Hamilton County Facilities

Elevar

230 – 11th Flr Training Rm Acoustics

PM: Rycca, Eryn
04/30/26 – SOSS to be submitted shortly.
05/28/26 – SOSS submitted.
06/25/26 – Acoustic testing occurred 06/19. Consultant will provide design recommendations based on report.
07/30/26 – Report provided by testing consultant to HCFD. Elevar to research other panel providers and will provide report in layman’s terms.
08/27/26 – Report and design options provided. Consultant working on final design images based on actual photos of the space.
09/24/26 – Rendering photo and samples provided to COA.
10/29/26 -Costs provided to COA.

230 – 11th Flr Training Rm Acoustics Read More »

111 – Employee Break Shelter (No ITB)

PM: Rycca, Eryn
eeagle@elevar.com;

04/30/26 – SOSS provided for CA.
05/28/26 – Awarded to Tumlin and Elevar receiving initial Div 01 submittals.
06/25/26 – No update.
07/30/26 – Submittals complete and unit moved into production planning. Contractor will provide stamped drawings soon.
08/27/26 – Contractor will provide stamped drawings soon with Elevar to follow up. Anticipated unit installation in Oct.
09/24/26 – Contractor provided stamped drawings. Anticipated unit installation in early Oct. Elevar/HCFD/GC to meet onsite prior to installation.
10/29/26 – Unit installed. Need closeout docs from GC.

111 – Employee Break Shelter (No ITB) Read More »

230 – Lobby Security Upgrades

PM: Rycca Thacker, Eryn Thamann
02/26/26: Added as new project. Need meeting with COA/Probate/HCFD to review scope.
03/26/26: SOSS provided for concepts/SD phase.
04/30/26 – No update.
05/28/26 – Will wrap into elevator project. Elevar to provide new SOSS and will work on design options.
06/25/26 – SOSSs in process for approval with HCFD now.
07/30/26 – Concepts reviewed at initial meeting and working thru final concept now. Will review with HCFD prior to scheduling full group meeting. 230 Court Admins wanted this work to be completed faster than if combined into 230 Lobby Security project.
08/27/26 – A third option for the rear secure elevator area was discussed with Rycca and will be provided this week. Another meeting with the main group will then be scheduled. Exterior Lighting portion broken back out to separate project.
09/24/26 – A third option was provided to the entire group and another meeting was held. Another revision was sent to entire group for input and potential third meeting.
10/29/26 – Another mtg was just held and option 7 is under design.

230 – Lobby Security Upgrades Read More »

All Buildings – Space Allocation Drawings

PM: Rycca Thacker, Eryn Thamann
12/11/25 – SOSS requested for space allocation drawing updates. Awaiting final building priority list from HCFD to finalize SOSS.
01/29/26 – Elevar working on SOSS.
02/26/26 – Elevar provided SOSSs.
03/26/26 – SOSSs approval pending.
04/30/26 – SOSS approved for three buildings. Need schedule from HCFD for access hours, building priority, and deadlines.
05/28/26 – Waiting for Elevar badging to be finalized.
06/25/26 – Started scanning of 1701 06/22 and will last the week. Drawings will be updated as scans come back and starting with JFS areas for leasing diagrams.
07/30/26 – Working thru 1701 set and met with HC IT Dept to review on 07/23. Scanning complete for 111 Tri-Co. Scanning scheduled at TPC for 08/10-08/14.
08/27/26 – Provided 1701 CAD and pdf files. Just received pdfs files of the parking garage and will bgin on those soon. Scanning completed at TPC and 111 Tri-Co. As staff area vailable, these drawings will be checked against scans.
09/24/26 – CAD files received of 1701 parking garage from Champlin to complete that portion of work. Files for 111 are almost complete and sent to HCFD for indications of tenant spaces. Templates for 138 are complete.
10/29/26 – Working thru TPC now.

All Buildings – Space Allocation Drawings Read More »

TPC – BOCC Security Upgrades

PM: Matt Butz, Eryn Thamann, Mike Barth
06/26/25 – Fee estimates from Elevar/DEG were provided based on the Sheriff’s risk assessment document. ROM construction estimates were also provided.
07/31/25 – No update. The County commented that all has been submitted, waiting on comments.
08/28/25 – No update.
09/25/25 – No update.
12/11/25 – No update.
01/29/26 – No update.
02/26/26 – No update.
03/26/26 – No update.
04/30/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – No update.
10/29/26 – Submitted SOSS for egress study.

TPC – BOCC Security Upgrades Read More »

230 – Multipurpose Room Renovation, Prosecutor’s Office

PM: John Nester, Eryn Thamann
05/28/25 – Initial scope meeting held and Elevar to provide SOSS with TEI.
06/26/25 – Need SOSS from DEG for final submission to HCFD.
07/31/25 – Pending SOSS approval. May be combined, hold for now.
08/28/25 – On hold as it may be combined with Mother’s Room project and moved to first floor VA area.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Combined with Mother’s Room. Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – Proposal requested for this as combined with Mother’s Room.
01/29/26 – Need meeting with COA/Probate/HCFD to review scope.

230 – Multipurpose Room Renovation, Prosecutor’s Office Read More »

230 – Mother’s Room Addition, Prosecutor’s Office

PM: John Nester, Eryn Thamann
05/28/25 – Initial scope meeting held and Elevar to provide SOSS with TEI.
06/26/25 – Need SOSS from DEG for final submission to HCFD.
07/31/25 – Pending SOSS approval. May be combined, hold for now.
08/28/25 – On hold as it may be combined with Mother’s Room project and moved to first floor VA area.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Combined with Training Room. Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – Proposal requested for this as combined with MultiPurpose/Training Room.

230 – Mother’s Room Addition, Prosecutor’s Office Read More »

230 – Exterior Signage Feasibility Study

PM: John Nester, Eryn Thamann
03/26/25 – SOSS provided and pending approved PO.
04/24/25 – PO provided. HCFD to schedule kick-off mtg.
05/28/25 – Design kick-off meeting held with the Court/Court Admin/HCFD. Elevar to provide timeline for first round of design.
06/26/25 – Elevar to provide zoning code info to HCFD and not signage design options yet.
07/31/05 – Draft code study sent to HCFD for review.
08/28/25 – Renderings provided to HC on 08/25.
09/25/25 – Elevar needs final design and digital seals to proceed with Small Projects bid.
10/30/25 – Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – No update.
01/29/26 – Archive?

230 – Exterior Signage Feasibility Study Read More »

Elevar – General Services 2025 (F021)

02/25/25 – PO approved.
08/28/25 – CH fifth floor interior sign code summary provided to HC on 08/27.
12/11/25 – No updates.
01/29/26 – Combine with General Services F015.
03/26/26 – 230 exterior lighting study and 111 Tri-Co smoker’s hut performed under Gen. Services.
04/30/26 – Submitted SOSSs for additional PM and CA time to support HCFD and a Prevailing Wage Coordinator.
05/28/26 – SOSSs not approved for PM and PW Coordinator. Juvenile Assessment Center walkthru occurred and Elevar/DEG to issue report.
06/25/26 – Elevar SOSS not approved yet for Juvenile Assessment. Complete the report under Gen Services?
07/30/26 – 230 Court Admins wanted this work to be completed faster than if combined into 230 Lobby Security project.
07/30/26 – Elevar Juvenile Assessment report complete and need DEG portion to fully integrate.
08/27/26 – 230 Exterior Lighting Project back to DEG for electrical design. Fixture options provided to Rycca.
08/27/26 – Does HCFD want Elevar’s Juvenile Assessment report without DEG’s report?
09/24/26 – Elevar assessment report provided to HCFD without DEG’s portion. Site visit was made to review potential relocation of operable partition but put on hold.
10/29/26 – No update.

Elevar – General Services 2025 (F021) Read More »

1916 – Building Assessment

PM: Rycca Thacker, Eryn Thamann
12/12/24 – Project created for tracking.
01/29/25 – Draft copy sent out. Elevar finalizing photo and final cost portions now.
02/25/25 – Final report provided after requested edits.
03/26/05 – Requested revisions have been made. Waiting on a few last elevator assessment items from Wes.
04/24/25 – Elevator evaluated. Final report provided to RT along with bound copies as requested.
05/28/25 – Final report provided in April.
05/29/25 – Archived.

1916 – Building Assessment Read More »

800 – Exit Stair Security Cages

PM: Matt Butz, Eryn Thamann
01/29/25 – Met onsite 01/27 to review scope and SOSS requested.
02/25/25 – SOSS provided for Elevar/TEI. Pending approved PO.
03/26/25 – Pending PO approval. Onsite meeting with City AHJ is scheduled for 03/27 to walk spaces and review for any AHJ concerns.
04/24/25 – Elevar had site visit walk-thru AHJ to review life safety concerns. City concerns sent out in meeting minutes with sketches. HCFD needs to confirm additional scope as indicated by AHJ. Elevar will work on stair scope only for now.
05/28/25 – Elevar provided drawing backup to TEI on 05/28. After MEP design is DD level, a design review meeting will be scheduled with HCFD. Elevar to provide design schedule and will need to meet with HCFD to review Div 01 requirements.
06/26/25 – Design review meeting scheduled for 06/30 to review CD set.
07/31/25 – HCFD has 95% set. Waiting on approval prior to preparing final bid set. Elevar to provide clarification on fee per MB’s request.
08/28/25 – Discussing remaining fee with MB/TEI.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Uploaded to Archibus.
12/11/25 – No update.
01/29/26 – Elevar met with HCFD to review 90% set and provided overview sheet for security committee. Waiting on security committee approval before proceeding with CDs. Project needs to be bid/award in 2026.
02/26/26 – Waiting on security committee approval before proceeding with CDs. Elevar has picked up internal revisions and ready when HCFD obtains approval.
03/26/26 – HCFD to setup security committee approval before proceeding with CDs.
04/30/26 – On hold pending HCFD approval of bidding costs.
05/28/26 – Out to bid now with bids due June 30.
06/25/26 – No update.
07/30/26 – Contractor recommendation provided to HCFD and contracts are in process with Purchasing.
08/27/26 – In final stages of contracts with Purchasing.
09/24/26 – Contract was finalized.
10/29/26 – Procurement starting but no submittals yet.

800 – Exit Stair Security Cages Read More »

All Buildings – Life Safety Drawings

PM: Rycca Thacker, Eryn Thamann
01/29/25 – SOSS requested. JN to confirm what buildings are included in SOSS.
02/25/25 – Pending approved PO.
03/26/25 – First site walk 03/27 at 230. Other buildings shall be scheduled after initial 230 bldg walk.
04/24/25 – 230 Building progressing. Examples with a few questions sent to HCFD for review/approval on 04/22. Elevar is scheduling other buildings with onsite facility managers.
05/28/25 – Example of 230 building was approved by HCFD. Site walks for TPC, 800, CH buildings have also been performed. Need updated drawings for JC care pods and TPC to accurately show floor plans. Need facility manager contacts for remaining locations to schedule site walks.
06/26/25 – JC walk-thru scheduled for 07/02 – 07/03.
07/31/25 – JC walk-thru occurred and Elevar has questions re: JC. Elevar received CH comments from Court Admin and an additional walk-thru is needed to confirm map orientation. Remaining buildings have not been walked yet.
08/28/25 – Evac maps for 230 building provided to HC on 08/27. Other buildings are ongoing.
09/25/25 – All maps will be provided before 11/01. Building 230 has been turned over.
10/30/25 – Evac maps are progressing and on schedule for 11/01 deadline except for a few floor plans where Elevar doesn’t have updated plans and can’t get updated plans.
12/11/25 – All buildings except Hillcrest campus and 6th Floor CH plans have been provided to HCFD with additional JC detainee-area evac plans.
01/29/26 – One floor of CH and Hillcrest to be completed by end of next week. Awaiting Tri-County drawings.
02/26/26 – Elevar working on final 111 Tri-Co drawings now and expect completion in approx. one week.
03/26/26 – Complete with 111 Tri-Co. Portion of Hillcrest remains until further notice.
04/30/26 – Complete. Keep project open for Hillcrest?
05/28/26 – No update.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – SOSS provided to complete 1701.
09/24/26 – No update on SOSS for 1701. CAD/pdfs provided to HCFD for other completed buildings.
10/29/26 – No update.

All Buildings – Life Safety Drawings Read More »

800 – 6th Floor Reno & Bsmt Plumbing Repairs

PMs: Sarah, Terry Cannon, Eryn Thamann
01/17/25 – SOSS Requested.
02/25/25 – SOSS submitted to HCFD. Pending approved PO.
02/26/25 – Awaiting approved SOSS.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. We will follow Elevar lead on first design meeting. TEI scope is in the basement and the 6th floor area. Elevar hasn’t received approved PO.
04/24/25 – PO provided and awaiting design kick-off meeting with Court Admin/team.
04/23/25 – Project setup and internal meetings underway. Elevar and ThermalTech setting up kickoff meeting.
05/28/25 – Awaiting kickoff meeting with Elevar and County. TTE ready to mobilize for design.
06/25/25 – Kickoff meeting in July.
07/30/25 – Drawings received from Elevar, ThermalTech working on MEP design, submitted questions about need for MSB in new restroom. Additional fieldwork done last week for basement repairs.
07/31/25 – Drawings are progressing for a bid review set Aug 8 and a bid set to HC Purchasing Aug 15. TTC changed name and assigned to Elevar and merged Plumbing Repairs and 6th Floor Reno.
08/28/25 – Project scheduled for bid advertisement on 08/29.
09/25/25 – Bids due 10/10. Last addendum due out 09/26 with final questions.
10/30/25 – Lowest bid was Triton and under advertised cost. Vetting mtg occurred and Elevar has recommended Triton for award.
12/11/25 – Project awaiting final contract award from purchasing.
01/29/26 – No update.
02/26/26 – Contract was approved but Elevar has seen no submittals or correspondence. Elevar to schedule construction kick-off mtg.
03/26/26 – Contract was approved but Elevar has seen no submittals or correspondence.
04/30/26 – Have reviewed some general trade submittals.
05/28/26 – Possibly complete with submittals but low on Triton’s priority list.
06/25/26 – No update as it’s low on Triton’s priority list. Not received change order pricing for flooring add.
07/30/26 – Construction kickoff meeting held 07/20. Recurring progress meetings scheduled.
08/27/26 – Triton likely back onsite now after ACM removal. Regular progress meetings to resume next Mon. We will keep the floor drain in the project based on today’s conversation.
09/24/26 – Working thru slab change order.
10/29/26 – New pricing is expected soon for slab work.

800 – 6th Floor Reno & Bsmt Plumbing Repairs Read More »

JC – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after fist walk of 230 bldg. Need updated drawings from Champlin and door labels from HCFD that match fire door report.
04/24/05 – Walk-thru not scheduled yet.
05/28/25 – Elevar needs building info that matches between original LSS report and building plans. Current plans don’t have door numbers listed and LSS report has inaccurate photos of doors. Walk-thru on hold pending further info.
06/26/25 – JC walk-thru scheduled for 07/02 – 07/03.
07/31/25 – Walk-thru performed but drawings have not been updated yet.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates almost complete but can review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – Paint removal will occur at JC. Elevar reviewed JC with Sheriff’s and a few items will be revised. No updates on progressing project into bidding.
07/30/26 – Elevar had questions regarding anti-ligature closer locations at JC and emailed to HCFD. List of doors needing paint removed sent to HCFD. Need final allowance amount from HCFD to add to bidding docs for door re-certificaiton/replacement if paint removal doesn’t work.
08/27/26 – Questions still remain for JC anti-ligature items but will be confirmed prior to bidding. HCFD to provide allowance figure for re-certification.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

JC – Fire Door Repairs Read More »

CH – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after first walk of 230.
04/24/25 – Walk-thru not scheduled yet.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
06/26/25 – Ready for review with Champlin/HCFD.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

CH – Fire Door Repairs Read More »

800 – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after first walk of 230 bldg.
04/24/25 – Walk-thru not scheduled yet but is next in line.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
06/26/25 – Ready for review with Champlin/HCFD.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

800 – Fire Door Repairs Read More »

230 – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and initial site walk scheduled for 03/27 with JN.
04/24/25 – Walk-thru occurred and drawings have progressed. Elevar to coordinate with Champlin on design in near future.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. Need to know if paint removal was successful on stickers.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

230 – Fire Door Repairs Read More »

CH – 6th Floor Sheriff’s Storage

PM: Eryn Thamann, Matt Butz
08/27/24 – Elevar SOSS approved. TEI to submit SOSS.
09/24/24 – TEI submitted SOSS to HCFD. Elevar requested design kick off meeting with HCFD.
10/30/24 – Drawings are setup and design team need to walk space for FV and finish discussions.
12/09/24 – Need to review finishes with HCFD. Will perform site work 12/12. BW said bring over finishes and he would like to maybe replaced tile in main hallways.
01/02/25 – TEI reached out for update on project progress.
01/27/25 – Kickoff meeting occurred 1/22, SD & Cost Due to John Nester 3-4 weeks after meeting.
02/26/25 – Elevar to gather full SD set for HCFD submission. Archibus project made and SD estimates can be added. ThermalTech will complete SD drawings by Friday 2/28.
02/27/25 – JN will bring in Sheriff Office for final review early March for this job.
03/26/25 – Team met with stakeholders to review SD options. Elevar will provide another round of SD options and storage options based on new info from meeting.
04/24/25 – Elevar provided second round of SD plan options and Sheriff storage options for selection. Upon plan and storage selections, the team can procced with design docs.
05/28/25 – No update.
06/26/25 – Elevar to update Archibus cost estimates.
07/31/25 – Elevar to update Archibus cost estimates.
08/28/25 – Estimates updated and new options uploaded.
09/25/25 – No update.
10/30/25 – No update.
12/11/25 – No update.
01/29/26 – Elevar to submit SOSS. Need final decision on Sheriff’s storage options or no storage included. Confirm no separate interior office for Sheriff’s IT group.
02/26/26 – Elevar has remaining fee and will start on this immediately.
03/26/26 – DEG to finalize MEP drawings and a final HCFD review set will be ready.
04/30/26 – Set is 95% and on hold for final bidding info.
05/28/26 – Need to prep documents for trades work. Elevar to submit building permit and DEG to submit IBI permit.
06/25/26 – Elevar to submit building permit and DEG to submit IBI permit this week.
07/30/26 – Kickoff meeting held 07/22. IBI permit approved. Building permit still under review.
08/27/26 – Kickoff meeting held with trades. IBI review approved and DEG will submit. Building permit paid for and wall bracing engineering change submitted.
09/24/26 – Will postpone construction start until approx. Nov 2026.
10/29/26 – Restart?

CH – 6th Floor Sheriff’s Storage Read More »

CH – Re-Drape and Blinds

PM: Eryn Thamann, John Nester, Jesse Estes
08/27/24 – SOSS approved. JN to send new drape/blind info for review prior to scheduling site visit.
09/24/24 – JN to send info and meeting invite to review mock up.
10/30/24 – Elevar met with Court Admin to review mockups. Drawings started for SD.
12/09/24 – SD review meeting with HCFD/Court Admin scheduled for next week.
01/29/25 – Met with Court Admin and revised drawings based on meeting. SD review package is nearly ready for HCFD final review.
02/26/25 – Drawing package submitted to HCFD for final review.
03/26/25 – No update.
04/24/25 – No update.
05/28/25 – No update.
06/26/25 – No update.
07/31/05 – Elevar to research historic requirements for elevations.
08/28/25 – No historic restrictions on interior window treatments and confirmation sent to HC.
09/25/25 – No update.
10/30/25 – No update.
12/11/25 – No update.
01/29/26 – Archive?

CH – Re-Drape and Blinds Read More »

Hillcrest – Campus Long Term Strategic & Master Planning

PM: Eryn Thamann, Bert Watts, John Nester
08/27/24 – Initial meeting held with HCFD, Juvenile Court, Elevar.
09/24/24 – SOSS submitted for strategic planning efforts. Juvenile Courts waiting on larger funding of Hillcrest projects/programs before approving.
09/26/24 – On hold.
10/30/24 – No update.
12/09/24 – No update.
01/29/25 – No update.
02/25/25 – No update.
03/26/25 – No update.
04/24/25 – No update.
05/28/25 – No update.

Hillcrest – Campus Long Term Strategic & Master Planning Read More »

230 – 10th Floor Marriage License Reno 2024

PK = Matt Butz, Mike Barth, Eryn Thamann
05/29/24 – TEI submits SOSS for approval.  Project pending PO and signed SOSS.
06/05/24 – Elevar submits SOSS for approval. Project pending PO and signed SOSS.
06/26/24 – Project pending PO and signed SOSS.
07/24/24 – TEI, Elevar and HCFD meet on site with end user. Scope changed and SOSS’s to be resubmitted for new revised scope.
08/27/24 – Elevar submitted new SOSS on 07/26 and awaiting approval.
08/28/24 – TEI receives signed SOSS and PO.
09/24/24 – Elevar scheduled a design kick off meeting for 10/01.
10/30/24 – Concepts provided to Probate for review.
12/09/24 – Finalizing concepts this week.
01/27/25 – ThermalTech awaiting schedule from HC/Elevar, HVAC SD level completed. In CD phase with 75% review in next few weeks. Electrical to finalize field confirmation after the partner meeting on 01/30/25.
02/25/25 – 75% review set sent to Probate for review and schedule of onsite meeting. Elevar still owes additional SOSS for lift removal/office add.
03/26/25 – Team met with Probate and has a few revisions. Still need finishes from HCFD. Elevar still owes additional SOSS for lift removal/office.
04/23/25 – Team is awaiting approval of lift/office SOSS to complete CDs.
05/28/25 – Progressing with CD drawings while waiting on final finishes approval.
06/26/25 – CD set was reviewed Probate and approved. Final finishes and systems furniture selected. Waiting for Probate to approved final SOSS for lift removal and additional office at which time they will be added to the drawings.
07/31/25 – Probate set to issue PO for additional work last wee/this week. Elevar to coordinate additional work and provide backgrounds. Need final approval for bidding from HCFD.
08/05/25 – THP received project authorization and signed agreement.
08/22/25 – THP – Elevar, County and THP reviewed field conditions for infill project.
08/28/25 – Additional SOSS approved and THP made site visit to field verify existing lift. Project will be ready to start HC review/bidding prep after this final scope is completed.
09/08/25 – THP issued infill repair detail for review.
09/25/25 – Drawings 95% complete and likely ready for a final review. ROM cost estimate sent to Probate for review.
10/21/25 – THP issued structural bid documents for project package.
10/30/25 – Project out to bid as of 10/22. Pre-bid mtg scheduled with team for 11/05.
12/11/25 – Post-bid vetting meeting scheduled for Alpha on 12/10 with Triton as next lowest.
01/29/26 – Permit/revisions applied for at City. Waiting on final contracts thru Purchasing.
02/26/26 – Contract awarded to Alpha on 02/19. Elevar to schedule construction kick-off mtg.
03/26/26 – Elevar to schedule construction kick-off mtg after Alpha provides construction schedule; expect this soon. HCFD to award special inspections SOSS.
04/30/26 – Construction kick-off meeting scheduled for end of May.
05/28/26 – Construction kickoff mtg occurred 05/27. Eryn to issue mtg mins and setup recurring progress mtgs. Construction to start June 1.
06/25/26 – Construction ongoing.
07/30/26 – Construction ongoing. Approx. carpet delivery is Aug 4. Phase 1 is waiting on carpet install prior to shifting to Phase 2.
08/27/26 – Construction ongoing in phase 2. Working on HVAC duct issue.
09/24/26 – Punch list for Ph. 2 occurred and contractor moved to Ph. 3.
10/29/26 – Approx. 2 weeks from Phase 3 completion. Furniture move is scheduled for 10/28. Closeouts will also remain.

230 – 10th Floor Marriage License Reno 2024 Read More »