Hamilton County Facilities

CH – Vestibule Air Curtains 2023

PM: Jesse Estes, Terry Cannon
09/21/23 – Tony requested SOSS for this work. Replace all three he confirmed in a phone call with him.
09/27/23 – Working on SOSS today.
10/25/23 – Review set will be ready Friday for owner review.
12/06/23 – Bids received from DK and Triton. DK is the apparently low bidder. Tony suggested accepting only the Alternates to add heaters to the left and right vestibules. TTC will review the bids with DK and recommend the award for this project.
01/11/24 – DK submitted additional paperwork for this project per request.
02/23/24 – Contract under review.
03/22/24 – Contract under review.
04/24/24 – Contract in for final review.
05/28/24 – Stamped permit drawings sent to DK for permitting.
05/29/24 – Setup kickoff meeting with AJ, Tony, Tyler for starting this project.
06/23/24 – Pre Const meeting held, coredrill complete, team met on door swing issue this morning.
06/26/24 – DK reported that heater was deeper than the door swing and submitted an RFI for resolution.
06/28/24 – A top cap “box” solution was given to DK for pricing. This would move the heater up high enough for the door to open.
06/30/24 – IBI Issued the electrical permit. CIC2402080
07/08/24 – TTE requested factory review of the proposed box solution for the heater depth issue.
07/09/24 -The factory reported that we did not have enough clearance for proper airflow and TTC discovered the maintenance access was blocked by the proposed design.
07/10/24 – A revised solution was sent to the County for comment that moves the heater on top of the panel.
07/24/24 – TTC checked back on the revised design and it was accepted by Tony Matre, TTC forwarded to DK for review. Tyler inquired about still using the box solution.
08/28/24 – Left and Right heaters are installed. Reviewed and approved by TTE and Facilities. DK engaged for change order revision on the center heater in the middle vestibule with the exact same unit the left and right has. DK agreed CO#1 using the allowance monies to pay for the additional heater. Paperwork signed and sent to AJ this week.
09/23/24 – The left and the right heaters are installed, painted, and electrified. The center heater was ordered via change order and should ship 10/2. Once the third heater is installed the electric and controls will be finished for all three heaters.
10/30/24 – All three heaters are installed. Two of them have power and final paint. AJ trying to get electrician on site to power up the final heater. AJ lining up Joe Bulach for DDC integration after third heater is ready.
01/02/25 – Controls are installed, all heaters should be working, punchlist sent, contractor has been asked to start closeout on this project. The heaters are discharging about 110F.
01/27/25 – Still waiting on final closeout documents from contractor.
02/26/25 – Closeout Documents almost complete., they are coming in.
03/25/25 – Closeout documents received and final pay apps being processed.
04/02/25 – Jesse Submitted final pay app today.
04/23/25 – Project can be archived.