Hamilton County Facilities

OMJ Accessibility Entrance Study

02/08/22 – Signed SOSS Received. Scope reduced to exterior entrance only.

03/31/22 – Field verification complete. Plan and estimate in progress.

04/28/22 – Work in progress.

5/26/22 – Civil Engineer to provide Champlin with drawings end of day friday 5/27. Final set can be ready to review the following week.

6/30/22 – Bid set and project manual submitted to County for final release.

07/28/22 – One bid came in above 50,000. Bid review to be completed to determine ITB advertised estimate.

08/23/22 – Project out to bid. Pre-bid meeting scheduled for 8/31.

09/27/22 – Bid awarded to Prus. Contracts in progress.

10/27/22 – Pre-construction meeting scheduled for 11/4

12/15/22 – Construction complete.  Punchlist by county and champlin complete. Punchlist by Kleingers to be scheduled.

01/26/22 – Punchlist sent to Prus. They are to fix items that need correcting and confirm slope conforms to code requirements.

02/22/23 – Punchlist completed. Waiting on closeout documents.

03/30/23 – Waiting on closeout documents.

04/27/23 – Close out documents received.

05/25/23 – Waiting on Prus to send final pay app.

06/29/23 – Close outs and final pay app received.