PM: Matt Butz, Mike Barth
04/24/24 – TEI receives approved SOSS and PO. Kick off meeting occurred on site on 04/23/24.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – Project issued for small, projects bid. Prebid meeting occurred. Addendum #1 to be issued by 07/26/24.
08/28/24 – Bids received on project (2 bids Glenwood and DK), DK apparent low bidder. TEI vets the bid from DK.
09/25/24 – Project in contract phase.
10/30/24 – HCFD, HCSO, HCRM, TEI and contractor meet for pre-construction meeting. Anticipated construction to start 11/11/24
12/11/24 – DK states that the installation of the system in the JAX area is approx 90% complete.
02/26/25 – Project complete pending punchlist and closeout.
03/26/25 – HCFD and TEI perform and issue punch list. Pending closeout.
04/23/25 – Project pending closeout.
05/28/25 – Project pending closeout.
07/31/25 – OK to Archive, send final bill.