Hamilton County Facilities

CH – AHU-B4 Replacement

PM: Terry Cannon, John Nester
12/10/20 – SOSS submitted for approval.
12/28/20 – SOSS approved.
01/26/21 – Kickoff meeting scheduled for 2/2/21 at 9:00am with Jesse.
02/24/21 – Project setup and work underway. TTC and TAB to meet next week on Alternate work.
03/25/21 – HVAC design pretty much complete, TTC needs to review and share with the County for comment.
04/29/21 – Still need TTC review and then to JN for comments.
05/26/21 – Reviewed and back in for editing. Our plan is to have the mechanical and electrical sets in for County review by June 18, 2021.
06/18/21 – Review drawings submitted to owner for final review.
06/24/21 – AIA contracts sent to TTE for bidding purposes and calendar days set at 120 for this job.
07/21/21 – Ready for ITB request. TTC to create project manual and get ready for bidding next week. This project will be bid in August.
08/26/21 – Project will be finalized after JC HVEC goes out for bid.
10/28/21 – Project issued for bids and DeBra Kuempel is apparent low bid. Expectation is to award Base bid, plus Alternates #1 and #2. HCFD to confirm. TEI will schedule pre-award meeting week of 11/1.
12/13/21 – Bids were received and DK was the apparent low bidder.  TTE conducted a pre-award interview with DK and recommended them for the Work.  Contract and PO were submitted for approval and we await their return.  Submittals have been sent to TTE for approval.  The Trane unit submitted has an extra coil access panel that makes the unit longer.  we are going to approve this unit as it provides better maintenance of the unit and doesn’t affect access around the unit.  A pre-const mtg will be scheduled soon.
01/25/22 – Submittal returned for equipment order. Project is ready to begin.
02/24/22 – Controls discussion with Honeywell.
04/28/22 – Const Mtg next Tuesday for full kickoff and construction start.
05/25/22 – Const Mtg was held. DK putting together the final schedule but we don’t have good dates from Honeywell yet. For now, we are scheduling the AHU replacement over the weekend of 6/25. Controls submittal was received, marked up, and sent back to Honeywell but some statements in the sequences didn’t match actual conditions, waiting on revised control sequences.
06/30/22 – Shutdown is scheduled for 6/7,8,9 with County and DK. CH VAV box replacement scheduled the 7/12 at 8am for next phase.
07/27/22 – AH B-4 is up and running. Controls are being upgraded this week and next. Debra scheduled to begin Alternate Work the weekend of August 6.
08/16/22 – DK has made coredrill for new hot water reheat piping and made hot taps for connection to HTX-5 system. VAV boxes are being installed and Honeywell will be right behind them for control work.
08/17/22 – One set of hot taps not on an active line, TTE to investigate. TTC met with County and determined that this was correct, we showed one set of lines coming off the HTX-2 header. We will update the drawings and coordinate with DK on getting both lines fed from HTX-5.
09/22/22 – The unit is installed and working. The programming is not complete yet. The county is working on providing a new data drop near the B-4 unit for Honeywell to finish their programming. TTC met with Ameresco on the solar water heating components because we need the solar water heating to reheat for B-4 courtrooms.
10/26/22 – Honeywell programming and adding three extra VAV boxes on Monday, then the job will be done and ready to punchlist.
12/15/22 – All mechanical and electrical work is complete, and the unit is running. Honeywell scheduled last Friday to make their final programming changes have not gotten confirmation on if that work is complete.
01/24/23 – Honeywell was down last Friday to complete controls on this unit. The labor is complete.
02/22/23 – Honeywell worked on the controls two times and is currently troubleshooting an IT compatibility issues.
03/30/23 – Balance report sent to TTE for review. JN asked for updated PM’s.
04/26/23 – Unit is complete and in use. TTC requested training from Honeywell on new system. It is ready for punchlist.
05/21/23 – Work is complete, TTE ready to punchlist.
06/28/23 – Unit seems to be running well but I need to see the Courtrooms and check unit from front end.
07/26/23 – Punchlist scheduled for 7/27.
07/27/23 – Punchlist distributed to team members.
08/23/23 – No updates on closeout, DK checked earlier this month.
09/27/23 – Still not closed out, nor has DK confirmed punchlist work. We will check in with Dave again.
10/25/23 – DK contacted Randy for closeout documents yesterday. No payments sent until final closeout is completed.
12/06/23 – Trying to get DK to closed this job out. Need documents from contractor.
01/18/24 – The CHW line froze across the driveway. DK dispatched to fix the line and and added insulation and heat tape for future protection. Heat tape not hooked up but ready.
01/30/24 – DK has submitted the closeout documents for this project.
02/23/24 – TTE needs to get final closeout from Honeywell for this job.
03/22/24 – B-4 not on the Bacnet yet but running manually remotely.
04/24/24 – Can’t close out this project unit Honeywell gets the unit back on the front end and under Bacnet control.
04/25/24 – Give this work to Emcor and have them integrate B4 early in the HVAC Controls job. TTC to coordinate between the contractors.
05/28/24 – B-4 is back on graphics. Final closeout documents requested from DK. Some received, but we need the rest.
06/26/24 – Not completely closed out yet. TTC waiting on final documents from DK.
07/24/24 – Closeout documents still not received. TTE reached out to DK and Honeywell for final documents earlier this week.
08/28/24 – We have the G706 and G706A now. We are waiting on the Surety and Affidavits. TTE agreed to create the books, thumb drive and As-Builts.
09/24/24 – Project Closeouts paperwork received. TTC to markup final drawing for As-Built then this job can be closed. TTE has dedicated one person for closeout to help with getting these wrapped up. OK to add closeout time to SOSS.
10/31/24 – All closeout documents received except for as-built drawing that has to be updated by TEI now without the heat tape across the hallways.
12/12/24 – Everything submitted for closeout.
01/28/25 – Project ready to archive.