02/08/22 – Signed SOSS Received. Scope reduced to exterior entrance only.
03/31/22 – Field verification complete. Plan and estimate in progress.
04/28/22 – Work in progress.
5/26/22 – Civil Engineer to provide Champlin with drawings end of day friday 5/27. Final set can be ready to review the following week.
6/30/22 – Bid set and project manual submitted to County for final release.
07/28/22 – One bid came in above 50,000. Bid review to be completed to determine ITB advertised estimate.
08/23/22 – Project out to bid. Pre-bid meeting scheduled for 8/31.
09/27/22 – Bid awarded to Prus. Contracts in progress.
10/27/22 – Pre-construction meeting scheduled for 11/4
12/15/22 – Construction complete. Punchlist by county and champlin complete. Punchlist by Kleingers to be scheduled.
01/26/22 – Punchlist sent to Prus. They are to fix items that need correcting and confirm slope conforms to code requirements.
02/22/23 – Punchlist completed. Waiting on closeout documents.
03/30/23 – Waiting on closeout documents.
04/27/23 – Close out documents received.
05/25/23 – Waiting on Prus to send final pay app.
06/29/23 – Close outs and final pay app received.