PM = Matt Butz, Mike Barth
02/23/2022 – HCFD requests SOSS from TEI. TEI submits SOSS, and receives signed SOSS and PO. Project pending kickoff with HCRM and HCFD.
04/27/22 – Matt Butz and TEI meet with RM, and determine locations for adding the security cameras. Design documents are getting started now that Barth has returned from medical LOA. Will have review set for MButz upon his return form medical LOA.
05/26/22 – TEi and Matt to review the design documents for the camera locations. DK indicates that the materials are in inventory at their facility. TEI to certify equipment prior to approving the billing.
06/28/22 – HCFD, HCSO, HCRM and TEI meet with DK re status and DK provides tentative schedule. DK starts installation of cabling on the second floor.
07/27/22 – Installation continues with cabling and camera installation.
08/24/22 – Installation completed. TEI and Matt Butz perform punchlist. TEI issues punchlist to DK.
09/26/22 – HCFD issues DK change order for work associated access control on the second floor. Upon material procurement, and installation of access control equipment, TEI and HCFD will punchlist those items.
10/26/22 – Installation of access control pending procurement of materials.
12/15/22 – Installation of access control pending procurement of materials.
01/25/23 – Installation of access control pending procurement of materials.
02/23/23 – Installation of access control pending procurement of materials.
03/29/23 – DK indicates that the materials are in their shop and that the installation will be complete by 03/31/23.
04/27/23 – DK having issues with the double doors near the freight elevator. Working on solutions.
05/23/23 – DK having issues with the double doors near the freight elevator. Working on solutions.
06/28/23 – DK having issues with the double doors near the freight elevator. Working on solutions.
08/31/23 – Work is complete, ready to close out the project.
12/06/23 – Pending final closeout documents from DK.
01/30/24 – TEI waiting on warranty letter from DK.