW will be in town for the prebid. Everything appears to be set for bidding att his time.

11/04/04 – TE found and sent the AV drawings to WJHW today. Final design is still scheduled for final delivery on 12/08/04.

10/25/04 – WJHW sent an informal report from the field trip last week. PDF

10/19/04 – TE, WJHW, PBS and HamCo had a meeting and set the following schedule for this project (see below)

10/19/04 – TE and WJHW met onsite with the owners and ironed out the scope of the project, schedule of the project and the expectations of the project. WJHW will begin design and target first week of December for final engineering documents. TE will release minutes in a follow up email. Contract will be bid to a local EC with a Audio Specialist assigned as a sub.

10/15/04 – TE will meet WJHW onsite on Tuesday for kickoff meeting. WJHW will be onsite late Monday afternoon. They have coordinated their time with Scott Simpson.

ThermalTech solicited consultant bids and wants to team with WHJW from Texas for this project.

Conference call on August 17 between Eric Brown, Bob Bedinghaus, Joe Feldkamp and Terry Cannon with WHJW was held to discuss itemized consultant cost and scope of consultant work on this project.

TE is awaiting a signed SOSS from the County.

The County is awaiting a one page report from WHJW outlining the added benefits of using WHJW on top of the Durrell report.

Project scheduled to be signed in August 04, Designed in Sept – Oct 04, Bid Nov 04, Awarded in Dec 04, Construction Jan 05.

PBS – Sound System Repair Project Read More »

PBS – Occupancy Redistribution Project

03/20/06 – Joe approved TEI’s cost on the ECO for Sound project. This project is officially complete and ready to be archived.

11/30/05 – After speaking with City Permit office they confirmed that TE did pay for these permits. TTC called Randy this morning and told him that these permits were paid for on 10/18/05. TTC is awaiting a call back to clear this up.

11/25/05 – Randy Campion called to inform TE that there is a remaining balance on these permits. TTC called the city to see what that cost was because TE has already paid for the new permits with a check. Once this is cleared up Randy will send new Certificates of Occupancy.

10/18/05 – All revisions have been accepted and approved by the City. New permits costs = $354.00. New occupancies have been set to 1021 (East Club) and 986 (West Club). According to Randy Campion once the permit is paid for, which TTC did today, the permit will close and information will be sent to Fire Dept. They will issue a new occupancy for private club events. to PBS.

09/28/05 – The City received all the information from Cole & Russell but need it properly inserted into the permit dwg sets. TTC will stop at the permit office and manually do this on Friday or earlier if possible.

09/20/05 – After the City sent the letter emailed by TTC to PBS yesterday requesting additional egress information, TTC talked to Cole & Russell about this information. C&R believes that they already have all that information collected from the sliding door project and will call Carl Graeber and discuss directly with him. They can get all that information to the City on Friday or early next week. TTC will check back with city and C&R about progress at that time. We believe the city will accept this and process the permit app immediately thereafter for final inspection.

09/08/05 – TTC contacted city. Permit should be reviewed by 09/13/05. TTC will check back at that time.

08/25/05 – The permit is still being reviewed by the City. TTC will continue to check on status.

0815/05 – TTC met Randy Campion at the PBS site on Monday, Randy approved the 821 and 851 increased occupant load and will sign the CO paperwork and send it to PBS. After the meeting, PBS said that the 30% OA was not a problem so that they want even higher occupant loads. TTC turned in another set of prints with the higher numbers of 986 and 1021. The city made us turn in for all new permits: 2005P06669 and 2005P06670.

07/18/05 – City called with Approved Permit numbers today. Permit was split up into 2 permits 2005P05544 AND 2005PO5589 ($284). TTC will pick-up permit on Tuesday morning. Inspector, Randy Campion has to come to the site to approve and give us a new CO for the space. This will be coordinate with HamCo & PBS in the next couple of weeks.

06/30/05 – TTC got GD to sign occupancy permit drawings in regards to HVAC OA requirements. TTC submitted for permit. Permit # 2005P05544. TTC informed all parties that permit can be checked at www.cincinnati-oh-gov at anytime. Amit was also promoted to Project Manager, so we are unclear if he will review this permit.

06/16/05 – Eric called today and TTC reported that Amit had returned one of his phone calls stating that he was seriously behind in permit reviews. With that knowledge, TTC stated that we should just go ahead and subject a revised CO application and talk to him them as opposed to conferencing in with him early.

06/06/05 – TTC sent an email outlining TE’s field findings to Joe, Sam and Eric. TE need direction from PBS to proceed on next level or work.

06/03/05 – Sam Boehringer of TE collected field data to update actual occupancies of the space.

05/25/05 – Eric Brown setup a meeting with the CFD department about occupancy requirements of the club level space.

PBS – Occupancy Redistribution Project Read More »

PBS – Deep Well Pump Replacement

03/23/06 – TTC spoke to John Wagner of Moody’s today and here is where the problem is: the actual repairs cost $15,573 not $6573, the 6573 +the 9000 already paid = the total cost of repairs on this job. This means that they are still giving you back $4427 on the job. John outlined this in a letter in September which I am having faxed to me. With this information, I will redo the paperwork and send it up to John for use on completing this project. I have to write a new change order, allowance usage and final pay application to make all the numbers work out right.

03/20/06 – TEI received final paperwork on this project today from Moody’s. This will be forwarded to Joe for payment on this project. TEI to begin phase II service contract immediately.

02/16/06 – Moody contacted TEI to request AIA forms. TTC sent them out in US mail for their use. They should complete these, notarize them and get them back for closeout.

02/06/06 – After an inquiry by Sam Kinman, TTC found the payapps sent to ThermalTech for approval. They were approved by Sam on 11/21/05. The problem is that they are not on AIA invoices which means there is no where for TTC approve. Assuming they are approved by TTC on these forms, the Contractor still has not turned in standard county documents for project closeout. TTC will forward a copy to Moody’s and ask for return of these documents. TTC completed a full packet of information required and mailed to Moody’s today via US Mail. TTC will follow up with a phone call today as well.

11/30/05 – Sam Kinman reported today in an email back to TTC that the deep well pump replacement job is complete. Since TE wasn’t used very much during construction, TTC assumes the punchlist is fine and no additional work needs to be done. TTC will archive the project from the database and closeout the project number. TE has never received a payment to approve, nor the final County paperwork to approve for that payment, nor manage any of the allowance monies. All this will need to be done before the project is closed out in the County’s books.

08/08/05 – TTC contacted the County about status of the Deep Well Pump Contracts. The previous entry does not state that the contracts were sent to PBS.

07/18/05 – Bid were opened. Moody was apparent low bidder at about $29,400. $20,000 in Alternates can be taken (ALT #1 and ALT #3). TE has contract written for $49,400 and will give 4 original copies to PBS for approval with Board. Bid PDF

07/05/05 – TTC worked on July 4 to get Addendum 2 complete and sent it out for distribution. PDF

06/27/05 – TE worked on Add01 and it will go out to the Contractors on 06/28/05. PDF

06/13/05 – TE sent out Project Manual for bidding. PDF

06/06/05 – Comments received from Sam and John Wagner of Moody in Dayton. TTC will update Project Manual and prepare for bidding ASAP. PBS talked about including a 3-year service contract on top of the bid. TE has done these in the past and can add this scope to the project if so directed by the County for bidding. This would be an engineering scope change to this project but it makes very good sense to include it now (12 hours x $80 = $960) and that includes the contract modifications for the Alternate bid to take optional years.

06/01/05 – Comment received from Joe and Eric. Nothing from Sam yet.

05/30/05 – TTC sent a project manual out for review over the weekend to PBS and County. Once comments are received, TE will distribute to public for bidding. All dates must still be coordinated with HamCo Purchasing.

05/26/05 – TTC contacted Moody’s for some specific questions about parts replacement. The Project Manual is built for front end. TTC needs to add dwgs and mechanical section. Bid Form needs to be modified for this job.

05/17/05 – The team had serious discussions about project schedule today. PBS re-iterated their concern about flooding. TE provided a timetable for construction that appeared not to be acceptable to PBS. TE had discussions with JF about project and will try to speed up project manual creation significantly to lessen risk. It is TE’s belief that County Purchasing has already decreed that this project does not meet Emergency Status.

PBS – Deep Well Pump Replacement Read More »

PBS – Pro Shop Metering Project

03/29/06 – TTC reviewed the billed KW and KWH to the PBS Pro Shop and the numbers looked good. The pro shop is using less than 1% of the total power consumed at the building.

KW KWH
February

50.91 21,863
January

34.91 28,950
December

79.91 25,448
November

59.28 16,077
October

72.30 14,661
September

63.67 16,528
August

53.30 4,166
02/01/06 – TTC check on the meters and to review monthly billings at the site. The meters appear to be reading in the Megawatts which seems really high at first glance. TTC to reconcile with actual building data.

11/16/05 – TA visited the site today. Reviewed punchlist and determined that Bond Electric has not completed the issues described on the punchlist. TE called Bond to tell that them that can’t get paid until these items and the final paperwork is complete.

11/15/05 – As-Built drawings for this job were turned over to Wayne Trent of HamCo Facilities today.

06/17/05 – Const Mtg was held at PBS. Sam did not attend. Equipment is not on site yet but Bond is ready to get to work as soon as it arrives.

02/28/05 – Purchasing called to inform TE that Bond does NOT have a performance bond or check submitted for this project. We should not let them begin work without this paperwork in place. TA to confer with Jack Boland today and emphasize the need for this check immediately.

02/10/05 – Contracts and Bid Results are in County’s hands. TE awaiting further direction on this project.

11/17/04 – Bid Results

10/12/04 – Project is out for bidding.

PBS – Pro Shop Metering Project Read More »

PBS – Deep Well Pump Service Contract

02/02/07 – After many contract revisions, phone calls and problems, the Prosecutor finally allowed preventative only maintenance contract that Kerry wrote and gave back to everyone to use. Other repairs and emergency repairs must be bid our as prevailing wages. TEI does not and will not every agree with this approach. We took prices for many other services to save the County money but those were not accepted as part of this job by Hamco Prosecutors office.

01/10/07 – TTC got Kerry’s new email address and forwarded the revised contract to her for any final changes that she would like to make. Kerry confirmed that the packet was received at her office.

01/08/07 – TTC hand delivered the final contract with Kerry’s marks to security for Jenny and Joe to pick up and resubmit to the Prosecutor’s Office.

12/26/06 – TTC will finalize the deep well pump contract this week.

03/29/06 – TEI has not heard from Daktronics with a registered service repair list yet so I called and got Greg’s email and sent him the request again.

03/21/06 – TEI finished the SOSS and will drop it off at the HamCo Facility Department on Wednesday for this project.

PBS – Deep Well Pump Service Contract Read More »

PBS – Energy Study

03/20/07 – Project ready to archive.

11/30/05 – TTC and GD have to meet internally to review the 10/11/05 findings and energy usage. GD believes there can be savings found in schedules and space control but we will need “buy in” from facility department to implement. TTC has to setup meeting with GD to review other items but County end of year crunch on projects has dampened progress. All work will be done by end of year.

10/11/05 – TTC and GD met on site and reviewed the whole facility with Sam, Joe, Eric and the financial manager.

05/10/05 – Kickoff meeting for project with JF, TTC.

PBS – Energy Study Read More »

PBS – Video Wall Replacement Project

12/19/07 – Nor Comm has provided the AIA closeout paperwork, warranty letter and payapps. TTC signed and City Dashed it to Joe Feldkamp. This project is complete.

09/03/07 – TTC has received and approved the O&M’s. TTC is hand delivering the box of O&M’s and final payapp to PBS tomorrow at 9am at the Deep Well Pump prebid.

08/28/07 – TTC contacted Nor-Com again about final payment via email with a Read Receipt.

08/20/07 – Nor-Com contacted Joe today about final payment. TTC emailed Joe back station what happened to Payapp #2 as listed below. To date, we have not received any additional paperwork.

07/02/07 – TTC has contacted Howard Milkis and Nor-Com several times for closeout on this project. No response to TEI. TTC will try to contact the office directly today and find out how we are going to close out this project.

05/14/07 – PBS did not use TEI service much at all on site during this project. TEI has been in contact with Joe and Scott numerous times during construction as things were going well. TEI contacted owner today for punchlist and closeout items for Nor Comm. As far as TEI knows, this project is complete.

03/30/07 – TE received submittals for review and promised to work on them this week. Nor-Com has a schedule forthcoming.

03/16/07 – Scott and Joe held a kickoff meeting. TTC to follow up and publish some const mtg notes this week. A second Const Mtg is to be scheduled. PBS would like TV in before draft day.

02/13/07 – All contracts and information is in the Prosecutors office for review. Comments have been added and the contract should be approved very soon. TEI provided a copy of the bid results to Kerry Dowling per her request last week. Joe Feldkamp is following up with the Prosecutor Office.

01/30/07 – TEI finished the revised contract and returned it to PBS for use on this project. Now TEI is waiting for approval and signatures to move into a pre construction meeting.

01/10/07 – TTC hand delivered the contract based on the Base Bid cost to Joe for submission to the Prosecutor’s office. TTC included a $2500 allowance in the project after the bids were opened.

12/26/06 – TTC will finalize the deep well pump contract this week.

PBS – Video Wall Replacement Project Read More »

PBS Video Switcher

10/26/09 – Final paperwork is received. TTC approved and mailed to Joe.

09/22/09 – Project is complete. We have approved payapp #2. Once all the closeout paperwork has been received and training is complete. We can close out this project.

08/25/09 – One payapp has been approved. Punchlist has started. Training continues.

07/29/09 – Project has been bid and awarded to Rosco. Work is proceeding and Chris Williams will be able to check in on progress on August 4th when he visits Cincinnati for the Brewers game.

06/23/09 – This project is in contract approval stage at HamCo.

PBS Video Switcher Read More »

PBS Z-Ramp Replacement

09/14/09 – Additional documentation has been sent to Kerry for contract approval.

08/25/09 – Joe needs additional bid information for the project. United needs to provide final bid paperwork to Joe.

0729/09 – Project has been bid. Prices were tabulated and sent to bidders. Final contract was $16,300 and included $500 in allowance monies. TEI has written the contract and given to the County for signing.

06/23/09 – This project is out for small project bidding.

PBS Z-Ramp Replacement Read More »

Parkhaus Garage Assessment

September 7, 2011 THP sent assessment report to County

THP anticipates completing the report by August 5.

July 25, 2011 THP completed all field survey.

Assessment placed on hold until Ram completes stair tower work.

THP anticipates field work in next two weeks and report to be complete by June 30.

April 26, 2011 SOSS approved.

County reviewing SOSS.

April 18, 2011 THP provided requested SOSS to complete garage assessment for the Parkha

Parkhaus Garage Assessment Read More »

Northside MR/DD Masonry Review

THP closed out project.

October 29, 2010 THP provided a summary letter of masonry work.

THP anticipates publishing a letter to GBBN documenting field condition on October 29, 2010.

October 14, 2010 THP notified GBBN that lintel repairs were not recommend and THP will follow-up with a letter documenting the field visit.

September 29, 2010 the County, GBBN and THP met to review the lintel condition of the west wall of the Northside MR/DD facility.

Northside MR/DD Masonry Review Read More »

DDS-Beckman Adult Center Change of Use Remediation Project

5/17/10- GBBN received final Structural Analysis for Beckman Change of Use Code Review.

5/25/10- Arcodect delivered final Code Review for implementation into Permit Set of Construction Documents.

5/26/10- Final Permit Set of Construction Documents printed, signed and stamped. Set to be hand delivered to TEI at the Partnering Meeting for issuance to the Hamilton County Planning Department.

6/4/10- Issuance of ITB#047-10 by Hamilton County Purchasing Department.

6/14/10- Attend Pre-bid Meeting at Beckman Adult Center.

6/15/10- Issuance of Addenda #1 with Pre-bid meeting minutes.

6/23/10- Bid question sent directly to GBBN. Bidder instructed to send question to Purchasing per the bidding documents.

7/1/10- Building Department Response Letter received from TEI with two items concerning occupany separations. Building Department requesting drawing showing Use Group separations, net/gross areas and occupancy locations on floor plan.

7/02/10- Responses for Building Department Response Letter received from Wayne Meyer at Arcodect.

7/19/10- Newly created Occupancy Summary Drawings for Building Department Response Letter delivered to TEI.

9/15/10- Construction meeting was held.

9/27/10- TEI announced the Plans Examination was completed and approved for Building Permit by Hamilton County.

1/27/11- TEI and Kevin Maue confirmed the permit is now closed on this project. The Certificate of Occupancy and the Colerain Township Fire Department Letter of Release have been obtained.

1/27/11- Kevin Maue indicated at the Partnering meeting this project can be archived.

DDS-Beckman Adult Center Change of Use Remediation Project Read More »

DDS-Beckman Adult Center Change of Use Code Investigation

3/19/10-Met with Jim Bowman, Colerain Fire Department, and Kevin Maue at Beckman Adult Center for walk-through on current renovation project.

3/20/10-Kevin Maue requested SOSS be submitted. This is first of two SOSS’s for this overall project.

3/21/10-Preliminary Code Investigation performed and submitted to Kevin Maue by email.

3/23/01-Fee proposal from Arcodect (code consultant) received. GBBN spoke to Cindy Rutherford, Hamilton County Building Department to discuss Change of Use requirements and submissions.

3/31/10-Schedule of submissions to Hamilton County Building Department submitted by email to Kevin Maue.

4/1/10-SOSS to be revised and re-submitted showing THP as a structural consultant to GBBN for any seismic implications per directions of Kevin Maue at Partnering Meeting.

4/7/10- GBBN met with Kevin maue, Terry Cannon (TEI) and Tom Frimming of Communale Fire Protection to review proposed AFSS implementation.

4/14/10- Signed SOSS without Ralph Linne’s signature and approval delivered by Kevin Maue to GBBN.

4/27/10- Signed SOSS with Ralph Linne’s signature and approval delivered by Bert Watts via email to GBBN.

4/27/10- Bryan Korb of GBBN assigned to project. Bryan to meet with Wayne Meyer code consultant at Beckman on Thursday and Friday for site investigation

4/29/10- GBBN to meet with owner, Colerain Fire Department, and Hamilton County Building Department to review building and change of use scope.

5/12/10- Kevin Maue announced ThermalTech Engineering would be the lead design professional on this project and GBBN would be the consultant. GBBN established estimated hours for completion to TEI for SOSS.

DDS-Beckman Adult Center Change of Use Code Investigation Read More »

DDS Signage Refacing

10/01/09 – Kevin Maue of MR/DD contacted GBBN about the pending name change as mandated by the State of Ohio. Sign letters on 1520 Madison to be removed as part of ceremony and will be handled as a purchase order. The signage refacing of all other sites will be on a SOSS through the Partnership contract.

10/05/09- ASI Modulex was approved to handle the purchase order work for 1520 Madison based on a submitted quote to MR/DD.

10/07/09-Existing electronic drawings sent to ASI for signage permit with City of Cincinnati.

10/23/09- Shop drawings for 1520 Madison approved for layout and lettering style.

10/30/09- Signage Refacing RFP sent to four selected bidders.

11/24/09- Adams Signs was selected for Signage Refacing and P.O. 536683 released.

12/08/09-1520 Madison sign permit approved. ASI
to order building sign letters.

1/04/10-Adams Signs re-submittal shop drawings approved.

2/19/10-Adams Signs has completed all installations. Kemper Meadow Road sign has bleed through of old signage.

2/22/10-Email sent to Rick Cain of Adams Signs about corrective measures at Kemper Meadow Road location.

2/25/10-Received signed SOSS from Bert Watts at monthly partnering meeting.

3/15/10-Resent email to Rick Cain with photos of Kemper Meadow. Rick claimed the corrections would be completed soon.

4/3/10- Email sent to Rick Cain of Adams Signs about corrective measures at Kemper Meadow Road location.

4/10/10- Rick Cain called to indicate Adams Signs very busy but will try and expedite completion of remediation measures to Meadow Road location.

5/19/10- Kevin Maue sent an email to Adams Signs indicating Application for Payment non-payment until corrective work is accomplished at Meadow Road location.

6/18/10- Notified Adams Signs to submit warranty information to comply with close-out documentation.

6/23/10- Sent Invoice from Adams Signs to Kevin Maue.

6/24/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

6/29/10- Rick Cain called to indicated work is commencing to author standard warranty details.

7/28/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

7/30/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

8/24/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

9/27/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

10/25/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

11/25/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

12/14/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment. Rick Cains email was returned as undeliverable.

DDS Signage Refacing Read More »

MRDD – THOMAS KIDD CLASSROOM ADDITION

02/14/08 – Punch list submitted.

02/13/08 – CRA sent additional service signed 2/13/08 to Bert

02/13/08 – TEI attended the const mtg today for MRDD. EDI is almost complete. Additional concrete will be installed around the new air handlers.

12/07/07 – CRA job meeting held on 12/05/07

11/14/07 – CRA received and approved shop drawings and substitution request for automatic door operators.

11/10/07 – The construction has commenced.

11/01/07 – Pre-construction meeting was held. See Meeting Minutes below.

10/26/07 – GC/EC submitted revised insurance certificate. GC/EC contracts have been approved approved. HVAC contract is still pending.

09/28/07 – Awaiting GC/EC to submit revised insurance certificate for final executed Contract.

08/16/07 – Contracts submitted 07/31, CRA received comments, re-issued 08/16.

08/02/07 – C+RA and TE submitted the Building Permit Application to the Village of Evendale Building Department.

06/25/07 – Addendum issued. Bids are due 07/02/07.

06/15/07 – A pre-bid meeting was held on location yesterday, June 14, 2007. This project is set to open for bid on June 26, 2007.

06/08/07 – This project has been sent to Cole & Russell for review. TE is awaiting comments back.

04/27/04 – Final review meeting is scheduled for next week.

04/20/07 – Updated drawings are being sent out today, April 20 2007.

04/13/07 – Project is progressing as expected.

04/06/07 – Preliminary set of drawings were sent to Architect today, April 6, 2007. Awaiting review comments.

03/30/07 – Final field work has been assessed. TE working on design.

03/23/07 – Project is progressing as expected.

03/20/07 – Kickoff meeting complete. Check CRA for updates.

MRDD – THOMAS KIDD CLASSROOM ADDITION Read More »

MRDD – JACKSON CENTER RENOVATION

02/15/08 – Add service CR-077a for $6,755.00 signed by MRDD on 2/12/08, forwarded to Bert Watts.

01/16/08 – Mtg held re additional service request my MRDD.

01/17/08 – Meeting held at site for scope definition. TJ and MAH attended. A few deletions and additions from original scope. ZZ ran meeting and will produce meeting notes. TJ and MAH will produce notes and forward to ZZ.

12/20/07 – Add service requested by MT

12/07/07 – CRA Told by MT that project will be from 2008 budget.

10/10/07 – Received signed SOSS.

09/06/07 – SOSS submitted.

05/18/07 – Kickoff meeting was held.

MRDD – JACKSON CENTER RENOVATION Read More »

MRDD – Franks Center Renovations

03/31/08 – Bids due 4/11/08

03/31/08 – Pre-bid meeting

03/21/08 – Addendum 1 issued

03/08/08 – Issued for bid

02/15/08 – CRA Add Service CR-084a $6,999.00 signed by MRDD on 2/12/08, forwarded to Bert Watts.

01/11/08 – SOCC CR-084a modified per WM email 1/11/08

12/20/07 – CRA add service requested by MT 12/20/07

11/09/07 – SD review meeting was held at Franks Adult Center. CRA presented Schematic Design drawings and color and finishes samples.

11/02/07 – Next review meeting is scheduled for 11/08/07 at Franks Adult Center at 3pm.

10/24/07 – Meeting was held at Franks Adult Center to discuss the scope of the project and verify existing conditions.

09/24/07 – CRA received signed and approved SOSS.

08/30/07 – CRA submitted the SOSS.

MRDD – Franks Center Renovations Read More »

MRDD – 1520 MADISON RD RENOVATION

08/29/08 – Triton is still working on warranty issues. Boiler control boards. Humidity issues. RCP problems.

02/25/08 – Triton and JCI have been working to remedy the remaining warranty issues on this project which include boiler flame outs, VAV box control, min airflows through VAV boxes, winter heating. TEI has to look at cold restrooms in the 1956 building for Kevin Maue.

12/17/07 – JCI and Triton had to go back to the site today to continue to work on DDC issues since the RTU-2 is still not running properly. Triton put the unit in had on Friday at 40%. TEI does not have an update on Monday from the troubleshooting field trip.

12/14/07 – TTC was on site today with JCI and Carrier going over warranty issues on the job including the LON talk interface between RTU-2 and DDC. Scott fixed the misnomers on the RTU-1 unit in the points list. Scott fixed the economizer program so RTU-1 would actually run in economizer mode when conditions were right (there was a programming glitch in the system) and he addressed the setback temperatures which are correct as programmed. Training will be schedule the second week of January 2008 with MRDD. There was a cold call in the lobby today from Wayne Mckee and Triton and JCI was dispatched to investigate the problems with the space. The hot water is 156F so there should be plenty of hot water available for the system.

12/04/07 – CDFP is scheduled the FM200 training directly with the MRDD folks and they will keep TTC in the loop. CDFP sent a change order in today for additional services on this project that TTC forwarded to ZZ for approval on this project for the extra sprinkler work, additional fan test.

11/28/07 – Jim Lape emailed to ask about closeout on this job. TEI stated that TJ should be 100% complete on this project. Triton is also done but we don’t have final closeout documents from them on this job. TTC is trying to get Grady to give us all closeout docs for this job.

10/17/07 – TTC visited the site and produced some more items for JCI and Triton to take care of on this job. He emailed pics and instructions to the contractors for completion. Everyone is working on completing all the work this week. Triton says the final balance reports are complete. TTC said today that he would adjust the manual high limit controllers to 210F and let the factory 190F shut the boilers down on auto reset. TTC also said he would caulk up the hole in the concrete hatch patch while he was on site. TTC will also check the installation of the electric heaters in the stairwell today while he is on site.

10/08/07 – TTC answered Jim Lape’s email about door control hardware. On drawing E400 #12 & #13 state that TJ will wire up the devices furnished & installed by the GC.

10/01/07 – TTC was on site last week performing commissioning. The control system was not ready to be back checked by TEI. JCI had not performed the functional test and TTC did not have the CX sheets. Nevertheless the system is running and with another week of actual work, it will be fine. TTC requested trend reports for verification of working systems.

09/19/07 – TTC approved JMW change order for roof drain and sent email to Jim, Zach and Kevin to that effect. TTC reviewed Triton invoice and asked for change order modifications before actual billing to the County. Change Orders were not reflected on actual payapp but they were on the schedule of values.

09/17/07 – Discussed Change Orders # 09,10,11 with Tim and Kevin Maue. I approved them as submitted. The steel issue is still are large issue that doesn’t appear close to resolution. TTC responded by email about controlling the pressure of the system by setting the static residual to 5 psig and letting the building set the pressure from there. If we have to change the relief valves to 65 psig from there, we can. The static of the building on the basement pumps should be 26.64 psig (50 ft bldg ht / .4328 ft h20/ psi + 5 psig to keep air out).

09/12/07 – Triton is on site checking the existing VAV boxes for repairs. They found one bad damper and believe 6 of the 7 boxes that are not operating properly. We are concerned that we have paid for some of this work already at the beginning of the job, but we will pay for the repairs to the dampers now and fix the electric heaters.

09/04/07 – JCI has given training but the controls are not complete and they still need some work. Boiler are not operational at this time and Denny Lammers is still need to program the internals of the boilers so JCI can communicate and give them their firings rates and monitor alarms. TTC dropped off TJ Williams hard copy as-builts drawings for the project that need to be included into the O&M’s that Kevin already has in his office.

08/23/07 – TEI printed out 2 more originals for Change Order #1, signed them, and sent them to T.J. Williams with instruction to sign them and forward them to HCFD.

08/17/07 – TEI received as-built drawings from TJ. Williams today. TEI will update the electronic drawings with the information and forward them back to CRA early next week. TTC delivered the O&M’s for EC, PC and FPC to Jim Lape at his office today.

08/16/07 – TTC and Cintas performed and passed the final server room fire alarm test on Wednesday. TTC has the paperwork in the folder and will include in the O&M. Triton said that the handrail was ordered and will be put back by Pat Murphy.

08/06/07 – TJ will do the security camera and emergency lighting change order work at T&M not to exceed but they will not come down in price. TTC sent this info to Jim Lape and approved on his end. TEI needs direction from the owner. TTC contacted MRDD about installing gaskets behind wall plates in server room.

08/02/07 – TTC talked to Kevin today about TJ outstanding issues at the MRDD. Security Camera change order and Emergency Lighting change order. JMW has O&M’s into TEI and they all closeout paperwork into Kevin Maue. TEI received TJ Williams closeout paperwork on this project as well. NV had TTC give to it to NR for approval.

07/23/07 – TTC spoke to Tim Myers today about project closeout, change orders, punchlist and controls. TTC discussed the allowance usage with Tim which totaled $13459 to date not including the refrigerant changeout which is a different cost. TTC emailed CRA about distributing the correct paperwork for change order pricing from Triton on this job and listed 6 items that need to be priced for this project.

1. Extra Diffuser for 1956 building. 17 in Qty. Linear Slots and 2×2’s to meet job requirements.
2. Refrigerant Check, Removal, Replacement on RTU-1. This work wasn’t included in the allowance cost but we authorized Triton to do the work on a separate ticket.
3. Overtime for IT closets and occupation over one weekend (i believe KM authorized triton to do this work)
4. Replacement cost for handrail? Triton removed it but someone else threw it in the garbage. Hobert is supposedly looking for it today but Triton will have to replace it if it can’t be found.
5. Demolition of all housekeeping pads in boiler room. This was Empire work but Triton had to do it all because Empire refused to do it. If Triton is going to pay the steel cost as a change order to Empire which I now believe they will after speaking with Tim Myers this morning, Empire either has to reimburse them this cost or deduct from the steel change order cost. Tim brought up a good point. A $2029 redesign fee is steep. That is 20 hours of a ThermalTech Principal time or 40 hours of a contractors time. It did not take that long. Redrawing that steel took about 6 to 8 hours. That fee should from the sub-contractor $500-$700. Please try to get them to give us a “real” cost and the housekeeping pad back charge could go away. As a side note, the new designed decreased the amount of steel and grating required, why are they paying an upcharge of $2522.97?
6. Replacement of 2 electric heaters. Provide 2 recessed ceiling heaters in the 1956 stairwell in lieu of the scheduled heaters. Return the surface mounted fin heater and the wall heater.
07/17/07 – TTC has scheduled a backcheck of the plumbing punchlist on Thursday. He will meet Jason on site for the walk through. Triton has committed to Approved Products being on site to finish the balance portion of the work starting on 07/23. TTC sent 2 sketches to CRA for plumbing ASI’s.

07/03/07 – The job is mostly complete aside from outstanding issues. The MRDD people are in and using the building. Items that we are still working on include: balancing HVAC & water, relocating a fp line out of the elevator shaft, final test of FM200, hot water boiler loop, controls, roof drain near unit, and punchlist by all contractors.

06/26/07 – All TEI punchlist were generated last Friday. TEI gave Jim Lape a complete set of extra materials required on this project to included in substantial completion for the project. TTC was onsite with JMW plumbing early Monday morning to discuss punchlist items which they are addressing. TTC spoke with Kevin about roof drain issue on 1956 building and we agreed that changing the scupper might be the best option. We can drain it down to the canopy roof.

06/15/07 – TE will be generating a punch list next week.

06/07/07 – RTU is still surging. we are trying to find out the status of the jci & carrier contractors. JMW plumbing will be on site on Friday to demo the 4″ plumbing vent from the elevator room. we believe fire protection is complete and ready for testing.

06/04/07 – Inspections are scheduled for Tuesday 06/05. MRDD personnel are moving equipment into the building today. ttc did not approve payapp #6 for triton and asked them to back down the % on the ground floor of the 1956 bldg to 90% and controls down a bit lower.

05/30/07 – TEI was on site on Tuesday for our weekly walk through. TEI contacted the vendors with questions, TCO milestones and coordination issues at the MRDD to help get it ready for the MRDD move on June 4. Items include ceiling layout, diffuser locations, ductwork insulation, EF flashing, fire protection work, elevator details, sump work, controls, etc.

05/21/07 – Triton reported that all fire dampers were completed over the weekend and that mason would be finishing up wall penetrations today and tomorrow. Kevin Maue seemed unimpressed with the quality of the work being done over the weekend and hopes they pass inspection. Tim, Terry and Kevin will walk the site on Tuesday AM to check progress and get commitments for completion.

05/17/07 – Triton will not be working this weekend but will have another crew on the MRDD job starting on Monday and they will have masonry sub helping with the patching of the duct shaft. The new RTU will not be ready to be ran this weekend.

05/14/07 – A lot has happened since my last entry. We have attended weekly const mtgs. We have attended several additional field trips for construction issues. The 1992 building has reached occupancy. The 2nd floor move was today. The 1992 RTU-1 unit is up and running but not under full control. The FM200 system is not fully tested yet even though the room is built. The 1956 building has ceiling grid in the entire building and now diffusers and fire protection piping is being installed.

04/17/07 – TTC and TA walked the project with all the contractors in lieu of a const mtg. The RTU is on the roof. The Server room is nearly complete. Cintas is working to complete the testing procedure and set it up for us. Shaft wall is offset form fire dampers. TE approved shifting the wall over to catch the sleeve of the fire dampers. The wall holes in the return shaft are open and Triton asked about filling them in (even the ones that weren’t done by them). TE directed Triton that they could sleeve the chimney with the boiler vents. The elevator room exhaust fan will reuse one of the openings that goes up to the chimney. A gooseneck may have to be added to the top of the chimney to keep the exhaust 10ft away from our unit intake.

04/13/07 – Project progressing as expected.

04/06/07 – Project progressing as expected.

03/30/07 – Project progressing as expected. Triton reported that the Liebert unit can’t be started today because of a breaker size issue (req 40A we have a 20A spec’d). TA resolved with TJ and Triton will have startup technician for unit after power is provided. TE received submittals today from JCI and GD has been looking them over all day. KM & TTC emailed Triton with acceptance on the retro-commissioning items on RTU-1.

Replace the Supply Fan Motor $3566.00 – APPROVED

Replace two bad compressor contactors $408.00 – APPROVED

Repair static pressure control for exhaust $2720.00 – APPROVED

Replace one bad condenser fan motor $1149.00 – APPROVED OR REPLACE WITH ALL 6 DEPENDING ON PRICE TBD

Perform leak check of Ref system, repair and replace refrigerant as needed $2339.00 – HOLD

Cleaning of coils and inside if unit including combing of coils as needed $1633.00 – APPROVED

Repair of Inlet Guide Vane and controls $3931.00 or replace same with VFD control $5108.00. – APPROVED BASED ON AVAILABILITY OF PARTS

03/23/07 – Lobby lights are on order and all issues with this item have been resolved. 480V electrical service has been changed over by Duke Energy, has been inspected and is up and running. 240V service to be removed the last week of March 07, tentatively.

03/20/07 – 02/19/07 – Last week the structural steel modifications began for the Carrier unit changes. Triton provided a dwg to SSA and CRA showing the new steel dims. SSA is sending back a proposal. The return duct shaft is open and must be sealed to provide proper airflow back into the unit. CRA is checking on some mold issues in that shaft from a roof leak. The FPC dwgs have been submitted to the city. The new FM is located and routed through an existing coredrills in the connector. TA release approval on change orders for TJ Williams for emergency lighting battery packs and dishwasher power in the 1992 building. Triton is still behind on the VAV boxes for the 1992 building and will have to work with Empire for ceiling pad out.

02/09/07 – TTC walked the site last Tuesday to check on progress. MEP is moving forward okay. Duct chase holes have not been cut yet. Triton is installing ductwork on the 1992 building

01/17/07 – Triton has coordinated with Empire on existing work. Kevin is worried that we don’t have enough written documentation that we told Triton to get this work coordinated and scheduled with the owner

01/15/07 – Somehow this job has not been tracked. Here’s the catch up data. The MC is Triton, the EC is TJ Williams, the PC JMW plumbing. We have had several job meetings. Triton has been poorly represented at these meetings. Last week after missing a rescheduled job meeting, Triton came on board with some initiative in catching up to the rest of the contractors. Triton has added more people to the job and is beginning new HVAC in the 92 building. Triton has demolished two floors of work in the 56 building. Triton has 2 men finishing the demo of the multi-zone unit and boilers in the basement of the 56 building. Triton has submitted an RFI questions who is cutting the holes in the shaft floor for his ductwork. TTC responded the GC and this was confirmed by CRA. The RFI was replied to but Empire responded they did not agree. The work is shown on the Demo and Arch dwgs for the GC and the summary of work says superstructure work is by the GC. The CWW has denied the underground permit and tap because the CGE pit is in the Right of Way of the street. TEI has negotiated with them and Cin-Day Fire Protection to provide the new line inside the building through the connector and throughout the building. This should save money and remove trenching and such in the yard. Kevin Maue has agreed that he likes this approach.

09/14/06 – Weekly design meetings continue. We reviewed cost estimates with the client and architect. Final estimates and drawings are due on September 25th for review and bidding is scheduled shortly thereafter.

MRDD – 1520 MADISON RD RENOVATION Read More »

MRDD Jackson Center Renovation

07/28/09 – Peck dropped off O&M’s today for this project. TEi will review them and give them to kevin for Closeout.

06/23/09 – This project is complete. I am not sure if Kevin has received all his closeout documents, please check and confirm at monthly meeting.

05/22/09 – We are closing out the project with TJ Williams next week. All work is complete and we are down to closeout documents. the Substantial completion for this project is Feb 20, 2009.

04/15/09 – CR Architecture + Design awaiting final punchlist items to be completed and closeout documents.

04/10/09 – Back punchlist issued.

03/09/09 – TTC sent out punchlist for Mechanical, Electrical and Plumbing and finalized Allowance & Change Order Payments with the punchlist so the contractors had everything they needed to close out the project.

02/19/09 – Project was punchlisted yesterday. Punchlist due at the end of the week.

02/02/09 – TTC continues to attend const mtgs for TEI. TTC drafted a letter to TJ Williams outlining the problems with the licensed door operator. The letter states that TJ Williams is responsible for hiring the licensed sub-contractor per the drawings and specs. We are however going to try to minimize the cost to TJ of this extra work that we believe they did not have in their original bid.

12/23/08 – Const Mtg 9 shows we are ahead of scheduled. TEI needs to address the sink in room 47, the trench drain, the curve sink is on site, the junction boxes need to be t&m by tj.

11/24/08 – Phase II is complete. TEI must do a Phase II punchlist. Peck requested a sheave change on HV-1 to get new airflow. TEI approved and sent to Kevin. TEI completed new allowance change orders for TJ Williams and sent them to John Parfitt for approval. TJ Williams revised payapp was received.

10/16/08 – Phase I is complete. Phase II has begun. Trenching for new sink was this week. No reports after TTC clarification was given. We are hoping things go well.

09/10/08 – TTC contacted Carrigan & Grimm about WC-4 for this project. MRDD wants light lens on warehouse lighting. Phase 2 is first. Phase 1 is second. All permits are approved.

08/25/08 – HVAC and Plumbing submittals are complete. TEI sent back to contractors. Building & HVAC permits are ready. $2,769.87 for the building permit $1,045.45 for the HVAC permit.

08/22/08 – TEI sent permit drawings to the project team. TEI sent out all HVAC submittals back to PHB.

08/08/08 – No update on approved IBI permit for this project.

07/29/08 – TTC hand delivered third revision contracts to KM at MRDD. We are awaiting project kickoff.

Bids came in acceptable. Pre Award meetings are complete. Contractors are approved.

MRDD Jackson Center Renovation Read More »

MRDD Due Diligence Report

09/21/09 – Kevin called with final comments on the final draft. TTC incorporated these and other comments into the final printing. TEI made 3 copies and mailed 2 of them to Kevin. Per Kevin’s request we will assemble the report into pdf format and email as well.

08/25/09 – Reports are due Sept 4 to Kevin Maue.

07/29/09 – All buildings have been visited. The reports are about 50% updated. Cost estimates, write-ups and grade cards remained to be inputted.

06/18/09 – TTC turned over the final Beckman report for Kevin to review. TTC spent a few days proving that the EH rate is the best rate for the County in these buildings. During this investigation, we found that several of the MRDD buildings are already on the EH rate but are also buying gas on the open market from a broker. TEI has visited Beckman, Northside and Franks so far and completed the field work. The Beckman report is complete. The Northside report is going to be sent to Kevin next. TTC will have Folck & Counts write up and estimate the Franks Adult Center report next week. Kevin said that we will be visiting the schools next. Try to get a date and time for Danny and Amy to do the next building.

MRDD Due Diligence Report Read More »

MRDD 1520 Madison Road Renovation

12/31/09 – There are minor control issues with the economizer in question but the building and controls are working as designed. TTC archived on 12/31/09.

10/20/09 – Kevin has JCI coming out to change return air humidity to zone average humidity on RTU-1 on Thursday. TTC may attend. Three items remain on the service punchlist. TTC contacted Brett to get answers about economizer control,

09/22/09 – I believe the final controls punchlist items to be complete is to acquire the software CD’s and backups of the current settings.

08/25/09 – Building is overcool in mornings. JCI is supposed to come out and fix timing and response loops. Many emails and phone calls have been made trying to get this done.

07/29/09 – Today we received updated As-Builts on the controls for the building from Chuck Vedder. I forwarded them to Kevin Maue for his keeping. I am also printing out a full set of 11×17’s to keep in the basement of the MRDD building again for our use. Everything seems to be running really really well.

06/23/09 – Triton, JCI and Carrier have finally been to the building enough to help us change the programming on the unit to get it to coordinate with the JCI system. This project may finally be finished. Things are working well in both buildings.

02/02/09 – Triton is reporting that Chuck Vetter will finalize this project for 1520 Madison. TTC contacted TJ Williams for the smoke detector work on the 1956 unit. TTC sent a summary email for controls to Brett at Triton for final completion items. The unit is finally running well but the building pressurization & the duct heaters are not working quite right yet.

10/16/08 – Grady says Triton will put together a final sequence that incorporate everything that is really working on the project and the way it works.

09/26/08 – Const Mtg 2 is over. TEI responded to TJ Williams RFi about another light in the hallway. TEI is approving the PHB Honeywell controller for the HVAC unit.

08/25/08 – Triton emailed today to discuss remaining closeout items. TTC explained about OA sensor.

08/22/08 – Triton is ordering a new board for Boiler 2. Triton relieved the pressure on the hot water system to prevent relief valve issues. Triton may have to get TJ to troubleshoot the overloading problem on the recirculation pumps. Kevin emailed that the OA sensor was flaky again.

07/29/08 – Brett Harpel of Triton discussed final control sequences with JCI. Modifications to system were made a month ago and again last week. Building is running fine. KM wants TEI to bless the control system as it meets design intent of the specs. JCI replied stating TEI sequences were in fact in place on RTU-2 but local overrides were keeping the system from operating as designed on that day.

Triton asked to switch the disconnects serving the RCP to troubleshoot low voltages problems at Boiler-2.

Triton to test expansion tank pressure to see if it is causing over pressurization.

MRDD 1520 Madison Road Renovation Read More »

Scroll to Top