PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/06/23 – Hamilton County approved the SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 3rd.
10/03/23 – THP completed rappelling and façade monitoring survey.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
06/24/24 – Email status of report and repairs to address both City issues.
06/27/24 – Budget sent to County for City repairs.
08/29/24 – THP working on repair package for City repairs.
12/10/24 – THP closing out the project.