Hamilton County Facilities

CH – Backflow Preventer Replacement

PM: Jesse Estes, Terry Cannon
04/18/23 – Request for SOSS to replace BFP at CH
05/05/23 – SOSS submitted.
06/21/23 – Fieldwork scheduled.
06/29/23 – We decided to bid this job Small Project given our previous experience with the JC BFP. Project submitted for final review to John.
07/26/23 – Final drawings being prepared, we will add two shutoff valves ahead of the BFP when they are replaced. We should be able to get this bid out within the next month.
08/29/23 – Project is ready for XBE. TTC to prepare for bidding.
09/27/23 – We are putting together front end documents together for this bid now.
10/25/23 – Addendum 1 ready to go out today. Bids are due 10/31.
12/06/23 – Bids received and vetted by ThermalTech. DK was the apparent low bidder and was recommend for award. Contract and PO approval stage.
01/17/24 – Additional paperwork requested by John Nester for this project.
01/24/24 – TTC contacted Bill Roach again for bid documents.
01/31/24 – Nothing received yet.
02/23/24 – Waiting on contract documents from DK.
03/22/24 – Contract under review.
04/24/24 – Contract signed by DK, County waiting on insurance from DK. Submittals were received and sent back for updates. The revised submittals were received today and sent back to the County and put back in the queue for TTE review.
05/28/24 – PO and Contract ready, setup kickoff meeting with DK and County.
06/26/24 – Pre Const held last week. DK has equipment in stock. We need to decide on a couple of valve questions before DK gets started.
07/01/24 – Pre Const meeting minutes distributed to the group. the BFP are in town and the work can be scheduled with HamCo on their schedule. No payapps or SOV has been received or approved yet.
08/28/24 – DK waiting on one more background check to clear and then they will schedule the work.
09/24/24 – Last DK worker did not make it through background checks. DK preparing to do the job with three workers. Bill setting up new schedule.
10/30/24 – Bill ready to do work in November, December time frame with three plumbers over two weekends. He will pick the weekend and give us a scheduled soon.
12/12/24 – The West BFP Replaced last week plus the two isolation valve above the city water booster pump. A small leak was discovered in the West BFP. GCWW does not know where the main city water shutoff is on the east side of the Courthouse so they are doing more fieldwork this week. DK will be after the holidays to do the next BFP. We received work from the city water inspector that the BFP clearances from the floor are acceptable.
01/28/25 – GCWW still searching for east side shutoff valve for east BFP. We are getting conflicting data about the exact location of the existing valve. Regardless it appears as thought GCWW would like to replace this valve when found. One valve found in the street apparently has bad packing, this valve would also be replaced. We will continue to coordinate and get updates from DK and keep the County up to date.
02/26/25 – Still waiting on GCWW to located and fix East Side main shutoff.
03/25/25 – HamCo provided updated from GCWW about locating and find the East shutoff valve for the building. As soon as that is located we will proceed with the next phase.
04/23/25 – GCWWW has scheduled multiple visits to fix or replace the Courthouse isolation valve for the East side of the building. As of this meeting, it is not complete. DK is checking in weekly with GCWW for updates. The DK change order has been submitted for the spool piece leak repair.
05/28/25 – DK meeting GCWW on site Friday to verify the new shutoff valve is holding. Then they will scheduled BFP replacement with County including the new spool piece.
06/01/25 – Will spoke with Justin at DK and have the following update to our never-ending waterworks saga. The isolation valve in the street has been replaced by GCWW. They haven’t patched the road yet so there’s no access to the valve without a backhoe to remove the road plate. DK will wait until the road is patched before performing work(expecting sometime this week or next week for that to take place). At the earliest, DK may replace the backflow preventer next Friday. They’ll be in touch to schedule the work.
06/25/25 – Second BFP replaced last Friday. Spool piece replaced at the same time. Everything seems to be working correctly.
07/28/25 – Both backflow preventers are replaced. TTE needs to do a final punchlist and verify final invoices before closeout.
08/26/25 – Punchlist complete and sent to Debra for signature and updates.
09/24/25 – Checking in with DK weekly for closeout and approvals.
10/29/25 – No closeout paperwork or additional communications from DK have been received. We reached back out for an update. Billy was out 10/6-10/10.
12/12/25 – Ready to Archive. Final documents being delivery to Jesse on 12/13.