PM: Matt Butz, Mike Barth
04/24/24 – TEI receives signed SOSS ands PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – Cameras installed last week. TEI and HCFD to schedule punchlist and review of camera views on the system.
10/30/24 – Project completion pending punchlist and closeout documents.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.