PM: Bert Watts, John Millar
10/24/23 – Hamilton County requested SOSS.
10/31/23 – THP provide SOSS for review.
11/08/23 – Hamilton County approved SOSS.
02/29/24 – Record Center roof was noted to be leaking in a number of locations. Roof is under warranty. THP documented the conditions and met with the manufacturer and contractor. Manufacturer’s warranty department has approved a repair approach. Contractor is pricing.
02/29/24 – 800 Broadway tile in NE stair tower had cracking at the first floor level. THP coordinated contractor stabilization, removal and repair. Repair is complete. THP to provide a summary report.
04/25/24 – THP no update.
06/27/24 – Record center roof repair started today and is planned for the next 2-3 weeks. THP scheduled to be on site Friday to review progress.
07/12/24 – Tremco completed warranty repairs and submitted reports for review.