PM: Eryn Thamann, Matt Butz
08/27/24 – Elevar SOSS approved. TEI to submit SOSS.
09/24/24 – TEI submitted SOSS to HCFD. Elevar requested design kick off meeting with HCFD.
10/30/24 – Drawings are setup and design team need to walk space for FV and finish discussions.
12/09/24 – Need to review finishes with HCFD. Will perform site work 12/12. BW said bring over finishes and he would like to maybe replaced tile in main hallways.
01/02/25 – TEI reached out for update on project progress.
01/27/25 – Kickoff meeting occurred 1/22, SD & Cost Due to John Nester 3-4 weeks after meeting.
02/26/25 – Elevar to gather full SD set for HCFD submission. Archibus project made and SD estimates can be added. ThermalTech will complete SD drawings by Friday 2/28.
02/27/25 – JN will bring in Sheriff Office for final review early March for this job.
03/26/25 – Team met with stakeholders to review SD options. Elevar will provide another round of SD options and storage options based on new info from meeting.
04/24/25 – Elevar provided second round of SD plan options and Sheriff storage options for selection. Upon plan and storage selections, the team can procced with design docs.
05/28/25 – No update.
06/26/25 – Elevar to update Archibus cost estimates.
07/31/25 – Elevar to update Archibus cost estimates.
08/28/25 – Estimates updated and new options uploaded.
09/25/25 – No update.
10/30/25 – No update.
12/11/25 – No update.
01/29/26 – Elevar to submit SOSS. Need final decision on Sheriff’s storage options or no storage included. Confirm no separate interior office for Sheriff’s IT group.
02/26/26 – Elevar has remaining fee and will start on this immediately.
03/26/26 – DEG to finalize MEP drawings and a final HCFD review set will be ready.
04/30/26 – Set is 95% and on hold for final bidding info.
05/28/26 – Need to prep documents for trades work. Elevar to submit building permit and DEG to submit IBI permit.
06/25/26 – Elevar to submit building permit and DEG to submit IBI permit this week.
07/30/26 – Kickoff meeting held 07/22. IBI permit approved. Building permit still under review.
08/27/26 – Kickoff meeting held with trades. IBI review approved and DEG will submit. Building permit paid for and wall bracing engineering change submitted.
09/24/26 – Will postpone construction start until approx. Nov 2026.
10/29/26 – Restart?