PM: John Nester, Mike Barth
05/29/24 – HCFD requests SOSS from TEI on 5/29/24.
06/26/24 – TEI submits SOSS. Project pending SOSS approval and PO.
07/24/24 – TEI receives signed SOSS and PO. Study in development in conjunction with the JC Study.
08/28/24 – TEI meets with vendors to discuss industry trends and current offerings. Report in development.
09/25/24 – TEI finalizing report to send to HCFD for review.
10/30/24 – TEI submits report for review and comments from HCFD.
12/11/24 – HCFD and TEI meet with HCSO to review draft report. Final report to be submitted.
01/29/25 – Final report to be submitted with the JC report. JC report pending 1 item.
02/26/25 – TEI sends final report. HCFD sends additional final comments. TEI to incorporate and resubmit final report.
04/23/25 – TEI receives budgetary numbers from suppliers for additional features. TEI finalizing report and to submit draft.
05/28/25 – TEI Submits finalized reports to HCFD.
06/25/25 – TEI submits final report. HCFD requests cost for engineering (not an official SOSS at this time)
07/30/25 – DEG submits estimated SOSS cost to HCFD for review.
08/27/25 – No updates. County has all closeout documents. Ready to Archive. Put study into Archive Room.