PM: Eryn Thamann, John Nester, Jesse Estes
08/27/24 – SOSS approved. JN to send new drape/blind info for review prior to scheduling site visit.
09/24/24 – JN to send info and meeting invite to review mock up.
10/30/24 – Elevar met with Court Admin to review mockups. Drawings started for SD.
12/09/24 – SD review meeting with HCFD/Court Admin scheduled for next week.
01/29/25 – Met with Court Admin and revised drawings based on meeting. SD review package is nearly ready for HCFD final review.
02/26/25 – Drawing package submitted to HCFD for final review.
03/26/25 – No update.
04/24/25 – No update.
05/28/25 – No update.
06/26/25 – No update.
07/31/05 – Elevar to research historic requirements for elevations.
08/28/25 – No historic restrictions on interior window treatments and confirmation sent to HC.
09/25/25 – No update.
10/30/25 – No update.
12/11/25 – No update.
01/29/26 – Archive?