PM: Matt Butz, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to review scope of work and locations for equipment. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – project pending Historical society review of proposed mounting hardware and installation by DK.
12/11/24 – Historical Society approves installation. Project pending installation by DK.
01/29/25 – Project installation nearly complete. DK states that there is an Injector issue to resolve and project will be ready for punchlist.
02/26/25 – Project complete pending closeout.
03/26/25 – HCFD and TEI perform and issue punch list. Project pending closeout.
04/23/25 – Project pending closeout docs from DK.
05/28/25 – Pending closeout documents.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.