SPHQ – Furnace 1, 2, 3 Replacements

PM – John Nester, Terry Cannon
12/10/20 – SOSS submitted.
12/28/20 – SOSS approved.
01/11/21 – Fieldwork. ThermalTech & Ian.
01/25/21 – Verified furnace units new and old. Talked to Jackson about historical work at SPHQ and what “3” furnace replacement meant back then. He confirmed what we found on site last week. F-3 in the main SPHQ is new circa 2019. F-17 and F-18 are in the Academy and were installed in 2015, 2016. F-19 is in the Fitness area and was installed in 2004. Thse units may a newer condenser. TTE to verify this.
01/26/21 – Reached out to Ian to setup second field trip for TTE to take off HVAC for CAFM drawings and get information on the Property Barn unit so it can be replaced as part of this project.
02/24/21 – Fieldwork and CAD complete on existing Fitness center. Loads complete on all spaces. TTC to review work.
03/25/21 – HVAC design complete, TTC needs to review and share with the County.
04/29/21 – Marked up changes, awaiting CAD changes and TTC will send to JN for review.
05/26/21 – Talked to Ian and agreed that we need to do more fieldwork on the Property Barn before putting anything on paper for that Alternate. Base Bid and Alternates marked up and turned in for edits. I am waiting to get the electrical on board until the HVAC is complete. I am shooting to have this bid out this summer.
06/11/21 – We met on site and discussed basic scope and alternates with Ian and John. It was decided to demo the non-working Reznor unit and replace the three ceiling hung Reznor units on the back wall. Investigate expanding the ductwork in the property barn for additional comfort control as an alternate.
06/25/21 – MEP drawing mostly ready for county review except for the Alternate on the property barn. The Reznor units are obsolete but we found very similar replacement from our local rep. A cost and new venting was provided for our use in the Alternate design.
07/28/21 – Revised design into CAD for final markups. This will go out for bidding in August.
08/26/21 – TTC getting help to finish this project in the next couple fo weeks.
10/28/21 – Project released for bidding. Addendum #1 was issued on 10/27/21. Bids opening 11/08/21.
12/13/21 – Bids were received and Northern KY was the apparent low bidder.  A pre-award meeting was conducted by TTE and NKYHC was recommended for the work  The PO and Contract were approved in late November.  Submittals were sent to TTE and returned on Sunday 12/12 by TTC.  A pre const meeting is scheduled for 12/22 with the County and contractor.
01/25/22 – Revised scheduled sent to County from NKHC for work in February.
02/24/22 – Work is coming along nicely. New furnace is in, two new unit heaters are installed, RTU is on grade.
03/31/22 – Property Barn thermostat replaced and reprogrammed. Temperature swings still happening overnight but we think the unit heater is off. Ian to check for us.
04/28/22 – New thermostat seems to be working fine. Tony asked about heat in garage because door is being replaced and I told him all new units are installed and working. the old Reznor above the bathrooms is defunct and not being replaced. F-3 is complete and working.
05/25/22 – All work complete on the original scope. IBI permitting getting updated by Rick and Holstegge Electric. We are looking at change order work now with Ian and Rick.
06/30/22 – Electric rework is complete. Rick submitted revised change order for new Condensing Units and is fixing a bad fan on one now.
07/26/22 – Change Order #1 was approved and signed for the replacement of two condensing units. We solicited a change order bid for the full ALC control package which came in and was forwarded to the County for review.
08/09/22 – Sent Change Order #2 request to NKYHC for pricing.
08/23/22 – Checked back on CO progress for the condensing units and the reheat pricing. Controls pricing is already here.
09/22/22 – Submittals received from NKYHC. Payapps received and process for payment. Change Order for the condensing units and coils approved. Hot water reheat change order is but not officially approved yet. County working on PO increase for rest of work. Emcor provided reduced prices for remaining control work.
09/29/22 – Meeting on Monday to review change order work at SPHQ.
10/26/22 – Change Order 3 drawing ready for pricing. TTC coordinate with Rick. Permit drawings almost ready to give to rick for permitting on this job. We updated the floor plan to include the additional RHC locations and upsized the piping for the new work.
12/15/22 – Condensers are installed and ready. The initial refrigerant charge is on the new units. We have a controller question on on of the air handlers but both are wired up and running. Additional change orders are out for pricing. Emcor conversion of existing JCI field components came through this week.
01/24/23 – We have been working all week on getting the change order in placed and the submittal for the hot water coils approved. We are working on Rev-3 versions now. All change order #1 work is complete and inspections are approved.
02/22/23 – Revised RHC drawings sent to Rick and CAI for coil sizing and prices with new temperatures and CFM’s. Base bid and change order 1 work is complete.
03/30/23 – Working on repricing the CO#2 and CO#3 cost with Emcor and NKYHC. CO3 came in at $51,000 but ALC offered a $9000 credit for combined work.
04/17/23 – Controls submittals have been received. NM reviewed the RHC, TTC to do the rest.
04/26/23 – Change Order #3 approved for rest of RHC conversion and controls upgrades for the DDC system at SPHQ. The first batch of RHC are here. Check on start time with Rick.
05/21/23 – RHC are in. Piping is complete for all 15 RHC coils to valves . 7 valves are installed. TTE ready to punchlist first phase.
06/28/23 – Punchlist completed and sent to NKYHC. Requested update from Emcor on ALC progress. New compressors need controls update.
07/26/23 – Emcor upgrading controls, this work should be done in August.
08/23/23 – The project is nearly complete, only a couple of controllers are left.
09/27/23 – All work for this project is complete including HVAC, Electrical and Controls. However there are operational issues we are still addressing which include 1) HW pump did not appear to be pumping enough water, contacted vendor reset control sequence. 2) new condensing units did not have the right controller for dual circuit operation, but this is not fixed but led to question in #3. 3) one of the AHU has a VFD on it and NKYHC reset the speed of this fan in the summer for full load but now that it’s fall, they had to reset to fan to a slower speed. We are working on this to fix it for all seasons because it’s too cold in some areas. NKY working on final punchlist items.
10/25/23 – NKYHC is complete and finalizing punchlist. Emcor is complete but controls have not been commissioned. Boiler is going out on high limit. NKYHC has been working on reprogramming the unit with help from Lochinvar. We are meeting Friday to work out control issues with the pumps, boiler and new reheat coils. So far new the boiler had to be reprogrammed because ALC landed new controls on the boiler, a jumper had to be changed on one Admin VAV box, water had to be added to the HHW system. We will find out more on Friday.
12/06/23 – Project is complete and in final punchlist phases. We need to spend some time commissioning with Emcor to get the sequences worked out with them.
01/09/24 – This week we worked on AHU-2 gas heating furnace not working correctly. After several trips and replacements, the furnace is working but may not be working well all the time, the rollout switch was replaced with a non-automatic reset switch, creating more nuisance work for Ian. When the first floor heater is working the building work a lot better. The first floor boiler was not sized for full heating of the entire building, it is sized for heating on the second floor and some reheat on the first floor only. We must have the gas furnace working on the AHU-2 to heat the building in the winter.
01/31/24 – This project is complete and the final programming work moved to SPHQ BAS Recommissioning project.
02/23/24 – Closeout documents sent to NKYHC for use on closeout docs.
03/22/24 – Closeout documents AIA forms sent to County, we need the rest of the closeout paperwork, requested from Lisa today.
04/24/24 – NKYHC doing warranty work on AHU-1 and AHU-4 as part of this project. Emcor commissioning the dual circuit control for the new units. Closeout paperwork submitted to John Nester with a thumb drive. This project is ready to Archive.
05/28/24 – O&M manuals updated and complete, this project ready to archive.