Hamilton County Facilities

CH – Bronze Door Repair

PM: Matt

02/15/22 – Signed SOSS received.
03/31/22 – Field investigation completed. Preliminary drawings completed. We have been in contact with several historic door restoration companies.
04/28/22 – Drawings at 75% complete. Need to schedule a review meeting.
05/10/22 – Review meeting with Rycca. Determined more documentation per door is needed.
06/30/22 – Bid package to be finalized and submitted for final review.
07/28/22 – Additional site visit performed. detailed scope photographs added to drawing set.
08/24/22 – 95% check set sent to HC.
09/29/22 – Project out to Bid
10/27/22 – Olek won bid. West doors and Cleaning awarded. Contracts in progress.
12/15/22 – Contracts signed and returned. Kickoff meeting to be scheduled
01/26/23 – Call with Olek, County and Champlin to discuss details of kickoff meeting. kickoff meeting to be scheduled by end of February.
02/22/23 – Kickoff meeting to be scheduled in near future. Champlin has reached out to Olek twice for dates.
03/30/23 – Kickoff held on site. Preliminary schedule received. Olek to provide firm dates as we near demolition.
04/27/23 – Doors have been removed and sent to New Jersey for refurbishment.
05/25/23 – Doors have been taken apart and analyzed. Doors are in better shape than anticipated. Submittals to come soon.
06/29/23 – Photographs received. Work in progress.
07/27/23 – Restoration ongoing. restoration revealed that the door pulls were originally nickel plated. Change order to nickel plate the door pulls in progress.
08/31/23 – Olek to return to site 9/11. Test fit of closer complete.
09/28/23 – Olek cleaned existing bronze and prepped hardware installation. No crocs in sight.
10/25/23 – Construction ongoing. County requested pricing for additional bonze cleaning.
12/07/23 – Installation scheduled tentatively for march. Olek returned pricing for all items requested.
02/29/24 – Change orders approved. Several doors are complete. Still on schedule for late March Install.
03/28/24 – Doors to be installed first week of April. Site and prep work will continue into the following week.
04/25/24 – Doors to be installed in may. Firm dates to be determined.
05/30/24 – Olek is on site. Two doors are in. One Torchiere was blown over in a storm. Olek is shipping damaged parts to their shop.
06/27/24 – Work on site complete. Olek will need to come back for punchlist work. Matt ask Murphy to review final retainage payment submit.
08/29/24 – Olek needs to come back out to complete punchlist.
09/26/24 – No Update.
10/31/24 – Olek was back on site for the punch work. They did not complete the list and will need to come back.
12/12/24 – Olek came back for the back punch work but did not complete their work. They will be back for the punch and for a closer warranty issue.
01/30/24 – Olek still has punch work to complete. close outs to be submitted.
2/27/25 – Scott reached out to olek to request closeouts and a timeline for punch work. The closeouts are in progress. The punch work will be done in tandem with the first phase of the north and south doors.
03/27/25 – No Update.
04/24/25 – No Update.
05/29/25 – No Update.
06/26/25 – No Update.
10/30/25 – No Update.
12/11/25 – No Update.
01/28/26 – Olek to complete punch work when on site next.
02/26/26 – Olek onsite March 9th to finish punch work.
03/26/26 – Olek is onsite. Punch work is in progress.
04/30/26 – Work is complete. Closeouts nearly complete.
06/25/26 – No update.
07/30/26 – No update.
08/28/26 – No update.
09/24/26 – No update.