Hamilton County Facilities

CH – HVAC Control System Replacement (081-22)

PM: Matt Butz, Terry Cannon, Will Fisher
Closeout: Joe Bulach, joe_bulach@emcorgroup.com, Dayna O’Brien, dobrien@davieseg.com


02/19/22 – ThermalTech submitted SOSS for the project.
03/04/22 – Met with Emcor on Ameresco pricing and scope exercise.
03/09/22 – Met with SBS on new technology and ALC interfacing capabilities
03/10/22 – TEI has created all the background drawings and base specifications for the project in the new CSI format.
03/11/22 – SOSS received and work begins. TTC setting up kickoff meeting on this project.
03/15/22 – Met with Honeywell onsite today and reviewed scope of Chiller controls and scope of this project in more detail. Two new corporate guys met us onsite and review past history and what they plan going forward.
03/22/22 – TTE met and review the action item list for bidding this out in 2022. We need to get background checks complete, BDS coming down tomorrow for BGC, Fisher has his badge, Constable BGC is complete and needs his badge. We’ve agreed to meet with Honeywell and JCI as the additional manufacturer’s for this project. We also want some time to sit with the con
03/23/22 – Started specs in new CSI format. Set up meeting with Honeywell for April 8 and JCI for April 11. We are trying to meet with Barth to review acceptable communication paths in the CH. We will schedule fieldwork soon.
03/31/22 – Meeting updated with JCI for 4/7. The badge process is started for 3 guys.
04/15/22 – Final controls meeting with vendors held this day. All said they can bid this job and meet the requirements.
04/28/22 – Project design schedules distributed. Fieldwork and design in April, May, June, July. Bidding in August, September. Award and contracts are October, November. Fieldwork started last Tuesday with Bracken and Matt. Basement, sub-basement, and roof equipment was verified.
05/25/22 – ThermalTech has been on the building finalizing equipment locations and needs for the last month. Our review drawings for all the equipment including VAV boxes will be out the County on June 3. We are also developing airflow diagrams for the control sequences based on our findings and Honeywell existing information. We are on schedule to bid in August.
06/30/22 – This month we finished up equipment takeoffs and sent them back to the County for review. Comments came back in a day and we have scheduled another field trip to check out additional equipment. JN asked for us to check our equipment against the archibus database, however, I cannot see the equipment database in archibus yet. Ask HC for help at meeting.
07/27/22 – A full equipment set of drawings was submitted to the County for review. TEI scheduling another field trip for final equipment information next week. We want to be on site with Randy so we can finalize sequences on standalone equipment and missing equipment in the sequences.
10/26/22 – Out for Bid. Prebid complete, Addendum 1 & 2 issued. Bid was extended to Nov 15. At least one more addendum before bid opening.
12/15/22 – Bids were opened on schedule and the apparent low bidder is Debra Kuempel. A full pre award meeting was held and the recommendation sent to the County for Base Bid and several Alternates for this job that were still under the published estimate. Project is moving forward, Emcor called for an update yesterday.
12/20/22 – County sent the contract to Emcor for signature.
01/24/23 – Contract was sent, not sure if the PO is back yet. Ready for kickoff.
01/30/23 – John checked back with Steve on contract status.
02/23/23 – Project is in front of the board for approval. DK putting together their project team and was instructed to run all communications through the County PM.
03/29/23 – All contracts are in place and we are ready to have pre-const kickoff meeting. TTC to schedule and reach out to ZH commissioning for their background checks.
04/25/23 – The Pre-Const meeting was help and Emcor was introduced to the project team. After the meeting, we walked one AHU and DK spent time on site surveying the existing building and equipment. We are in submittal and background check phases.
05/21/23 – It Meeting was help this month. DK putting together proposed network locations for our review. The County is working on ordering 7 network switches for the new Control VLAN inside the Courthouse.
06/28/23 – DK continues to work on background checks. Initial network switch location rejected, looking for new locations. TTC & MCB to suggest locations, then will give to DK to review, we may need additional network switches.
07/26/23 – Emcor still working on getting staff background checked for this job. Net network locations reviewed and sent to County for their review. We may potentially meet and go over them at Partner Meeting on Thursday. TTC invited IT and Telecom.
08/16/23 – Met with DK and have new prices for the fiber backbone change order. Steve Yockey sent them to TTC who will review and send to County.
09/27/23 – We are very close to finalizing the change order for the fiber infrastructure for this job. TTE will create a final room location drawing for DK after we receive comments from Jack, Steve and the County. Any issues with what is on the our change order markups for VE options? Controls Submittals have arrived for TTE review.
10/25/23 – Background and LEAD checks underway. DK working with JN. Network location finalized with County and Debra and Change Order #1 for network infrastructure sent to DK for signatures, we are accepting the Value Engineering proposal for this work. Controls submittals returned to DK Revise and Resubmit. We’ve incorporated ZH commissioning comments, WF, BDS and TTC comments into specifications. DK and TTE have coordination meeting on Thursday to review in details to ensure resubmittal is correct.
11/03/23 – Bi-Weekly Construction meetings begin. Emcor working on schedule. TE working on submittal review. Team working on network infrastructure. Jack can’t make Friday meetings until 2024.
11/17/24 – Const Meeting. Working on Background Checks and LEAD checks. Emcor low voltage working on cable runs.
12/01/23 – Const Meeting. Start working on deficiency report format, LEADS checks, low voltage routes.
12/15/23 – Const Meeting. Continue with Submittals work, background check and low voltage routes.
12/20/23 – Submittals returned for equipment and sequences. We still have a couple of outstanding items.
01/05/24 – Const Meeting. Work continues and is making progress.
01/19/24 – Const Meeting #6. Emcor and DK working on after hours progress, TE working on missing piece of equipment and getting ZH in Leads checks program.
01/26/24 – Deficiency List and Honeywell Scope meeting in Room 608.
02/23/24 – Const Mtgs continue. DK running new fiber continues. Deficiency list is begin worked and updated. Honeywell contacted for their portions. Emcor pricing up actuator replacements from deficiency report. Submittals are being updated, penthouse controls are being updated.
03/22/24 – Biweekly meetings continue. This month Honeywell got the chiller plant online, the secondary chilled water pumps VFD’s are online and working, Bacnet has been added to three of the four chillers. DK submitted change orders for four pneumatic upgrades to four units. TTE reached out to Honeywell for pricing on these same four units plus their deficiency list items. Emcor has many of the fibers ran to the server room, they need to repair the walls where they brought items into the room and finishing punching down the cabling. The DDC server is installed in the Rack.
04/24/24 – Next Const Mtg tomorrow is this Friday. Will is out this week and Bracken will cover the meeting. Emcor is being pushed to provide a best guess schedule. AH-52 has been submitted. TTE is reviewing sequences for the new equipment, we will have a design meeting with Emcor to go over sequences and make sure they can do what we have asked for in the Project Manual.
04/25/24 – Biweekly meetings continue. The fiber and CAT6 installation is scheduled to be finished by April 30th. The new network and front end are scheduled to be online during May and equipment changeover to the new controls system shall begin immediately afterwards. Emcor will begin with changing smaller equipment in the basement that is less disruptive to everyday operations. Emcor is beginning to work on replacing the approved pneumatic valve actuators that were deficient.
05/28/24 – Biweekly meetings continue. Low voltage wiring will be completed in the next 2 weeks, only the fourth floor remains incomplete. The new ALC controls database will be uploaded to the old server by Emcor this week. The database will then be transferred over to the new server once HAMCO brings the new server online. Emcor will be starting the first equipment change overs next week, once the database is uploaded. Emcor will begin with the smaller equipment in the basement that is less disruptive to everyday operations. CO#3 has been approved to add AHU-52 to the scope of the project, changing that unit to ALC controls. Emcor and ThermalTech have reviewed the controls sequences and are working to finalize the sequences.
06/24/24 – Biweekly meetings continue. Low voltage wiring on the fourth floor will be completed this week and the new network switch will be installed. Emcor has uploaded the new ALC controls database to the new server. Emcor has begun bringing materials to the site and are planning to begin work in the next 2 weeks to change over equipment in the basement. ThermalTech, Emcor, and ZH are working to finalize the controls sequences based on the latest comments provided by ThermalTech.
07/22/24 – Biweekly meetings continue. Emcor has begun to change over equipment in the basement to ALC controls. Emcors graphics department has begun work on the graphics for the front end. CO-01 is nearing completion, ThermalTech will be creating a punchlist to close out the work. Emcor and ZH Commissioning are coordinating to commission the equipment that’s been changed over. ThermalTech is coordinating a controls sequence meeting with ZH and Emcor. ThermalTech is also coordinating a deficiency list review meeting to close/address any open deficiency list items.
07/24/24 – Met with Dale and Ben today on sequences, they should be finalized before end of next week. Met with ZH commissioning today and ALC not ready with graphics for them to star CX, so we are pushing them back a week.
08/26/24 – Biweekly meetings continue. Emcor continues to change over equipment in the sub-basement and basement to ALC controls. Emcor has changed over the south central VAV’s on the first floor, further work on the first and second floor will begin in the next 2 weeks. Emcor continues to develop the graphics, expecting to complete them by the end of August. A preliminary BAS training took place this month to get Tyler Laws and his team familiar with the new system; another training will be scheduled once the graphics are complete. Commissioning by ZH Commissioning will take place once the graphics are completed. Controls sequences have been finalized by ThermalTech and Emcor, the sequence submittal is expected to be submitted by Emcor within August. Work for CO-01 is almost complete, Emcor will provide a punchlist and ThermalTech will verify it. The deficiency list is nearing completion, with a few items being addressed by HAMCO and a few items still to be investigated by Emcor.
09/23/24 – Biweekly meetings continue. Emcor continues to change over equipment in the basement and first floor to ALC controls and has begun work on the second floor. Emcor continues to develop graphics with an expected completion at the end of October. A BAS training session will take place on October 1st to review the graphics in more detail with Tyler Laws and his team. Commissioning by ZH Commissioning has begun starting with the basement equipment. The fiber and CAT6 installation is nearly complete; Emcor has turned over a punchlist that ThermalTech has started to review. The deficiency list is nearing completion with a few items being addressed by HamCo and some items requiring Honeywell assistance.
10/28/24 – Biweekly meetings continue. Emcor continues to change over equipment on the second and third floors to ALC controls. Emcor continues to develop graphics with an expected completion at the end of October. A BAS training session has taken place on October 1st to review the graphics in more detail with Tyler Laws and his team. Commissioning by ZH Commissioning is ongoing and currently focused on the basement equipment. The fiber and CAT6 installation are complete. Once the record network submittal drawings are received, ThermalTech and HAMCO will review and walk down the punch list items. The deficiency list is nearing completion with the last few items being addressed by HAMCO once the steam system is turned on for the winter.
10/29/24 – ThermalTech scheduling change order review meeting with HamCo. We need to work out some scope issues on the drawings vs reality of what is in the space.
12/12/24 – Emcor is mostly complete with the basement and moving up through the building to floors 1 thru 4 as well. They are onsite every day and working towards the April deadline. ZH commissioning has started creating an CX list that Emcor will have to help correct the CX issues as we move forward and complete the work. VPN seems to be working.
12/23/24 – Biweekly meetings continue. Emcor has completed all changeovers on the second floor and third floor. Emcor continues to change over equipment on the fourth and fifth floors to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement, basement, and first floor. Emcor has a few small items to update in the BAS per HAMCO preference. Commissioning by ZH Commissioning is ongoing and currently focused on the first and second floor equipment. The fiber and CAT6 installation are complete. Record network drawings have been received from Emcor. ThermalTech and HAMCO will review and walk down any network related punch list items. The deficiency list will be checked again in January, no deficiencies have been checked on in December. Change order #2 work for AHU-21, AHU-22, OAHU-1, and AHU-B2 has begun. All of the AHU’s mentioned previously have new valves installed per CO#2, only the damper work remains to be completed.
01/27/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, and third floor. Emcor continues to change over equipment on the fourth and fifth floors to ALC controls; these floors should be completed in January. Emcor will begin the sixth floor in early February. There is a small amount of equipment left to be changed over in the sub-basement and basement. Commissioning by ZH Commissioning is ongoing and currently focused on the first and second floor equipment. Most equipment in the basement that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network related punch list items. The few remaining items on the deficiency list should be closed out in February. Change order #2 damper actuator replacement work for AHU-21, AHU-22, OAHU-1, and AHU-B2 should be completed in January, closing out CO#2 work. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 82, 85) have been changed over.
02/24/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, and fourth floor. Emcor continues to change over equipment on the fifth and sixth floors to ALC controls. The fifth floor should be completed in February. There is a small amount of equipment left to be changed over in the sub-basement and basement. Chiller plant changeover will begin in February. Commissioning by ZH Commissioning is ongoing and currently focused on the third and fourth floor equipment. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network related punch list items. The one remaining item on the deficiency list should be closed out in February. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going and should be completed in February, closing out CO#2 work. AHU-52 has been changed over, closing out CO#3. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 82, 85) have been changed over.
03/24/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to change over equipment on the sixth floor as well as wrapping up the equipment in the basement and beginning on the chilled water system and large AHU’s. AHU-82 is the first large AHU that has been changed over to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement and basement. Chiller plant changeover is on-going. Commissioning by ZH Commissioning is ongoing and currently focused on the third and fourth floor equipment. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going. AHU-52 has been changed over, closing out CO#3. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 85) have been changed over. March will focus on the large systems in the courthouse, the chilled water system and the remaining large AHU’s.
04/23/25 – Work is progressing with about about 84% of the project complete. Emcor has asked for a two month extension for completion. ZH is following behind Emcor and catching up on commissioning. The County has some decent request for front end modifications that Emcor needs to work through. The large AHU’s are being converted now. The Chilled Water plant is current under integration and Emcor has been asked to provide a boiler plant integration cost outside of the scope of this project (see TTC & AKM).
04/28/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to work on the sixth floor, seventh floor, and the chilled water system. All large AHU’s (AHU-68, 75, 82,85) have been changed over to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement and basement (Pending deficiency item repairs). Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning will be next. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going. A schedule extension change order is in progress. May will focus on completing changeover of the remaining items and resolving any commissioning deficiencies identified by ZH Commissioning.
05/27/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to work on the few remaining items and the chilled water system. The following are the remaining items to be changed to ALC controls for the project: Chilled water system, AHU-B, AHU-B16, EF-71, and misc. (4) condensing units. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HAMCO and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is on-going. Change order #4 is closed. Change order #5 has been signed, extending the schedule to June 13 and adding in the changeover of FCU-8 and AHU-B to full ALC controls. June will focus on completing changeover of the remaining items and resolving any commissioning deficiencies identified by ZH Commissioning.
05/28/25 – Emcor did not submit a payapp for January. Payapps 12, 13 and 14 are wrong. We are working on corrections. We received corrected copies of 13 & 14 today but 12 is still wrong.
06/23/25 – Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. Emcor has completed all changeovers except for the chilled water system and (4) misc. condensing units, which are on-going. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HamCo and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network (CO#1) related punch list items. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is on-going. Emcor is back checking all of their work, currently expecting to be done and ready for ThermalTech to punchlist on August 1. Basement, first, and second floors are largely complete and functioning correctly. HamCo is coordinating directly with Emcor to resolve any issues that are identified in the day to day building operations. July will focus on checking all equipment and resolving any commissioning deficiencies identified by ZH Commissioning to prepare for August 1 punchlist.
07/25/25 – Const Mtg held with HamCo, TTE, and Emcor. ZH not present.
07/28/25 – Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. Emcor has completed all changeovers except for (4) misc. condensing units in the basement, which are on-going. The chilled water plant is now changed over and running in automatic mode. Emcor is focusing the majority of their time back-checking the commissioning items found by ZH and resolving any issues with the large AHU’s (85R has some pressure sensor issues being worked on). All change order work is completed. CO#6 is being drafted to give credit to HAMCO for systems that have been removed from scope and to extend the schedule. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is completed. State contract work is on-going for misc. repairs. Commissioning by ZH is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HAMCO and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network (CO#1) related punch list items. Emcor is back checking all of their work, revised date for ThermalTech to begin punchlist is now August 15. Basement, first, and second floors are largely complete and functioning correctly. HAMCO is coordinating directly with Emcor to resolve any issues that are identified in the day to day building operations. County wants to make sure that DK is doing the t-stat touch up plates. Make sure the County knows when.
08/25/25 – The project has entered the punchlist phase. Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. The chilled water plant is continuing to run in automatic mode. Emcor is focusing the majority of their time backchecking the commissioning items found by ZH and resolving any issues with the large AHU’s. All change order work is completed. CO#6 is being drafted to give credit to HamCo for systems that have been removed from scope and to extend the schedule. State contract work is on-going for misc. repairs. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HC and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network (CO#1) related punch list items. Punchlist walk with ThermalTech and HC is scheduled for early September.
08/26/25 – We are having a hard time narrowing down the graphics for the generators in the Courthouse. EGEN is the emergency generator in the basement. GEN-1 is the standby generator on the platform.
09/22/25 – The project is in the punchlist phase. Punchlist was developed during a one-day site walk with HAMCO and ThermalTech. Draft punchlist was supplied to Emcor, punchlist will be submitted to Emcor as final once ZH’s commissioning is completed. Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. The chilled water plant is continuing to run in automatic mode. Emcor is focusing on completing items on the punchlist or checking the commissioning items found by ZH and resolving any issues. All change order work is completed. State contract work is on-going for misc. repairs. Commissioning by ZH Commissioning is nearing completion. All equipment (except for heating equipment) has been commissioned. ZH has commissioned the chilled water plant. ZH is coordinating with HamCo and Emcor to resolve any issues found. The Punchlist has been issued, and we are ready to enter the closeout documents phase.
10/29/25 – The second training session was held earlier this month with the operators. I think it started our rough but was better received by the end of Training. More use will make the end user more comfortable with the new product. The Project punchlist still being completed. ZH Commissioning has a few days left to complete their work on the deficiency list for this project. We found that the free cooling HTX was not on the graphics yet, DK fixed yesterday and the heating plant is not working correctly yet, DK to assist Tyler in making this right.
12/12/25 – Functional testing deficiencies list meeting held today to review progress from Dec 3-5. Some items complete, many are not. DK needs to devote resources and technician to site to complete the CX work. DEG will have to setup owner internal review meeting later this week to review our outstanding resolution items. TTC pushing for 02/28/26 drop dead date for all the outstanding work, requested basic progress scheduled for DK too address final items.
12/22/25 – Punchlist completion is on-going. Site visits in December discovered that there are numerous open items on the resolution tracking form to be resolved. Resolution tracking form items are planned to be resolved by the end of February. HAMCO has given a PO to Emcor to replace HX-1 and HX-3 steam valves to DDC on state contract terms. Weekly meetings have been scheduled to check on the progress of the resolution tracking form items.
12/23/25 – HTX-4 Meeting scheduled for Jan 7 with County, DK and Davies.
01/25/26 – Emcor and DK making good progress, we are hopeful that this project will complete by the end of February. Ethan making good progress knocking out all final items and coordinating with HamCo and ZH Commissioning. VPN access requested for Will Fisher, Anthony said they will send him application. Smell and temperature on sixth floor better but not gone all the way that I know of. Weekly meeting continue with DEG, Emcor, DK and Facilities.
02/25/26 – Weekly Const meetings continue. Emcor has completed the TE punchlist and ZH resolution tracker except for the chiller plant which they are working on this and next week. The HTX will be taken apart and tested in March or April. TTC reached out to Emcor for a full PW download directory as requested.
03/25/26 – Emcor working on Chiller and Cooling tower plant controls. Emcor commissioning ready to start as soon as chillers are started. DEG and ZH met on commissioning deficiencies. DEG issued Punchlist #2, ZH working on revised resolution tracker worksheet. We are scheduled to inspect the HTX next month.
04/20/26 – Emcor, DEG and ZH reported for final commissioning and worked through the final punchlist and functional testing markups this week.
04/28/26 – Checked in with Tyler and everything seems to be working well.
04/29/26 – Tyler reported this morning at the cooling tower overflowed with water this morning and the penthouse was flooded. Investigation showed that some equipment was commanded off and a second condenser water pump started causing the overflow condition. DEG asked Emcor for an additional logic step to prevent this from happening in the future. Emcor also asked that equipment be release to operated in automatic mode so this does not happen.
05/27/26 – All punchlist and resolution tracker work is reported as complete. DEG requested closeout documents from Emcor for project closeout.
06/25/26 – Project in closeout.
07/30/26 – Working on closeout documents. Emcor collecting OM’s and paperwork. We check back every Friday.
08/26/26 – Almost all closeout documents received including releases. We are working on full closeout.
09/23/26 – After months of work, coordination, and emailing Emcor, we have the final closeout documents and TTC will hand delivery to Ted and Mat ton 9/24. We have requested final payapp for processing.
10/26/26 – Project is in Closeout.

Scroll to Top