PM: John Nester, Mike Barth
05/29/24 – TEI submits SOSS for approval. Project pending PO and Signed SOSS.
06/26/24 – TEI receives approved SOSS and PO. Documents in Process. Trades will be doing this work, TE to send final dwgs in for review. It will permitted through City of Blue Ash.
07/24/24 – TEI sends drawings to HCFD for review.
08/28/24 – TEI obtains permit from Blue Ash. TEI delivers permit and approved drawings to Keith Otis. Electricians state that material procurement stage – once materials arrive – will get installed.
09/25/24 – HamCo Trades Electricians to notify TEI when they are ready for inspections.
10/30/24 – TEI coordinates breaker types with trades. TEI to arrange inspections when notified by trades.
12/11/24 – Inspections pending call from trades re completed installation.
01/29/25 – Inspections pending call from trades re completed installation.
02/26/25 – Trades calls TEI and are ready for inspections. TEI to schedule with trades and Blue Ash.
09/24/25 – DEG and trades meet with blue ash and has approved inspection. Blue ash did not have records for final inspections for re-circuiting work. that inspection is scheduled for 10/01
10/29/25 – Revised documents in plan review stage.
12/10/25 – Permit applied for – pending approval for final inspection.
01/28/26 – DEG follow up with the City of Blue Ash.
02/25/26 – DEG and trades gets final inspections. All inspections and work passed with City of Blue Ash. Project complete.
02/26/26 – Give County as-built drawings and archive the project.